SASAL TRAD. CONT. CO. L.L.

C
S AS AL
MATERIAL APPROVAL SUBMITTAL

Material Submittal Number:01 Date: 30.05.2023

Project Number: DH‐NZW-E-141‐2023 Location: AL MARA


Project Name: EXTENSION OF POWER SUPPLY TO HOUSE OF MR. SALEEM SALMAN MARGHOUN AL TOBI
List of Materials:

Sl Manufacturer& country DCRP active product


Material Description Supplier / Agent
No. of origin list reference
400A, 6WAY MFP WITH
01 TALENT, NEI TALENT, NEI 6.1.3
PANEL LIGHT
4Cx50‐120mm2 cable
02 REYCHAM, YAMUNA ZAWAWI Trading 9.1
termination & Joint
BRASS CU & ALLOY LTD,
03 16SQMM EARTH ROD ELITE, GLOBAL 17.2.2
CITIZEN
04 70mm Y/G Earth wire Oman cable Industries OCI 17.2.2

05 Caution tape Oman Plastics Global international 1.7.4


Route Marker, Plinth Set
06 SASAL TRAD SASAL TRAD
& Earth Chamber
07

08

09

10
Use additional sheet if required

Contractor: (Name, Signature & stamp) MZEC:


Approved Not Approved

(Name, Signature & stamp)


Comments:

Note:
1. This approval does not relieve the Contractor of his responsibilities / obligations under the unit price Tender 01/2019
2. Approval subject to compliance with Oman Electricity Specifications (OES).
3. Test certificates shall be submitted at the time of material delivery.

Issue: 01, Rev: 00 01 April 2018 Doc # MZEC‐PM‐Ext‐F‐001 Page 7 of 10


SASAL Trade Cont Co LLC,Ibri, Oman

PROJECT EXECUTION SCHEDULE

Work order number : DH.NZW.E.141.2023 Location: MARA Work order issued date : 21.05.2023

Completion date as per work order : 04.07.2023


Project Title :EXTENSION OF POWER SUPPLY TO THE HOUSE OF MR.MOHAMMED SALIM OMAR AL HASHMII

EXECUTION PLAN
Contractor: SASAL TRAD & CONT. CO. L.L.C

Duration Month 1 Month 2 Month 3 Month 4


Sl. Activity Start Date End Date
(days) week1 week2 week3 week4 week1 week2 week3 week4 week1 week2 week3 week4 week1 week2 week3 week4
Collection of Work Order, BOQ
1 and Drawings from MZEC Office 21.05.2023 22.05.2023 2

2 Approvals from Authorities 23.05.2023 19.06.2023 28

3 Trench Excavation, 20.06.2023 26.06.2023 7

4 Equipment Erection 27.06.2023 29.06.2023 3

5 Final Inspection & Testing 30.06.2023 04.07.2023 5

Contractor's Engineer (name & Sign) For MZEC

Issue:01, Rev:00, 01 Apr 2018 Doc # MZEC-PM-Ext-F-002 Page 1 of 1