You are on page 1of 19

3

SKYLINE BUILDERS PALARIVATTOM

SKYLINE POLARIS

Skyline Polaris (jawahar Nagar, Kadavanthra,Kochi)


3

SKYLINE POLARIS

SKYLINE POLARIS
 Head of regional officer – Bibin Sir
 Deputy manager projects – Suvin Paul Sir
 Deputy manager projects – Sindhu Mam
 Site engineer – Mahesh Sir
 Trainee Engineer – Joyel Sir
 Material Supervisor - Arun Sir
3

Date of site visit 08-11-2021

No of students participated
 Chithra C
 Aleena Thomas
 Arun P M
 Athif K
 Sreerag P

Project name : Skyline : Polaris Jawahar Nagar, Kadavanthra,


kochi

Project started on :2018

The apartment are following configuration:


o 3BHK,4BHK apartments
o The size in between 1713 Sq.ft. to 2230 sq.ft (carpet
Area:1188 sq.ft -1579 sq.ft
o Air -conditioned luxury apartment
3

INTRODUCTION

Skyline Builders presents its luxury apartment project -


Skyline Polaris. Set in a quiet and serene location in Jawahar
Nagar, Kadavanthra, Kochi, this Air-conditioned luxury
apartment project takes you to a comfortable corner in the
best part of the city, close to everything that a modern
lifestyle demands. Be it the best supermarkets, hospitals and
schools, Jawahar Nagar has everything you desire to live the
dream lifestyle. Skyline Polaris is thoughtfully and
intelligently designed to give you the widest space for your
comfort zone. This luxury apartment project offers 47 comfy
homes with 3&4 BHK options ranging from 1713 sq.ft to 2230
sq.ft(Carpet Area: 1188 sq.ft-1579 sq.ft). Skyline Polaris gives
you the best of luxury amenities, taking you one step closer
to a higher living.
3

Day 1:08-11-2021
HEIGHT
 Ground Floor to First Floor =4.10m
 First Floor to Second Floor =3.20m
 Third Floor to Thirteenth Floor = 3x11=33m
 13 Apartments
 47 flat
 4 Type- A B C D
 A(Option 1 and 2)
 4BHK
 B C D - 3BHK

BASEMENT :
Pump room, Parking -2 and 4 Wheelers, Collection
pit ,STP(Soil Treatment Plant) Sump tank[ 1) Domestic, 2)
Rain water harvesting, 3) Flesh, 4) Fire
GROUND FLOOR:
Lobby, Main Lobby, Panal Room, Toilet ( Women, Gents,
Handicap), DG, Driver's rest room, Fire control.
FIRST FLOOR :
3

A flat and B flat , Swimming pool, Gym, Game room,


Health club, Pergola, Party area.
2ND TO 10TH FLOOR
A ,B ,C ,D Flat

11TH 12TH and 13 FLOOR


A,C,D Flats

13TH FLOOR
Terrace , 2 Pergola , Over head tank
3

Day 2:09-11-2021
QUALITY STANDARDS

SEQUENCE OF ACTIVITIES FOR STRUCTURAL WORKS

1 PILE SETOUTING
2 PILING
3 PILE CHIPPING
4 PILE INTERGRITY
5 PCC @PILECAP, PLINTH BEAM & LIFT WELL
6 PILE CAP, PLINTH BEAM, COLUMN & LIFT WELL STEEL
WORK
7 PILE CAP. PLINTH BEAM & LIFT WELL SHUTTERING
8 PILE CAP, PLINTH
9 FLOOR PCC
10 BASEMENT FLOOR SLAB & LIFT WELL CASTING
11 LIFT WALL & COLUMN SHOE
12 LIFT WALL, COLUMN STEEL & SHUTTERING WORK
3

13 LIFT WALL & COLUMN CASTING


14 SLAB & BEAM SHUTTERING & STEEL WORK
15 SLAB & BEAM CASTING
16 ROOF ELEMENTS (MACHINE ROOM & OVER HEAD TANK
ETC...)
17 ROOF PARAPET

SEQUENCE OF ACTIVITIES FOR APARTMENT FINISHING

1 NYLON THREAD PULLING IN CEILING →


2 UTTON MARK FIXING FOR CEILING PLASTERING →
3 CEILING PLASTERING →
4 SETOUT FOR MASONRY →
5 MASONRY →
6 COUNTER SLABS (If RCC slab providing) →
7 BOTTON MARK FIXING FOR WALL PLASTERING
8 BALCONY HANDRAIL FIXING →
9 DOOR FRAMES →
10 ELECTRICAL MODULE BOX & DB FIXING →
11 ELECTRICAL WALL CHASINGS →
12 NYLON THREAD PULLING →
3

13 WALL PLASTERING INCLUDING BALCONY/TOILET


14 BUTTON MARK FIXING FOR WALL TILE →
15 CORE FOR PLUMBING FIRE AND BALCONY →
16 PIDE FIXING→
17 PRIMER AT TOILET CEILING →
18 PLUMBING CONCEALED WORKS →
19 PRESSURE TEST FOR PLUMBING →
20 FILLING THE CONCEALED PIPES →
21 LEDGE WALL →
22 WATER PROOFING INCLUDING BALCONY →
23 LEAK TEST →
24 PROTECTION PLASTERING →
25 PLUMBING SUSPENDED LINE FIXING→
26 FIRE FIGHTING WORKS →
27 PRESSURE TEST FOR FIRE FIGHTING →
28 1ST & 2ND COAT PUTTY APPLICATION →
29 PRIMER AT LIVING/DINING/BED ROOMS/KITCHEN & WIA
CEILING →
30 CORNICE/GYPSUM FIXING →
31 PUTTY AND PRIMER APPLICATION FOR GYPSUM →
32 1ST COAT PAINTING FOR CEILING →
33 KITCHEN/TOILET/DINING COUNTER G.I FRAME FIXING
3

34 GRANITE COUNTER FIXING AT KITCHEN / TOILET/


DINING →
35 TOILET DADO COUNTER TOP DADO→
36 KITCHEN DADO →
37 FALSE CEILING COMPLETION FOR TOILET/LIVING/DINING

38 EXTERNAL PLASTERING COMPLETED →
39 RAIN WATER PIPE FIXING→
40 BALCONY AND TOILET SCREEDING→
41 HAUNCH WALL MASONRY AND PLASTERING →
42 ALUMINIUM WINDOW FIXING →
43 GRILL FIXING →
44 FRONT DOOR SHUTTER FIXING →
45 ELECTRICAL WIRE PULLING & DB DRESSING →
46 MAIN FLOORING &SKIRTING INCLUDING→
47 TOILET FLOORING →
48 TILE WASHING →
49 TILE PROTECTION →
50 UPVC FRAME FIXING →
51 1ST COAT PAINT ON WALLS →
52 SWITCHES & DB FIXING →
53 INTERNAL DOOR SHUTTERS FIXING →
3

54 CP AND SANITARY →
55 INTERNAL & EXTERNAL WALL FINAL COAT PAINTING→
56 TILE CLEANING & POINTING→
Our STD Final Engg Inspection Procedure
(Process to Ensure Zero Defect Product)

57 Engr-in-charge taken for all Snags completion of


rectification and ready for SIC Inspection
58 Site In Charge ensure for all snags attended and
ready for marketing inspection
59 C.R Inspection note the all sangs attended to SIC and Iform
to ready for B.C.E/Mgr, Q.C Inspection
60 B.C.E/Mgr.Q.C Certified by All engineering and marketing
comments are rectified, apartment is defect free and fit for
handing over

61 Branch Manager Approved for product Release....


62 FINAL CLEANING →
63 CLIENT INSPECTION & HAND OVER
3

Day 3:10-11-2021
WORK IN PROGRESS
Things we noted
 STP= Soil Treatment Plant
 118 Pile
 Pile Depth: 46m
 Soil type of site: Black soil area
 Sunken
 Cranking
 Mix Design: M25 Concrete
 Steel fe500D

BEAM DESIGN AND REINFORCEMENT CHECK


If wind load is designed by Structural Engineer, First
cast the column up to half portion. Next slab beam cast by
top bar lap development length. Finally cast slab and
column.

STRUCTURAL DESIGNS
We go through the plans of structural designs of
drawings .Structural designs is very important for a project.
Structural designing provide all the crucial information about
3

foundations, walls,
floors, roof types, steep beams,
material quality, and more to
ensure that the structure
is built to be safe and sound.
3

Day 4:11-11-2021

Basement
Pressure grouting-pressuring pumb
Ramp work in process for rebar fixing
Reinforcement (slab) work in progress
STP -2' width pipeline trench

First floor
Pergola reinforcement work & column shuttering
External wall plastering work in progress

Second floor
Water proofing (Dr fixit) -liquid + powder
Floor cleaning
Sanitary fittings
Skerting piece work & cutting
3

Third floor

Flooring work (wall tile - main floor work)

Fourth floor
Water proofing coat

Fifth floor
Wiring work

Sixth floor
Scaffolding
Framework - lift
Wiring work

Seventh floor
Tile work -bathroom,main floor

Eighth floor
Kerb plastering
3

Plumbing

Ninth floor
Wiring
Plumbing
Bathroom flush tank fixing

Tenth floor
Wiring
Painting - fire ducts

Eleventh floor
Pergola -plastering

Twelveth floor
Lift work
Plumbing work -bathroom

Thirteenth floor
Pergola top finishing
3

Day

5:12-11-2021
 Visited sample room
(2A)
 Visited whole site and
works.
3
3

CONCLUTION
The training section at a live firth made us now the practical
of various theories that are thought in the class room. It
made aware of the planning and activities adopted at site.
Training was very beautiful in each requirement to read
building in a very short span of time.

You might also like