Professional Documents
Culture Documents
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 1 / 13
R 2023
METHOD STATEMENT FOR CRANE BARGE REPAIRING, WELDING AND CUTTING OPERATIONS AT WEST PIER OF
COMERCIAL PORT
Document No. :
Revision : A00
Date of Issue : 22 September 2023
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 2 / 13
R 2023
Contents
1. Scope of Work................................................................................................................ 3
2. Preparation........................................................................................................................ 4
2.1 Personnel List.................................................................................................................. 4
2.2 List of mechanical equipment and tools...........................................................................5
3. Maintenance Process Steps and Methods......................................................................5
3.1 50 tons truck crane mobilization and setting up...............................................................6
3.2 Flatbed Trailer Truck in place..........................................................................................6
3.3 Lifting the steel plate onto the ship...................................................................................6
3.4 Set up a temporary work platform....................................................................................6
3.5 Steel plate cutting and removal........................................................................................7
3.6 Correction and fixation of steel plate................................................................................7
3.7 Welding work................................................................................................................... 7
4. Safe and civilized construction and environmental protection requirements...................7
4.1 Technical requirements for job safety..............................................................................7
4.2 Safety requirements for lifting operations.........................................................................8
4.3 Safety measures during maintenance..............................................................................9
4.4 Civilized construction measures.....................................................................................10
4.5 Other Safety Measures..................................................................................................11
5. Site Pictures.................................................................................................................. 12
JEC - City Commercial Port Project OFFSHORE
Contract No. REVISION A00
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 3 / 13
R 2023
1. Scope of Work
Yuegongqi 9 (Crane Barge) is docked at the west wharf of the commercial port to wait for
the hoisting and maintenance of the No. 5 floating wharf. Now it is necessary to cut and
replace the rusted steel plates and fenders above the waterline around the ship. A 50-ton
mobile crane assists in hoisting new steel plates and removing old ones.
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 4 / 13
R 2023
Yue Gong qi
58 25 5 1.7 4.2 702
9
2. Preparation
2.1 Personnel List
Table 3: Manpower
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 5 / 13
R 2023
seria
l Specificati quanti
name use
numbe on ty
r
lifting steel
1 Mobile crane 50t 1 set
plate
4
Acetylene &
3 bottle cutting material
Oxygen
s
2
5 Welding Machine 500A welding
units
2
6 Life Jacket Safety
pieces
Floating sequence: Hoist the steel plate to the ship by mobile Crane → Set up a
temporary work platform → Cut and remove the ship plate → Correct and fix the
steel plate → Welding operation → Remove the temporary work platform →
recover materials.
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 6 / 13
R 2023
The 50-ton mobile crane chooses to open the outriggers at the west wharf Pier,
and the outriggers are kept 4m away from the edge of the wharf. The rigger
inspects the slings to be used and sets the safety warning line for lifting operations.
Drive the Trailer Truck to the vicinity of the mobile crane and keep a safe distance
from the truck crane.
The sling is connected to the lifting point of the steel plate, and the tail rope is
fastened. The hoist carefully checks the lifting point and the sling, slowly lifts the
force, and always keeps the balance of the object being lifted. When the lifting
height is reached, the crane rotates slowly to lift the 9th deck. Unoccupied space,
unhook the load until there is no force.
Use angle steel and wooden boards to build platforms according to the required
size, lay wooden boards, and set up safety belt hanging points.
After the platform is set up, a special person is arranged to watch the fire, and the
fire extinguisher is placed. The welder uses gas cutting to cut the steel plate that
needs to be replaced on the platform. so on.
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 7 / 13
R 2023
According to the size of the cut old steel plate, the new steel plate is cut, the lifting
point is set, and the crane is used to hoist it to the side of the ship for correction
and fixing.
The welder uses the welding machine to weld the steel plate, and the welding is
completed. Remove the work platform. Proceed to the next step according to the
above method.
1) Make a detailed maintenance plan, safety technical measures, and specify the
person in charge before operation to ensure efficient and safe equipment
operation.
2) All operators entering the site must abide by and obey the management
requirements of the safety managers on the construction site.
3) Before the operation, the operator should understand the operation plan, unify
the thinking with the commander, and cooperate closely. If the command signal is
unclear or wrong, he has the right to refuse to execute it. Be aware of red flags
sent by others, too.
4) When entering the construction site, Personnel protection Equipments (PPE)
must be strictly and correctly worn according to the requirements.
5) The work area should be segregated, and warning line and warning signs
should be erected around it. Special personnel should be set up on the ground to
command, and special safety personnel should guard outside the work area. Non-
staff personnel are strictly prohibited from entering the construction site.
JEC - City Commercial Port Project OFFSHORE
Contract No. REVISION A00
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 8 / 13
R 2023
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 9 / 13
R 2023
ground Do not lift; do not lift people standing on the hanging objects; do not lift if
the binding is not firm or stable; do not lift heavy objects with sharp edges and no
protective measures.
9 ) During the hoisting process, the commander's whistle must be loud and the
semaphore must be accurate.
10 ) When the equipment is hoisted, the wind force level shall not exceed level 6,
and disassembly operations are strictly prohibited in thunderstorm weather;
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 10 / 13
R 2023
7 ) Weather effects: During the hoisting process, the weather forecast within three
days must be mastered. In case of severe weather such as wind force exceeding
level 6, hurricane, etc., protective preparations must be made in advance and the
operation should be stopped.
8) Relevant operating permits must be obtained before operation, special
personnel must be arranged to watch the fire on duty for hot work, and seat belts
must be hung high and low.
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 11 / 13
R 2023
and ensure that workers’ rest area and work area are sufficiently away from
moving traffic.
Heat stress awareness shall be given to workers during regular pre task
briefing and workers will be given 10 minutes of rest break every 1 hours
and electrolytes such as Oral Rehydration Salts (ORS) shall be made
available. Working in the outdoor during the 12:00 Pm to 03:00 will be
completely restricted and ensure that workers get enough rest during that
time.
All electrical tools and equipments, cables shall be inspected on a monthly
basis by the electrician and install monthly colour coding. All defective tools
and equipments shall be removed from the site. Proper cable management
practice shall be followed.
Housekeeping and waste management shall be done on a regular basis and
ensure no loose materials, waste materials get airborne and reach the sea.
The site supervisor and HSE officer shall ensure that 100 per cent PPE
Compliance is maintained always and ensure that every workers is provided
with basic PPE.
A detailed job safety analysis has been prepared and the method statement and Job
safety Analysis will be communicated to the workers and site supervisor and safety
officer shall ensure that the work is carried out as per the method statement and
job safety analysis.
All workers shall wear life jacket full time and keep themselves from the edges of the
ship or work platform
5. Site Pictures.
JEC - City Commercial Port Project OFFSHORE
Contract No. REVISION A00
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 12 / 13
R 2023
JEC - City Commercial Port Project OFFSHORE
Contract No. REVISION A00
22
ISSUED BY CHEC ISSUED DATE SEPTEMBE PAGE 13 / 13
R 2023
Welder Certificate