MOM - 66 - BCU ARCADIA PROJECT

Date: 26-Dec-23
Venue: Arcadia - Site walk
Time: 04:15 PM to 06:25 pm
Attendees:

MPPL : Mr. Shreemaan, Mr. Santhosh Shetty, Mr. Sarathkumar.


JLL: Mr. Karthikeyan, Mr. Trivikram.
KPTL: Mr. Patil.
TSI: ABSENT.
Santech: Mr. Dhirender sahoo.
OTIS: Mr. Hidayathulla.
JK Traders: Mr. Suresh, Mr. Afroz.
Technogreen: Mr. Ujair
Pragati Infratech: Mr. Vivek
Pioneer: Mr. Sudhan.
Gefab: Mr. Rajeev.
FJ Enterprises: Mr. Sunil.

Sl No Description of works Vendor


Podium

1 West side (podium) staircase walls plastering and painting works to be completed KPTL

West side (podium) staircase beam rectification (line/offset) works to be


2 KPTL
completed
Conduiting works to be completed parallel to Paver line (Marking to be done by
3 PE/JKT
M/s Pioneer Engineer)

GROUND FLOOR

1 Shaft door fixing to be completed near ST 03 (electrical and PHE shaft) KPTL
HVAC 12 Shaft area lintel, blockwork and plastering to be done with opening
2 KPTL
provision as confirmed at site.
3 Electrical room to be painted and handover KPTL
Near East side entrance (Back door) blockwork and plastering to be done with
4 KPTL
lintel at 2.10m level form FFL.
ST 02 wall painting (1st coat) to be completed and cleaning to be done from BM
5 KPTL
floor to terrace floor.
6 Water supply line works to be completed (west side shaft) Santech
7 HVAC opening - Grill size confirmation to be provided MPPL
8 All HVAC duct opening to be closed with GI Sheet for Fire NOC inspection Technogreen
9 ST 02 - Balance HVAC ducting works to be completed Technogreen
Toilets duct opening size clearance provided to TG and completion schedule to be
10 Technogreen
shared
11 ST 02 North side HVAC pipe insulation works to be completed Technogreen
12 SL 01 lobby Drop down of FPS piping to be done till false ceiling level TSI
13 ST 01 near FPS shaft - Chequer plate to be fixed and shaft to be cleaned. TSI
14 SL 02 lobby Drop down of FPS piping to be done till false ceiling level TSI
15 Balance hooter box to be fixed near ST 01 TSI
16 Shaft opening to be closed with chequer plate in front of Big elec room TSI
17 SL 01 - False ceiling works to be completed Pragati
18 SL 02 - Balance wall granite cladding (600mm) works to be completed Pragati
19 SL 02 - Additional suppots for false ceiling works to be completed Pragati
20 SL 02 - Lobby false ceiling works to be completed Pragati
Near East side entrance lobby wall painting works to be completed and existing all
21 FJ Enterprises
samples to be grinded and to be removed.
22 Near East side entrance lobby (Back door) lighting works to be completed JKT
23 Earthing strip works to be completed - 60 Nos balance JKT

1st Floor

1 ST 01 behind area deshuttering works to be completed KPTL


2 Shaft door fixing to be completed near ST 03 (electrical and PHE shaft) KPTL
Small electrical room (near ST 01) - ventalation shaft blockwork and plastering
3 KPTL
works to be done
HVAC 12 Shaft area lintel, blockwork and plastering to be done with opening
4 KPTL
provision as confirmed at site.
5 ST 02 - HVAC ducting works to be completed Technogreen
6 All HVAC duct opening to be closed with GI Sheet for Fire NOC inspection Technogreen
Small electrical room (near ST 01) - ventalation shaft Grill fixing to be done and
7 MPPL/TG
sizes to be confirmed
8 All circular windows to be fixed Gefab
9 West entrance façade - Frame and glass to be fixed. Gefab
10 Southwest corner glass fixing works to be completed. Gefab
11 ST 03 inside wall towards FPS shaft to check, as FAPA cabling done on the wall MPPL
12 All lift lobby false ceiling works to be completed Pragati

2nd Floor

1 ST 03 - Gypsum works to be completed Pragati


2 Rain water shaft (south side) PHE works to be completed Santech
HVAC 12 Shaft area lintel, blockwork and plastering to be done with opening
3 KPTL
provision as confirmed at site.
Proper Safety barrication to be done in opening area and housekeeping/cleaning
4 KPTL
to be done.
5 PL's ventilation shaft to be closed with blockwork and plastering KPTL
6 Shaft door fixing to be completed near ST 03 (electrical and PHE shaft) KPTL

3rd Floor

1 No detectors fixed in all lobbies; to be checked and to be fixed TSI


2 SL 01 - 3 in 1 box cable termination works to be done and box to be fixed TSI
3 Refuge area glazing works to be completed Gefab
4 West side room 3 No's columns to be chipped off and steel to be removed KPTL
5 West side room grinding and touch-up works to be completed KPTL
HVAC 12 Shaft area lintel, blockwork and plastering to be done with opening
6 KPTL
provision as confirmed at site.
7 Shaft door fixing to be completed near ST 03 (electrical and PHE shaft) KPTL

4th Floor

1 West side void area FPS works to be completed TSI


2 West side void area wall grinding works to be completed KPTL
3 West side void area steel cutting works to be completed KPTL
4 Shaft door fixing to be completed near ST 03 (electrical and PHE shaft) KPTL
5 Staircase tiling to be exteneded till fire door of lift lobby. KPTL
6 Fire door requirement to be checked and to be installed MPPL/IHMS

5th Floor (terrace floor)

1 ST 02 - Shaft head room finishing works to be completed KPTL


2 No detectors fixed in all lobbies; to be checked and to be fixed MPPL/TSI
3 Light grey painting works to be done in parapet wall of above terrace FJ Enterprises
4 Fire door requirement to be checked and to be installed MPPL/IHMS
ARCADIA PROJECT

Target date Remarks


3-Jan-24
ARCADIA - FPS PENDING WORKS - 28-Nov-23

Location Responsible Hydrant / sprinkler incl testing FA completion Remarks