Coordination Meeting Start Install Gate Leaf & Hoist No.

1 Diversion Weir

Agenda
1. Hand Over Date
- The handover date will be determined at the coordination meeting and get
permission from the engineer to start the gate leaf & hoist installation work
2. Confirmation Permission Remove Scaffolding
- To remove the scaffolding, we need 1 day, and we will coordinate with the lot 1
contractor for the removal of the scaffolding. See Figure A
3. Installasi Gate Leaf
- Fit Up and Insert to the slot Only We Need 15 Days. See Figure A
4. Installasi Hoist w4e3
5. only lifting Up and Put Hosit on the pier We need 3 Days. See Figure Chipping Concrete.
- For open Space Hoist, The engineer request for a re-survey, we think it's no problem
if we just put hoist base on the pier
we will place it some distance from the open space hole, so that if we do re-survey it
doesn't interfere with the measurement.
6. Confirmation Permission Remove Handrail Inspection Bridge
- When we start install gate leaf, we need permit to lot I contractor for remove
handrail inspection bridge at around sandflush gate slot. See Figure. B
7. Cleaning Area at front Spillway Gate Block Out
- Clean the work area in front of the spillway gate blockout, because we need a clean area
from mud and water for the gate leaf base, So That we request the Lot I contractor to be
willing to lend us a water pump, while we will provide the electricity power source. and we
will use the water pump every morning. See Figure C.

Figure A.

Barchart Schedule for Installation Spillway Gate, Sandflush Gate and Hoist Spillway Gate
Duration Nov-21
No Activity
(day) 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1. Remove Scaffolding, Prepartion Electrical, Transport Mobile Crane 1 days


2. Installation Spillway Gate Fit-Up Only Without Welding 12 Days
3. Installation Sandflush Gate Fit-Up Only Without Welding 5 Days
4. Assembly Hoist & Install Hoist Only Put on The Pier 3 Days

Note :
= Planning
Figure B. Remove Handrail Inpection Bridge

Only Remove
Handarail Handrail
Inpection Bridge Connection To
of Sandflush Deck Plate Olny
Gate use Bolt & Nut

Figure C. Cleaning Work Area at Front Spillway Gate From Water and Mud

Clean From
Water & Mud