Professional Documents
Culture Documents
DATA SHEET
SUPPLIER STANDARD
OTHERS :
DATA SHEET
COMPANY : SUEZ OIL PROCESSING COMPANY DATA SHEET No. : 05020-250 - 090-MDS-116-01-01
EQUIPMENT : STORAGE TANKS TAG No. : 090TK-001/002
LOCATION : SUEZ - EGYPT REV. No. : 2
DESIGN DATA
Rev
1
DATA SHEET
COMPANY : SUEZ OIL PROCESSING COMPANY DATA SHEET No. : 05020-250 - 090-MDS-116-01-01
EQUIPMENT : STORAGE TANKS TAG No. : 090TK-001/002
LOCATION : SUEZ - EGYPT REV. No. : 2
SURFACE PREPARATION & PAINTING (NOTE 7)
Rev
1
19 FLANGE
MARK QTY SIZE SERVICE REMARKS
20 RATING TYPE FACING
21 N1 1 10" 300 lb WN RF VR INLET
22 N2 1 14" 150 lb WN RF VR OUTLET
23 N3 1 6" (HOLD) 300 lb WN RF SPILLBACK with internal pipe
24 N4 1 2" 300 lb WN RF LP STEAM INLET (to 090E-001) NOTE- 26
25 N5 1 2" 150 lb WN RF CONDENSATE OUTLET (from 090E-001) NOTE- 26
26 N6 (**) (**) 150 lb WN RF SIDE ENTRY PROPELLER MIXERS NOTE- 12
N7 1 (**) 150 lb WN RF VENT NOTE- 4
N8 1 4" 150 lb WN RF DRAIN with internal pipe
27 N9 1 4" 150 lb WN RF DRAIN with internal pipe
30 N10 1 4" 150 lb WN RF UTILITY CONNECTION
31 N11 (*) (*) 150 lb WN RF HEAT DETECTION NOTE-22
N12 1 24" API STD MECH. LEVEL GAUGE (Note-27) (NOTE-24)
N13 1 24"(HOLD) 300 lb WN RF LEVEL TRANSMITTER (Note-27) with stilling well
N14 1 4" (*) 300 lb WN RF LEVEL TRANSMITTER (Note-27) with stilling well
32 N15 1 2" (*) 300 lb WN RF TEMP. GAUGE (Note-27)
33 N16 1 2" (*) 300 lb WN RF TEMP. TRANSMITTER (Note-27)
34 N17 1 2" (*) 300 lb WN RF TEMP. TRANSMITTER (Note-27)
10000-000-GE1-TMP-0005 (03/19)
DATA SHEET
COMPANY : SUEZ OIL PROCESSING COMPANY DATA SHEET No. : 05020-250 - 090-MDS-116-01-01
EQUIPMENT : STORAGE TANKS TAG No. : 090TK-001/002
LOCATION : SUEZ - EGYPT REV. No. :2
SKETCH
10000-000-GE1-TMP-0005 (03/19)
DATA SHEET
COMPANY : SUEZ OIL PROCESSING COMPANY (SOPC) DATA SHEET No. : 05020-250 - 090-MDS-116-01-01
EQUIPMENT : STORAGE TANKS TAG No. : 090TK-001/002
LOCATION : SUEZ - EGYPT REV. No. : 2
NOTES
Rev.
1 - All dimensions are in mm unless otherwise noted.
2 - Minimum ambient temperature is 4oC.
3 - Any missing data shall be completed by tank supplier. Tank supplier shall be responsible to determine the final thickness, weights and
foundation loads during detailed engineering phase.
4 - Total numbers of emergency hatches (24”) & Sizing of vent as per API 2000 latest edition shall be included in tank supplier scope of
supply.
5 - Nozzles elevation, orientation and projection shall be confirmed during detailed engineering phase.
6 - Flanges bolt holes shall evenly straddle vertical axis.
7 - Surface preparation and painting shall be according to project specification no. 05020-250-100-020. Tank shall be internally lined
with phenolic epoxy for bottom, sump and first 1m of shell, and also for shell courses above HHLL and roof surfaces.Coating system
shall be suitable for operating temperature. System details shall be specified by the vendor.
8 - All flanges shall be as per ASME B16.5 with smooth facing surface finish 125 AARH to 250 AARH. Nozzle flanges: ASME B16.5
up to 24" NPS, for NPS >24" use ASME B16.47 series A.
9 - The proposed tank height by PETROJET (16000) mm will be approved during detailed engineering considering freeboard (above
HHLL) necessary to contain liquid sloshing wave. This freeboard shall be sufficient to be fully contained within the shell, the sealing
ring and the secondary seal. Consequently; supplier shall consider this in tank design.
10 - Loads superimposed by platforms and brackets and loads resulting from connected piping shall be considered in the tank design.
11 - Manways & Cleanout doors shall be supplied with blind covers with hinges / davits, gasket, bolts and handles, Internal grab rungs
shall provide for manways (as applicable).
12 - Design, test, supply, and installation of Side-entry tank mixer located below low low liquid level complete with electric motor driver
and all accessories, as per datasheet no. 05020-250-090-MDS-136-02-01, mechanical mixer specification no. 05020-250-100-021,
motor data sheet no. 05020-250-090-EDS-500-08-02, and low voltage induction motor specification no. 05020-250-500-008.
Quantity of mixer is hold and to be indicated by tank supplier based on CFD calculations.
13 - Spare parts for commissioning and start up shall be:
■ Three complete set of gaskets for manways, blind connections.
■ 10% of bolting (min. 5 pieces of each size/ type) for manways, blind connections.
14 - Tank supplier shall provide list of recommend spares for two years (listed) continuous operation.
15 - Tank shall be provided with minimum three SS - 120 degree Earthing boss complete with all stainless steel fixation and termination
accessories (earthing lug suitable for bolt size M8 , washer ,nut etc..)
16 - Reinforcing pads and all other external attachement pads shall have rounded corners of minimum 50 mm (2 inch) radius. Pads that
cover shell seams shall be provided with a 6 mm telltale hole.
17 - Welding shall be according to project specification 05020-200-100-076.
18 - Supplier shall submit Tank allowable nozzle loads and nozzles stiffness (Forces and Moments). In case actual calculated piping loads
exceed the submitted allowable loads, Contractor shall submit the actual calculated nozzle piping loads for supplier execution.
19 - In case of piping need any Piping Bracket\Guide Supports will fabricated by supplier, then Piping Bracket\Guide Clip list will be
submitted during detailed engineering phase.
20 - External bolting shall be PTFE coated suitable for design temperature.
21 - PMI shall be according to project specification 05020-200-100-077.
22 - Tanks shall be equipped with a firefighting deluge system of water spray rings arranged to operate as two independent halves, each
half is covering half shell surface area and half roof surface area, the water spray system including design, supply, installation and
testing up to the tie-in flange (300mm Min. from grade level) shall be inside supplier scope battery limit. Two linear heat detectors
on each tank shall be covering top side area while of design, supply, installation, wiring, termination, fixation, and testing up to the
interposing junction box of those detectors shall be into supplier scope battery limit. Deluge Valve feeding the water spray system on
tanks is not part of supplier scope of supply.
23 - Process fluid physical properties are as follows:
Vacuum Residue Viscosity: 66 – 690 cP
Thermal Conductivity: 0.07 kcal/h-m-Oc CP: 0.5 kcal/kg-oC
24 - Mechanical level gauge to be float operated / guided wire type indicator with oil seal unit and to be readable from ground level.
25 - Heat Conservation Insulation shall be as project spec. no. 05020-250-400-005
26 - Tanks shall be equipped with inside steam heating coil (located below low low liquid level) to maintain the fluid temperature as
minimum at 140°C. Thermal/Mechanical Design , material supply, fabrication, inspection and installation of inside heating coil
complete with all supports shall be included in tank supplier scope of supply as per below data:
Low Pressure Steam Design Pressure = 25 kg/cm2g / FV Design Temperature = 350 oC
Operating Pressure = 8 kg/cm2g (min.) / 10 kg/cm2g (max.)
Operating Temperature = 220oC (min.) / 230oC (max.)
Design Steam Consumption= 400 kg/hr
10000-000-GE1-TMP-0005 (03/19)
Heater design duty is 0.27 MMkcal/h (calculated based on mineral wool with 40mm thickness tank insulation.)
27 - Nozzles instrumentation Tag No.s For TK-001/TK-002:
N12: 090-LG-001 for TK-001, 090-LG-002 for TK-002.
N13: 090-LT-001 for TK-001, 090-LT-003 for TK-003.
N14: 090-LZT-002 for TK-001, 090-LZT-004 for TK-002.
N15: 090-TG-001 for TK-001, 090-TG-002 for TK-002.
N16: 090-TT-001 for TK-001, 090-TT-003 for TK-002.
N17: 090-TZT-002 for TK-001, 090-TZT-004 for TK-002.
28 - Gauge hatch complete with flange, cover, stilling well, gasket, bolts and nuts shall be in scope of tank supplier.