You are on page 1of 50

FACTORY TEST ITP No.

SAD/02/12
SIEMENS PROCEDURE
ARABIA ELECTRIC LTD (E) REV No. 0
ENERGY AUTOMATION

SAUDI ELECTRICITY COMPANY


(EASTREN REGION)

CONSTRUCTION OF SADARAH 380/230kV BSP IN JIC-2


SEC CONTRACT NO. 31133112/00

FACTORY TEST PROCEDURE


FOR

SUBSTATION AUTOMATION SYSTEM

SIEMENS LTD.
P. O. BOX 4621, JEDDAH 21412
SAUDI ARABIA

15-2-2012 FAT Procedure SAS (Rev. 0) Page 1 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
FACTORY TEST ITP No. SAD/02/12
SIEMENS PROCEDURE
ARABIA ELECTRIC LTD (E) REV No. 0
ENERGY AUTOMATION

CONSTRUCTION OF SADARAH 380/230kV


1 Project Name : BSP IN JUBAIL INDUSTRIAL CITY-2
SEC Contract No. 31133112/00
2 Client's PO. :

3 SIEMENS Contract No. : WBS # 79OP-00086.P

4 Name of Manufacturer : SIEMENS LTD.,

: ARABIA ELECTRIC LTD. (E)


5
Place of FAT & address P. O. Box 4621
Jeddah 21412
Saudi Arabia

6 Contact person : Mr. MUHAMMAD IQBAL

: Tel No. (02) 661 9931


7 Telephone No. / Telefax No.
Fax No. (02) 661 9031

15-2-2012 FAT Procedure SAS (Rev. 0) Page 2 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Table of Contents

1 GENERAL...........................................................................................................5

1.1 The purpose of this document............................................................................................ 5

2 STATION LEVEL................................................................................................6

2.1 System Configuration.......................................................................................................... 6


2.1.1 Hardware check............................................................................................................... 6
2.1.2 Redundant Substation Controller SICAM PAS Fullserver................................................8

2.2 Communication................................................................................................................... 11
2.2.1 IEC 61850 Protocol....................................................................................................... 11
2.2.2 RuggedCom Switch RSG 2100 with IEC 61850 Communication Protocol....................12
2.2.3 Checking LED’s of RuggedCom Switches and accessing the switches........................12

2.3 Special Functions............................................................................................................... 15


2.3.1 Time Synchronization with Redundant GPS Timer Server as Master Clock..................15

2.4 Monitoring........................................................................................................................... 19
2.4.1 Acoustic Horn Activation via Binary Contact..................................................................19

3 BAY LEVEL......................................................................................................20

3.1 Communication of the Bay Devices to the Station Level via the IEC 61850 Protocol. .20
3.1.1 Optical connection......................................................................................................... 20

15-2-2012 FAT Procedure SAS (Rev. 0) Page 3 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

3.2 Special Functions............................................................................................................... 23


3.2.1 Time synchronization via SNTP.....................................................................................23

3.3 Monitoring........................................................................................................................... 23
3.3.1 Indication Transmission via IEC 61850 Protocol at the HMI..........................................23
3.3.2 Indication Display at the Bay Device with Graphic Display............................................24
3.3.3 Optical Indication Display at the Bay Device with LEDs................................................25

3.4 Control................................................................................................................................. 25
3.4.1 Commands processing with the IEC 61850 Protocol....................................................26
3.4.2 Changing the Switching Authority (LOCAL/REMOTE) at the Bay Device with the Key
Switch 26

3.4.3 Control at the Bay Device with Graphic Display............................................................27


3.4.4 Bay and Substation Interlocking on Bay Level...............................................................28

3.5 Measurement....................................................................................................................... 31
3.5.1 Measurement Acquisition with Direct Connection to CT/VT..........................................31

3.6 Timing Test.......................................................................................................................... 31


3.6.1 Binary Input status in BCU & HMI......................................................................................32
3.6.2 Goose message running through time...............................................................................33

4 HMI....................................................................................................................32

4.1 System Configuration........................................................................................................ 33


4.1.1 HMI Configuration – Redundant Servers used as Two-Station System........................33

4.2 Operator Control and Monitoring – Display Structure and Navigation..........................35


4.2.1 Operating Concept with SICAM PAS CC.......................................................................35
4.2.2 Status Bar...................................................................................................................... 36
4.2.3 Login and Logout with SICAM PAS CC.........................................................................36
4.2.4 User Administration with SICAM PAS CC.....................................................................38
4.2.5 Displays......................................................................................................................... 41
4.2.5.1 System Overview....................................................................................................... 41
4.2.5.2 Bay Representation in the Detail Display...................................................................42
4.2.5.3 Help Picture............................................................................................................... 42
4.2.6 Indication List................................................................................................................. 43
4.2.6.1 Event List................................................................................................................... 43
4.2.6.2 Alarm list function....................................................................................................... 44
4.2.7 Printing.......................................................................................................................... 46
4.2.7.1 Message Logging with Line Printer............................................................................46
4.2.7.2 Hardcopy.................................................................................................................... 46
4.2.8 PRP Function................................................................................................................ 47
4.2.8.1 Testing PRP Function................................................................................................47

5 TELECONTROL PROTOCOL..........................................................................48

5.1 Control Center Connection with the Telecontrol Protocol IEC-60870-5-101 (Slave).............48

15-2-2012 FAT Procedure SAS (Rev. 0) Page 4 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

1 General

1.1 The purpose of this document

During FACTORY ACCEPTANCE TEST the provided hardware and software solution will be
tested and the results will be recorded.

This test procedure will show the proper function of the provided system. A typical test will be
provided during FAT.

This document is limited for use by Siemens FAT representatives and respective customer
nominated representatives.

Within every test the necessary preconditions have been listed within the notes section prior to
carrying out the test. Columns checked or approved for every item under test are provided
together with one column for remarks. If a test point is not applicable this can be marked in the
column n/a.

The approval ensures that approved tests can be signed and closed off.

Occurring problems will be documented in a List of open Points (LoP). A consecutive number from
the LoP will be entered in the remarks column of the appropriate point.

REFERENCE DOCUMENTS

Below is a listing of the Reference Documents that will be used during the FAT.

Sr.
Document Checklist Status Available
No.
SICAM PAS PANEL PANEL No. 1, 2,
1
3,4,5,6,7
2 SYSTEM ARCHITECTURE DIAGRAM
3 STATION SINGLE LINE DIAGRAM
4 Switches interfaces
5 Substation SU Controller Manual
Substation Automation System
6
Overview Diagram
Substation Automation System
7
Signal list (incl. I/O assignment)

15-2-2012 FAT Procedure SAS (Rev. 0) Page 5 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 1

Description:
 Check that necessary documentation for equipment as listed above is available in hard copy
and soft copy

Result:
 Necessary documentation for equipment under test is available

Sr.No. Description checked approved n/a remarks

1 Equipment List check

2 Station Level

2.1 System Configuration


2.1.1 Hardware check

The purpose of this test is to check hardware components of the substation controller.

Hardware checklist

Sr. Qty Device


Description n/a remarks
No. (Nos) available

SICAM PAS Station Unit (FS)


2
1 Type ...................................

SICAM PAS Station Unit (GW)


2
2 Type ..............................................

Engineering Work Station (EWS)


3 1
Type ..................................

HMI Computer 2
4
Type ....................................

Ethernet Switches
5 Type..................................................
Ethernet Switch
6 Type ..................................................
........
Event List Printers
7 1
Type…………………..

Laser Color Printer


8 1
Type..............................

HMI 24”-LCD Flat Screen Monitors


9 4
Type ..................................

HMI 42”-LCD Flat Screen Monitor


10 1
Type ..................................

15-2-2012 FAT Procedure SAS (Rev. 0) Page 6 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

GPS time receiver 2


11
Type………………..

Test scenario 1 : Hardware - Completeness check

Description:
 Completeness check according to above hardware checklist

Result:
 The hardware components of the substation controller are complete

Sr.
Description checked approved n/a remarks
No.

1 Hardware components check for the


PAS panels

Test scenario 2 : Hardware Installation & operational inspection

Description:

Sr.
Description checked approved n/a remarks
No.
All equipment is free of
1 foreign materials (dust,
loose wires etc.)
All devices are mounted in
2 line with the GA (general
arrangement)
Labels & Markings on
3 front /rear /internal &
external of panels
Panel Dimensions, Colour
4 Selection, Locking System,
etc.
Visual inspection: Units
5 and individual devices are
fixed firmly & damage free
Visual inspection: Correct
6
wiring practices (RJ45, FO)
Proper earth ground shield
7
connections
Proper wiring in cable
8
troughs
Terminal blocks and MCB’s
9
are mounted properly
Top Fan connectivity &
10
operation check

15-2-2012 FAT Procedure SAS (Rev. 0) Page 7 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Panels lighting & door


11
switch operation check
Panels heater & thermostat
12
operation check
Front panel mounted
13
devices healthiness check

2.1.2 Redundant Substation Controller SICAM PAS Full server

Test scenario 4 : Hardware – Connectivity Check

Sr.
Description checked approved n/a remarks
No.

1 Switch interconnection

Substation Controller &


GW connections as per
2 System Architecture to the
switch at correct port
designations
HMI connections as per
System Architecture to the
3
switches at correct port
designations
Engineering Work Station
connection as System
4
Architecture to the
switches at correct port
Connection of time GPS to
5 the substation automation
system
Connection of bay device
6
loops

Test scenario : 5 startup check

Description:

Test requirements:

The substation controllers are switched off.

The check is performed after startup of the substation controllers via a remote desktop connection
between a PC and the substation controllers (P11 / P21).

 The substation controllers are switched on

15-2-2012 FAT Procedure SAS (Rev. 0) Page 8 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Result:
 PAS starts on both FS (check with SICAM PAS Operation)
 One substation controller is the master (it is connected to the HMI)
 The other substation controller is the not connected to the HMI (it is the slave)
 Communication between FS master and PAS CC is carried out (open System Overview at
HMI and check the display of the communication links)
 Communication between the two substation controllers and the IEC61850 bay devices is
carried out (check with SICAM PAS Operation)

Sr.
Description checked approved n/a remarks
No.

1 Startup check

Test scenario 5b : Faults on monitoring system start up-test

Description:

During the FAT it shall be checked, if the faults listed in the alarm list are plausible.

Note:
The followings are few typical alarms only.

Sr.
No. Alarm as per alarm list (typical alarms only)

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

15-2-2012 FAT Procedure SAS (Rev. 0) Page 9 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 6 : Redundancy test 1

Description:

Test requirements:

Undisturbed network between the IEC61850 bay devices and the redundant substation controllers

Bay devices and substation controllers operational


 Information is generated by test simulation at a bay device

Result:
 Identical information on both substation controllers (can be checked in PAS by using the
SICAM PAS Value Viewer)

Sr.
Description checked approved n/a remarks
No.

1 Redundancy Test 1

Test scenario 7 : Redundancy test 2

Description:

Test requirements:

Connection to the HMI is established and one substation controller is the master.
 Switch off the master

Result:
 The slave becomes the master (check with SICAM PAS Operation)
 The HMI is connected to the new Master (check with SICAM PAS Operation)
Sr.
Description checked approved n/a remarks
No.

1 Redundancy Test 2

Test scenario 8 : Teaming card function check

Description:
 The HMI computers are connected in a redundant way to the network. Either the respective
data flows via the first OR the second connection
 The loss of either the first or the second connection must not lead to loss of the HMI
connectivity. The loss of the HMI connectivity can be identified by the screen.

15-2-2012 FAT Procedure SAS (Rev. 0) Page 10 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Teaming function check HMI1


Sr.
Description checked approved n/a remarks
No.

Verify that the HMI1 is not


1
affected.

Reconnect the first LAN


2 connection and verify that
HMI1 is still not affected

Remove the second LAN


connection of HMI1.
3
Verify that the HMI1 is not
affected.

Reconnect the second LAN


4 connection and verify that
HMI1 is still not affected

Teaming function check HMI2


Sr.
Description checked approved n/a remarks
No.

Remove the first LAN


connection of HMI2.
5
Verify that the HMI2 is not
affected.

Reconnect the first LAN


6 connection and verify that
HMI2 is still not affected

Remove the second LAN


connection of HMI2.
7
Verify that the HMI2 is not
affected.

Reconnect the second LAN


8 connection and verify that
HMI2 is still not affected

2.2 Communication
2.2.1 IEC 61850 Protocol

Following tests shall be executed to verify the functionality of communication interface for protocol
IEC 61850 of the substation controller.

Test requirements:

Communication cable plugged into switch ports.

Communication network undisturbed.

15-2-2012 FAT Procedure SAS (Rev. 0) Page 11 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Check the current state of data link with SICAM PAS UI - Operation.

Test scenario 1

Description:
 Remove two communication cable from the RSG switches for one switch

Result:
Blue arrows in SICAM PAS UI indicate the active interface and the broken link to the system

Sr.
Description checked approved n/a remarks
No.

1 Switch communications broken

Test scenario 2

Description:
 Establish the disconnected loop again by plugging in the removed cables

Result:
Green arrow in SICAM PAS UI indicates the active interface and the link to the system has been
established

Sr.
Description checked approved n/a remarks
No.

1 Switch communications restored

2.2.2 RuggedCom Switch RSG 2100 with IEC 61850 Communication Protocol

The purpose of this test is to verify error-free communication between the switches and the devices
of the substation automation system via the IEC 61850 protocol

Test requirements:

Communication cable plugged into switch ports

Communication network undisturbed

Test scenario 1

Description:
 Remove and plug in the communication cables of one of the RSG2100 switches. Do this port
wise (one port after the other to disconnect and then to reconnect)

Result:
 Disconnected port is indicated in the HMI (list or picture)

15-2-2012 FAT Procedure SAS (Rev. 0) Page 12 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.
Description checked approved n/a remarks
No.

1 Switch communications HMI


indications check

Test scenario 2

Description:

 Remove one end of an existing Control loop fiber optic connection at the RSG2100 switch
 Verify that the affected RSG2100 Ethernet port is announced as faulty in the HMI and
that all other devices within the loop are not affected and remain undisturbed and in service
even if the network is being reconfigured
 After some 10 seconds reconnect the FO cable and verify if all devices keep undisturbed in
service
 Repeat the tests above for all protection & control loops

Sr.
System Loop checked approved n/a remarks
No.

1 380 kV Control Loop

2 230 kV Control Loop

15-2-2012 FAT Procedure SAS (Rev. 0) Page 13 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

2.2.3 Checking LED of Rugged COM ports and accessing the switches

Switch Name: ________________

Port Number USED LED REMARK


1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Accessing to the switch …………………..

Note: The above table can be used for different switches separately and shall be enclosed along
with test protocol during testing.

15-2-2012 FAT Procedure SAS (Rev. 0) Page 14 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

2.3 Special Functions


2.3.1 Time Synchronization with Redundant GPS Timer Server as Master Clock

The purpose of this test is to verify time synchronization of the substation controller and connected
peripherals (HMI, bay devices).

The following tests are very time consuming since the SAS databases time synchronization
needs a certain time due to its size and complexness.
It shall be decided during the FAT, if all tests shall be done. The target of achieving the SAS
FAT certificate shall not be affected by the decision.

Test requirements:

The substation controller receives a valid GPS time signal from one of the redundant GPS Time
Servers (GPS receiver 1, GPS receiver 2).

Test scenario 1 :

Description:
 Manually setting (change) of the time of the substation controller (e.g. in a console window
using the TIME command)

Result:
 After some time, the substation controller has obtained the current time again from the GPS
 The connected peripherals have the right time, too

Sr.
Description checked approved n/a remarks
No.

1 GPS Synchronizing

Test scenario 2 :

Description:
 Manually setting (change) of the time at HMI PC (e.g. in a console window using the TIME
command)

Result:
 After some time, the HMI PC has obtained the current time again from the GPS

Sr.
Description checked approved n/a remarks
No.

1 Time Synchronizing in HMI

15-2-2012 FAT Procedure SAS (Rev. 0) Page 15 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 3

Description:

Perform the test for connected typical BCUs (if in service)

 Switch off bay device


 Switch on bay device (invalid time in the bay device)
 After some time, simulate indications at the bay device

Result:
 After some time, the bay device has obtained the current time of the time master
 TIME FAULTY indication at bay device is set to OFF
 Indications have a valid time stamp

Sr.
Description checked approved n/a remarks
No.

1 Time Synchronizing in BCU

Test scenario 4

Description:

The purpose of the following tests is to verify the redundancy of the time synchronization.

Test requirements:

The substation automation system is time synchronized by GPS receiver 1.

The System Overview picture is displayed at the HMI.


 Power off GPS receiver 1

Result:
 At the system overview picture GPS receiver 1 is indicated as faulty
 GPS receiver 2 synchronizes the time at the substation automation system

Sr.
Description checked approved n/a remarks
No.

1 GPS redundancy

15-2-2012 FAT Procedure SAS (Rev. 0) Page 16 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 5

Description:
 Power on GPS receiver 1

Result:
 At the system overview picture GPS receiver 1 is indicated as connected
 Indications have a valid time stamp

Sr.
Description checked approved n/a remarks
No.

1 GPS receiver 2 on & 1 off

Test scenario 6

Description:
 Power off GPS receiver 2

Result:
 At the system overview picture GPS receiver 2 is indicated as faulty
 GPS receiver 1 synchronizes the time at the substation automation system

Sr.
Description checked approved n/a remarks
No.

1 GPS receiver 1 on & 2 off

Test scenario 7

Description:
 Power on GPS receiver 2

Result:
 At the system overview picture GPS receiver 2 is indicated as connected
Indications have a valid time stamp

Sr.
Description checked approved n/a remarks
No.

1 GPS receiver 2 on

15-2-2012 FAT Procedure SAS (Rev. 0) Page 17 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 8

Description:
 Disconnect antenna from GPS receiver 1

Result:
 GPS receiver 2 synchronizes the time at the substation automation system
Indications have a valid time stamp

Sr.
Description checked approved n/a remarks
No.

1 GPS receiver 1 cable plug out

Test scenario 9

Description:
 Connect antenna to GPS receiver 1

Result:
 Indications have a valid time stamp

Sr.
Description checked approved n/a remarks
No.

1 GPS receiver 1 cable plug-in

Test scenario 10

Description:
 Disconnect antenna from GPS receiver 2

Result:
 GPS receiver 1 synchronizes the time at the substation automation system
 Indications have a valid time stamp

Sr.
Description checked approved n/a remarks
No.

1 GPS receiver 2 cable plug-out

Test scenario 11

Description
 Connect antenna to GPS receiver 2

15-2-2012 FAT Procedure SAS (Rev. 0) Page 18 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Result:
 Indications have a valid time stamp

Sr.
Description checked approved n/a remarks
No.

1 GPS receiver 2 cable plug-in

2.4 Monitoring
2.4.1 Acoustic Horn Activation via Binary Contact

The purpose of this test is to check the horn function. Several alarm indications are randomly
simulated for this purpose.

Test scenario 1

Description:
 The indication is simulated

Result:
 The audible horn sounds (or respective contact closes)

Sr.
Description checked approved n/a remarks
No.

1 Alarm Horn ON simulation

Test scenario 2

Description:
 The horn is acknowledged via the ACKNOWLEDGE button in the HMI

Result:
 The horn stops (or respective contact opened)

Sr.
Description checked approved n/a remarks
No.

1 Alarm Horn ON Acknowledge

15-2-2012 FAT Procedure SAS (Rev. 0) Page 19 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

3 Bay Level

3.1 Communication of the Bay Devices to the Station Level via the IEC
61850 Protocol
3.1.1 Optical connection

The purpose of this test is to verify error-free communication between bay devices and substation
controller via the IEC 61850 protocol. In addition to the above, a bit test is performed; this means
that proper acquisition of the information at the bay device is verified.

Test requirements: FO network fault-free.

COMMUNICATION FAULT CLEARED of devices involved.

Test scenario 1

Description:
 Switch off one bay device

Result:
 Uninvolved bay devices are error-free
 Status change from TOPICAL to NOT TOPICAL

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 2

Description:
 Switch on bay devices

Result:
 COMMUNICATION FAULT CLEARED
 Status change from NOT TOPICAL to TOPICAL
 Uninvolved bay devices are error-free

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

15-2-2012 FAT Procedure SAS (Rev. 0) Page 20 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.
Feeder checked approved n/a remarks
No.

2 380/230kV/13.8kV Transformer

Test scenario 3

Description:
 Pull the FO cable of the bay device in the optical ring

Result:
 Indication FAILURE EN100 CHANNEL 1 or FAILURE EN100 CHANNEL 2 RAISED of the
bay device at the destination (HMI)
 Indication FAILURE EN100 CHANNEL 1 or FAILURE EN100 CHANNEL 2 RAISED of the
adjacent bay device at the destinations
 Uninvolved bay devices are error-free

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 4

Description:
 Plug in the FO cable

Result:
 Indication FAILURE EN100 CHANNEL 1 or FAILURE EN100 CHANNEL 2 CLEARED of the
bay device at the destinations (HMI)
 Indication FAILURE EN100 CHANNEL 1 or FAILURE EN100 CHANNEL 2 CLEARED of the
adjacent bay device at the destinations (e.g. bay device, HMI)
 Uninvolved bay devices are error-free

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

15-2-2012 FAT Procedure SAS (Rev. 0) Page 21 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 5

Description:
 One or two Indications are simulated either by the DIGSI function for simulating indications
and/or during the process

Result:
 The indications are displayed at the different destinations (e.g. bay device, HMI) as defined
by the parameter list

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 6

Description:

Test requirements:

Interlocking conditions satisfied.

 One Commands is sent to the bay devices from the HMI, and the corresponding feedback is
simulated

Result:
 The commands are output at the corresponding bay devices and switching devices and
logged correctly as defined by the parameter list

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 7

Description:
 One Measured values is simulated

15-2-2012 FAT Procedure SAS (Rev. 0) Page 22 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Result:
 The measured values are displayed at the different destinations (e.g. bay device, HMI) as
defined by the parameter list

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

3.2 Special Functions


3.2.1 Time synchronization via SNTP

The purpose of this test is to verify time synchronization of the bay devices.

Test requirements:

The time server sends a valid time signal.

Test scenario 1

Description:

Perform the test for some bay devices.


 Switch off bay device
 Switch on bay device (invalid time in the bay device)

Result:
 After some time, the bay device has obtained the current time of the time server
 TIME FAULTY indication at bay device is set to OFF

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

3.3 Monitoring
3.3.1 Indication Transmission via IEC 61850 Protocol at the HMI

The purpose of this test is to verify the transmission of indications from the bay device to the
destination (HMI). All indications of the bay device are checked according to parameter list.

Test scenario 1

Description:

15-2-2012 FAT Procedure SAS (Rev. 0) Page 23 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

 All indications are triggered

Result:
 The indications are transmitted properly (e.g. indication type, value, state) to the destination

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

3.3.2 Indication Display at the Bay Device with Graphic Display

The purpose of this test is to verify whether the pictures are properly presented on the display of
the bay device.

Test scenario 1

Description:
 The representation of text, switching devices, measured values and indications is checked

Result:
 The display shows correct representation of text, switching devices, measured value and
indications.

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 2

Description:

The purpose of this test is to verify the correct functionality of the function keys.
 Check the correct functionality of the function keys.
F1 : Event log
F2 : Measured value list
F3 :
F4 :

Result:
 The function key configuration is operable.

15-2-2012 FAT Procedure SAS (Rev. 0) Page 24 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

3.3.3 Optical Indication Display at the Bay Device with LEDs

The purpose of this test is to verify whether signaling of messages using LEDs works properly.
Perform this test for all messages that shall be signaled using LED.

LED display unlatched

Test scenario 1

Description:
 Indications routed to LEDs are simulated as RAISED

Result:
 The corresponding LEDs light up

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 2

Description:
 Indications routed to LEDs are simulated as CLEARED

Result:
 The corresponding LEDs are off

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

15-2-2012 FAT Procedure SAS (Rev. 0) Page 25 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

3.4 Control
3.4.1 Commands processing with the IEC 61850 Protocol

The purpose of this test is to verify command execution by the HMI to the bay device and recording
in the event log of the bay device. All commands of the bay device are checked according to
parameter list.

Test requirements:
 The switching authority at bay level is REMOTE
 The operator is authorized to control the switching devices
 The interlocking conditions for the switching devices to be controlled are satisfied
 The switching authority at station level is LOCAL for command initiation from HMI

Test scenario 1

Description:
 Command is sent from HMI
 In case of commands with feedback, the feedback is to be simulated at the bay device within
the feedback monitoring time

Result:
 The commands are output
 Logging of the command output in the event log of the bay device (B+, CO+ and in case of
commands with feedback FB+)

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

3.4.2 Changing the Switching Authority (LOCAL/REMOTE) at the Bay Device with
the Key Switch

The purpose of this test is to verify the switching authority check at the bay device during command
output initiated from the front panel of the device.

Test requirements:

The interlocking conditions are satisfied.

Test scenario 1

Description:
 The key switch LOCAL/REMOTE is set to LOCAL

15-2-2012 FAT Procedure SAS (Rev. 0) Page 26 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

 Command output at the bay device is started

Result:
 The commands are output

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 2

Description:
 The key switch LOCAL/REMOTE at the bay device is set to REMOTE
 Command output at the bay device is started (initiated from the fron panel of the device)

Result:
 The commands are not output

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

3.4.3 Control at the Bay Device with Graphic Display

The purpose of this test is to verify the switchgear control function and proper configuration of the
command outputs at the bay device according to parameter lists. Perform this test for all switching
devices of the bay device.

Test requirements:

The key switch is set to LOCAL

The interlocking conditions are satisfied.

Test scenario 1

Description:
 Open the control picture using the CTRL key
 Select the switching device by using the navigation keys
 Select switching direction ON by using the I key
 Control the switching device by using the ENTER key
 Feedback simulation

Result:

15-2-2012 FAT Procedure SAS (Rev. 0) Page 27 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

 Switching devices flashes in specified position ON


 The command is output
 Feedback is simulated and the switching device is represented as being ON
 The command is logged in the event log

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 2

Description:
 Open the control picture using the CTRL key
 Select the switching device by using the navigation keys
 Select switching direction OFF by using the “O” key
 Control the switching device by using the ENTER key
 Feedback simulation

Result:
 Switching devices flashes in specified position OFF
 The command is output
 Feedback is simulated and the switching device is represented as being OFF
 The command is logged in the event log

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

3.4.4 Bay and Substation Interlocking on Bay Level

The purpose of this test is to verify the bay-specific interlocking check at the bay device during
command output.

Test requirements:

The key switch LOCAL/REMOTE is set to LOCAL.

The key switch INTERLOCKING OFF/NORMAL is set to NORMAL.

Following switching operation will be randomly checked:

15-2-2012 FAT Procedure SAS (Rev. 0) Page 28 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 1

Description:
 The interlocking conditions are not satisfied
 Command output at the bay device is started

Result:
 The commands are not output

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 2

Description:
 The interlocking conditions are satisfied
 Command output at the bay device is started

Result:
 The commands are output

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 3

Description:

Test requirements:

The key switch LOCAL/REMOTE is set to REMOTE.

The key switch INTERLOCKING OFF/NORMAL is set to NORMAL.

Switching authority at HMI is LOCAL.

The operator is authorized to control the switching devices.


 The interlocking conditions are not satisfied
 Command output at HMI is started

Result:
 The commands are not output and logged in the HMI event list (command, command-)

15-2-2012 FAT Procedure SAS (Rev. 0) Page 29 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 4

Description:
 The interlocking conditions are satisfied
 Command output at HMI is started

Result:
 The commands are output and logged in the event list (command, command+, feedback,
command execution end +)

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 5

Description:

Test requirements:

The key switch LOCAL/REMOTE is set to REMOTE.

The key switch INTERLOCKING OFF/NORMAL is set to NORMAL.

Switching authority at HMI is REMOTE.


 The interlocking conditions are not satisfied
 Command output at Control Center is started

Result:
 The commands are not output

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

15-2-2012 FAT Procedure SAS (Rev. 0) Page 30 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.
Feeder checked approved n/a remarks
No.

2 380/230kV/13.8kV Transformer

Test scenario 6

Description:
 The interlocking conditions are satisfied
 Command output at Control Center is started

Result:
 The commands are output

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

3.5 Measurement
3.5.1 Measurement Acquisition with Direct Connection to CT/VT

The purpose of this test is to check the acquisition of the measured values in the bay device and to
verify the transmission of measured values from the bay device to the destinations (e.g. HMI). The
measured values of the bay device are checked according to parameter list.

Test requirements:

The nominal values for all measured values are input at the bay device.

Test scenario 1

Description:
 The 100% value of the measured values is fed in

Result:
 The measured values are properly displayed at the destinations (e.g. bay device display)

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

Test scenario 2

Description:

15-2-2012 FAT Procedure SAS (Rev. 0) Page 31 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

 The 50% value of the measured values is fed in

Result:
 The measured values are properly displayed at the destinations (e.g. bay device display)

Sr.
Feeder checked approved n/a remarks
No.

1 380kV Line

2 380/230kV/13.8kV Transformer

3.6 Verification of the time between changing of an binary input (BCU) and
the related changes in HMI / BCU
3.6.1 Binary input status to HMI

 For this test a signal is programmed in a source BCU (Binary Input “A”) and transmitted to
the HMI.

 The time in between initiating the signal (see time tag of the BI of BCU “A”) and

Sr. Time
Signal origin / destination Time Tag difference Approved
No. in [ms

1 BCU Binary Input “A”

2 HMI1

3.6.2 Goose message running through time

The Goose message transport time itself cannot be measured on premises of panel manufacturer.
Instead a Goose message shall
 be implemented in BCU “A” and be transmitted to BCU “B”. The source signal shall be
assigned to any available binary input of the BCU “A”

 In BCU “B” (receiving device) the Goose message received shall be assigned to an internal
indication

 The time in between initiating the signal (see time tag of the BI of BCU “A”) and triggered
internal indication at BCU “B” (see time tag of internal indication at BCU “B”) is roughly the
entire running through.

Sr. Time
Signal origin / destination Time Tag difference Approved
No. in [ms

1 BCU Binary Input “A”

15-2-2012 FAT Procedure SAS (Rev. 0) Page 32 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr. Time
Signal origin / destination Time Tag difference Approved
No. in [ms

2 BCU “B” internal Indication

4 HMI

4.1 System Configuration

4.1.1 HMI Configuration – Redundant Servers used as Two-Station System

The purpose of this test is to check hardware and software and proper startup of the HMI
components.

Test scenario 1

Description:

Test requirements:

The substation controller is switched on and ready for use, the HMI Servers are switched off.
 The HMI Servers are started

Result:
 The operating system starts on the HMI Servers
 PAS CC starts on the HMI Servers, the start screen comes up
 Communication between substation controller and PAS CC of both HMI Servers is carried
out


Sr.No. Description checked approved n/a remarks

1 PAS CC & HMI


communication

Test scenario 2

Description:
 Checking the pictures and of HMI Servers for consistency

Result:
 The pictures and on both HMI Servers are identical

Sr.No. Description checked approved n/a remarks

1 HMI servers picture

15-2-2012 FAT Procedure SAS (Rev. 0) Page 33 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.No. Description checked approved n/a remarks

status

Test scenario 3

Description:
 Deactivate HMI Server 1
 Simulate indications after HMI Server 1 is deactivated
 Start command execution at HMI Server 2

Result:
 Indication HMI Server 1 FAILURE ON simulated indications in pictures of the HMI Server 2
 HMI Server 2 undisturbed
 Commands are executed (Precondition: operation and interlocking conditions are fulfilled)

Sr.No. Description checked approved n/a remarks

1 HMI 1 OFF & HMI 2


healthy

Test scenario 4

Description:
 Activate HMI Server 1

Result:
 Indication HMI Server 1 FAILURE OFF in pictures of the HMI Server 2
 HMI Server 2 undisturbed
 The pictures are identical on both HMI servers
 changed process image is displayed at HMI Server 1

Sr.No. Description checked approved n/a remarks

1 HMI 1 start & HMI 2


healthy

Test scenario 5

Description:
 Deactivate HMI Server 2
 Simulate indications after HMI Server 2 is deactivated

15-2-2012 FAT Procedure SAS (Rev. 0) Page 34 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

 Start command execution at HMI Server 1

Result:
 Indication HMI Server 2 FAILURE ON simulated in pictures of the HMI Server 1
 HMI Server 1 undisturbed
 Commands are executed (Precondition: operation and interlocking conditions are fulfilled)

Sr.No. Description checked approved n/a remarks

1 HMI 2 OFF & HMI 1


healthy

Test scenario 6

Description:
 Activate HMI Server 2

Result:
 Indication HMI Server 2 FAILURE OFF simulated in pictures of the HMI Server 1
 HMI Server 1 undisturbed
 The pictures are identical on both HMI servers
 Changed process image is displayed at HMI Server 2 (lists and pictures)

Sr.No. Description checked approved n/a remarks

1 HMI 2 start & HMI 1


healthy

4.2 Operator Control and Monitoring – Display Structure and Navigation


4.2.1 Operating Concept with SICAM PAS CC

The purpose of this test is to verify the implementation of the operating concept such as start
picture, display composition and navigation between the different views.

Test scenario 1

Description:
 The operating concept is checked. To do so, different views are accessed by using the
navigation buttons

Result:
 The different views have been accessed by using navigation buttons and found O.K.

15-2-2012 FAT Procedure SAS (Rev. 0) Page 35 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.No. Description checked approved n/a remarks

1 Different view check

4.2.2 Status Bar

The purpose of this test is to check the function and the representation of the status bar for
completeness.

The status bar will be checked for layout, and naming in line with customer requirements. The
functionality of the buttons and objects in the status bar is checked and the general look and feel
will be verified.

Test requirements:

The operator is authorized to execute the operations.

Test scenario

Description:
The display of the status bar is checked, the following buttons are working properly

Sr.
Status bar checked approved n/a remarks
No.

1 LOGIN

SWITCHING
2
AUTHORITY

3 STATION OVERVIEW

4 SYSTEM OVERVIEW

5 TRAFO OVERVIEW

6 ALARM LIST

7 SOE LIST

8 EVENT LIST

9 ACKNOWLEDGEMENT

10 PRINT HARD COPY

11 HORN

4.2.3 Login and Logout with SICAM PAS CC

Test scenario 1

Description:
 No User is logged on

15-2-2012 FAT Procedure SAS (Rev. 0) Page 36 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

 Operations that require authorization are executed

Result:
 Unauthorized operations are blocked

Sr.No. Description checked approved n/a remarks

1 Unauthorized
operations block

Test scenario 2

Description:
 Press button Login on the status bar
 Enter the password and confirm with OK after opening the Login dialogue

Result:
 The current user is displayed in the status bar
 The login results in an entry into the Event list
Login time and user name are also logged

Sr.No. Description checked approved n/a remarks

1 Authorized
operations check

Test scenario 3

Description:
 An user is logged on
 Operations that require authorization are executed

Result:
 Operations for which the user has authorizations are not blocked.
 Unauthorized operations are blocked

Sr.No. Description checked approved n/a remarks

1 User login

Test scenario 4

Description:

15-2-2012 FAT Procedure SAS (Rev. 0) Page 37 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

 An user is logged on
 No operation is carried out during the time of automatic logout

Result:
 Operator is logged out
 No user is displayed in the status bar, the logout results in an entry into the Event list
 Unauthorized operations are blocked

Sr.No. Description checked approved n/a remarks

1 User logout

Test scenario 5

Description:
 An user is logged on
 Press button Login on the status bar
 Press Logout button after opening the dialogue

Result:
 Operator is logged out
 No user is displayed in the status bar, the logout results in an entry into the Event list
 Unauthorized operations are blocked

Sr.No. Description checked approved n/a remarks

1 User logout

4.2.4 User Administration with SICAM PAS CC

The User Administration Function describes the certain levels of the authority of a User.
During the FAT it shall be agreed which levels of Authorities shall be available.

The following levels (categories) can be an example and be applicable for the SAS.

a) Supervision category.
b) Control category
c) Configuration category
d) Administrator category

Test requirements:

The user is not authorized to use the function User Administration (e.g. user Operator)

15-2-2012 FAT Procedure SAS (Rev. 0) Page 38 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 1

Description:
 For verification of the access limitation by the user rights, login as a user for Supervision
category. Try to do the following actions:
a) Change between different pictures in the HMI project
b) Send a command to a switching device
c) Open RECPRO to view the fault records
d) Shut down the PAS CC Runtime

Result:
 a) OK
b) Not possible
c) Not possible
d) Not possible

Sr.No. Description checked approved n/a remarks

1 Supervision user
login

Test scenario 2

Description:
 For verification of the access limitation by the user rights, login as a user for Control
category. Try to do the following actions:
a) Change between different pictures in the HMI project
b) Send a command to a switching device
c) Open RECPRO to view the fault records
d) Shut down the PAS CC Runtime

Result:
 a) OK
b) OK
c) Not possible
d) Not possible

Sr.No. Description checked approved n/a remarks

1 Control user login

15-2-2012 FAT Procedure SAS (Rev. 0) Page 39 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 3

Description:
 For verification of the access limitation by the user rights, login as a user for Configuration
category. Try to do the following actions:
a) Change between different pictures in the HMI project
b) Send a command to a switching device
c) Open RECPRO to view the fault records
d) Shut down the PAS CC Runtime

Result:
 a) OK
b) OK
c) OK
d) Not possible

Sr.No. Description checked approved n/a remarks

1 Configuration user
login

Test scenario 4

Description:
 For verification of the access limitation by the user rights, login as a user for Administrator
category. Try to do the following actions:
a) Change between different pictures in the HMI project
b) Send a command to a switching device
c) Open RECPRO to view the fault records
d) Shut down the PAS CC Runtime

Result:
 a) OK
b) OK
c) OK
d) OK

Sr.No. Description checked approved n/a remarks

1 Administrator user
login

15-2-2012 FAT Procedure SAS (Rev. 0) Page 40 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

4.2.5 Displays
4.2.5.1 System Overview

The purpose of this test is to check the representation of the system overview picture for
completeness.

Test scenario 1

Description:
 Check the devices on the system overview

Result:
 The devices on the system overview are complete and named correctly

Sr.No. Description checked approved n/a remarks

1 System overview
Representation check

Test scenario 2

Description:
 Check the communication connections

Result:
 The display of the communication connections is shown correctly.

Sr.No. Description checked approved n/a remarks

1 System overview
communication
check

Test scenario 3

Description:
 Remove a network connection (i.e. between two switches) to check the coloring and
behavior of the dynamized lines

Result:
 The coloring and behaviors of the dynamized lines are correctly shown.

SLD colour change test:

Sr.No. Description checked approved n/a remarks

1 Feeder not
energized

15-2-2012 FAT Procedure SAS (Rev. 0) Page 41 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.No. Description checked approved n/a remarks

2 Feeder energised

3 Feeder Earthed

4.2.5.2 Bay Representation in the Detail Display

The purpose of this test is to check the representation of detail pictures for completeness.

The detailed displays (by typical) will be checked for layout, and naming in line with customer
requirements. The general look and feel will be verified.

Verify in each typical detail picture that the bay corresponds with the single line diagram.

Typical to check:
 380kV Line
 380/230/13.8 kV Transformer

Test scenario 1

Description:
 Check naming of the switching devices and buttons
 Check shape of the switching objects
 Check colouring of the lines
 Check display of measurements and all other relevant information
 Check display of the respective bus section

Result:
 The naming, shape, coloring, measurement & bus section display are found correct.

Sr.No. Description checked approved n/a remarks

1 Bay
representations

4.2.5.3 Help Picture

The purpose of this test is to check the representation of the help picture for completeness.

Verify that shown switching devices are in line with previous pictures, all states of switching devices
as well as the line colours are described correctly.

Links on further help files and documentations (like PAS CC documentation etc.) are given.

Test scenario 1

Description:

15-2-2012 FAT Procedure SAS (Rev. 0) Page 42 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

 The display of the help picture is checked

Result:
 The display of the help picture is correct

Sr.No. Description checked approved n/a remarks

1 SLD element help


pictures

4.2.6 Indication List


4.2.6.1 Event List

The purpose of this test is to check the names of the columns and colours in the event list.

Test scenario 1

Description:
 Verify that all required columns are listed and available in the event list

By default all incoming signals will appear in the event list.

1. Events Only (Events that are not configured as alarms)


Background Colour: (white)....................................................
Font Colour: (black)...................................................

2. Event – Alarms (Events that are also configured as Alarms)


Incoming Alarms
Background Colour: (red).............................................
Font Colour: (black)..........................................
Disappearing ACK Alarms
Background Colour: (yellow)...........................................
Font Colour: (black)............................................

Sr.No. Description checked approved n/a remarks

1 Event List
discription

Test scenario 2

Description:
 Simulate an event (e.g. Circuit Breaker OPEN/CLOSED)

Result:

15-2-2012 FAT Procedure SAS (Rev. 0) Page 43 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

The event is logged with the properties of the Events Only (it is NOTdisplayed in the Alarm list)

Sr.No. Description checked approved n/a remarks

1 Event simulation

4.2.6.2 Alarm list function

The purpose of this test is to check the names of the columns and colours in the alarm list.

Test scenario 1

Description:
 Verify that all required columns are listed and available in the alarm list

The behavioural patterns together with the colour designations assigned will be verified as per the
customer’s requirement.
 Incoming Alarms
Background colour: (red)....................................................
Font colour: (black).................................................

 Persistent ACK Alarms


Background colour: (yellow)............................................
Font colour: (black)............................................
 Disappearing UnACK Alarms
Background colour: (green).............................................
Font colour: (black).............................................
 Disappearing ACK Alarms
Alarm disappears

A step by step approach is used to verify the above possibilities.

Sr.No. Description checked approved n/a remarks

1 Alarm Messages

Test scenario 2

Description:
 Simulate a persistent alarm

Result:
 The alarm is logged with the properties of the Incoming Alarm

15-2-2012 FAT Procedure SAS (Rev. 0) Page 44 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.No. Description checked approved n/a remarks

1 Incoming alarm
check

Test scenario 3

Description:
 Acknowledge the persistent alarm

Result:
 The alarm is logged with the properties of the Persistent ACK Alarm

Sr.No. Description checked approved n/a remarks

1 Alarm
Acknowledgement

Test scenario 4

Description:
 Simulate an alarm reset (cleared) from the source and acknowledge it

Result:
The alarm disappears

Sr.No. Description checked approved n/a remarks

1 Alarm Reset

Test scenario 5

Description:
 Simulate an alarm and immediately reset the alarm from the source

Result:
 The alarm is logged with the properties of the Disappearing UnACK Alarm

Sr.No. Description checked approved n/a remarks

1 Alarm Cleared

Test scenario 6

Description:
 Acknowledge the disappearing UnACK alarm

Result:
 The alarm disappears

15-2-2012 FAT Procedure SAS (Rev. 0) Page 45 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.No. Description checked approved n/a remarks

1 Alarm UnACK

4.2.7 Printing
4.2.7.1 Message Logging with Line Printer

The purpose of this test is to verify functioning of the line printer.

Test scenario 1

Description:
 Simulation of messages, printer is ready and online

Result:
 Messages are printed promptly in the required layout

Sr.No. Description checked approved n/a remarks

1 Message Logging

4.2.7.2 Hardcopy

The purpose of this test is to verify functioning of the Hardcopy printer.

Test scenario 1

Description:
 Press the HARDCOPY button

Result:
 Hardcopy is printed correctly

Sr.No. Description checked approved n/a remarks

1 Hardcopy printer

Test scenario 2

Description:
 Open event list an click button “Printing” at event event list

Result:
 Hardcopy is printed correctly

15-2-2012 FAT Procedure SAS (Rev. 0) Page 46 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Sr.No. Description checked approved n/a remarks

1 Event printing

Test scenario 3

Description:
 Open alarm list an click button “Printing” at alarm list

Result:
 Hardcopy is printed correctly

Sr.No. Description checked approved n/a remarks

1 Alarm printing

4.2.8 PRP Function


4.2.8.1 Testing PRP Function

Test scenario 1

Result:
 PRP Function is working

Sr.No. Description checked approved n/a remarks

1 PRP Function

15-2-2012 FAT Procedure SAS (Rev. 0) Page 47 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

5 Telecontrol Protocol

5.1 Control Center Connection with the Telecontrol Protocol IEC-60870-5-


101 (Slave)

The purpose of this test is to verify the principal functionality of telecontrol connection IEC 60870-5-
101 (slave) and furture IEC 60870-5-104 (slave). One Indication and one command shall be
configured for the test.

Perform this test for all control centers.

Test requirements:

The control center simulation is ready to operate. The message exchange between the substation
controller and control center is monitored by the simulation software (IECTEST 101 & 104 and/or
FINK 101 & 104).

Test scenario 1

Description:
 The communication link between the substation controller and the simulated control center is
set up and checked

Result:
 After the maximum startup monitoring time, the TI 70 end-of-initialization is displayed in the
simulation
 Data traffic is present (one indication is suffitient for principal test)
 Indication COMMUNICATION FAILURE CLEARED at the destinations (e.g. HMI)

Sr.
GW Channel checked approved n/a remarks
No.

SAS PSC S/S


1
GW 1 – IEC101 Channel 1

SAS PSC S/S


2
GW 2 – IEC101 Channel 2

SAS PSC S/S


3
GW – IEC104 Channel 3

SAS PSC S/S


4
GW – IEC104 Channel 4

SAS PSC S/S


5
GW – IEC104 Channel 5

15-2-2012 FAT Procedure SAS (Rev. 0) Page 48 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 2

Description:
 The control center generates organizational commands (e.g. GI)

Result:
 The corresponding action is executed and checked by using simulation software

Sr.
GW Channel checked approved n/a remarks
No.

SAS PSC S/S


1
GW 1 – IEC101 Channel 1

SAS PSC S/S


2
GW 2 – IEC101 Channel 2

SAS PSC S/S


3
GW – IEC104 Channel 3

SAS PSC S/S


4
GW – IEC104 Channel 4

SAS PSC S/S


5
GW – IEC104 Channel 5

Test scenario 3

Description:
 One Information is generated in the bay level or station level

Result:
The indication is transmitted with the correct type identification (TI), the correct value and the
correct quality code and checked by using simulation software.

Sr.
GW Channel checked approved n/a remarks
No.

SAS PSC S/S


1
GW 1 – IEC101 Channel 1

SAS PSC S/S


2
GW 2 – IEC101 Channel 2

SAS PSC S/S


3
GW – IEC104 Channel 3

SAS PSC S/S


4
GW – IEC104 Channel 4

SAS PSC S/S


5
GW – IEC104 Channel 5

15-2-2012 FAT Procedure SAS (Rev. 0) Page 49 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.
SIEMENS
CONSTRUCTION OF SADARAH 380/230kV S/S BSP in JIC-2

Test scenario 4

Description:

Test requirements:

The interlocking conditions are satisfied.


 The control center generates commands and checks them by using simulation software

Result:
The command is executed

Sr.
GW Channel checked approved n/a remarks
No.

SAS PSC S/S


1
GW 1 – IEC101 Channel 1

SAS PSC S/S


2
GW 2 – IEC101 Channel 2

SAS PSC S/S


3
GW – IEC104 Channel 3

SAS PSC S/S


4
GW – IEC104 Channel 4

SAS PSC S/S


5
GW – IEC104 Channel 5

15-2-2012 FAT Procedure SAS (Rev. 0) Page 50 / 50


This document shall not be transmitted or reproduced, nor shall its contents be exploited or disclosed to third persons without prior written consent.
Infringements shall entitle to damage claims. All rights are reserved.

You might also like