Professional Documents
Culture Documents
26 m
350m
REVISED LENGTH & ROUTES OF PIPELINES (PIER 4 TO
BLK 13)
26 m 24 m
350m 150m
ACTUAL LENGTH AND ROUTE OF PIPELINES(WORKS
BY EEI)
RE: 011
Relocation of Grease Plant
P 18, 294, 719.10
The following is our evaluation on subject COR:
3 Office This is a deductive work. There should be a 2 storey office area (41 sqm)
inside the grease plant.
RE: 011
Relocation of Grease Plant
P 18, 294, 719.10
The following is our evaluation on subject COR: No. Item Original Actual Change Order
I. Engineering
A. Engineering ₱1,710,443.79 ₱60,015.57 -₱1,650,428.22
Construction
The original scope covers dismantling of B. Management ₱989,093.28 ₱34,705.03 -₱954,388.25
existing grease plant facility and reinstalling II. Procurement ₱0.00 ₱0.00 ₱0.00
same equipment at new Lube Oil Blending III. Construction
Plant. This original scope was cancelled Grease Plant Package (57 units)
because of incidental cost of building buffer A. VI Improver ₱1,091,192.21 ₱1,091,192.21 ₱0.00
supply equivalent 6 months' supply needed B. Drum Oven ₱818,394.16 ₱818,394.16 ₱0.00
during shutdown. In addition, a study was Grease Plant
C. Package (55 units) ₱13,639,902.63 ₱0.00 -₱13,639,902.63
conducted which indicated that use of new
Sub- Total ₱15,549,489.00 ₱1,909,586.37 -₱16,244,719.10
technology would be better in addressing Civil Works
existing quality issues of grease products. Offi ce (82 sqm gross
D. area) ₱2,050,000.00 ₱0.00 -₱2,050,000.00
TOTAL -₱18,294,719.10
COMMERCIAL BID FORM
RE: COR 77 B- Heavy Duty Filter (Air Filter)
Air at Harbor Center is contaminated with dust coming from adjacent
cement and coal storage and those generated by moving trucks. In such
condition, OEM recommends installing air filter to prevent engine damage.
RE: COR 63 G
Laboratory Fire Extinguisher
P 527, 381.50
The following is our evaluation on subject COR: