LIRR #6240 EXPANSION PROJECT

FROM FLORAL PARK TO HICKSVILLE

February 22, 2019

Bi-Weekly Joint Utilities Coordination


Meeting Minutes

Location: 900 Merchants Concourse, 1st Floor Conference Room (Suite 104)
Date: February 21, 2019
Time: 9:00 am
Attendance: See attached Sign-In Sheet

Agenda:
1. Current Projects - New Hyde Park Road Under-Grade Crossing
 Utility Relocation Plans
 Construction Schedule
 Progress Reporting
2. Upcoming Projects – See Attached Design/Construction Schedule

New Hyde Park Road Grade Crossing:


 RFC issued 2/22/19
 Underpass Construction Start 6/3/19 (southwest pile line)
 Southwest Traffic Shift 8/2/19 (for southeast pile line)
 Grade Crossing Closure 10/10/19 (install SOE)

Altice:
1. Utility Relocation Plan: Issued 10/18/18
2. Construction Schedule: Started 12/18/18
3. Progress Report (Status):
 Percent Complete – 85%
 Estimated Completion – Mid March
 Conflicts/Observations – None reported
 Requirements by Others – 3TC noted that PSEG replacing riser pole # P3 on Clinch
Ave, pole to be placed near existing for easy transfer.

AT&T:
1. Utility Relocation Plan: N/A
2. Construction Schedule: N/A
3. Progress Report (Status): N/A
 No utilities on NHPR
 No representative present at meeting

Crown Castle / Lightower:


1. Utility Relocation Plan: Issued 2/26/18
2. Construction Schedule: Estimated Start TBD
 Completed pole licensing
LIRR #6240 EXPANSION PROJECT
FROM FLORAL PARK TO HICKSVILLE

 Revised aerial ROW crossing @ Baer/Millers


3. Progress Report (Status):
 Percent Complete – 0% (based on revised ROW crossing plan, start next 2-3 weeks)
 Estimated Completion – TBD, will be completed long before 8/1/19 milestone target
 Conflicts/Observations – None reported
 Requirements by Others – None reported

PSEGLI:
1. Utility Relocation Plan: Issued 1/30/19
2. Construction Schedule: Start 2/26/19 (EJ Electric)
3. Progress Report (Status):
 Percent Complete – 0% Poles will be staked on 2/23/19 for field review & analysis
 Estimated Completion – Late March
 Conflicts/Observations – Install temp pole prior to demo of 115 NHP (permanent
location)
 Requirements by Others – 3TC to stake poles and release for installation

National Grid:
1. Utility Relocation Plan: Issued 3/2/18
2. Construction Schedule: Started 1/22/19
 Installed south main dry 1/22/19 – 2/6/19
 ROW jacking week of 2/25/19
 NHP North waiting on 115 NHP Demo
3. Progress Report (Status):
 Percent Complete – 70% (installing south side house connections 2/21/19)
 Estimated Completion – TBD (pending demo of 115 NHPR)
 Conflicts/Observations – 3TC noted NHPR street crossing work should be completed
prior to 4/15/19 Covert Ave street closure, NG acknowledged and will schedule
accordingly
 Requirements by Others – None reported

Verizon NY:
1. Utility Relocation Plan: Issued 10/1/18
2. Construction Schedule: Started 11/5/18 (Combined Covert & NHPR)
3. Progress Report (Status):
 Percent Complete – 50% (previously focused on Covert Ave)
 Estimated Completion – TBD following internal meeting scheduled for this week
 Conflicts/Observations – (8) high profile customers, new equipment replacing
existing environmentally controlled vault. Equipment order, not all delivered.
 Requirements by Others – Completion subject to customer coordination and outage
restrictions. Customers have been notified. Verizon to provide info on potential
environmental hazards within vault (if any).

LIRR ROW Relocations:

Verizon Business:
1. Utility Relocation Plan: Issued 2/9/18 (Rev 1)
LIRR #6240 EXPANSION PROJECT
FROM FLORAL PARK TO HICKSVILLE

2. Construction Schedule: Start Tentative 2/25/19


• Completed Pole Licensing
• High Speed Loop South – West - S Tyson, Lowell Ave, N 1st , Hillside Ave, Willis Ave
• High Speed Loop North - East - 2nd St., Roslyn Rd., Old Country Road, Post Ave
3. Progress Report (Status):
 Percent Complete – No representative present at meeting
 Estimated Completion – No update, previously reported May-June 2019
 Conflicts/Observations – No update
 Requirements by Others – No update, previously reported need NYSDOT permits for
Hillside Ave work.

Upcoming Projects –Design/Construction Schedules:

Under-grade Crossings:
1. School Street (RFC 10/17/19, construction start 6/16/20)
2. South 12th Closure (RFC 10/25/19, construction start 8/14/20)
3. Willis Ave (RFC 10/23/19, construction start 4/10/21)
4. Main Street Closure (RFC 11/6/19, construction start 3/23/22)

Bridges:
1. Cherry Lane (construction in progress):
 Relocated: Altice & Lightower
 Cleared: National Grid, Verizon NY
 PSEG SS Feeders (double track outage push)
2. Nassau Blvd (construction start 5/31/19):
 NCDPW Pump Station Electric Service
 National Grid, PSEG
3. Plainfield Ave (RFC 5/1/19, construction start 8/30/19)
 Relocated: Verizon Business & Altice
 Verizon NY underground
4. Glen Cove Road (RFC 6/19/19, construction start 8/13/19):
 PSEG, Sanitary Sewer, Water, Verizon, Lightower, Altice
5. Meadowbrook (RFC 4/1/19, construction start 2/29/20):
 DOT Messenger Inform
6. Denton (RFC 12/6/19, construction start 1/21/21)
 Altice, PSEG, National Grid

Garages:
1. Harrison Garage – Mineola (construction in progress)
 PSEG distribution in progress
2. Westbury North Garage (construction start 3/20/19)

Stations:
1. Carle Place Station (construction in progress)
2. Merillon Station (RFC 2/15/19, construction start 3/16/19)
3. Hicksville Station (construction start 4/1/19)
4. Floral Park Station (construction start 5/3/19)
LIRR #6240 EXPANSION PROJECT
FROM FLORAL PARK TO HICKSVILLE

5. Westbury Station (RFC 11/2/19, construction start 6/26/21)


6. Mineola Station (RFC 7/15/19, construction start 4/22/21)

Open Issues / Action Items:


1. S. 12th St Fire Station (3TC coordinating with individual utilities)
2. Verizon NY to provide environmental information on vault.
3. 3TC to provide 60% design drawings to utilities for preliminary review
4. 3TC will provide 30% design drawings as requested (if design is advanced enough)
5. Next Meeting 3/12/19 at 9:00 am to 10:30 am.