NATIONAL ALUMIUM COMPANY LIMITED

STEAM AND POWER PLANT


DAMANJODI-763008
BAR CHART OF BOILER OVERHAULING (MECH)
Starting date -09/10/2021 M/S.ROTODYNE ENGINEERING SERVICES PVT.LTD Hydro test expected -06/11/2021
BOILER NO:3 OR-443
Dates 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7
S.NO ACTIVITIES /DAYS----- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 Valve servicing

2 Coal & oil firing system Servicing

3 Air Preheater Servicing

4 Servlcing of Soot blower

5 Servicing of De-aertor, FWT & MWT

6 Fabrication & Erection of plate wok

7 Painting of Equipment

8 Commissioning and Light up activties

1 SIGNATURE OF CONTRACTOR 2 SIGNATURE OF ENGINEER INCHARGE


1 SERVICING OF BOILER VALVES
SL.NO JOB ACTIVITIES ESTIMATE DATE ACTUAL DATE OF MAN POWER
COMPLETION
1 Boiler:- Air vent valve 8/18/2021
2 Drum RHS valve 19/
3 Drum LHS valve
4 Economiser inlet
5 Firing floor HFO & LDO
6 Firing floor crn valve
7 Filling header and super heater
8 Drain valve
9 Motorized valve
BFP:-
1
ENG/SUP. BOQ RATES REMARKS