DETAILED SPECIFICATIONS OF CIVIL WORKS TO BE EXECUTED ON TURNKEY


BASIS FOR CONSTRUCTION AT MULLANPUR
PROJECT COST: - AREA ASSUMED 6300 SQFT @1100 = RS 6930000.00

A. Civil Work Rate @Rs.1100/- Per Sqft


Measurement shall be as per actual at site

1. Anti-termite treatment in As per IS 6313 (Part2): 2001


foundation, floors and outer
periphery by the professional
agency
2. Specification/ Composition 1:4:8 using cement, coarse sand and aggregate (20mm to
PCC 40 mm) 4” under the floors. As per specified

3. Reinforced cement concrete 1:1.5:3 (M20) using cement sand and coarse aggregate in
beams, slabs and columns & Steel Shuttering to be used
4. Brick work .9” thick in Brick walls 9” thick will be undertaken using cement sand
Superstructures / Toe walls mortar composition of 1:6 in superstructure /toe walls as
required in various jobs (First class bricks)

5. Brick work.4.5” thick in Brick walls 4.5” thick in superstructure will be undertaken
Superstructure using mortar of cement sand composition 1:4 (First class
bricks)

6. D.P.C. Plinth Beam as specified. 1:1.5: 3 (M 20) shall be laid with


water proofing compound (Make: Sikka)

7. Steel TMT bars Make: TATA TISCON will be used as per


structural drawing by the structural engineer.
8. Cement Ambuja / Ultratech/ACC cement to be used
Water Fixing compound (only exterior plastering) to be
added wherever needed
9. Rain Water Harvesting well Complete with chamber cover (Not Included)

SM CONSTRUCTIONS
Hno. 2115 sector 15, Panchkula. Distt. Panchkula. Email id: smconstructions1@gmail.com
Contact: +91 94175 00223
10. Plumbing and Sanitary Work Laying Down of Pipes Only
GI pipes (Make: TATA Only) shall be used for all water
supply work.
* Diverters /Concealed Tanks with requisite accessories
required to be put in toilet walls
To be provided by the owner separately
11. Sewerage Work Finolex / Supreme Sewerage Pipes 4’’ & 6’’ pipes shall be
used (6 kg. /cm2) Also a continuous PVC Schedule 40
Pipe with of 50 mm dia shall be laid for Gas Pipe
Provisioning for all the Kitchens.
12. Electrical Work 1” and ¾” PVC conduit pipes, ISI mark, HMS grade (2mm
thick) Diplast will be laid in the slabs as well as the wall in
order to allow smooth passage of wires
Rust protected 120 GSM GI Boxes as per range
requirement (Nos of switches required at a particular
location) shall be fitted in the walls.
Conduits for Telephone, TV and Cable (2’’dia conduit)
Conduits in Boundary Wall for Gate Lights, staircase lights
shall be provided etc
No automation has been considered for the costing
purpose, in case automation is there the electrical
piping for the same will be charged as per actuals
13. Water Tank 1 No, RCC underground water tank of 5000 ltr.
Two No’s triple layer overhead tanks of 2000 Ltr
Each shall be provided by the owner with Sensor
System for automation of Water transfer from underground
tanks to overhead tanks
(Pressure Pumps- to be provided by owner)
14. Wood Work/UPVC Owners Scope (Only wooden frames to be fixed by
contractor)

15. Flooring All the floors shall be finished by PCC Flooring including
Driveway / Verandahs and Balconies
16. Roof Brick bat Cobba or mud fuska

SM CONSTRUCTIONS
Hno. 2115 sector 15, Panchkula. Distt. Panchkula. Email id: smconstructions1@gmail.com
Contact: +91 94175 00223
17. Gate & Grills Grills for the Boundary wall and Main Gate, Wicket Gate
shall be provided by owner and fixed by contractor.

18. Boundary wall Boundary walls included with plastering

Terms & Conditions:

1. All rates quoted are basic cost, GST (as applicable) will be payable extra
2. Electricity and water to be provided by the client
3. Any dues towards Govt. in respect of the said plot or any Electricity Security for
permanent electric connections, water meter security or any Govt. fees/charges towards
sanctioning of building plans etc. will be at owner’s end.
4) Solar Water heater – to be borne by the owner

PAYMENT SCHEDULE

1 MOBILIZATION ADVANCE 5,00,000.00


2 AFTER COMPLETION OF FOUNDATION 5,00,000.00
3 AFTER COMPLETION OF R C C OF SLAB GROUND FLOOR 15,00,000.00
4 AFTER COMPLETION OF R C C OF SLAB FIRST FLOOR 15,00,000.00

5 AFTER COMPLETION OF BRICK WORK. GROUND FLOOR 5,00,000.00


6 AFTER COMPLETION OF BRICK WORK. FIRST FLOOR 5,00,000.00
7 AFTER COMPLETION OF PLASTER WORK. GROUND FLOOR 5,00,000.00
8 AFTER COMPLETION OF PLASTER WORK. FIRST FLOOR 5,00,000.00
AFTER COMPLETION OF EXTERNAL PLASTER AND PCC
9 5,00,000.00
UNDER FLOORS
10 AFTER COMPLETION 5,00,000.00