Duration
Sl No Activities In Months

A Municipality Approval ,Structural Design & Drgs 5


1 Preparation of final drgs and submission to Municipality 1

2 Getting Municipal Approval 3

3 Preparation of Tender Document 1

4 Soil Investigation/ Review & Deciding Foundation Type 1

5 Floating Tender and Getting Quotations 1

6 Finalisation of Civil Contract 1

7 Relocation of Equipments and demolition of existing Structures 2

8 Structural Design Drgs from Architect 3

B Civil Construction Works 15

9 Excavation for foundation 1

10 Foundations 1

11 Columns upto Plinth Beam 1

12 Back Filling & Compaction upto Plinth level 1

13 Plinth Beam 1

14 RCC Flooring at Plinth level 0.5

15 Columns upto Ground Floor Roof 1

16 Slab and Beam at First Floor 1

17 Columns upto Second Floor 1

18 Slab and Beam at Second Floor 1


19 Columns upto Third Floor 1

20 Slab and beam at Third Floor 1

21 Columns upto Third Floor Roof (Terrace Slab) 1

22 Slab and Beam of Terrace Slab 1

23 Weathering Course for Terrace 1

24 Finishing Works-Block Work in Ground Floor 1

25 Block work in First Floor 1

26 Block work in Second Floor 1

27 Block work in Third Floor 1

28 Doors Rolling Shutters and Windows Fixing 4

29 Tiles in Ground Floor 1

30 Tiles in First Floor 1

31 Tiles in Second Floor 1

32 Tiles in third floor 1

33 Painting and Other finishing Works 3

34 Lift machine room and over head water Tank 2

35 Plumbing and Sewerage Connections/Fittings 3

C Electrical Works/Equipments/Furnitures 3

36 Electrical cables and Fittings 3

37 Installation of Lift and commisioning 1

38 Furnitures-Ordering and Installing 3

39 Shifting Old Equipments/Procuring and Installing Computers - 3


and Other Video Conf Equipments
40 Approval from Sewerage Board/Water Supply/Electricity Board 2
Statutory Bodies approval/Obtaining Completion Certificate

D Upgrading Infrastruture 3
Roads
Street Lights
Storm water drains
Manipal University New Building
Duration

Jun-21 July Aug Sept Oct Nov Dec Jan-22 Feb March
Dated 9th March 21
on

Apr May June July Aug Sept Oct Nov Dec-22 Jan-23
Remarks
Feb March Apr May Jun-23
Inauguration
of the building
on 1st Oct 2019