Rate Analysis

Glass Railing for Building Works


Decription of Items Unit Qty Market Rate

8mm Thick Toughened Glass Sqm 1 1100


10mm Thick Toughened Glass Sqm 1 1345
12mm Thick Toughened Glass Sqm 1 1560

13.52mm Laminated HS Glass (6mm + 1.52mm PVB + 6mm Glass) Sqm 1 2950
Cost 6mm Glass - 750/- Sqm and PVB Sheet 1450/- Sqm

12.79mm Laminated Glass (6mm + 0.79mm SGP + 6mm Glass) Sqm 1 3050
13.52mm Laminated Glass (6mm + 1.52mm SGP + 6mm Glass) Sqm 1 4250

Cost 6mm Glass - 750/- Sqm and SGP Sheet 0.79mm Thk -1550/- Sqm and 1.52mm Thick SGP - 2750/- Sqm
If Glass in Curve / Round Sape the price of glass would be 4 Times Extra
If Glass used Extra Clear / Ultra Glass the cost would be 1.2 Times Extra

With SSS Raiiling & Fittings SS 304 Grade Kg 1 350

With Aluminium Extruded Section Kg 1 275


PVDF Poweder Coating Cost Finish 30-40 Micron Kg 1 60
Anodized Finish Kg 1 35

Expandable Dash Fastners Each 1 65

Sl.No. Description of Works Unit Qty Rate Amount


1.1 Alumminium Baserail Glass Railing Works
Design, Supply, Fabrication and installation of Glass Railings Systems (H
- 1200mm) as per approved drawings complete using SS 304 Top
handrail 65mm dia, anchor bracket Alum. U Channel / mechanism
including Cover Profile & Silicon Grip as mentioned below with all
necessary hardwares along with 10 mm thk toughened Glass as per
specifications etc including providing all fixing arrangement and fixing of
all accessories as per manufactures standard, and instruction as per
instruction of engineer incharge.

Rate Analysis for 10 Rmt


Materials
10mm Thick Toughened Glass Sqm 11 1345 14795
Wastage @ 10% Sqm 1.1 1345 1480

Aluminium Extruded Sections (4.5 Kg / Rmt) Kg 45.0 275 12375 0.2041


Wastage @ 5% Kg 2.3 275 619 2.883933 65
Powder Coating Cost Kg 45 65 2925 28.83933
EPDM Gasket Rubber Rmt 20 60 1200 33.16523
Expendable Fastners Each 30 65 1950

SS -304 Grade Top Rail 65mm Dia Kg 30 350 10500 8.4 18.66667
SS - 304 Glass Top Caping Section Kg 7 350 2308
Bracet, Rivet & Screws Fittings @ 20% 2562
0.628
Design & Value Engineering Cost / Shop Drawings @ 30% 15214 6.28
Labour Cost
Fabrication Erection & Installation (Avg. 1000/- Rmt) Rmt 10 1000 10000

Tools & Plant Accessories @ 2% 1519


Total 77445
Electricity Charges @ 2% 1549
Total 78994
Add CPOH @ 15% 11849
Total Cost for 10 Rmt 90843
Per Rmt 9084
Per Rft 2770

1.2 SS Post Glass Railing Works

Design, Supply, Fabrication and installation of Glass Railings Systems (H


- 1200mm) as per approved drawings complete using SS 304 Top
handrail 65mm dia, anchor bracket Alum. U Channel / mechanism
including Cover Profile & Silicon Grip as mentioned below with all
necessary hardwares along with 10 mm thk toughened Glass as per
specifications etc including providing all fixing arrangement and fixing of
all accessories as per manufactures standard, and instruction as per
instruction of engineer incharge.

Rate Analysis for 12 Rmt


Materials
13.52mm Laminated HS Glass (6mm + 1.52mm PVB + 6mm Glass) Sqm 11 1100 12100
Wastage @ 10% Sqm 1.1 1100 1210

SS 304 Vertical Post (Avg. 5 Kg / No.) Kg 55.0 350 19250 0.2041


Wastage @ 5% Kg 2.8 350 963 2.883933 65
EPDM Gasket Rubber Rmt 40 25 1000 #REF!
Expendable Fastners Each 33 65 2145

SS -304 Grade Top Rail 65mm Dia Kg 30 350 10500 8.4 18.66667
Bracet, Rivet & Screws Fittings @ 20% 2100
0.628
Design & Value Engineering Cost / Shop Drawings @ 25% 12317 6.28
Labour Cost
Fabrication Erection & Installation (Avg. 1000/- Rmt) Rmt 12 1000 12000

Tools & Plant Accessories @ 3% 1472


Total 75056
Electricity Charges @ 2% 1501
Total 76557
Add CPOH @ 15% 0
Total Cost for 12 Rmt 76557
Per Rmt 6380
Per Rft 1945

1.2 Pin Glass Railing Works


Design, Supply, Fabrication and installation of Glass Railings Systems (H
- 1200mm) as per approved drawings complete using SS 304 Top
handrail 65mm dia, anchor bracket Alum. U Channel / mechanism
including Cover Profile & Silicon Grip as mentioned below with all
necessary hardwares along with 10 mm thk toughened Glass as per
specifications etc including providing all fixing arrangement and fixing of
all accessories as per manufactures standard, and instruction as per
instruction of engineer incharge.

Rate Analysis for 10 Rmt


Materials
8mm Thick Toughened Glass Sqm 10 1100 11000
Wastage @ 10% Sqm 1 1100 1100

Round / Square - SS 304 Glass Pins Kg 40 550 22000 0.157

SS -304 Grade Top Rail 50mm Dia Kg 23 350 7875 8.4 18.66667
Bracet, Rivet & Screws Fittings @ 10% 788
0.628
Design & Value Engineering Cost / Shop Drawings @ 10% 4276 6.28
Labour Cost
Fabrication Erection & Installation (Avg. 600/- Rmt) Rmt 10 600 6000

Tools & Plant Accessories @ 2% 1061


Total 54100
Electricity Charges @ 2% 1082
Total 55182
Add CPOH @ 15% 8277
Total Cost for 10 Rmt 63459
Per Rmt 6346
Per Rft 1935
24