GCC / EPC VENDOR STATUS

 Composite Works – M/s. Petron - Civil & Underground Piping Works – Forecast Completion by
Nov’16 ; Cooling Tower Cell 1 by Dec’16.
 Major balance work of Pipe Supports, valve pits, manhole, area grading and paving. Progress of
manhole casting work pertaining to UG piping is very slow.
 Cooling tower cell 1 likely completion by Dec 16 due to sequential activities.
 In UG piping approx. 50,000 IM piping erection and complete system testing pending due to
resources issue with Petron.
 Composite Works – M/s. Petron – Structure Work – Likely Completion by August’16
 Only 31 MT steel erection balance. Alignment and documentation is main focus area now.
 Composite Works – M/s. Petron, Jobby & B&R – Above Ground Piping – Likely Completion by
Feb’17
 Piping erection is a main area of concern with almost 190,000 IM erection and 49,000 ID welding
pending. There are 64 systems pending for mechanical completion.
 Mobilisation of B&R (3rd Piping agency) under progress.
 Composite Works – M/s. Petron & M/s. Powernet – Electrical – Likely Completion by Feb’16
 CEIG clearance received for SS-1, SS-2 and DM MCC Room. Charging planned by Mid Aug 2016
based on completion of Fire Fighting work completion.
 SS-3 likely completion & ready for charging by Nov.16.
 Balance cable laying work likely completion by Dec.16 & readiness of last EPC packages electrical
system by Feb’16.
GCC / EPC VENDOR STATUS
 WWTP – M/s. S4 & M/s. Jobby – Civil Work – Likely Completion by Oct’16

 Balance work of Paving and Supports.

 WWTP – M/s. UEM – Balance of Plant - Likely Completion by Feb’17


 Balance structure (including shelter and sheeting) likely completion by Oct16.
 Balance piping erection and hydrotest by Dec16. CPVC piping Jan17.
 Balance electrical work (after SS-3 charging by Nov’16) ready for motor no load by Dec16.
 Balance instrumentation work completion by Jan17.
 D M Plant – M/s. Pennar - Likely Completion by Oct16
 62/65 piping loop HT completion. 4/11 system Format I submitted.
 Electrical installation completed.
 FWST tank paining is balance major construction activity. Likely completion Sept16.
 Precommissioning activities to start from Aug 16 and plant ready for commissioning forecast is end
Oct’16
 N2 Storage Area – M/s. INOX - Plant Complete and ready for commissioning
 All installation complete. Waiting for power and utilities from client
 Likely commissioning by Oct16
GCC / EPC VENDOR STATUS
 BOILER Package – M/s. L&T Scope - Likely Completion by Jan’17
 Civil work completed except site grading and paving in the boiler area and Boiler Control Room.
 SFB Hydro test completed and anchor welding for refractory under progress.
 ONG A & ONG B likely completion by Oct’16 and Dec’16. Then piping and interconnection can
commence (other agency)
 Balance boiler area structure and peripheral work as per L&T scope of work is likely to be
completed by Jan’17.
 BOILER Package – M/s. Supertech Scope - Likely Completion by March’17
 Piping fabrication 70% complete, erection only 10% completed. Forecast Piping erection, loop
clearance and hydrotest completion by Jan’17
 Coal Conveyor and Ducting erection completion forecast Nov16 and Dec16 respectively.
 Electrical work – cable laying started and instrumentation work yet to commence.
 Boiler control room balance work award to be expedited.
 Insulation contract to be finalised with Supertech.
 BOILER Package – M/s. Phisem Scope - Likely Completion by Jan’17
 Refractory work likely completion by Jan’17 based on front release by L&T.
GCC / EPC VENDOR STATUS
 Cooling Tower– M/s. Hamon - Likely Completion by Dec‘16 (9 cells) & Mar‘17 (Cell 1)
 Civil work for 7 cells complete. 8th and 9th Cell completion by Aug’16 & last cell by Dec16.
 Civil work for pipe supports and paving pending. Forecast completion by Aug16.
 Balance supply of CLO2 package, erection of H2SO4 package likely completion by Oct’16.
 Piping work erection, loop clearance and Hydrotest pending. Likely completion by Nov.16 for 9
cells. Balance 1st Cell piping completion by Jan’17.
 Electrical cable laying for main pumps completed, fan deck under progress. Likely completion of
electrical work with motor no load run by Nov16 (for 9 cells).
 Instrumentation work yet to start.
 Tankage – Supertech and Fabtech - Likely Completion by Dec‘16
 PX tank A & B: HT complete. Balance work of painting and seal. Likely completion by Oct16.
 FWST tank – inside and outside painting balance. Likely completion by Oct.16
 TTSW tank – MC clearance under progress. HT likely to start from 20 th July16. balance work of
painting – inside and outside. Likely completion by Dec’16.
 Diesel Tank – Final Painting finished and handed over for Petron.
 LSHS Tank – HT complete. Painting and insulation pending. Likely completion Dec16.
 DM Tank – HT under progress. Pending work of painting (inside and outside) – likely completion
Dec’16.
GCC / EPC VENDOR STATUS
 DG System – M/s. Powerica – Likely Completion (ready for commissioning) – 30 th Aug 16
 All installation complete. Format I under submission.
 Piping HT completion. Flushing under progress.
 Electrical installation complete and punch listing under progress.
 CEIG approval for DG design complete. Site visit planned in first week Aug’16.
 Likely commissioning by end August’16.
 220 KV Switch Yard – M/s. BBL - Likely Commissioning by 30th Aug’16
 All installation completed and tested.
 CEIG design approval received. Site visit clearance pending likely to be planned in 1 st week of Aug
2016. Commissioning likely to be taken up in end Aug 2016.
 Control Room CCR and ITR – Various agencies – likely completion – Dec’16
 Civil RCC work completed. Finishing work under progress. Likely Completion Dec’16.
 HVAC – duct installation completed in CCR, work in progress in ITR-2. Balance to be taken up in
ITR-1, ITR-3, SS-1, SS-2 and SS-3. Likely completion by Sept’16.
 HVAC – AHU delivery likely by Aug end 2016.
 Clean Agent System – work started in CCR. Likely completion by Sept2016. For ITR-1, ITR-2 and
ITR-3, work to commence from Aug’16 onwards and likely completion by Nov16.
 Fire Detection System – work yet to commence.
 Panel Erection and interconnection – started in ITR-2 and ITR-1. CCR and ITR-3 likely to start by
end July and End Aug respectively. Likely completion with cable termination by Dec16.
 Balance work completion in buildings forecast by Dec’16