LOCATION :MotoWorld
OWNER : Outcomm Inc.
SUBJECT : Cost Breakdown P
DATE : July 14, 2023
ITEM NO. ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST
SCOPE OF WORKS
Electrical Wiring
Termination and testing
I GENERAL REQUIREMENTS
Mobilization/Demobilization 1 lot 0.00
Insurance 1 lot 0.00
SUB-TOTAL ITEM I = 0.00
III ACRYLIC LOGO (OPTION 2)
acrylic white diffuser 5mm 1 sheet 4,050 4,050.00
Power Supply 12volts 100 watts 1 set 1,200 1,200.00
waterproof flexible LED strip 7.2
3
watts/meter mtrs 350 1,050.00
Cyno paste 1 pc 120 120.00
aluminum bracket 1 lot 1,500 1,500.00
Royal Chord w/ Male plug 1 set 500 500.00
labor cost 1 lot 3,500 3,500.00
SUB-TOTAL ITEM III = 11,920.00
General Requirements 0.00
Total Material & Labor Cost 11,920.00
5% Contingency Cost 596.00
12% VAT 1,430.40
TOTAL PROJECT COST 13,946.40