BILL OF QUANTITY

PEKERJAAN DRAINAGE FOREST CITY


" THE OKURA INTERNATIONAL BUSINESS CITY "
KOTA MANDIRI OKURA PEKANBARU
KOTA PEKANBARU PROVINSI RIAU INDONESIA
JUM SAT URAIAN HARGA SATUAN ( Rp ) UPAH KERJA ( Rp ) HARGA MATERIAL ( Rp ) TOTAL ( Rp )

PEKERJAAN DRAINAGE
1. Galian untuk drainage per m3
0,2142 jam Mandor 350.000,00 74.970,00 0 74.970,00
0,0535 jam Pekerja 155.000,00 8.292,50 0 8.292,50
0,0535 jam Excavator 357.000,00 0 19.099,50 19.099,50
0,0955 jam Dumptruck 325.000,00 0 31.037,50 31.037,50
1,0000 LS Alat bantu 22.500,00 0 22.500,00 22.500,00
155.899,50
Nilai Pek Galian Tanah Saluran : M3 655.039.811,16
4.201,68

3. Beton Pracetak (BOX CULVERT) penutup beton U 600x800 cm tebal 20 cm


1,0000 hari Pekerja 155.500,00 155.500,00 155.500,00
0,1 hari Tukang 210.500,00 21.050,00 21.050,00
0,1 hari Mandor 350.000,00 35.000,00 35.000,00
1,0 m Box beton precast 80X80X100 cm 2.365.000,00 2.365.000,00 2.365.000,00
0,97 m3 Kerikil kali di saring 285.000,00 276.450,00 276.450,00
0,4555 m3 Pasir beton 250.000,00 113.875,00 113.875,00
5,7222 kg semen 115.000,00 658.053,00 658.053,00
15,000 kg Pembesian - -
0,2 m3 Beton K300 - -
0,4444 jam Concrete mixer - -
0,4444 jam concrete vibrator - -
0,4444 jam Pompa air 75.000,00 33.330,00 33.330,00
0,28 LS Alat bantu 22.500,00 6.300,00 6.300,00
22.500,00 3.664.558,00
Nilai Pek Saluran Precast : 6.200,0 M' 22.720.259.600,00

Total 23.375.299.411,16
Ppn 11 % 2.571.282.935,23
Grand Total 25.946.582.346,39
Dibulatkan 25.946.000.000,00

Jakarta , 27 Maret 2023


PT.RIZKI KAPITAL MANDIRI INDONESIA