Professional Documents
Culture Documents
RAS LAFFAN PETROCHEMICAL PROJECT (RLPP)WASTEWATER TREAMENT PLANT (WWTP) MECHANICAL & CIVIL
DOCUMENTS AT RAS LAFFAN
S/N
1
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
66
67
68
RESPONSE TO RLC COMMENTS FOR VI/D/IEE/23/735/2240
RAS LAFFAN PETROCHEMICAL PROJECT (RLPP)WASTEWATER TREAMENT PLANT (WWTP) MECHANICAL & CIVIL DESIGN
DOCUMENTS AT RAS LAFFAN
Comment
1. Road plan and profile # 65-CVRD-00001, Rev-1, Road plan and profile.
a) Pathway shall be asphalted and constructed up to all plant equipment and tank isolation valve
locations.
Please avoid gravel spreading on rest of the area of light duty pathway as well as
heavy-duty area. Gravel is not convenient for personnel movement, as well as for Self-loader/
crane positioning.
Soil around the area shall be well compacted for occasional movement with
self-loader (5T)/ crane.
b) The depth of GRP pipe installation shall be suitable for crossing a vehicle weight not less than
5ton.
1- Balancing tank:
a. Dismantling joint to be installed for 14” isolation valve.
b. Pump discharge pipe: Drain nozzle to be installed between pump and NRV.
3- Aeration tank:
a. Isolation valve to be installed on tank nozzle and with dismantling joint.
b. Isolation valve to be installed between aeration tank and secondary settling tank.
4- RAS/WAS pumps:
a. Pump suction pipe: drain nozzle to be installed between pump and suction solation valve.
b. Pump discharge pipe: Drain nozzle to be installed between pump and NRV.
c. Jacking bolts to be installed on motor baseplate for motor alignment.
9- TSE tank:
a. Isolation valve to be installed on tank nozzle with dismantling joint.
f. All GRP and valves flange shall be flat face type and raised face is not acceptable.
g. GRP joint type shall be laminated, and other types of joints are not acceptable.
h. As liquid is corrosive media the GRP pipe internal and external liner thickness shall be 1mm
QatarEnergy requires all piping layouts / General Arrangement Drawings (GAD) for our review and
approval. Also, piping configuration and plant utilities pipeline routing shall be presented to
QatarEnergy for further acceptance.
QatarEnergy has reviewed the Piping Specification and finds it acceptable in principle. However, the
responsibility of proposed material review and approval rests with RLPP-PMT, to ensure the suitability
& safety of the piping system as per applicable codes and standards. QatarEnergy bears no
responsibility for any failure of defects in the design and construction.
AL & CIVIL DESIGN
Reply
*As earlier agreed with RLIC, concrete walkways / paving has already been provided. We will provided 40mm Ashpalt layer
over the concrete Pathway.
* As advised Gravel has been removed
*Soil is compacted at 95% of the MD and have a a minimum bearing capacity of 100 KN/m2 (10.2 Ton/m2) as referred in the
Geotechnical Report which cover occasional crane/Vehicles.
Light duty vehicles (Up to 2 ton), which are normally required for O&M, can circulate safely all over the plant area.
However if a heavy vehicles (above 5 ton) is required to cross the pipe corridor as a special case, a steel sheet shall be
provided over the pipe coridors.
The average pipe depth is 1.5 m below ground with a minimum 1 m.
The elevation are provided in the over all Piping Layout.
GRP pipes can be moved back or side ways to install the Valves. . There are no dismanteling joints provided in NFE WWTP
project also. In NFE it was demostarted and accepted.
Platforms or step ladders are provided wherever not accessible to the operator for normal O&M.
There is pump casing drain to drain the liquid from the pump casing.
At the suction there is a counter spool with a cap where the pipe can be completely drained .
Drains are provided between the check valve & the isolation valve to drain out the liquid from the CV body .
To inspect the valve internals by removing the top plate of the check valve. How ever the pipe drains are not provided for
the removal of the Isoation valve. This was also not part of the Hazop Causes & Consequences.
The motor & the pump are on the same base plate factory aligned , If dismanteled during maintenance Alignment are
carried out as per the vendor recommendations illustrated in the installtion manual.
TRV Not required. The valves in the discharge line to be taged as lock open.
This was also the recommendation in the hazop to tag the Valves where required.
PRV is not required since the Pump casing or the internals are tested at factory for the pressure above the shut of Head of
the pump .
Platforms or step ladders are provided wherever not accessible to the operator for normal O&M.
Noted
Isolation Valve is installed between the distribution chamber & the Aeration tank , dismateling joint not required in GRP
piping system, pipe size is 200mm dia pipe
Valve is not required between Aeration Tank & the secondry settling tank , if the secondry tak is under maintennce the
isloation vale to the areation tank is closed.
There is pump casing drain to drain the liquid from the pump casing.
At the suction there is a counter spool with a cap where the pipe can be completely drained .
Complied
The motor & the pump are on the same base plate factory aligned , If dismanteled during maintenance Alignment are
carried out as per the vendor recommendations illustrated in the installtion manual.
TRV Not required. The valves in the discharge line to be taged as lock open.
This was also the recommendation in the hazop to tag the Valves where required.
PRV is not required since the Pump casing or the internals are tested at factory for the pressure above the shut of Head of
the pump .
Platforms or step ladders are provided wherever not accessible to the operator for normal O&M.
Noted
GRP pipes can be moved back or side ways to install the Valves. . There are no dismanteling joints provided in NFE project.
In NFE it was demostarted and passed
Isolation Valves are installed at the tank nozzle at places where the nozzle is below the water level.
Platforms or step ladders are provided wherever not accessible to the operator for normal O&M.
Platforms or step ladders are provided wherever not accessible to the operator for normal O&M.
Filter drain pipe is hold on guided type as shown in the drawing. The support is sliding not fixed
Platforms are installed at 3 places where the flow meter is not reachable/ viewed by the operator
Complied
GRP pipes can be moved back or side ways to install the Valves. . There are no dismanteling joints provided in NFE project.
In NFE it was demostarted and passed
GRP pipes can be moved back or side ways to install the Valves. . There are no dismanteling joints provided in NFE project.
In NFE it was demostarted and passed
Platforms or step ladders are provided wherever not accessible to the operator for normal O&M.
Noted
Item -3 : ELEVATED COMPACT INLET WORKS - SS 316 L
Item-7 : MANUAL BAR SCREEN - SS 316
Item -38: POLYMER PREPARATION UNIT MIXERS -HDPP
Item -47: LIME SCREW CONVEYOR -SS 316
Item-50: LIME/ DEWATERED SLUDGE MIXER -SS 316
Item - 51: DEWATERED SLUDGE CONVEYOR - SS 316
In Waste water treatment plants Austenitic grades are used both SS 316/SS 316L are used.
The diffrence is only low carbon in SS 316L which is more resisitance to corrosion used mainly in Pipes where the pipes have
to handel pressure .
However in non Pressuried equipments SS 316 is suitable for WWTP plant Equipments . All the above equipents are
operating at atmospheric pressure.
However in the the lime area after the Beltpress the sludge handeled is 15 %-18% concentration sludge , the the effect of
corrosing is minmal that in intial process stages.
All valves are Hand wheel operated refer to Valve schedule TR Number:
GRP pipes can be moved back or side ways to install the Valves. . There are no dismanteling joints provided in NFE project.
In NFE it was demostarted and passed
GRP pipes can be moved back or side ways to install the Valves. . There are no dismanteling joints provided in NFE project.
In NFE it was demostarted and passed
Platforms or step ladders are provided wherever not accessible to the operator for normal O&M.
Platforms or step ladders are provided wherever not accessible to the operator for normal O&M.
GRP pipes can be moved back or side ways to install the Valves. . There are no dismanteling joints provided in NFE project.
In NFE it was demostarted and passed
Noted Design review /Hqazop was conducted and all the recoendation & action pionts are Incorporated
Noted