You are on page 1of 1

Date : May 23, 2023

Attention : Mr. Jack Valerio


Thru :
Project : Proposed tugegarao Public Market Sewage Treatment Plant
Location : Tugegarao City, Isabela Philippines
Owner :
Subject : Proposed Supply and Installation of Electro-Mechanical of Sewage Treatment Plant

A. SCOPE OF WORKS
UNIT RATE
ITEM NO. ITEM DESCRIPTION UNIT QTY TOTAL AMOUNT
MATERIAL LABOR OTHERS TOTAL
I Electrical Works
Supply and Installation 1.00 LOT 185,000.00 55,500.00 11,100.00 251,600.00 251,600.00
Main Control Panel for STP
Features:
Equipped by overload Relay, Voltage Regulator,
Magnetic Contactor, Stop/Start Button and light
indicator,Trip light Indicator
Main: 150 AT/AF, 2 pole, 25Kaic
2- 40AT/AF, 2 pole, 25Kaic (Roots Blower w/ timer)
2- 20AT/AF, 2 pole, 25Kaic (Transfer Pump Controlled
by Float Switch)
2- 20AT/AF, 2 pole, 25Kaic (Ozone Generator w/ timer)
2- 20AT/AF, 2 pole, 25Kaic (Re-Circulation Pump w/
timer)
2- 25AT/AF, 2 pole, 25Kaic (Discharge Pump Controlled
by Float Switch)
sub-total II 251,600.00
II Multi Media Depth Filter
Manual (Parallel Connection) Supply Only
FRP Tank 24x72 TB 4” MB Pentair with riser tube and 3.00 LOT 53,000.00 - 53,000.00 159,000.00
bottom lateral
Runxin Manual Valve Filter With top strainer 3.00 LOT 45,000.00 - 45,000.00 135,000.00
Anthracite 25kgs/bag 12x40 24.00 LOT 2,500.00 - 2,500.00 60,000.00
Gravel #5 25 kgs/bag 12.00 LOT 680.00 - 680.00 8,160.00
Gravel #10 25 kgs/bag 12.00 LOT 680.00 - 680.00 8,160.00
Silica Sand 25 kgs/bag 15.00 LOT 880.00 - 880.00 13,200.00
Monitoring Gauges 3.00 LOT 1,200.00 - 1,200.00 3,600.00
Horizontal Pump 1.5hp 220V, 60Hz, Single phase 2.00 LOT 65,000.00 - 65,000.00 130,000.00
sub-total IV 517,120.00
SUB-TOTAL PROJECT COST 768,720.00

INDIRECT COST (II-III) 768,720.00


TOTAL PROJECT COST 768,720.00

B. TOTAL AMOUNT OF THIS OFFER: PHP 768,720.00


C. AMOUNT IN WORDS: Seven hundred sixty-eigth thousand, seven hundred twenty-pesos and 00/100 only.
D. TERMS OF PAYMENT: 40% DOWN-PAYMENT , BALANCE SHALL BE PAID IN PROGRESS BILLING BASED ON ACCOMPLISHMENT.
E. WORK COMPLETION: Sixty (60) - Ninety (90) calendar days.
F. VALIDITY OF QUOTATION: THIRTY (30) CALENDAR DAYS FROM THE DATE OF THIS QUOTATION
G. WARRANTY: One (1) year on mechanical equipment and workmanship against factory defects.
NOTE: If the equipment / device are mishandled, mis-used or causes human error. Unbalanced or improper power supply
the warranty will be void, Client will shoulder freight cost upon warranty claims.
F. Value Added Tax are excluded in this quotation.
Note:
1 Client should provide area / facility for materials and equipment storage area.
2 Electricity and water consumption shoulder by the client.
3 The Contractor will provide Municipal Health Certificate only (if needed), For antigen/Swab test
the client will shoulder the payment.
4 Permits / Entry pass fees shoulder by the client (if needed)

Prepared by : Conformed by :

John Axl Lajom