Professional Documents
Culture Documents
Date 11/07/2018
Project Al Oyoun Plaza at Diyar Al Muharraq
Contractor GEOHARBOUR MIDDLE EAST CONSTRUCTION LLC
8 Amount in Words: Two Hundred Six Thousand Five Hundred Eighty Seven Only
Equipment Model YTR300D
Drilling Rig/Nos 1 No.
Shift/day 2 1
Production m/10h UCS<5MPa 70.00 2
Actual Duration 7 3
Sum Duration/days 27 4
Sum Duration/months 0.9 5
6
7
岩石不需要护筒 8
5-1 Casing
5-2 Auger
5-3 Drilling Teeth
5-4 Bucket
5-5 Tremie Tipe
Fittings
5-6 Pile Spacer
5-7 Water Tanks
5-8 Sonic Pipes
5-9 Plywood
5-10 Nails,Timber
5-11 Others
7-1 Lowbed
7-2 Flat
Mob and Demob
7-3 Auxiliary Crane 1.00
7-4 Others 1.00
Profit 20.76%
Cost/m 235.34
Quotation/m 297.00
Total Quotation (AED) 284,259
Cost/Nos. 3,692.56
Quotation/Nos. 4,659.98
Profit 20.33%
Cost/m 638.13
Quotation/m 801.00
Total Quotation (AED) 766,637
Cost/Nos. 10,012.33
Quotation/Nos. 12,567.82
BOQ
Dia/mm Nos Length/m
900 55 15.10
900 6 21.10
Sum 61 957
nos. 0.00
nos. 6.00 3,000.00 16,101.86
nos. 2.00 4,000.00 0.00
nos. 1.00 3,500.00 3,130.92
nos. 0.00
nos. 61.00
m3 608.88 15.00 9,133.21
nos.
nos.
nos.
nos.
nos.
Total Excluding Concrete & Steel (AED) 225,245.95
Total Cost (AED) 610,752.29
Cost(AED):
A. Mob & Demob 20,200.00
B. Setting Out 5,000.00
C. Execution 610,752.29
D. Testing 0.00
E. Trimming Works 4,472.74
F. Spoil Removal 9,133.21
ALL 649,558.24
Cost(AED):
A. Mob & Demob 20,200.00
B. Setting Out 5,000.00
C. Execution 610,752.29
D. Testing 0.00
E. Trimming Works 4,472.74
F. Spoil Removal 9,133.21
ALL 649,558.24
Construction Speed
Production m/10h Soil 100
Production m/10h UCS<5MPa 70
Production m/10h 5<UCS<10MPa 50
Production m/10h 10<UCS<30MPa 40
UCS<10Mpa 25m/10h
10<UCS<30Mpa 5-10m/10h
哈电10Mpa以下1天2-3根12-13m
Notes
Diesel 200L/10h Rent60,000aed
1 shift/10,0000aed 2 shift
Diesel 100L/10h for Pile
Rent 45,000aed 1 shift/70,000aed 2
shift
Diesel 20L/10h
For Pump and Site Office
For casing Diesel 200L/10h
Purchasing 100,000aed
Purchasing 100,000aed
Diesel 100L/10h
Diesel 100L/10h
3 labors/rig/shift
50kg/bag
Each Set 300L/10h
12.5kg/m for 600mm dia
25kg/bag
2 bedrooms
Rent A Car
1 day
3.5 days 1.5 load 12 hours
73.32
Concrete
Start
Ground Cut off Empty Toe Bore Soil Rock
No. Dia/mm Qty Socket
Level level Boring Level Length Length Length
Level
A B C D E=A-D F=E-G G
1 600 55 3.20 2.10 1.10 -1.36 -11.90 15.10 4.56 10.54
21.10 35.80
01 36 Main bar 25 1.25
270.65
1.15 311.25 Steel Wastage 5%:
bar
15.10
12.00 3.854 93.27
21.10
12.00 3.854 19.65
116.32
Steel Wastage 5%: 1.05 122.13
As per BS8110, Part 1 - 1997, The ultimate axial load should not exceed the value of "N" given by:
600mm
C45 460.00
N/kN fcu/kPa Aps/m2 fy'/kPa As'/m2 Applied Axial Load
Vertical Nos Dia/mm
1800.00 45000.00 0.28 460000.00 -0.01 11.00 12.00
700mm
C45 460.00
N/kN fcu/kPa Aps/m2 fy'/kPa As'/m2 Vertical Nos Dia/mm
3500.00 45000.00 0.38 460000.00 0.00 11.00 14.00
800mm
C45 460.00
N/kN fcu/kPa Aps/m2 fy'/kPa As'/m2 Vertical Nos Dia/mm
0.00 45000.00 0.50 460000.00 -0.02 14.00 14.00
"N" given by: