Phase 01
1-buliding internal protective scaffold with plywood will be installed adjacent to the
internal side of Wall, its function is to protect the internal pipes in the chamber from
breaking parts during demolishing activities
2-start excavation works around the old drain chamber for NR/SR valves by using
excavator
4-excavation area shall be covering the area around the old chamber and area
around the NR/SR main export pipes and excavation will be extend till almost half
the road of entrance to station
5- take in consideration all shoring and sloping activities combine with excavation
works and area near the police building at the west side to be suspending by
sheeting to prevent failure
Phase 02
NR line SD works
SOW
2
Phase 03
new chamber construction and backfilling and road and paving repairs
3
Excavation and shoring and demolishing existing chamber (Phase 01)
Prepare DOCS approvals and PTW submitting 1july
building internal protective scaffold with plywood 2-6 July
and rescue scaffolding for entry
start excavation works around the old drain 7-12 July
chamber to be steeped on each one meter
Demolishing old chamber during excavation 8-11 July
Shoring and sheeting works near police building 9-11 July
Civil excavation works/area of main export 12-21 July
lines/shoring and sloping activities combines with
excavation area
Demolish road pavement and shoring works 18-24 July
new chamber construction and backfilling and road and paving repairs -phase 03
Prepare DOC s including MS/RA/RSP/LP 15 Sep
prepare the area for new chamber building 15-17 Sep
works/
Leveling and compaction area and install 16Sep
vacuuming pumps over all works duration
prepare chamber area by leveling in order to cast 18-19 Sep
15cm blinding concreate layer
Blinding +Foundation base works frame works 19-29 Sep
and repairing and pour concreate
civil works activities/prepare for wall 30 Sep-12 Oct
reinforcement /frameworks/ carpentering works
/water stop laying /frameworks fixing by
bolts/casting concrete for 1st phase of pour
concreate /
wall sleeves installation works /chamber has 4 8-12 Oct
sleeve 48 inch and 2 sleeve 24 inch
install scaffolding around the chamber in order to 12-25 Oct
start 2nd phase on wall casting
civil works activities/prepare for wall 26sep-15 Nov
reinforcement /frameworks/ carpentering works
/water stop laying /frameworks fixing by
bolts/casting concrete for 2nd phase of pour
concreate
start removing all the farmwork around the 15 Nov-22 Nov
chamber and removing all the connections bolts
for plywood and repair and surface treatments
work from outside and inside the chamber
bitumen paint and layering applied on the outer 23-24 nov
side of wall chamber.
backfilling works around the chambers / each 1- 25nov -3dec
meter layering with compaction works
Platform and handrails work fabrication workshop 1 nov-18 nov
NDT and painting 10-25 nov
Installation steel works/ladders/platform grating 3 dec-11 dec
and staircases asper the layout and detailing
DWGs
Pavement works and side walkways casting and 10 dec-18 dec
curbstone works required with painting
Completion and handover 20 dec