Composite Works – M/s. Petron - Civil & Underground Piping Works – Forecast Completion by
Nov’16 ; Cooling Tower Cell 1 by Dec’16.
Major balance work of Pipe Supports, valve pits, manhole, area grading and paving. Progress of
manhole casting work pertaining to UG piping is very slow.
Cooling tower cell 1 likely completion by Dec 16 due to sequential activities.
In UG piping approx. 50,000 IM piping erection and complete system testing pending due to
resources issue with Petron.
Composite Works – M/s. Petron – Structure Work – Likely Completion by August’16
Only 31 MT steel erection balance. Alignment and documentation is main focus area now.
Composite Works – M/s. Petron, Jobby & B&R – Above Ground Piping – Likely Completion by
Feb’17
Piping erection is a main area of concern with almost 190,000 IM erection and 49,000 ID welding
pending. There are 64 systems pending for mechanical completion.
Mobilisation of B&R (3rd Piping agency) under progress.
Composite Works – M/s. Petron & M/s. Powernet – Electrical – Likely Completion by Feb’16
CEIG clearance received for SS-1, SS-2 and DM MCC Room. Charging planned by Mid Aug 2016
based on completion of Fire Fighting work completion.
SS-3 likely completion & ready for charging by Nov.16.
Balance cable laying work likely completion by Dec.16 & readiness of last EPC packages electrical
system by Feb’16.
GCC / EPC VENDOR STATUS
WWTP – M/s. S4 & M/s. Jobby – Civil Work – Likely Completion by Oct’16