GHANA INSTITUTE OF MANAGEMENT

AND PUBLIC ADMINISTRATION(GIMPA).

CONSTRUCTION OF 2 NO. 3 STOREY LECTURE


HALL BLOCKS AT GIMPA CAMPUS LOT 1 & 2 –
Accra

Monthly Progress Report

AS AT OCTOBER 11th,2018

Employer: GIMPA, Accra-Ghana

Consultant: ALBERT ESSAMUAH ASSOCIATES LIMITED.

Contractor: China State Hualong Construction (GH) Ltd.


MONTHLY PROGRESS REPORT AS AT OCTOBER 11th ,2018

Client: Ghana Institute of Management and Public


Administration, (GIMPA), Accra – Ghana
Commencement date: 24/11/17
Expected completion
date: 02/01/19
Overall Planned Progress: 50%
Overall Actual progress:50%
Forecast progress: 65%

1. WORK PROGRESS FOR LOT 1

PLANNED ACTUAL FORCAST


ITEM ACTIVITY PROGRESS(%) PROGRESS(%) REMARKS
PROGRESS(%)

(LOT 1)

SUPERSTRUCTURE
WORKS

1.0 Ground floor works


i)Blockworks 100 100

ii)First fix 75 80 100

iii)Plastering works 50 60 100

iv)Doors and windows


installation 50 70

2.0 First floor works

i)Blockworks 95 100

ii)First fix 75 90 100

iii)Plastering 60 80 100

iv)Doors and windows


installation 50 70
1
3.0 Second floor works

i)Blockworks 100 100

ii)First fix 75 80 100

iii)Plastering 60 80 100

iv)Roofing works 80 85 100

v)Doors and windows


installation 50 70

Planned Progress for


Lot 1: 50%
Actual Progress for
Lot 1: 50%
Forcast Progress for
Lot 1 60%

2
2. WORK PROGRESS FOR LOT 2

PLANNED ACTUAL FORCAST


ITEM ACTIVITY PROGRESS(%) PROGRESS(%) REMARKS
PROGRESS(%)
(LOT 2)

SUPERSTRUCTURE
WORKS

1.0 Ground floor works

i) Blockworks 90 95 100

ii) First fix 80 90 100

iii) Plastering 50 70

2.0 First floor works

i)Blockworks 90 95 100

ii) First fix works 80 90 100

iii)Plastering works 50 65

3.0 Second floor works

i)Blockworks 95 95 100

ii) First fix works 50 85 100

iii)Plastering works 50 70

iv)Roofing works 40 40 70

Planned Progress
for Lot 2: 40 %
Actual Progress
for Lot 2: 45%
Forcast Progress
for Lot 2: 55 %

3
3. Site Labour Force

Ghanaian Staff
1.Foremen 2
2.Masons 4
4. Material s on Site 3.Carpenters 6
4.Steel benders 3
S/N Item Unit Q’ty
5.Plumbers 2
1 Fine Aggregate m³ 15
6.Security 2
2 Coarse Aggregate 7.Labourersm³ 20
15
8.Driver 1
3 Cement bags bags 265
9. Cook 1
4 Timber(2x6) pcs 260

5 6” blocks pcs 1000

6 4” blocks pcs -

7 2” Nails boxes 2

8 2.5 Nails boxes 2

9 6” Nails boxes 0.5

10 Binding wire rolls 3

11 Plywood pcs 35

12 20 mm reinforcement bars kg -

13 16mm reinforcement bars kg -

14 10mm reinforcement bars kg -

15 8 mm reinforcement bars kg -
5. Health and Safety.

The site experienced no injury related issue.

6. The Weather
The site experienced rains on 09/10/18.

7. Progress Photos

L OT 1 & 2

Ongoing Plastering works on LOT 1

Fig 1

Ongoing blockworks Ongoing roof works at LOT 2


Fig 2 Fig 3.

5
Endorsed by: George Dabi

……………………………
Clerk of works (GIMPA)

Endorsed by: Mr. Mao

………………………………………......
Site Manager (China State)

Prepared by: Emmanuel Siaw

………………………………………......
Works Engineer (China State)