Professional Documents
Culture Documents
APRACN3 - ARC151
Name GROUP 2 - DE PAZ ARCHITECTURE + DESIGN STUDIO Professor
Ar. Hilario P. Gutierrez
DETAILED ESTIMATES
Materials Labor & Equipment
Item Description Qty. Unit Unit Unit Total
Cost Cost
Cost Cost
I. General Requirements / Siteworks
1.0 Mobilization/Demobilization Works
1.1 Mobilization/Demobilization 3 T.L. 5,000.00
5,000.00 15,000.00 15,000.00 30,000.00
1.2 Layout & Batterboards 147 sqm
120.00 17,640.00 120.00 17,640.00 35,280.00
1.3 Building Permits lot By Owner
- -
1.4 Occupancy Permit lot By Owner
- -
1.5 Haul Debris/Excess Materials 7 T.L. 5,000.00
- 35,000.00 35,000.00
Subtotal
32,640.00 67,640.00 100,280.00
2.0 Bonds & Insurances
2.1 Homeowner's Asso. Bond -
- - -
2.2 Construction Bond/Permits -
- - -
2.3 Delivery Truck Pass 28 T.L.
- 1,000.00 28,000.00 28,000.00
2.4 Worker Insurance/Clearance/IDs 23 pax
- 450.00 10,350.00 10,350.00
Subtotal
- 38,350.00 38,350.00
3.0 Temporary Facilities
3.1 Bunkhouse/Warehouse Rental 1 lot 12,000.00 12,000.00 - 12,000.00
3.2 Toilet Facilities 3 lot
3,500.00 10,500.00 - 10,500.00
3.3 Accommodation mos.
- - -
3.4 Personal Protective Equipment 23 sets 4,500.00
- 80,500.00 80,500.00
3.5 Electricity 8 mos. 3,500.00
- 24,000.00 24,000.00
3.6 Water 8 mos. 3,000.00
- 5,600.00 5,600.00
3.7 Communication 8 mos.
- 700.00 5,600.00 5,600.00
Subtotal
22,500.00 115,700.00 138,200.00
4.0 Earthworks
4.1 Excavations
F-1 21.473 cum
- - -
F-2 71.81 cum
- -
F-3 12.923 cum
- - -
TB-1 0.534 cum
- - -
SV 30 cum
- - -
CB 3 cum
- - -
DP cum
- - -
4.2 Backfill/On-fill 79
200.00 15,800.00 -
4.3 Gravel Fill 14 cum -
700.00 9,800.00 9,800.00
4.4 Compaction 91 cum -
300.00 27,300.00 27,300.00
Subtotal
25,600.00 27,300.00 37,100.00
Cement 20 bags -
650.00 13,000.00 13,000.00
Sand 2 cum -
8.50 17.00 17.00
10 mm Ø def bars 10 pcs -
130.00 1,300.00 1,300.00
Ga 18 GI Wire 4 kg -
70.00 280.00 280.00
2.4 Concrete flooring topping 22 cum - - -
Cement 10 bags -
650.00 6,500.00 6,500.00
Sand 4 cum -
8.50 34.00 34.00
Subtotal -
486,189.00 486,189.00
3.0 Reinforcing Steel Bars
3.1 Footings - - -
10 mm Ø def bars 51 pcs -
130.00 6,630.00 6,630.00
16 mm Ø def bars 91 pcs -
340.00 30,940.00 30,940.00
Ga 18 GI Wire 12 kg -
70.00 840.00 840.00
3.2 Columns/Pedestals - - -
10 mm Ø def bars 125 pcs -
130.00 16,250.00 16,250.00
16 mm Ø def bars 88 pcs -
340.00 29,920.00 29,920.00
Ga 18 GI Wire 17 kg -
70.00 1,190.00 1,190.00
3.3 Slab on-fill/on-grade - - -
10 mm Ø def bars 31 pcs -
130.00 4,030.00 4,030.00
Ga 18 GI Wire 9 kg -
70.00 630.00 630.00
3.4 Beams - - -
10 mm Ø def bars 50 pcs -
130.00 6,500.00 6,500.00
12 mm Ø def bars 30 pcs -
200.00 6,000.00 6,000.00
16 mm Ø def bars 100 pcs -
340.00 34,000.00 34,000.00
Equipment Rental 15 days -
500.00 7,500.00 7,500.00
3.5 Miscellaneous Items - - -
10 mm Ø def bars 30 pcs - - -
12 mm Ø def bars 20 pcs - - -
Ga 18 GI Wire 3 kg - - -
Subtotal
136,930.00 7,500.00 144,430.00
4.0 Formworks & Scaffolds
4.1 Columns
1/2" thick Plywood 50 sheets -
847.00 42,350.00 42,350.00
Nails (assorted sizes) 30 kg -
70.00 2,100.00 2,100.00
Consumables lot - 43,000.00
- -
Subtotal -
44,450.00 44,450.00
5.0 Roof Framing
5.1 Steel Framing & Purlins
1/4 x 2 x 2 Angle bars 200 pcs -
700.00 140,000.00 140,000.00
1/4 x 1.5 x 1.5 Angle bars 220 pcs -
460.00 101,200.00 101,200.00