TOTAL 1,495,115,000.00
PPN 10% 149,511,500.00
GRAND TOTAL 1,644,626,500.00
ALOYSIUS RONI
DIREKTUR
1 / 10
MATERIAL TAKE OFF
MTO SITE FACILITIES EXISTING TO LAY DOWN
1 Install Transformer 20kV/400V, 150kVA 1.00 Ea 0.00 0.00 7,500,000.00 7,500,000.00 7,500,000.00 JASA
2 Install Panel MV Distribution Panel (MVP01) 1.00 Ea 0.00 0.00 6,000,000.00 6,000,000.00 6,000,000.00 JASA
3 Pulling Kabel 20kV, NA2XSEFGby 3c x 300 Sqmm 2,000.00 Mtr 0.00 0.00 43,000.00 86,000,000.00 86,000,000.00 JASA
4 Pulling Kabel NYY 4C x 70 Sqmm 50.00 Mtr 0.00 0.00 25,000.00 1,250,000.00 1,250,000.00 JASA
5 Termination Kit 20 kV untuk kabel 3c x 300 sqmm 4.00 Set 5,000,000.00 20,000,000.00 1,800,000.00 7,200,000.00 27,200,000.00 JASA+MATERIAL
6 Install Genset 80 Kva 1.00 Ea 0.00 0.00 25,000,000.00 25,000,000.00 25,000,000.00 JASA
7 Install Change Over Switch (COS) 200A, 4 pole 1.00 Ea 0.00 0.00 12,000,000.00 12,000,000.00 12,000,000.00 JASA
8 Install Main Panel Genset 80 kVA (600x800x250) (1 Ea) 1.00 Ea 0.00 0.00 12,000,000.00 12,000,000.00 12,000,000.00 JASA
Opsi 1
9 Cable Tray W200 c/w cover tray, clamp cover 670.00 Ea 470,000.00 314,900,000.00 80,000.00 53,600,000.00 368,500,000.00 JASA+MATERIAL
10 Jointing Tray c/w Bolt and Nut 1,340.00 Ea 27,000.00 36,180,000.00 5,000.00 6,700,000.00 42,880,000.00 JASA+MATERIAL
11 UNP 100 200.00 Btg 295,000.00 59,000,000.00 120,000.00 24,000,000.00 83,000,000.00 JASA+MATERIAL
12 Hi-pot Test 1.00 Lot 0.00 0.00 3,500,000.00 3,500,000.00 3,500,000.00 JASA
Opsi 2
13 Exavation dan back fill 2,000.00 Mtr 0.00 0.00 90,000.00 180,000,000.00 180,000,000.00 JASA
14 Install Tile concrete 1.00 Lot 180,000,000.00 180,000,000.00 70,000,000.00 70,000,000.00 250,000,000.00 JASA+MATERIAL
15 Hi-pot Test 1.00 Lot 0.00 0.00 3,500,000.00 3,500,000.00 3,500,000.00 JASA
TOTAL 610,080,000 498,250,000 1,108,330,000.00
ALOYSIUS RONI
2 / 10
MATERIAL TAKE OFF
MTO SITE FACILITIES EXISTING TO LAY DOWN
3 / 10
MATERIAL TAKE OFF
MTO SITE FACILITIES WIKA
1 Install Panel Lighting (Terlampir Panel Schedule) 1.00 Ea 3,500,000.00 3,500,000.00 2,000,000.00 2,000,000.00 5,500,000.00
2 Lampu TL-2x36W 30.00 Titik 595,000.00 17,850,000.00 180,000.00 5,400,000.00 23,250,000.00
3 Lampu TL-1x36W 14.00 Titik 520,000.00 7,280,000.00 180,000.00 2,520,000.00 9,800,000.00
4 Downlight 36W 12.00 Titik 800,000.00 9,600,000.00 180,000.00 2,160,000.00 11,760,000.00
5 Exhaust Fan 8.00 Ea 635,000.00 5,080,000.00 200,000.00 1,600,000.00 6,680,000.00
6 AC Indoor 2 PK 10.00 Ea 6,885,000.00 68,850,000.00 435,000.00 4,350,000.00 73,200,000.00
7 AC Indoor 1 PK 5.00 Ea 5,585,000.00 27,925,000.00 435,000.00 2,175,000.00 30,100,000.00
8 Receptacle Inbow 16A 28.00 Ea 170,000.00 4,760,000.00 180,000.00 5,040,000.00 9,800,000.00
9 Kabel NYY 4C x 50 Sqmm 70.00 Mtr 405,000.00 28,350,000.00 45,000.00 3,150,000.00 31,500,000.00
10 Kabel Grounding, 1c x 50 sqmm 100.00 Mtr 100,000.00 10,000,000.00 30,000.00 3,000,000.00 13,000,000.00
11 Grounding Rod, Length 3 m, c/w clamp rod 10.00 Ea 1,150,000.00 11,500,000.00 350,000.00 3,500,000.00 15,000,000.00
ALOYSIUS RONI
DIREKTUR
4 / 10
MATERIAL TAKE OFF
MTO SITE FACILITIES WIKA
REMARKS
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
5 / 10
MATERIAL TAKE OFF
MTO SITE FACILITIES OFFICE KAN
1 Install Panel Lighting (Terlampir Panel Schedule) 1.00 Ea 3,500,000.00 3,500,000.00 2,000,000.00 2,000,000.00 5,500,000.00
2 Lampu TL-2x36W 12.00 Titik 595,000.00 7,140,000.00 180,000.00 2,160,000.00 9,300,000.00
3 Lampu TL-1x36W 4.00 Titik 520,000.00 2,080,000.00 180,000.00 720,000.00 2,800,000.00
4 Downlight 36W 6.00 Titik 800,000.00 4,800,000.00 180,000.00 1,080,000.00 5,880,000.00
5 Exhaust Fan 5.00 Ea 635,000.00 3,175,000.00 200,000.00 1,000,000.00 4,175,000.00
6 AC Indoor 2 PK 5.00 Ea 6,885,000.00 34,425,000.00 435,000.00 2,175,000.00 36,600,000.00
7 AC Indoor 1 PK 2.00 Ea 5,585,000.00 11,170,000.00 435,000.00 870,000.00 12,040,000.00
8 Receptacle Inbow 16A 14.00 Ea 170,000.00 2,380,000.00 180,000.00 2,520,000.00 4,900,000.00
9 Kabel NYY 3C x 25 Sqmm 30.00 Mtr 190,000.00 5,700,000.00 30,000.00 900,000.00 6,600,000.00
10 Kabel Grounding, 1c x 50 sqmm 60.00 Mtr 100,000.00 6,000,000.00 30,000.00 1,800,000.00 7,800,000.00
11 Grounding Rod, Length 3 m, c/w clamp rod 2.00 Ea 1,150,000.00 2,300,000.00 350,000.00 700,000.00 3,000,000.00
ALOYSIUS RONI
DIREKTUR
6 / 10
MATERIAL TAKE OFF
MTO SITE FACILITIES OFFICE KAN
REMARKS
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
7 / 10
Bontang, 22 APRIL 2019
SKEDUL PELAKSANAAN CV CAHAYA SOLO
PEKERJAA : PENGECATAN TOWER LAMPU STADION MULAWARMAN & BTS PT. PUPUK KALTIM
SCHEDULE : 60 (ENAM PULUH) HARI KALENDER
LOCATION : PT. PUPUK KALIANTAN TIMUR
HJ. TENRI
BOBOT BULAN KE-1 BULAN KE-4 REMARKS
NO URAIAN PEKERJAAN
[%] 1 2 3 4 1 2 3 4
1 Install Panel Lighting (Terlampir Panel Schedule) 1.00 Ea 3,500,000.00 3,500,000.00 2,000,000.00 2,000,000.00 5,500,000.00
2 Lampu TL-2x36W 6.00 Titik 595,000.00 3,570,000.00 180,000.00 1,080,000.00 4,650,000.00
3 Downlight 36W 5.00 Titik 800,000.00 4,000,000.00 180,000.00 900,000.00 4,900,000.00
4 Exhaust Fan 2.00 Ea 635,000.00 1,270,000.00 200,000.00 400,000.00 1,670,000.00
5 AC Indoor 2 PK 2.00 Ea 6,885,000.00 13,770,000.00 435,000.00 870,000.00 14,640,000.00
6 AC Indoor 1 PK 2.00 Ea 5,585,000.00 11,170,000.00 435,000.00 870,000.00 12,040,000.00
7 Receptacle Inbow 16A 1.00 Ea 170,000.00 170,000.00 180,000.00 180,000.00 350,000.00
8 Kabel NYY 3C x 10 Sqmm 30.00 Mtr 110,000.00 3,300,000.00 25,000.00 750,000.00 4,050,000.00
9 Kabel Grounding, 1c x 50 sqmm 60.00 Mtr 100,000.00 6,000,000.00 30,000.00 1,800,000.00 7,800,000.00
10 Grounding Rod, Length 3 m, c/w clamp rod 2.00 Ea 1,150,000.00 2,300,000.00 350,000.00 700,000.00 3,000,000.00
TOTAL 49,050,000 9,550,000 58,600,000.00
ALOYSIUS RONI
DIREKTUR
9 / 10
MATERIAL TAKE OFF
MTO SITE FACILITIES MUSHOLA
REMARKS
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL
JASA+MATERIAL