1.GENERAL
For designing the framed structure we have followed the limit state method
of design and referred to IS 456-2000, SP 16 and IS 875-1987.
6
1.2 SEQUENCE
The sequence of process that we have followed in our project is:
Plan
Load calculation
Structural analysis
Structural design
Preparation of structural drawing and detailing
2.3 SPECIFICTION
2.3.2Footing concrete
The footing will be of M20 grade of concrete. The P.C.C 1:4:8 mix
is used for a plain surface for the sensing of footing concrete.
4.3.4Plinth beam
Plinth beam made in M20 grade of concrete, 230 mm x 230 mm size
provided over the basement all round.
5.3.5Basement
7
The basement is filled with earth to a depth of 100 mm and clear sand to a
depth of 450 mm.
1.3.6Super structure
The super structure is to be 1st class B.W in C.M 1:5, 230 mm
thick
2.3.7Plastering
All walls including basement will be plastered smooth with C.M
1:5 externally and internally, 12 mm thick.
3.3.8Roofing
The roofing will be of M20 grade of concrete, 120 mm thick flat
slab and plastered smooth with C.M 1:3, 10 mm thick.
4.3.9Flooring
The flooring will be of M20 grade of concrete, flooring finished
with granite tile in C.M 1:3, 20 mm thick for all rooms and tiles is used for toilets.
6.3.11Lintel
R.C.C lintel will be provided with 1:1.5:3 mix, 150 mm thick cut
lintel. All external openings are provided with lintel cum sunshade.
1.3.12Staircase
Stair will be of M20 grade of concrete. Rise of 170 mm and
thread of 250 mm with a landing of 1025 mm.
2.3.15Electrification
Electrical network is formed within the structure itself. Ordinary
plastics tubes are used to form the network of electricity which conveys the
electrical power from the origin to destination during the time of converting
itself.
3.3.16Sanitary Fittings
A separate pipe network was used for the purpose of sanitation.
Concrete pipe are used to dispose the waste water from apartment.
1.4Plan details
10
11
12
FIRST FLOOR PLAN
13
14
SECTIONAL ELEVATION
15
16
CONCLUSION
The building acts as a three-dimensional space frame. All the slabs have
designed as two way slabs. The analysis of frames was done using middle strip
method. The beams have been designed by taking both bending moment and shear
force from the analysis results in to considerations.
The design of slabs, beams, lintels cum sunshade, footing and staircase were
done manually. All the drawing presented in these project reports were drafted using
Auto CAD 2009 software.