Construction Project Time Line with Proposed Bar Chart

Sidewalk, Drainage & Road improvement for Pedestrian Mobility in


Contract Package NO.

Item Apr-20 May-20 Jun-20 Jul-20 Augst-2020 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21
Name of Work
No. 1 8 16 24 30 1 8 16 24 31 1 8 16 24 30 1 8 16 24 31 1 8 16 24 31 1 8 16 24 30 1 8 16 24 31 1 8 16 24 30 1 8 16 24 31 1 8 16 24 31 1 8 16 24 28 1 8 16 24 31 1 8 16 24 30
Shutter making
Name of
project : 1 × Construction of Swimming & Survival pool

Pile casting
Pile curing
Pile layout & drive
Load test
Earth Excavation
Plie Breaking
Shore Pile For site protection
Water drying
C.C. casting
Reinforcement cutting, Placing and
M/S J R ENTERPRISE

binding binding
R.C.C casting
E/M portion
Filtration media
Site Cleaning and Hande Over

Note:
Agreed by the Contractor
Project Manager / Representative
Contract Package NO.
May-21
1 8 16 24 31
M/S J R ENTERPRISE

Name of
project : 1 ×
Construction of
Swimming & Survival
pool
SL NO Name of WorksDuration of Works
1 Shutter making 20.06.2020
2 Pile casting 02.07.2020
3 Pile curing 28.07.2020
4 Pile layout & drive 10.09.2020
5 Load test
6 Earth Excavation
7 Plie Breaking
8 C.C. casting
9 Rod binding
10 R.C.C casting
11 E/M portion
12 Filtration media
13
14
15
16
Finishedwork
30.06.2020
27.07.2020
26.08.2020
20.10.2020