WORK TIME CERTIFICATE

PROJECT : Install Pump CEP U1A Indramayu


CUSTOMER : PJB PLTU Indramayu
End User : PJB PLTU Indramayu
PRODUCT NO : PS521215/SO21000327 PO (Tori) No. :
Unit Service : JOB (Tori) No. :
Location : Indramayu , Jawa Barat SV Name : SURYANTO
Job Description : Install Pump CEP U1A Indramayu

Normal Over
No. Date Acc No. Day Open Close Description Coment
Time Time

perjalanan menuju site, Safety Induction, Unbolting piping and


1 8-Jan-24 Senin 08.00 22.00 9 5 uninstall Electromotor

Cleaning Barrel Pit (drain) and Pump Sole Plate, Install NewPump
2 9-Jan-24 Selasa 07.00 22.00 9 6 set onbarel pit

remove sleeve mc seal, remove sleeve nut, machining sleeve mc


3 10-Jan-24 Rabu 07.00 21.00 9 5 seal and sleeve nut, install mc seal, bearing, bearing housing and
pump sole plate

4 11-Jan-24 Kamis 07.00 19.00 9 3 Pump Coupling Alignment And setting Axial coupling

5 12-Jan-24 Jumat 07.00 18.00 9 2 Solo Test motor And Couple Coupling

6 13-Jan-24 Sabtu 07.00 19.00 - 12 Couple Coupling And Fueling oil Cooling Bearing

7 14-Jan-24 Minggu 07.00 19.00 - 12 Install piping and baricade unit for commissioning

8 15-Jan-24 Senin 08.00 17.00 9 0 Prepare tools and travel to mm2100

10

11

Reported by : Checked by :

SURYANTO Mr.
Date : 15/01/2024 Date :