Professional Documents
Culture Documents
DEVELOPMENT PROJECT
DPG PLATFORM
SUB-SYSTEM 2803
ANTIFOAM INJECTION
S.A.R.L.
32,Av. Pablo Picasso - TSA76032 92754 NANTERRE CEDEX - FRANCE
-- -- --
SIRRI “A”
Note : Third column is to be filled in, when the document is being updated/modified.
-- -- --
SIRRI “A”
1 TEST SUMMARY
None
MECHANICAL
1 Technician ~ full time
ELECTRICAL
1 Technician ~ part time
INSTRUMENT
1 Technician ~ part time
OPERATION
1 Operator ~ full time
-- -- --
SIRRI “A”
None
3 TEST REQUIREMENT
ù Temporary generator
ù Power distribution network
None
3.5 CONSUMABLES
ù Lubricants
ù Grease
3.6 SPARE
-- -- --
SIRRI “A”
3.7 SAFETY
3.8 UTILITTES
ù Electricity
ù Potable water
4 TEST PREPARATION
None.
ù Manufacturer :
ù Suction pressure : ATM
ù Discharge pressure : 98,4 bar G
ù Capacity : 0,5 L/H
-- -- --
SIRRI “A”
ù Energize PM-113710
ù Open tank line valve to suction pump
ù Open P-113710 A discharge line valve
ù Adjust the flow rate to 0,5 1/h by housing calibration pot
ù Start P-113710
ù Record 1 set of readings at each flow rate as per attached test sheet
form FG5223
ù Stop P-113710
ù Close suction and discharge lines valves
ù De-energize PM-113710
ù Drain the water out of the circuit
ùDisconnect the hoses
ù Re-install the pipe work
Note :
ù Maintain the water level in the drum while all tests
ù Discharge pressure injection pumps must be reached P>89 barg
None
7.2. PRESERVATION
None
-- -- --
-- -- --