March 12, 2018

3rd Track Meeting

1) MPT Utilities next Week. Final package of MPT plan from Munoz.
2) March 23, 2018 should be in Stantec hands and sent to Nassau County in mid-April.
3) Concrete thrust blocks around sanitary 3ft box when you are close to the right away (10’ away).
4) Pump stations may not be allowed. Follow up.
5) Drainage matrix from Stantec. Location, who owns the street and type of drainage.
6) New Hyde Park Need next.
7) Test Pit by Floral Park Viaduct.
8) Cherry Lane also is next.
9) Covert and Urban will be first.
10) Specifications from Cameron office on Nassau County requirements, remind Joe Sehested.
11) Sanitary Survey needed to be checked.