Professional Documents
Culture Documents
Estimate
Mark up
1.00
MATERIAL LABOR TOTAL TOTAL TOTAL MATERIAL
ITEM NO. ITEM DESCRIPTION U.M. QTY.
UNIT COST UNIT COST MATERIAL COST LABOR COST AMOUNT UNIT COST
I DIRECT
1. Mobilization/Demobilization lot 1.00 35,000.00 8,000.00 35,000.00 8,000.00 43,000.00 35,000.00
2. Permit and Licenses
2.1 Building Permit lot 1.00 268,382.42 5,500.00 268,382.42 5,500.00 273,882.42 268,382.42
2.2 Occupancy Permit lot 1.00 280,000.00 4,500.00 280,000.00 4,500.00 284,500.00 280,000.00
2.3 Working Drawing lot 1.00 4,100.00 167,300.00 4,100.00 167,300.00 171,400.00 4,100.00
3. Bonds and Insurances
3.1 Surety Bond lot 1.00 - - - -
3.2 Performance Bond lot 1.00 - - - -
3.3 CARI lot 1.00 - - - -
3.4 Construction Bond lot 1.00 - - - -
4. Temporary Power & Water Consumtion During Costruction
4.1 Temporary Power Consumption lot 1.00 92,500.00 92,500.00 - 92,500.00 92,500.00
4.2 Temporary Water Consumption lot 1.00 33,500.00 33,500.00 - 33,500.00 33,500.00
5. Others
5.1 As Built Plans and Shop drawings with Signed and Sealed lot 1.00 4,100.00 87,500.00 4,100.00 87,500.00 91,600.00 4,100.00
5.2 Hauling out and disposal of Construction Debris and Garbage lot 1.00 48,000.00 45,000.00 48,000.00 45,000.00 93,000.00 48,000.00
5.3 Cleaning and Housekeeping lot 1.00 8,500.00 15,000.00 8,500.00 15,000.00 23,500.00 8,500.00
5.4 Temporary Facilities lot 1.00 58,000.00 30,000.00 58,000.00 30,000.00 88,000.00 58,000.00
5.5 Project Supervision lot 1.00 126,000.00 - 126,000.00 126,000.00 -
5.6 Safety and protection lot 1.00 24,000.00 13,000.00 24,000.00 13,000.00 37,000.00 24,000.00
6 Others (please specify)
6.1 Secondary Framing Support for Falling Materials and Dedris ( Optional) sqm - 2,222,222.00 300.00 3,333,333.00 - 3,333,333.00 2,222,222.00
Sub Total
1 Construction Tools
Drills/drill bits pcs.
SDS masonry drill bit 20mm diameter 14 inch length
Tapping tool/bits pcs.
Hole Saw (Metal) pcs.
65mm diameter
120mm diameter
Magnetic drill stand pcs.
Grinders pcs.
Cutting disc pcs. 75.00 50.00 15.00 3,750.00 1,125.00 4,875.00 50.00
Grinding disc pcs. 30.00 150.00 45.00 4,500.00 1,350.00 5,850.00 150.00
2 Construction Equipment
3 Tonner forklift - 1 week lot 1.00 102,000.00 30,600.00 102,000.00 30,600.00 132,600.00 102,000.00
3 Field Materials
(assorted bolts and nuts, fittings, etc.) lot 1.00 2.00 2.00 6.00
Hexagon Socket Head Cap Screw DIN 912-M10x20-8.8
Hexagon Socket Head Cap Screw DIN 912-M8x16-4.8
Fitting tube elbow 90 deg. Male part no. 153048
Belt HTD Part no. 1760-8M-20
Anchor bolt and chem set (HILTI) - 16MM x 140MML pcs. 1.00 1.80 1.80 2.00
8 EI / PSI Documents Printing (Colored) lot 1.00 15,000.00 15,000.00 15,000.00 15,000.00
9 Overhead ( home, office, & field support ) & Profit
Sub Total
IV CONCRETING WORKS
3,500 psi: 28 days 3/4 crashed gravel
ok Footing cu.m. #REF! 5,200.00 1,800.00 #REF! #REF! #REF! 5,200.00
ok Restoration of Chip Slab cu.m. #REF! 5,050.00 1,800.00 #REF! #REF! #REF! 5,050.00
Chip Floor -
ok Stiffiner Column and Lintel Beam cu.m. #REF! 4,600.00 2,000.00 #REF! #REF! #REF! 4,600.00
ok Third Floor Suspended Slab cu.m. 30.93 5,534.93 900.00 171,206.60 27,838.80 199,045.40 5,534.93
309.32
1.96
Sub Total
VI MASONRY WORKS
CHB Laying
Exterior Walls 6" CHB including rebar and mortars sq.m. 210.01 620.00 220.00 130,203.72 46,201.32 176,405.04 620.00
419.17
Interior Wall sq.m. 141.54 550.00 200.00 77,845.90 28,307.60 106,153.50 550.00
736.19
Interior Wall sq.m. 283.08 550.00 200.00 155,691.80 56,615.20 212,307.00 550.00
Sub Total
V FINISHING WORKS
A. Floor Finishes
Ground
Floor Tiles
ok Lobby sq.m. 31.64 1,050.00 300.00 33,222.00 9,492.00 42,714.00 1,050.00
MATERIAL LABOR TOTAL TOTAL TOTAL MATERIAL
ITEM NO. ITEM DESCRIPTION U.M. QTY.
UNIT COST UNIT COST MATERIAL COST LABOR COST AMOUNT UNIT COST
Epoxy Flooring
Second Floor
ok Extension Floor sq.m. 29.80 450.00 210.00 13,410.00 6,258.00 19,668.00 450.00
Loft
ok Flooring sqm 162.13 550.00 250.00 89,171.50 40,532.50 129,704.00 550.00
Second Floor
ok Floor sq.m. 1.96 950.00 300.00 1,862.00 588.00 2,450.00 950.00
ok Wall sq.m. 18.28 850.00 300.00 15,534.60 5,482.80 21,017.40 850.00
Third Floor
ok Floor sq.m. 17.28 950.00 300.00 16,416.00 5,184.00 21,600.00 950.00
ok Wall sq.m. 53.52 850.00 300.00 45,492.00 16,056.00 61,548.00 850.00
Maam Alexis Toilet
ok Floor sq.m. 3.40 1,050.00 300.00 3,570.00 1,020.00 4,590.00 1,050.00
ok Wall sq.m. 16.46 950.00 300.00 15,640.80 4,939.20 20,580.00 950.00
Waterproofing
ok Male and Female Toilet and Toilet and Bath sq.m. 27.79 650.00 180.00 18,063.50 5,002.20 23,065.70 650.00
ok Second Floor New Toilet sq.m. 1.96 650.00 180.00 1,274.00 352.80 1,626.80 650.00
ok Firewall Rightside sq.m. 231.72 550.00 180.00 127,448.64 41,710.46 169,159.10 550.00
Sub Total
VI STEEL WORKS
Sub Total
ok Concreting cum 4.10 5,200.00 1,800.00 21,318.02 7,379.32 28,697.34 5,200.00
ok Restoration of Works
Ceiling 2nd Floor sqm 35.70 670.00 530.00 23,919.00 18,921.00 42,840.00 670.00
Flooring 2nd Floor set 10.00 1,500.00 1,200.00 15,000.00 12,000.00 27,000.00 1,500.00
Roof @ Old Tank
ok Dismantling of Old Framing and Roof sqm 10.68 10.00 350.00 106.80 3,738.00 3,844.80 10.00
ok Installation of New Framing and Roof sqm 10.68 1,030.00 620.00 11,000.40 6,621.60 17,622.00 1,030.00
ok Inside Gutter ( stainless) pcs 4.00 3,500.00 850.00 14,000.00 3,400.00 17,400.00 3,500.00
ok Side Flashing pcs 7.00 3,200.00 750.00 22,400.00 5,250.00 27,650.00 3,200.00
Storm Drain Line (Optional)
ok Chipping sqm 39.74 - - - - - -
ok Excavation cum 24.22 3,200.00 750.00 77,488.38 18,161.34 95,649.72 3,200.00
ok 250mm PVC Pipe pcs 19.00 3,876.00 750.00 73,644.00 14,250.00 87,894.00 3,876.00
ok Catch Basin sets 13.00 6,043.40 2,419.50 78,564.20 31,453.50 110,017.70 6,043.40
ok Extension of Old Downspout pcs 24.00 750.00 450.00 18,000.00 10,800.00 28,800.00 750.00
ok Restoration of Chip Floor cum 3.97 5,200.00 1,800.00 20,663.66 7,152.80 27,816.46 5,200.00
Sub Total
- - - -
- - - -
- - - -
- - - -
- 92,500.00 - 92,500.00
- 33,500.00 - 33,500.00
300.00 - - -
1,357,882.42
15,000.00 15,000.00
158,325.00
#REF!
796,704.26
517,723.00
#REF!
1,800.00 21,318.02 7,379.32 28,697.34
- - - -
750.00 77,488.38 18,161.34 95,649.72
750.00 73,644.00 14,250.00 87,894.00
2,419.50 78,564.20 31,453.50 110,017.70
450.00 18,000.00 10,800.00 28,800.00
1,800.00 20,663.66 7,152.80 27,816.46
515,232.02
#REF!