Unit 3C, 64F Planters Subdivision, Brgy.

Rincon, Valenzuela City


8-361-2017 / 0945-572-2324 / 0943-094-0017
echano.construction@gmail.com
Facebook Page: Echano Construction Inc.

Date : December 13, 2022


Attention : Sir Adrian Dy
Project : Dy International Bldg
Location : Gen. Miguel Malvar Street, Malate Manila

PROJECT TITLE : RENOVATION WORKS

BILL OF MATERIALS AND COST ESTIMATE


MATERIALS LABOR TOTAL AMOUNT
ITEM DESCRIPTION QTY UNIT
Unit Cost Total Cost Unit Cost Total Cost
63.35
SCOPE OF WORKS 231x477
617
Demolition of Existing Glass Window Stiffener 76.40 sq.m. 150.00 11,460.00 11,460.00
1 578
2 Rectification of Perimeter Window Openning 76.40 sq.m. 350.00 26,740.00 26,740.00
3 Installation of Window Fire Resistant Stiffener 76.40 sq.m. 550.00 42,020.00 42,020.00
4 Painting Works 76.40 sq.m. 250.00 19,100.00 19,100.00
5 Mobilization 1.00 lot 5,000.00
6 Demobilization 1.00 lot 5,000.00
total 900/lm
TOTAL DIRECT COST Final 800/m 109,320.00
MANAGEMENT COST (Overhead, Supervision & Profit) 10,932.00
2% WITHHOLDING TAX (SERVICES) 2,405.04
TOTAL PROJECT COST Paint care of sherwin 122,657.04

5 ficem boards
P1200

APPROVED BY :