Coordination to be expected recently.

20 August 2021

No.1 POWER STATION

1. Regulating weir
( No Comment)

2. Regulating weir, No.1 & 2 Diversion weir(control house)


Contractor Lot I (PP)
- Schedule of hand over to Lot II & Lot III
- Confirm schedule to complete control house

3. No.1 Diversion weir


(No Comment)

4. Penstock Shaft Area


Contractor : Lot I & Lot II
- When the Radiography Test for No.1 Steel Penstock No.24 carryout

5. No. 1 Outdoor Switchyard


Contractor: Lot I (Hyundai) and Lot III
- Pending list as shown in the attachment was confirmed with PLN, Lot III and Lot I at the site
meeting on July 13.
- Lot III: How much progress do you estimate as of today? And let us know your handover
schedule to Lot I, if available.
- Lot III: Do you have a request?
- Lot I: Do you have a request?

6. No.1 Switchyard Buildings


Contractor Lot I & Lot III
- Resubmit schedule control house building.

1|Page
- Keep schedule for hand over to Lot III by end of September

7. No.1 Powerhouse
Contractor: Lot I (Hyundai), Lot III and Lot II
- FYI,Lot I said that roof fabrication and installation needed for two months in total at the last
coordination meeting on August 6. Handover from Lot I to Lot I as scheduled on 1st October
in the contract will become quite difficult with this schedule.
Because of scheduling between both contractors, we have many questions as below.
- Lot I: Did you revise the above roof schedule?
- Lot I: Completion of columns up to at Elv.972.97 is scheduled middle of September. Coping
with overhead crane installation by Lot III, let us know your completion schedule of beams
for overhead crane.
- Lot I & Lot III: Which contractor will cover installation of rails for overhead crane?
- Lot III: Considering of the power house No.1 inside condition, do you need roof before your
overhead crane installation?
- Lot I: Can you install the roof after overhead crane installation?
- Lot III: Completion of Slab at Elv.964.50 (Erection bay) will is scheduled on August 28.
Could you study possibility of your equipment installation from this slab?
- Lot II: Are you still keep the following schedule as of today?
Transport date of Pipe No.105 on site on August 24 and Installation for 38 days.
Do you have any comments on this schedule?

8. No. 1 Tail Race Gate & Hoist (item 12)


- When time schedule of fabrication, transportation and installationsubmit (include Headrace
Inlet Gate, No. 2 Tailrace Gate)

No.2 POWER STATION

9. No.2 Diversion Weir


(No Comment)

2|Page
10. . Headrace Inlet Gate and Hoist (Item 20)
(No Comment)

11. . No. 2 Tailrace Gate & Hoist (item 25)


(No Comment)

12. No.2 Outdoor Switchyard


Contractor: Lot I (PP) and Lot III

- On August 2, Lot I and Lot III discussed about partial handing over schedule that Lot I
prepared. Its schedule will be handed over to the Lot III on October 6, 2021 and the joint
inspection will be carried out the September 29 before one week of the handing over date.

- To Lot I, yesterday access road between culvert bridge to Outdoor Switchyard was
impassable due to heavy rainfall and the vehicle could not pass on the road.Coming the rainy
season, Should you consider to improve this issue. Do you consider any countermeasures
work on this issue?

13. No.2 Switchyard Buildings


Contractor Lot I & Lot III
- Lot I schedule of completion of control house for handing over to Lot III.

14. No.2 Upper Penstock Line


Contractor: Lot I (PP) and Lot II

- Last meeting, Lot I and Lot II agreed the target of the handing over is 31 August 2021.

We request Lot I to have joint inspection on 24 August before one week of the handing over
date.

To Lot I, Is its inspection schedule Ok with us?

To Lot II, Is its inspection schedule Ok with us?

- To Lot I, When will you submit the repair method of the concrete slab surface.

3|Page
- When method Statement for Installation No.2 Steel Penstock submit?

15. No.2 Tailrace Outlet


(No Comment)

4|Page