GR Villa 2/4/9 [Block 2 Spartan]

S No Area Task Comment


1 Electrical Motor installation at each house
2 Electrical Some Switch are missing
3 Electrical Meter panel
4 Electrical Cable Wire

5 Wood Work Silicon filling Is pending for Windows/Door


6 Wood Work Door Stopper
Will procure it by Owners, amount will
7 Wood Work Lock change - Rust is there in current Locks
be deducted from Final payment
8 Wood Work Door replacement

9 MS Work Ladder in Shaft


Will procure it by Owners, amount will
10 MS Work Staircase
be deducted from Final payment

11 Plumbing Work Pressure and Leakage Testing of Pipelines


Will procure it by Owners, amount will
12 Plumbing Work CP fitting
be deducted from Final payment

13 Civil Work Tiles for kitchen


14 Civil Work Divider between Toilet and Room
15 Civil Work Grouting
16 Civil Work Granite Work
17 Civil Work Crack filling in house
Cementing/tiling Front of Villa 4 as there is a
18 Civil Work
big hole there
19 Civil Work Driveway for Villa 9 is still not done
Taking main house Rain water pipe till to
20 Civil Work
garden.

21 Painting Inside house Door, Grill - Pebble White L136


22 Painting External paint :Weather/Water-Proof Paint
23 Painting Putty and Water proofing Inside / Outside

24 Geyser Solar Geyser


GR Project Readiness
S No Area Task
Generator to be installed which is their in
1 External/ Occupancy Readiness Phase II

2 External/ Occupancy Readiness Electrical poles in garden : Back side of house


3 External/ Occupancy Readiness Borewell
4 External/ Occupancy Readiness STP
5 External/ Occupancy Readiness WTP
6 External/ Occupancy Readiness Pavement Park
7 External/ Occupancy Readiness Dustbin

8 External/ Occupancy Readiness Electrical poles in garden : Back side of house


9 External/ Occupancy Readiness Broadband connection
10 External/ Occupancy Readiness Camera Installation
Complete Basketball court , MS work still
11 External/ Occupancy Readiness pending
12 External/ Occupancy Readiness Making Park Ready with Grass and plants
13 External/ Occupancy Readiness Bescom Connection
14 External/ Occupancy Readiness GAIL Connection
15 External/ Occupancy Readiness Wire over Boundry wall
16 External/ Occupancy Readiness Covering of Well behind Villa 8 [Block 2]
17 External/ Occupancy Readiness Boundry for Phase II and Gate
18 External/ Occupancy Readiness Project Painting
19 External/ Occupancy Readiness Road to be made proper in front of house