Normal Over
No. Date Acc No. Day Open Close Description Coment
Time Time
perjalanan menuju site, Safety Induction, Unbolting piping and
1 8-Jan-24 Senin 08.00 22.00 9 5 uninstall Electromotor
Cleaning Barrel Pit (drain) and Pump Sole Plate, Install NewPump
2 9-Jan-24 Selasa 07.00 22.00 9 6 set onbarel pit
4 11-Jan-24 Kamis 07.00 19.00 9 3 Pump Coupling Alignment And setting Axial coupling
5 12-Jan-24 Jumat 07.00 18.00 9 2 Solo Test motor And Couple Coupling
6 13-Jan-24 Sabtu 07.00 19.00 - 12 Couple Coupling And Fueling oil Cooling Bearing
7 14-Jan-24 Minggu 07.00 19.00 - 12 Install piping and baricade unit for commissioning
10
11
12
Reported by : Checked by :
ASTOMO Mr.
Date : 15/01/2024 Date :