You are on page 1of 2

Concept Design for Jinka Town Road

1 Time Implication
1.1 Work Load Comparison
The project duration given for Jinka-Mendir project which is a 49km long road is 2 years. In direct
proportion, the duration for the 6km (2*3km)JinkaTown project would be approximately 3 months.
Considering the project value, based on a contract amount of ETB 1,214,208,380.51 for Jinka-Mendir
project, the Jinka Town section with a contract amount of ETB 121,870,140.87 shall take approximately
2.4 months.

However, as can be seen from the following work load comparison; rather than earth works which are
machine intensive, the structure works are the major work items for the Jinka Town section. Basically,
structure works like masonry, formwork, rebar, curbing, ditch cover and walkway tile works are labor
intensive which require longer duration for completion.
Table 1: Work Load Comparison

Jinka-Mendir
Jinka Town road
Work Group Original Contract
Work Load
Work Load
2000 and 4000 44% 13%
5100 6% 3%
5200 6% 6%
6000 19% 19%
3000, 8000 and 9000 24% 58%
9000, 1000 and 2000 2% 1%

1.2 Duration Estimation


As shown in the following table, by considering a critical path that accounts structure works, the
duration required to complete the construction of Jinka town section is 356Calander Days.
Table 2: Duration required for Completion of Jinka Town Section
Factored
Standard No. of
Average Daily No. of Days No. of days for
Uni Average Daily No. of Daily Days
No. Activity Workload Production for Overlap with contributed for
t Production Crew Output Require
Town Section next activity Critical Path
(Single Crew) d
(Single Crew)
1 Clearing ha 0.66 1.00 0.66 16 10 6
9.99 1.10
Ditch 22,623. 1
2 m3 90.00 4.00 360.00 63 57 6
excavation 52 50.00
Ditch 8,811
3 m3 15.00 4.00 60.00 147 - 147
Masonry .14 25.00
Capping 6,418 9
4 m3 588.00 1.00 588.00 11 - 11
layer .50 80.00
12,879. 4
5 Subbase m3 288.00 1.00 288.00 45 - 45
13 80.00
Base 8,558 8
6 m3 480.00 1.00 480.00 18 - 18
Course .00 00.00
AC 48,180. 3,5
7 m2 2,100.00 1.00 2,100.00 23 - 23
Pavement 00 00.00
Side-walk 5,548
8 m2 57.60 4.00 230.40 25 - 25
Tile .98 96.00
 Working Days Required 281
   Average Working Days per Month 24.04
Calendar Days Required 356

Note Average daily production for Town Section is assumed to be 60% of the Standard Average daily production due to the effect of ROW issues,
: traffic management, resource management and other reasons.

You might also like