You are on page 1of 7

SCON PROJECTS PVT LTD.

Client Name: - M/S. DR. REDDY’S LABORATORIES

Consultant Name: - Arnita Consultants Pvt. Ltd

Location: - VIZAG

INSTALLATION METHODOLOGY OF FIRE WATER TANK

Arnita M/S. DR. REDDY’S


WMS No. Rev. No. Date SCON
Consultants LABORATORIES

SCON/MEP/WMS/FT/01 R0

Signature:

Name:

Date & Time:

-
1. PREPARATION BEFORE INSTALLATION:

After confirming the diameter and height of tank this point must be checked before
starting installation of tanks.

1. Raft or tank platform must be leveled and stable prior to construction.

2. Ensure raft is larger than the diameter of your tank and is free of all
sharp objects like nails, stones and debris.

3. Slope is not recommended for the installation of the tank.

Tank Raft
2. INSTALLATIONOFTANK:

Pictorial Installation Process by Jack & Chain Pulley Block System:

For the lifting of GI panels, we will be using the chain block System as shown in the
below picture and will be lifting the panels safely as per the photographs below

1. There are 5 rings in the tank. Height of each ring is 1250 mm.

2. Tank will be installed from top to bottom, top ring being the first to get installed.

3. One ring consists of 10 panels of 2.5 m length each which will be bolted
together to form a ring.

4. We are providing Geo Textile for the cushioning Purpose over the raft.

5. Ring 1 will be installed first and with the help of jacks and chain pulley will be
pulled up.

6. Subsequently ring2,3,4 and bottom ring 5 will be installed.


7. As per drawing cut tank sheet for required no of outlet and inlet, also cut sheet
for drain, overflow.
8. Backing plate and nozzles should be attached to outlet and inlet fitting.

9. Use special kind of adhesives at the outlets and inlets to make the tank leak proof.

10. Manhole and air ventilation fan to be mounted on the roof.

11. Outside ladder, Level Indicator installation and water testing will be carried out.
PICTORIAL VIEW OF TANK AFTER INSTALLATION
COMMISSIONING:
i. At the completion of the tank assembly process on site, the tank will be
filled with the initial 200mm of water and/or ready the tank for
commissioning prior to departing site.

ii. At the completion of the assembly process it is normally part of the


procedure to test the tank to capacity. The testing of the tank will usually be
subject to availability of water for testing purpose and availability of
isolating valves required to isolate or close off the nozzles on the tank.

iii. If the tank can be tested, the tank should be filled to overflow level and
held for 24hours.The tank should hold water to the same level for the 24-
hour period without change to the top water level-allowance or
evaporation is assumed to be minimal.

iv. When the test is completed, the water can be drained from the tank.

v. If water is not available for testing, the initial fill to 200mm must be on
immediately on completion of the assembly of the tank. This must again be
maintained until the tank is ready for placement in to service.

vi. NOTE–The placement of the initial 200mm of water is more critical for the
open top tank than for the roof and tank given the exposure to the high winds
and no protection available from a roof system. Also there is a higher risk of
evaporation with the open top tank and there should be constant monitoring
of the water level to ensure that the water level is maintained at
theoriginal200mm minimum.

You might also like