SIRRI "A" and "E"
DEVELOPMENT PROJECT
DPG PLATFORM
CLOSED DRAINS
AIR LEAK TEST
SUB-SYSTEM 2301
03 10/09/97 RT Approved RT RG
02 08/09/97 RT Modified as per M/TS/SR/E01/287 (31/07/97) RT RG
01 08/08/97 RT Modified as per MOM # 3 (31/07/97) CV RG
00 27/06/97 BL Issued for Approval BL RG
CHECK APPR.
REV. DATE BY DESCRIPTION CONTR. COMP.
ENG. APPR.
TOTAL OR PARTIAL REPRODUCTION AND/OR UTILISATION OF THIS DOCUMENT ARE FORBIDDEN
WITHOUT PRIOR WRITTEN AUTHORIZATION OF THE COMPANY
S.A.R.L.
32,Av. Pablo Picasso - TSA76032 92754 NANTERRE CEDEX - FRANCE
TOTAL SIRRI / NIOC-OFFSHORE
EPSCC CONTRACT : SIR/PJ/004
DOCUMENT NUMBER REVISION STATUS CLASS
J01 DPG Z P 8002 03 C 1
SERIMER\2301.DOC
SIRRI “A”
AIR LEAK TEST PROCEDURE DPG
SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 2 OF 7
2301
REVISION RECORD SHEET
Revision List of Updated/Modified Sections, if
Purpose
Number any
00 Issued for Approval -
01 Modified as per MOM # 3 All pages
02 Modified as per M/TS/SR/E01/287 All pages
03 Approved -
Note : Third column is to be filled in, when the document is being updated/modified.
SIRRI “A”
AIR LEAK TEST PROCEDURE DPG
SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 3 OF 7
2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETE SIGNATURE
D
1 TEST SUMMARY
WARNING :
This procedure applies only to on-shore leak test. The equipped Wellheads
will be installed off-shore after the drilling operations, consequently the
present leak test will be performed from the blind flanges installed upstream
the choke valves and, not from the equipped Wellheads.
This procedure is written for DPG.
AIR LEAK TEST
The aim of air leak test at 2.5barg pressure is to minimize hazards that could
result from leaks.
1.1 DESCRIPTION
The sub-system will be air leak tested at the following pressure level :
2.5 barg ; partial closed drain system
Oil free air is to be supplied from an external source at around 7 barg
1.2 TEMPORARY INSTALLATION
Suitable hose connections shall be provided at several points of the
system.
SAFETY PRECAUTION
During hook up activity signs to warn of air pressure testing must be posted,
and portable horns must be used before starting the test.
2 PLANNING AND MANPOWER
2.1 PLANNING TASK
2.2 MANPOWER ESTIMATE
The manpower requirement are as follows :
PER SHIFT :
- 1 SUPERVISOR
- 4 PIPE FITTERS
SIRRI “A”
AIR LEAK TEST PROCEDURE DPG
SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 4 OF 7
2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
2.3 TEST DURATION ESTIMATE
The overall operation duration is scheduled to be three (3) days.
Once the sub-system is pressurized at about 2.5 barg with air, the leak last
one day
TEST REQUIREMENT
3
3.1 PRECOMMISSIONING ACHIEVEMENT
RFC dossier ready (contractor internal document) as per EPCC
contract.
There are no punchlist outstanding items priority A.
3.2 OTHER SUBSYSTEM
The subsystem 2301 is involved in the procedure.
3.3 SPECIAL TOOL AND EQUIPMENT
Four 4” blind flanges 300lb RF, unless already
supplied by project.
Two 2” blind flange 300lb RF, unless already supplied by project.
Pressure & Temperature Recorder.
3.4 CONSUMABLES
Liquid soap
Calibrated pressure gauge ranging 0-10 bars at several locations
Fitting (quick couplings)
3.5 SPARES
Gasket and RTJ for the various type flanges
3.6 SAFETY
One (1) work permit must be issued for the test and condition list must
be adhered to.
Only authorized personnel will be allowed in the areas where
testing is taking place.
SIRRI “A”
AIR LEAK TEST PROCEDURE DPG
SUB-SYSTEM : DESCRIPTION : CLOSED DRAIN PAGE 5 OF 7
2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
3.7 UTILITIES
None
4 TEST PREPARATION
4.1 BLIND LIST
One 4” blind flange on line 4” CD 114421 B03
One 4” blind flange on line 4” 0D 114313 B03
One 4” blind flange on line 4” FA 113216 B03
One 2” blind flange on 2"line adjacent to 4” FA 113216 B03
One 2” blind flange on line 2” CD 114429 D03
One 4” blind flange on line 4” CD 114421 B03
( See attached colored drawings )
4.2 MECHANICAL PREPARATION TASK PROCESS
Prepare fittings for air instrument pipe connection on the following
lines :
- 2” CD 114409 B03 (J01-DPG-Z-D-5002 )
- 1 1/2” CD 114415 B03 (J01-DPG-Z-D-5004 )
- 4” FA 113216 B03 (J01-DPG-Z-D-5006 )
· Apply masking tape around all the flanges to be checked.
5 START UP AND TUNING
Prepare the circuits according to attached colored drawings
J01-DPG-Z-D-5000
J01-DPG-Z-D-5001
J01-DPG-Z-D-5002
J01-DPG-Z-D-5003
J01-DPG-Z-D-5004
J01-DPG-Z-D-5005
J01-DPG-Z-D-5006
J01-DPG-Z-D-5007
SIRRI “A”
AIR LEAK TEST PROCEDURE
DPG
SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 6 OF 7
2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
5.1 START UP STEP BY STEP PROCEDURE
1) Leak test the whole system between the production flowlines,
production manifold, test manifold and pig launcher and receiver for
all closed drains.
(see colored P & ID’s).
2) Connect air hoses at different points of the system (at least 3).
(see marks on colored P & ID’s).
3) Install 0-10 barg pressure gauges on suitable vents of the system
(at least 5 ).
4) Close all the gate and ball valves to put the whole system balanced.
(see colored P & ID’s).
- HV valve on line 1 1/2” CD 1144A2 B03 (J01-DPG-Z-D-5001 )
- HV valve on line 1 1/2” CD 1144L2 B03 (J01-DPG-Z-D-5001 )
( until well N° 12)
- SDV 4421 ( PID J01-DPG-Z-D-5006 )
- HV valve on line 1 1/2” CD 114404 B03 ( J01-DPG-Z-D-5001 )
- HV valve on line 1 1/2” CD 114406 B03 ( J01-DPG-Z-D-5001 )
- HV valve on line 1 1/2” CD 114411 B03 (J01-DPG-Z-D-5003 )
- HV valve on line 1 1/2” CD 114413 B03 (J01-DPG-Z-D-5003 )
- HV valve on line 1 1/2” CD 114417 B03 (J01-DPG-Z-D-5004 )
- HV valve on line 2” OD 114312 B03 (J01-DPG-Z-D-5006 )
5) Open all the following valve (see marked-up drawings).
- FB valve on line 2” CD 114427 B03 (J01-DPG-Z-D-5006 )
- FB valve on line 2” CD 114428 D03 (J01-DPG-Z-D-5006 )
- HV valve on line 2” CD 114429 D03 (J01-DPG-Z-D-5006 )
- HV valve on line 2” CD 114428 D03 (J01-DPG-Z-D-5006 )
- HV valve on line 4” CD 114421 B03 (J01-DPG-Z-D-5006 )
6) When the maximum air pressure is achieved close air make up.
7) Proceed to a general inspection of flanges and carry out an initial
acoustics checking.
SIRRI “A”
AIR LEAK TEST PROCEDURE DPG
SUB-SYSTEM : DESCRIPTION : CLOSED DRAINS PAGE 7 OF 7
2301
DATE NAME AND
STEP TASK DESCRIPTION COMPLETED SIGNATURE
8) Observe the pressure fall on the different pressure gauge and record
the pressure losses.
9) If the pressure losses are within the 0.05 barg/hr criterion the test is
considered as successful.
10) Without the criterion range of 0.05 barg/hr the methodology of
masking tape is to be applied and each flange, valves glands checked
with soapy water until final success.
LEAK TEST PROCEDURES, including :
6.1 LEAK TEST REPORT FORM 4241
6.2 STEP BY STEP LEAK TEST PROCEDURE
6.3 P & ID WITH LINE LOCATION
POST LEAK TEST CONDITION
PRESERVATION
Following the leak test acceptance the whole system will be
depressurized
SUB-SYSTEM STATUS
Ready for Offshore leak test at operating pressure. ( If needed )