0% found this document useful (0 votes)
263 views7 pages

Air Leak Test Procedure: SIRRI A

This document describes an air leak test procedure for the closed drain subsystem 2301 of the SIRRI "A" and "E" DPG development project. The test will pressurize partial closed drain systems to 2.5 barg using oil-free air supplied at 7 barg. Temporary hoses will be installed at various points to pressurize sections and monitor pressure. The test is estimated to take 3 days with a 4-person team and will check for leaks using soap solution. Safety precautions like signage and horns will be followed.

Uploaded by

Mohammad Mohseni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
263 views7 pages

Air Leak Test Procedure: SIRRI A

This document describes an air leak test procedure for the closed drain subsystem 2301 of the SIRRI "A" and "E" DPG development project. The test will pressurize partial closed drain systems to 2.5 barg using oil-free air supplied at 7 barg. Temporary hoses will be installed at various points to pressurize sections and monitor pressure. The test is estimated to take 3 days with a 4-person team and will check for leaks using soap solution. Safety precautions like signage and horns will be followed.

Uploaded by

Mohammad Mohseni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
  • Cover Page: Title page detailing the air leak test procedure for closed drains in subsystem 2301, including document control details.
  • Revision Record: Lists revisions made to the document, specifying the purpose and sections updated.
  • Test Summary: Summarizes the air leak test procedure, including scope, methodology, and precautions.
  • Planning and Manpower: Covers the required planning and manpower estimates for conducting the test.
  • Test Requirements: Details the duration, precommissioning achievements, and logistic support necessary for the test.
  • Test Equipment and Tools: Specifies the equipment and consumables list required for the air leak test.
  • Procedure: Outlines detailed step-by-step procedures, including mechanical preparations and testing tasks.
  • Leak Test Procedures: Describes procedures for conducting leak tests, including final checks and post-test conditions.

SIRRI "A" and "E"

DEVELOPMENT PROJECT

DPG PLATFORM

CLOSED DRAINS
AIR LEAK TEST
SUB-SYSTEM 2301

03 10/09/97 RT Approved RT RG

02 08/09/97 RT Modified as per M/TS/SR/E01/287 (31/07/97) RT RG

01 08/08/97 RT Modified as per MOM # 3 (31/07/97) CV RG

00 27/06/97 BL Issued for Approval BL RG


CHECK APPR.
REV. DATE BY DESCRIPTION CONTR. COMP.
ENG. APPR.
TOTAL OR PARTIAL REPRODUCTION AND/OR UTILISATION OF THIS DOCUMENT ARE FORBIDDEN
WITHOUT PRIOR WRITTEN AUTHORIZATION OF THE COMPANY

S.A.R.L.
32,Av. Pablo Picasso - TSA76032 92754 NANTERRE CEDEX - FRANCE

TOTAL SIRRI / NIOC-OFFSHORE

EPSCC CONTRACT : SIR/PJ/004

DOCUMENT NUMBER REVISION STATUS CLASS

J01 DPG Z P 8002 03 C 1


SERIMER\2301.DOC
SIRRI “A”

AIR LEAK TEST PROCEDURE DPG

SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 2 OF 7


2301

REVISION RECORD SHEET

Revision List of Updated/Modified Sections, if


Purpose
Number any

00 Issued for Approval -

01 Modified as per MOM # 3 All pages

02 Modified as per M/TS/SR/E01/287 All pages

03 Approved -

Note : Third column is to be filled in, when the document is being updated/modified.
SIRRI “A”

AIR LEAK TEST PROCEDURE DPG

SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 3 OF 7


2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETE SIGNATURE
D

1 TEST SUMMARY

WARNING :

This procedure applies only to on-shore leak test. The equipped Wellheads
will be installed off-shore after the drilling operations, consequently the
present leak test will be performed from the blind flanges installed upstream
the choke valves and, not from the equipped Wellheads.

This procedure is written for DPG.

AIR LEAK TEST

The aim of air leak test at 2.5barg pressure is to minimize hazards that could
result from leaks.

1.1 DESCRIPTION

The sub-system will be air leak tested at the following pressure level :
2.5 barg ; partial closed drain system
Oil free air is to be supplied from an external source at around 7 barg

1.2 TEMPORARY INSTALLATION

Suitable hose connections shall be provided at several points of the


system.

SAFETY PRECAUTION

During hook up activity signs to warn of air pressure testing must be posted,
and portable horns must be used before starting the test.

2 PLANNING AND MANPOWER

2.1 PLANNING TASK

2.2 MANPOWER ESTIMATE

The manpower requirement are as follows :

PER SHIFT :
- 1 SUPERVISOR
- 4 PIPE FITTERS
SIRRI “A”

AIR LEAK TEST PROCEDURE DPG

SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 4 OF 7


2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE

2.3 TEST DURATION ESTIMATE

The overall operation duration is scheduled to be three (3) days.


Once the sub-system is pressurized at about 2.5 barg with air, the leak last
one day

TEST REQUIREMENT
3
3.1 PRECOMMISSIONING ACHIEVEMENT

RFC dossier ready (contractor internal document) as per EPCC


contract.
There are no punchlist outstanding items priority A.

3.2 OTHER SUBSYSTEM

The subsystem 2301 is involved in the procedure.

3.3 SPECIAL TOOL AND EQUIPMENT

Four 4” blind flanges 300lb RF, unless already


supplied by project.

Two 2” blind flange 300lb RF, unless already supplied by project.

Pressure & Temperature Recorder.

3.4 CONSUMABLES

Liquid soap
Calibrated pressure gauge ranging 0-10 bars at several locations
Fitting (quick couplings)

3.5 SPARES

Gasket and RTJ for the various type flanges

3.6 SAFETY

One (1) work permit must be issued for the test and condition list must
be adhered to.
Only authorized personnel will be allowed in the areas where
testing is taking place.

SIRRI “A”
AIR LEAK TEST PROCEDURE DPG

SUB-SYSTEM : DESCRIPTION : CLOSED DRAIN PAGE 5 OF 7


2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE

3.7 UTILITIES
None

4 TEST PREPARATION

4.1 BLIND LIST

One 4” blind flange on line 4” CD 114421 B03


One 4” blind flange on line 4” 0D 114313 B03
One 4” blind flange on line 4” FA 113216 B03
One 2” blind flange on 2"line adjacent to 4” FA 113216 B03
One 2” blind flange on line 2” CD 114429 D03
One 4” blind flange on line 4” CD 114421 B03

( See attached colored drawings )

4.2 MECHANICAL PREPARATION TASK PROCESS

Prepare fittings for air instrument pipe connection on the following


lines :

- 2” CD 114409 B03 (J01-DPG-Z-D-5002 )

- 1 1/2” CD 114415 B03 (J01-DPG-Z-D-5004 )

- 4” FA 113216 B03 (J01-DPG-Z-D-5006 )

· Apply masking tape around all the flanges to be checked.

5 START UP AND TUNING

Prepare the circuits according to attached colored drawings


J01-DPG-Z-D-5000
J01-DPG-Z-D-5001
J01-DPG-Z-D-5002
J01-DPG-Z-D-5003
J01-DPG-Z-D-5004
J01-DPG-Z-D-5005
J01-DPG-Z-D-5006
J01-DPG-Z-D-5007

SIRRI “A”
AIR LEAK TEST PROCEDURE
DPG

SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 6 OF 7


2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE

5.1 START UP STEP BY STEP PROCEDURE

1) Leak test the whole system between the production flowlines,


production manifold, test manifold and pig launcher and receiver for
all closed drains.
(see colored P & ID’s).

2) Connect air hoses at different points of the system (at least 3).
(see marks on colored P & ID’s).

3) Install 0-10 barg pressure gauges on suitable vents of the system


(at least 5 ).

4) Close all the gate and ball valves to put the whole system balanced.
(see colored P & ID’s).
- HV valve on line 1 1/2” CD 1144A2 B03 (J01-DPG-Z-D-5001 )
- HV valve on line 1 1/2” CD 1144L2 B03 (J01-DPG-Z-D-5001 )
( until well N° 12)

- SDV 4421 ( PID J01-DPG-Z-D-5006 )

- HV valve on line 1 1/2” CD 114404 B03 ( J01-DPG-Z-D-5001 )


- HV valve on line 1 1/2” CD 114406 B03 ( J01-DPG-Z-D-5001 )
- HV valve on line 1 1/2” CD 114411 B03 (J01-DPG-Z-D-5003 )
- HV valve on line 1 1/2” CD 114413 B03 (J01-DPG-Z-D-5003 )
- HV valve on line 1 1/2” CD 114417 B03 (J01-DPG-Z-D-5004 )
- HV valve on line 2” OD 114312 B03 (J01-DPG-Z-D-5006 )

5) Open all the following valve (see marked-up drawings).

- FB valve on line 2” CD 114427 B03 (J01-DPG-Z-D-5006 )


- FB valve on line 2” CD 114428 D03 (J01-DPG-Z-D-5006 )
- HV valve on line 2” CD 114429 D03 (J01-DPG-Z-D-5006 )
- HV valve on line 2” CD 114428 D03 (J01-DPG-Z-D-5006 )
- HV valve on line 4” CD 114421 B03 (J01-DPG-Z-D-5006 )

6) When the maximum air pressure is achieved close air make up.

7) Proceed to a general inspection of flanges and carry out an initial


acoustics checking.

SIRRI “A”
AIR LEAK TEST PROCEDURE DPG

SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 7 OF 7


2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE

8) Observe the pressure fall on the different pressure gauge and record
the pressure losses.

9) If the pressure losses are within the 0.05 barg/hr criterion the test is
considered as successful.

10) Without the criterion range of 0.05 barg/hr the methodology of


masking tape is to be applied and each flange, valves glands checked
with soapy water until final success.

LEAK TEST PROCEDURES, including :

6.1 LEAK TEST REPORT FORM 4241

6.2 STEP BY STEP LEAK TEST PROCEDURE

6.3 P & ID WITH LINE LOCATION

POST LEAK TEST CONDITION

PRESERVATION

Following the leak test acceptance the whole system will be


depressurized

SUB-SYSTEM STATUS

Ready for Offshore leak test at operating pressure. ( If needed )

SIRRI  "A"  and  "E"
DEVELOPMENT  PROJECT
DPG  PLATFORM
CLOSED  DRAINS
AIR LEAK TEST
 SUB-SYSTEM  2301
03
10/09/97
RT
Approve
AIR LEAK TEST PROCEDURE
SIRRI “A”
       
DPG
SUB-SYSTEM :
2301
DESCRIPTION : CLOSED DRAINS
PAGE  2 OF  7
REVISION  RECORD  S
AIR LEAK TEST PROCEDURE
SIRRI “A”
 
DPG
SUB-SYSTEM :
2301
DESCRIPTION : CLOSED DRAINS
PAGE  3  OF  7
STEP
TASK DESCRIPTION
AIR LEAK TEST PROCEDURE
SIRRI “A”
 
DPG
 
SUB-SYSTEM :
2301
DESCRIPTION : CLOSED DRAINS
PAGE  4  OF  7   
STEP
TASK DESCRIP
AIR LEAK TEST PROCEDURE
 
DPG
SUB-SYSTEM :
2301
DESCRIPTION : CLOSED  DRAIN
PAGE  5  OF  7  
STEP
TASK DESCRIPTION
DATE
COMPL
AIR LEAK TEST PROCEDURE
 
DPG
 
SUB-SYSTEM :
2301
DESCRIPTION : CLOSED DRAINS
PAGE  6  OF  7   
STEP
TASK DESCRIPTION
DATE
AIR LEAK TEST PROCEDURE
DPG
 
SUB-SYSTEM :
2301
DESCRIPTION : CLOSED DRAINS
PAGE  7  OF  7   
STEP
TASK DESCRIPTION
DATE
COMP

You might also like