QA1-Main gate development project works

Phase 01

Excavation and shoring and demolishing existing chamber

1-buliding internal protective scaffold with plywood will be installed adjacent to the
internal side of Wall, its function is to protect the internal pipes in the chamber from
breaking parts during demolishing activities

2-start excavation works around the old drain chamber for NR/SR valves by using
excavator

3- The excavation works will be gradual; excavation is to be a depth of only one


meter and then broken the wall by hammer excavator and then the excavation is
continued to a depth of one meter each time and the wall is broken every time.

4-excavation area shall be covering the area around the old chamber and area
around the NR/SR main export pipes and excavation will be extend till almost half
the road of entrance to station

5- take in consideration all shoring and sloping activities combine with excavation
works and area near the police building at the west side to be suspending by
sheeting to prevent failure
Phase 02

NR and SR mechanical piping and valves works

SR line SD works /SOW

1-starting mechanical isolation works for SR export line


2-installing spades on MOV400/410 behind 2nd lift station as 1st steps of line export line isolation
3-closing the upstream line near new Shuaiba station /near the fuel gas station-high way Basra/2nd
steps of line export line isolation
4-open the west/east river cross 24-inch drain SR
5- near the old RAK yard chamber /open the flange and install big capacity vacuuming pumps to
remove all the residual water inside the pipe.
6-asper the dwg/ cut and remove the flange and 24-inch drain valve under the old chamber and
shifting to the east side and to be placing/ fabricated and weld in the new chamber asper the new
detailing drawing and the site condition
6-clean the exposed pipes mainline and drain and wrapped correctly again
7-all isolation/cutting/welding/fabrication activities to be start after full excavation/sloping and
shoring of area and fully demolishing of old chamber works
8- NDT and painting touch up for all welding joints in the plan

NR line SD works

SOW

1-starting mechanical isolation works for SR export line


2-installing spades on MOV500/510 behind 2nd lift station as 1st steps of line export line isolation
3-closing the upstream line near new Shuaiba station /near the fuel gas station-high way Basra/2nd
steps of line export line isolation
4-open the west/east river cross 24-inch drain NR
5- near the old RAK yard chamber /open the flange and install big capacity vacuuming pumps to
remove all the residual water inside the pipe.
6-asper the dwg/ cut and remove the flange and 24-inch drain valve under the old chamber and
shifting to the east side and to be placing/ fabricated and weld in the new chamber asper the new
detailing drawing and the site condition
6-clean the exposed pipes mainline and drain and wrapped correctly again
7-all isolation/cutting/welding/fabrication activities to be start after full excavation/sloping and
shoring of area and fully demolishing of old chamber works
8- NDT and painting touch up for all welding joints in the plan

2
Phase 03

new chamber construction and backfilling and road and paving repairs

1-after excavation completion with shoring and slopping


2-prepre the are for new chamber building works /chamber shall be included the new shifted drains
valves and including both main line NR/SR branches to the drain valves
3-chamber dimensions to be around 12m long-6meter wide-6m minimum depth -bottom of
chamber slab to be 50cm from the BOP of NR/SR
4-prepre chamber are by leveling in order to cast 15cm blinding concreate layer
5-prepre the foundation slab reinforcement concrete layer asper approve detail civil dwg.
6- cast concrete for base slab (30cm thick) /including the sump area and foundation pedestals for
suspending pipe support
7-civil works activities/prepare for wall reinforcement /frameworks/ carpentering works /water stop
laying /frameworks fixing by bolts/casting concrete for 1st phase of pour concreate
8-install scaffolding around the chamber in order to start 2nd phase on wall casting
9--civil works activities/prepare for wall reinforcement /frameworks/ carpentering works /for 2nd
phase /frameworks fixing by bolts/casting concrete for first phase of pour concreate (1st phase at
3meter and below depth and 2nd phase for the rest depth of chamber)
10-start removing all the farmwork around the chamber and removing all the connections bolts for
plywood
11-start repair and surface treatments work from outside and inside the chamber
12-beteomen paint and layering applied on the outer side of wall chamber.
13-start backfilling works around the chambers / each 1-meter layering with compaction works
14-all the prefabrication works shall be started and completed in the workshop.
15install the steel works related with chamber building / handrails/aggress access and valves
platforms/stairs cases and ladders asper the approved detailing dwg.
16-pavements repairing works to the main entrance road asper Roo spec.

3
Excavation and shoring and demolishing existing chamber (Phase 01)
Prepare DOCS approvals and PTW submitting 1july
building internal protective scaffold with plywood 2-6 July
and rescue scaffolding for entry
start excavation works around the old drain 7-12 July
chamber to be steeped on each one meter
Demolishing old chamber during excavation 8-11 July
Shoring and sheeting works near police building 9-11 July
Civil excavation works/area of main export 12-21 July
lines/shoring and sloping activities combines with
excavation area
Demolish road pavement and shoring works 18-24 July

- NR and SR mechanical piping and valves works Phase 02


SR line SD works /SOW
Prepare DOC s including MS/RA/RSP/LP 1-Aug
mechanical isolation works for SR export line- 2-3Aug
installing spades on MOV400/410 behind 2nd lift
station
closing the upstream line near new Shuaiba 2-3Aug
station /near the fuel gas station
open the west/east river cross 24-inch drain SR 2-3Aug
near the old RAK yard chamber /open the flange 3-4Aug
and install big capacity vacuuming pumps 10- or
12-inch discharge pump
Fabrication works included NDT and warping 21july-4Aug
Site works/cut and remove the flange and 24-inch 4-6Aug
drain valve under the old chamber and shifting to
the east side and to be placing
Site fabrication and welding cut and replace at 5-13Aug
least 10 m new spool in the main line SR export
junction miter and reinforcement pad with new
drain line
NDT and painting touch and wrapping 4-14 Aug
mechanical de-isolation works for SR export line- 15-16Aug
removing spades on MOV400/410 behind 2nd lift
station
open the upstream line near new Shuaiba station 15-16Aug
/near the fuel gas station
Close the west/east river cross 24-inch drain SR 15-16Aug
near the old RAK yard chamber /close and 16-17Aug
reinstall the flange and install big capacity
vacuuming pumps 10- or 12-inch discharge pump

NR line SD works /SOW


Prepare DOC s including MS/RA/RSP/LP 20-Aug
mechanical isolation works for NR export line- 20-22Aug
installing spades on MOV500/510 behind 2nd lift
station
closing the upstream line near new Shuaiba 20-22Aug
station /near the fuel gas station
open the west/east river cross 24-inch drain NR 20-22Aug
near the old RAK yard chamber /open the flange 21-23Aug
and install big capacity vacuuming pumps 10- or
12-inch discharge pump
Fabrication works included NDT and warping 10-22Aug
Site works/cut and remove the flange and 24-inch 24-26 Aug
drain valve under the old chamber and shifting to
the east side and to be placing
Site fabrication and welding cut and replace at 26 Aug-5 Sep
least 10 m new spool in the main line NR export
junction miter and reinforcement pad with new
drain line
NDT and painting touch and wrapping 22 Aug-6 Sep
mechanical de-isolation works for NR export line- 7-8 Sep
removing spades on MOV500/510 behind 2nd lift
station
open the upstream line near new Shuaiba station 7-8 Sep
/near the fuel gas station
Close the west/east river cross 24-inch drain NR 7-8 Sep
near the old RAK yard chamber /close and 8-10 Sep
reinstall the flange and install big capacity
vacuuming pumps 10- or 12-inch discharge pump

new chamber construction and backfilling and road and paving repairs -phase 03
Prepare DOC s including MS/RA/RSP/LP 15 Sep
prepare the area for new chamber building 15-17 Sep
works/
Leveling and compaction area and install 16Sep
vacuuming pumps over all works duration
prepare chamber area by leveling in order to cast 18-19 Sep
15cm blinding concreate layer
Blinding +Foundation base works frame works 19-29 Sep
and repairing and pour concreate
civil works activities/prepare for wall 30 Sep-12 Oct
reinforcement /frameworks/ carpentering works
/water stop laying /frameworks fixing by
bolts/casting concrete for 1st phase of pour
concreate /
wall sleeves installation works /chamber has 4 8-12 Oct
sleeve 48 inch and 2 sleeve 24 inch
install scaffolding around the chamber in order to 12-25 Oct
start 2nd phase on wall casting
civil works activities/prepare for wall 26sep-15 Nov
reinforcement /frameworks/ carpentering works
/water stop laying /frameworks fixing by
bolts/casting concrete for 2nd phase of pour
concreate
start removing all the farmwork around the 15 Nov-22 Nov
chamber and removing all the connections bolts
for plywood and repair and surface treatments
work from outside and inside the chamber
bitumen paint and layering applied on the outer 23-24 nov
side of wall chamber.
backfilling works around the chambers / each 1- 25nov -3dec
meter layering with compaction works
Platform and handrails work fabrication workshop 1 nov-18 nov
NDT and painting 10-25 nov
Installation steel works/ladders/platform grating 3 dec-11 dec
and staircases asper the layout and detailing
DWGs
Pavement works and side walkways casting and 10 dec-18 dec
curbstone works required with painting
Completion and handover 20 dec