PEKERJAAN DRAINAGE
1. Galian untuk drainage per m3
0,2142 jam Mandor 350.000,00 74.970,00 0 74.970,00
0,0535 jam Pekerja 155.000,00 8.292,50 0 8.292,50
0,0535 jam Excavator 357.000,00 0 19.099,50 19.099,50
0,0955 jam Dumptruck 325.000,00 0 31.037,50 31.037,50
1,0000 LS Alat bantu 22.500,00 0 22.500,00 22.500,00
155.899,50
Nilai Pek Galian Tanah Saluran : M3 655.039.811,16
4.201,68
Total 23.375.299.411,16
Ppn 11 % 2.571.282.935,23
Grand Total 25.946.582.346,39
Dibulatkan 25.946.000.000,00
Ir.BERNAT HEHEGA