PROJECT: Proposed 2-3 Bedroom 2-Storey Residencial Apartment

CLIENT: AMr. Daniel Annan


LOCATION: Agbogba-Ga East Municipal,Greater Accra
Date: March 16, 2020

BILL OF MATERIALS
Item No. Description Unit Qty Rate Amount(₵)
1.0 GENERAL REQUIREMENTS
Signed and sealed plans and BOQ necessary for
lot 1 1,200.00 1,200.00
building and construction permit

2.0 SITE PREPARATION


Mobilization, site clearing and layout lot 1 1,000.00 1,000.00

3.0 EARTH WORKS


2.1 Excavation
Foundation cu.m 34 25.00 850.00
Wall footing cu.m 11 45.00 495.00
Septic Tank cu.m 5 42.00 210.00
2.2 Backfill/Compaction cu.m 22 40.00 880.00
2.3 Gravel Base cu.m 5 45.00 225.00
2.4 Soil debris disposal cu.m 12 15.00 180.00
Sub-total (Earth works) 2,840.00

STRUCTURAL WORKS

3.0 REINFORCEMENT BARS


3.1 Foundation/Footing
20mmø x 6.0m Gr.60 Rebars kg 35 22.50 787.50
16mmø x 6.0m Gr.60 Rebars kg 72 22.50 1,620.00
10mmø x 6.0m Gr.60 Rebars kg 32 22.70 726.40
3.2 Column
16mmø x 6.0m Gr.60 Rebars kg 35 22.50 787.50
10mmø x 6.0m Gr.60 Rebars kg 25 22.70 567.50
3.3 Beam/girders
16mmø x 6.0m Gr.60 Rebars kg 35 22.50 787.50
10mmø x 6.0m Gr.60 Rebars kg 33 22.70 749.10
3.4 Slab
10mmø x 6.0m Gr.40 Rebars kg 45 22.0 990.00
3.6 GI Tie wires #16 kg 50 35.0 1,750.00
Sub-total (Reinforcement bars) 8,765.50

4.0 CONCRETE WORKS


Class A mixture 1:2:4 @ 50 Kg cement bag
4.1 Foundation/Footing
Cement bags 35 35.00 1,225.00
Sand cu.m 34 42.00 1,428.00
Gravel cu.m 35 41.00 1,435.00
4.2 Column
Cement bags 45 35.00 1,575.00
Sand cu.m 44 125.00 5,500.00
Gravel cu.m 32 25.00 800.00
4.3 Beam/Girders
Cement bags 25 35.00 875.00
Sand cu.m 39 32.00 1,248.00
Gravel cu.m 25 25.00 625.00
4.4 Slab (Ground and second floor)
Cement bags 36 35.00 1,260.00
Sand cu.m 25 15.50 387.50
Gravel cu.m 24 25.00 600.00
Sub-total (Concrete works) 16,958.50