WORK PROGRESS FOR THE MONTH OF 31st MARCH, 2021

There is steady progress across site, please find work progress report along
with latest development images of HALLMARK VICINIA herewith for your
perusal.
A – BLOCK: WORK STATUS REPORT AS ON 31st MARCH, 2021

Sl. No WORK DESCRIPTION WORK PROGRESS STATUS


1 Internal Plastering & Common area plastering Completed.
2 Vitrified Flooring & Skirting 100% completed flats 184.
3 Lobby area flooring & Skirting Lift Lobby 1 & 2 cladding works completed,
4 Door Frame Fixing 11 & 12th floor in progress
5 Duct CPVC & PVC Vertical Lines Completed
6 UPVC Windows & Door Completed
7 Door Shutter fixing with hardware 11th & 12th floor in progress
8 Switch plate fixing 10th floor in progress
9 Lifts Lift lobby-2 In service
10 CP & Sanitary 11th & 12th floor work in progress
11 Electrical Switch board fixing 11th & 12th floor in progress
12 Solar water heater for 12th floor Installation completed
13 Apartment Handing over for Interior works 15 APARTMENTS HANDING OVER COMPLETED
14 Power meter Completed.
1 STRUCTURE(B2+B1+G+12) Completed. 5 Internal wiring with DB Dressing Completed
2 Internal Toilet CPVC Plumbing Completed. 6 Staircase Granite Works Completed.
3 Toilet, Utility & Balcony water proofing Completed. 7 Staircase Railing Works Completed.
4 Common area Block work Completed. 8 Cellar & Sub cellar VDF Completed.
s

B – BLOCK: WORK STATUS REPORT AS ON 31st MARCH , 2021


Sl.
No WORK DESCRIPTION WORK PROGRESS STATUS
1 Vitrified Flooring & Skirting Completed
2 External Painting B-block completed.
3 Lifts: standby
4 Apartment Power meters & communication wiring In progress
5 Apartment Handing over for Interior works 108 APARTMENTS HANDING OVER COMPLETED
6 2nd service lift Work in progress
7 B1 & B2 lift lobby flooring and false ceiling works Completed
1 STRUCTURE(B2+B1+G+12) Completed. 9 Internal Plastering & Common area plastering Completed
2 Internal Toilet CPVC 10
Plumbing Completed. Tiles - Toilet Dado & Flooring Completed.
3 Toilet, Utility & Balcony 11
water proofing Completed. Staircase Granite Works Completed.
4 Common area Block work & 12
Plastering Completed. Staircase Railing Works Completed
5 corridor area flooring & 13
Skirting Completed. Door Frame Fixing Completed.
6 Door Shutter fixing with 14
hardware Completed. Internal wiring inside apartment Completed.
7 Lift lobby 1: service lift and 15
passenger Completed. External Plastering Completed.
AMENITIES & INFRA: WORK STATUS REPORT AS ON 31st MARCH, 2021

Sl. No WORK DESCRIPTION WORK PROGRESS STATUS


1 GARBAGE CHUTE B-BLOCK COMPLETED
1 CLUB HOUSE – STRUCTURE & BRICK WORK Completed
2 Club house – Internal Works Tile works completed, False ceiling works in progress in all floors.
Planter box granite works and plantation work under progress at A &
3 Landscape works B block.
4 Cellar & Sub – Cellar VDF flooring B-block completed.
5 Cellar & Sub Cellar VDF flooring A-block completed.
6 Fire Fighting Systems at Cellar & Sub Cellar B-block completed & A-Block work in progress
8 Drinking Water Pipeline works Main pine line work completed.
9 STP Completed
10 WSP Completed
11 Transformer Yard In progress
12 Electrical & Communication Ducts Works under progress.
13 D G Sets B-block completed
14 Power line Work in progress.
15 Corridor doors B-block completed.
16 Corridor doors A-block completed.
VICINIA: VIEW OF A & B BLOCK
VICINIA: B-BLOCK LANDSCAPING
VICINIA : MAIN GATE ENTRY & EXIT
VICINIA: GAZEBO WORKS & OPEN GYM
VICINIA: SECURITY ROOM AND CC TV WORKS IN PROGRESS
TRANSFORMER INSTALLATION IN PROGRESS
VICINIA ENTRANCE & GRANITE CLADDING WORKS
CLUB HOUSE: EXTERNAL TEXTURE & GLASS WORK IN PROGRESS

CLUB HOUSE - 1st floor slab work in progress


CLUB HOUSE: DOOR SHUTTERS AND AC WORKS IN PROGRESS
CLUB HOUSE: GUEST ROOM WORKS IN PROGRESS
B-BLOCK : LMS WORKS COMPLETED A-BLOCK WORKS IN PROGRESS.
A & B-BLOCK APARTMENTS HANDING OVER IN PROGRESS
A-BLOCK APARTMENTS HANDING OVER IN PROGRESS
` A & B-BLOCK APARTMENTS HANDING OVER IN PROGRESS
A & B-BLOCK APARTMENTS HANDING OVER IN PROGRESS
THANK YOU

PATRONS