Professional Documents
Culture Documents
Location: 900 Merchants Concourse, 1st Floor Conference Room (Suite 104)
Date: February 21, 2019
Time: 9:00 am
Attendance: See attached Sign-In Sheet
Agenda:
1. Current Projects - New Hyde Park Road Under-Grade Crossing
Utility Relocation Plans
Construction Schedule
Progress Reporting
2. Upcoming Projects – See Attached Design/Construction Schedule
Altice:
1. Utility Relocation Plan: Issued 10/18/18
2. Construction Schedule: Started 12/18/18
3. Progress Report (Status):
Percent Complete – 85%
Estimated Completion – Mid March
Conflicts/Observations – None reported
Requirements by Others – 3TC noted that PSEG replacing riser pole # P3 on Clinch
Ave, pole to be placed near existing for easy transfer.
AT&T:
1. Utility Relocation Plan: N/A
2. Construction Schedule: N/A
3. Progress Report (Status): N/A
No utilities on NHPR
No representative present at meeting
PSEGLI:
1. Utility Relocation Plan: Issued 1/30/19
2. Construction Schedule: Start 2/26/19 (EJ Electric)
3. Progress Report (Status):
Percent Complete – 0% Poles will be staked on 2/23/19 for field review & analysis
Estimated Completion – Late March
Conflicts/Observations – Install temp pole prior to demo of 115 NHP (permanent
location)
Requirements by Others – 3TC to stake poles and release for installation
National Grid:
1. Utility Relocation Plan: Issued 3/2/18
2. Construction Schedule: Started 1/22/19
Installed south main dry 1/22/19 – 2/6/19
ROW jacking week of 2/25/19
NHP North waiting on 115 NHP Demo
3. Progress Report (Status):
Percent Complete – 70% (installing south side house connections 2/21/19)
Estimated Completion – TBD (pending demo of 115 NHPR)
Conflicts/Observations – 3TC noted NHPR street crossing work should be completed
prior to 4/15/19 Covert Ave street closure, NG acknowledged and will schedule
accordingly
Requirements by Others – None reported
Verizon NY:
1. Utility Relocation Plan: Issued 10/1/18
2. Construction Schedule: Started 11/5/18 (Combined Covert & NHPR)
3. Progress Report (Status):
Percent Complete – 50% (previously focused on Covert Ave)
Estimated Completion – TBD following internal meeting scheduled for this week
Conflicts/Observations – (8) high profile customers, new equipment replacing
existing environmentally controlled vault. Equipment order, not all delivered.
Requirements by Others – Completion subject to customer coordination and outage
restrictions. Customers have been notified. Verizon to provide info on potential
environmental hazards within vault (if any).
Verizon Business:
1. Utility Relocation Plan: Issued 2/9/18 (Rev 1)
LIRR #6240 EXPANSION PROJECT
FROM FLORAL PARK TO HICKSVILLE
Under-grade Crossings:
1. School Street (RFC 10/17/19, construction start 6/16/20)
2. South 12th Closure (RFC 10/25/19, construction start 8/14/20)
3. Willis Ave (RFC 10/23/19, construction start 4/10/21)
4. Main Street Closure (RFC 11/6/19, construction start 3/23/22)
Bridges:
1. Cherry Lane (construction in progress):
Relocated: Altice & Lightower
Cleared: National Grid, Verizon NY
PSEG SS Feeders (double track outage push)
2. Nassau Blvd (construction start 5/31/19):
NCDPW Pump Station Electric Service
National Grid, PSEG
3. Plainfield Ave (RFC 5/1/19, construction start 8/30/19)
Relocated: Verizon Business & Altice
Verizon NY underground
4. Glen Cove Road (RFC 6/19/19, construction start 8/13/19):
PSEG, Sanitary Sewer, Water, Verizon, Lightower, Altice
5. Meadowbrook (RFC 4/1/19, construction start 2/29/20):
DOT Messenger Inform
6. Denton (RFC 12/6/19, construction start 1/21/21)
Altice, PSEG, National Grid
Garages:
1. Harrison Garage – Mineola (construction in progress)
PSEG distribution in progress
2. Westbury North Garage (construction start 3/20/19)
Stations:
1. Carle Place Station (construction in progress)
2. Merillon Station (RFC 2/15/19, construction start 3/16/19)
3. Hicksville Station (construction start 4/1/19)
4. Floral Park Station (construction start 5/3/19)
LIRR #6240 EXPANSION PROJECT
FROM FLORAL PARK TO HICKSVILLE