TABLE

1. APPLICATION SCOPE & PURPOSE

2. PROJECT SUMMARY & SCOPE OF WORK


2.1 PROJECT SUMMARY
2.2 ENGINEERING MAN HOUR
2.3 NO. OF EQUIPMENT
2.4 NO. OF DRAWING
2.5 PROCESS DESCRIPTION
2.6 REGULATIONS OF THE DISCHARGE PERMISSION STANDARD

3. ORGANIZATION CHART FOR DESIGN EXECUTION & DIVISION OF DUTIES


3.1 Organization chart
3.2 Process Activities

4. BASIS OF WORK APPROVAL

5. GUIDE FOR DESIGN

6. DESIGN SPECIAL MATTERS & EXECUTION PLAN

6.1 DESIGN SPECIAL MATTERS & DRIVE PLAN


6.2 ISSUE SCHEDULE CONTROL PLAN ABOUT DESIGN PRODUCT
6.3 DESIGN QUALITY CONTROL PLAN
6.4 COST SAVING PLAN

ATTACHMENT
#1 : Project Design Criteria
#2 : Process description
#3 : Key Milestone Schedule
#4 : Deliverable List
#5 : Environmental Regulation

2 of 14
1. APPLICATION SCOPE & PURPOSE
- Application in general work of process engineering team
- Arrangement of the job execution organization and design basis for practical use
- Establishment of design consistency and quality

2. PROJECT SUMMARY & SCOPE OF WORK


This project must be executed in accordance with design basis stated below.

2.1 PROJECT SUMMARY

PROJECT NO SO-2331

PROJECT PROJECT NAME DHU NOCL Project

PLANT LOCATION Cuddalore , Tamil Naidu, India


Nagarjuna Oil Corporation Ltd. (NOCL)
CLIENT
PMC : CB&I Lummus

PROCESS
- Desulphurized Diesel & 1 MMTPA
- PRODUCT & CAPACITY

LICENSOR Axens
PROJECT PERIOD
2010.05.01 - 2012-01-28 Mechanical
Completion)*

Lump-sum Turn-key,
CONTRACT
EPCC (with performance test)
SCOPE OF WORK ENG. FOR PROCESS DETAIL DESIGN

PROCUREMENT SEI

CONSTRUCTION SEI

* Mechanical Completion Including Pre-comissioning.

3 of 14
2.2 ENGINEERING MAN HOUR

CLASSIFICATION DHDS PROCESS


ENGINEERING TOTAL
(M/H)
Process 7096 7096
Utilities 1774 1774
CAD 1700 1700
Pre-commissioning assistance 1500 1500
TOTAL 12070 12070
(for proposal cost calculation)

2.3 NO. OF EQUIPMENT

SEI Novation Item TOTAL


ITEM Item Piece Item Piece
HYDROTREATOR
- - 1 1 1
REACTOR
COLUMNS 2 2 1 1 3
VESSEL 21 22 1 1 23
HEAT EXCHANGER 5 8 3 8 16
PUMP 13 26 - - 26
COMPRESSOR - - 2 3 3
TURBINE - - 1
FIRED HEATER - - 1 1 1
AIR COOLERS 3 3 - - 3
MISC. 7 7 - - 7
TOTAL 51 68 9 15 84

2.4 NO. OF DRAWING

Description Size Unit DHDS TOTAL


P&ID A3 SHEET 43 43
PFD A3 SHEET 6 6
MFD A3 SHEET 3 3

4 of 14
2.5 PROCESS DESCRIPTION

Refer to attachment #2 : process description

2.6 REGULATIONS REVIEW OF THE DISCHARGE PERMISSION STANDARD

It will follow the national standards for effluents and emission approved by the
CENTRAL POLLUTION CONTROL BOARD (CPCB).

3. ORGANIZATION CHART FOR DESIGN EXECUTION & DIVISION OF DUTIES

3.1 Organization chart

Team Manager
Gautam Roy
Design Verifier
LE V.K. Bansal
Ketaki Adhikary

CAD Draftman
(2 No’s)

Dy. LE Key Person (KP)


Arun Goyal Pradeep Amale

Ass. Engg.(AE)
Amrit P. Ramesh
Ankur Agarwal
Mayank Gupta(GET)
Ajay Jain (GET)

5 of 14
3.2 Process Activities
‹ Updation of FEED Document
‹ Hydraulic calculations for line sizing, pump data sheet and in line instrument data
sheets
‹ Process Engg calculations
‹ Flare header and utility header sizing checking and calculation.
‹ PSV calculations , Control valve sizing checking and data sheet preparation
‹ P&ID review / updation for client comments / Hazop comments incorporation
‹ Instrument data sheets preparation
‹ Preparation of line list
‹ Equipment list
‹ Support for other disciplines
‹ Vendor Package / drawing review
‹ MR Review of Equipments
‹ Participation in HAZOP studies
‹ Cause and effect diagram updation
‹ Updation of Operating manual
‹ Participate in 3-D model review.
‹ Assistance to pre-commissioning and commissioning activities.
‹ Field Engineering.

6 of 14
4-BASIS OF WORK APPROVAL

Basis of work approval in this project is same with clause of Process Team Operation
Instruction (SEM-0900E-IND).

Approval Basis of Process Team

O : Originator C : Check A : Approve R : Review

7 of 14
5. GUIDE FOR DESIGN

VERIFICATION
DRAWING UP MATERIALS PROCESS
TERMS

1. DRAWING
1) PFD Review from BEP/FEED
2) P&ID (IFP) Essential Update from BEP/FEED
3) UDD Update from BEP/FEED

2. DATA SHEETS

1) EQUIPMENT LIST Review and update


2) EQUIPMENT DATA SHEETS Review and update
- REACTOR
- COLUMN
- VESSEL
- HEAT EXCHANGER
- AIR COOLER
- PUMP
- COMPRESSOR
- FIRED HEATER
- MISCELLANEOUS
- PACKAGE
3) INSTRUMENT DATA SHEET
- INSTRUMENT PROCESS DATA Prepare and update
- CONTROL VALVE PROCESS DATA Review and update

- SAFETY VALVE PROCESS DATA Review and update

4) PIPING PROCESS DATA Prepare and update

3. PROCESS REQUIREMENT & INFORMATION


1) PROCESS DESCRIPTION Review only
2) PROCESS REQUIREMENT FOR BEDD Review only

8 of 14
3) B/L CONDITION Review and develop
4) SUMMARY OF UTILITY CONSUMPTION Review and update

5) SUMMARY OF EFFLUENT Review and update

6) PARTICIPATION IN HAZOP STUDIES Participate


Prepare(not a
7) FEED VERIFICATION REPORT
deliverable)
8) OPERATING MANUAL Update
9) CAUSE & EFFECT DIAGRAM Update

6. DESIGN SPECIAL MATTERS & EXECUTION PLAN

6.1 DESIGN SPECIAL MATTERS & DRIVE PLAN

1) GENERAL

The project will be driven by SEI who is fully aware of the Contract requirement
including the final result of clarification and technical proposal update, minutes of
kick-off meeting, P&ID screen meeting memo, licensor document regarding design and
operation, engineering manual and correspondences from and/or to NOCL/PMC and reflect
them into the process design of detail engineering. All the project design activities
shall be performed based on Project Design Criteria.

Refer to attachment #1 : Project Design Criteria

2) BASIC DESIGN ENGINEERING PACKAGE (BDP) / FRONT END ENGG PACKAGE (FEED)

M/S Axens (Licensor) has prepared the Basic design Package (BDP) which has been used by
M/S Technip for preparation of FEED Package. FEED Package will be used for detail
engineering by SEI. If there is any discrepancy between BDP and FEED and or within BDP,
and FEED ,SEI shall verify it with Licensor and PMC to avoid the design revision and to
facilitate the fast track project execution.

3) COORDINATION PROCEDURE

Forwarding of document or transmittal must follow coordination procedure which has been
agreed with NOCL/PMC .Items which are related to Licensor design must be discussed and
confirmed by AXENS, in advance and the preservation of sufficient time for review and
discussion shall be considered. SEI will inform the deviation to the Licensor/PMC.

Battery Limit Condition and battery limit schedule summary should be confirmed and
clarified by Client in the beginning of the project.

Data base for common application and activities are to be made available in a common

9 of 14
server.

Detailed design of PSV should follow API codes (RP 520,521 etc) and standards.

4) PRACTICAL USE OF EXISTING DATA

SEI will use the existing data of the previous DHDS projects. If no proper existing
data are available, PMC to provide the same.

5) BL CONDITION

Contract or FEED specifies the battery limit condition which shall be taken into account
for the design of equipment, instrument, piping, etc. Especially the differential head
of pump and compressor and the size of ISBL headers and battery limit conditions are
often referred.

6.2 ISSUE SCHEDULE CONTROL PLAN OF DESIGN PRODUCT

1) COORDINATION & INTERACTION OF EACH DESIGN TEAMS


If design revision arises, ERI(Engineering Revision Instruction) will be used
after IFC P&ID stage to confirm that by document.

2) SCHEDULE OBSERVANCE
As a leading team, the observance of issue schedule about process product is highly
crucial to the overall project schedule.
Refer to Attachment #3 : Key Milestone Schedule

6.3 DESIGN QUALITY CONTROL PLAN

To meet project schedule, the interaction with other teams for information change and
especially, quality control is very important. Deliberation matters are same with below
matters.

6.3.1 DESIGN INFORMATION CONTROL PLAN


As leading team, observance of issue schedule about process product is very
influenceable to the overall project schedule. SEI will follow below procedure as
per the ITB requirement.

6.3.1.1 DELIBERATION AT EACH P&ID STAGE


 FOR PLAN (Ist issue)

10 of 14
FEED P&ID reflects AXENS design criteria and preliminary HAZOP Level
performed between client and licensor.
P&ID screen meeting ,new design changes as addendums and technical
clarifications given by client will be reflected on the P&ID’s after
discussion with client/PMC and IFP P&ID’s are to be issued to
Licensor for review. Validation of units and hydraulics, preliminary
equipment layout and over all plot plan changes, consistency related
changes will also be included in the P&IDs for process units as well
as utility distribution P&ID.

 FOR DESIGN (2nd issue)

All vendor input related with package item & rotating equipment will
be incorporated to issue IFD P&ID for Hazop. Also Inline instrument
(control valve, flowmeter), piping specialty, vendor information of
PSV will be reflected at IFD stage.

 FOR CONSTRUCTION (3rd issue)


All vendor information will be reflected based on final vendor print.
ALL comments of other teams and HAZOP recommendations will be
reflected after discussion with client.

 AS BUILT (4th issue)

6.3.1.2 APPLICATION OF ENGINEERING REVISION INSTRUCTION


ERI will be issued to reduce design schedule and reflect revised
information after IFC stage.
Issue purpose will be specified. If issue purpose is ‘For Information’,
ERI will be reflected directly.

6.3.1.3 EQUIPMENT DATA SHEET


Novation Items / Long delivery Equipment D/S will be issued by CLIENT/ PMC
for vendor quotation. Subsequently data sheets will be updated and issued
incorporating vendor inputs and other data.

6.3.1.4 INSTRUMENT PROCESS DATA SHEET


Control valve and inline instruments will be checked based on FEED process

11 of 14
data before D/S issue.

6.3.2 QUALITY CONTROL PLAN

SEI will follow below quality control plan for design quality to reduce field change
& schedule delay.

6.3.2.1 P&ID

Quality verification will follow clause of Process Team Operation


Instruction (SEM-0900E-IND).
All clauses on P&ID check list should be checked and reviewed.

 INTERNAL P&ID SCREENING MEETING


P&ID screening meeting will be conducted by QA group before IFP P&ID
is issued. So Result of meeting will be recorded by document.
All comments that need clarification will be confirmed by client/PMC
or licensor and reflected.

 NOTE SCREENING ON P&ID


Special requirements of licensor are suggested in P&ID note, So,
ambiguous comments should be clearly specified for prevention of
misunderstanding of piping team.

6.3.2.2 EQUIPMENT DATA SHEET

 NOTE SCREENING ON EQUIP. D/S


Special requirements of licensor are suggested in D/S notes. So,
ambiguous comments should be clearly specified for prevention of
misunderstanding of mechanical team.

 SCOPE OF WORK (PACKAGE ITEM)


SEI will confirm exact vendor scope by checking P&ID and will focus on
vendor package & connection for preventing missing items and remind
concerned department.

12 of 14
6.3.2.3 INSTRUMENT PROCESS DATA SHEET

 REMARK SCREENING ON INST. D/S


Special requirements are suggested in P&ID notes. SEI will compare
that for checking problems in terms of process.
(for example, orifice type flow meter on two phase line)

6.4 COST SAVING PLAN

1) COST SAVING (Value Engineering)


In case of removable or changeable item from the point of view of process design
based on Contract, SEI will persuade NOCL/PMC with the detailed operational or other
merits after having an agreement with licensor, Axens. The cost saving shall keep
pace with the project execution of fast track.

2) DEVIATION
No deviation against Contract is allowed by NOCL/PMC. In case the deviation is
required, the official approval from NOCL/PMC shall be acquired to avoid the
argument in the future. Procedure about all deviation (ex: removable or changeable
items) is same as below comment.
- REMOVABLE ITEM
Cost effect items must be reflected after client approval. All Items should
be specified by document.
- ADDITIONAL ITEM
When the need arises in terms of process, all items will be listed and
reflected. After list up, those items will be considered by client.

3) REWORK MINIMIZING
- SEI will always confer with resident NOCL/PMC engineer, so SEI will minimize
problems at initial stage.
- SEI will confer with resident NOCL/PMC engineer about design verification &
clarification at initial stage.

4) BUDGET MAN-HOUR
SEI will reduce rework by checking product of each stage, so SEI will control the
allotted budget MAN-HOUR. For this, weekly action list will specify instruction
about work allocation.

13 of 14
Attachment #1
Project Design Criteria

- Further development and revision of document available in FEED package will be done.
- Design requirement or philosophy of licensors will be distributed by correspondences.

Attachment #2
Process Description

- Proposal document for reference.


Process description for the project is available in licensor package.

Attachment #3
Key Milestone Schedule

- Further development and revision will be distributed by correspondences.

Attachment #4
Deliverable list

Attachment #5
Environmental Regulations

14 of 14
15 of 14
DIESEL HYDRODESULPHURIZATION UNIT
Deliverable list
Document Number :_______

PMC REVIEW
LICENSOR
SR NO. DOC./DWG. NO. DOCUMENT DESCRIPTION Review (R) / ISSUE DATE
REVIEW
Information (I)
DISCIPLINE : PROCESS
PROCESS FLOW DIAGRAM (PFD) 6 nos.
1 CS-140-PR-11-0001 PFD-SOR-Feed Section Licensor review 18 th June
2 CS-140-PR-11-0002 PFD-SOR-Reaction Section
3 CS-140-PR-11-0003 PFD-SOR-Stripping Section
4 CS-140-PR-11-0004 PFD-EOR-Feed Section
5 CS-140-PR-11-0005 PFD-EOR-Reaction Section
6 CS-140-PR-11-0006 PFD-EOR-Stripping Section

P&ID SYMBOLOGY AND LEGEND SHEET 3 nos.


7 CS-140-PR-14-0001 Mechanical, Instrumentation Symbols 18 th June
8 CS-140-PR-14-0002 Sample Connections
9 CS-140-PR-14-0003 Mechanical, Instrumentation Symbols

PROCESS PIPING AND INSTRUMENT DIAGRAMS 27 nos


10 CS-140-PR-15-0001 P&ID for Feed Filter 18 th June
11 CS-140-PR-15-0002 P&ID for Feed Section
12 CS-140-PR-15-0003 P&ID for Reactor Feed/Effluent Exchanger
13 CS-140-PR-15-0004 P&ID for Hydrotreater Reactor Feed Heater
14 CS-140-PR-15-0005 P&ID for Hydrotreater Reactor
15 CS-140-PR-15-0006 P&ID for Sour Water Flash Drum Reactor
16 CS-140-PR-15-0007 P&ID for H.P Seperation Section
17 CS-140-PR-15-0008 P&ID for Wash Water Section
18 CS-140-PR-15-0009 P&ID for H.P Amine Absorber K.O. Drum
19 CS-140-PR-15-0010 P&ID for H.P Amine Absorber Section
20 CS-140-PR-15-0011 P&ID for Recycle Compressor
21 CS-140-PR-15-0012 P&ID for Recycle Compressor K.O. Drum
22 CS-140-PR-15-0013 P&ID for Makeup Hydrogen K.O. Drum &
23 CS-140-PR-15-0014 P&ID for Hydrogen Makeup Compressor A
24 CS-140-PR-15-0015 P&ID for Hydrogen Makeup Compressor B
25 CS-140-PR-15-0016 P&ID for L.P Amine Absorber Section
26 CS-140-PR-15-0017 P&ID for Stripper Section
27 CS-140-PR-15-0018 P&ID for Stripper/Feed Effluent Exchangers
28 CS-140-PR-15-0019 P&ID for Gas Oil Cooling System
29 CS-140-PR-15-0020 P&ID for Stripper Condenser & Stripper Trim
30 CS-140-PR-15-0021 P&ID for Stripper Overhead Circuit
31 CS-140-PR-15-0022 P&ID for Coalescer
32 CS-140-PR-15-0023 P&ID for Sulfiding Antifoulant &Corrosion
33 CS-140-PR-15-0024 P&ID for Hydrotreater Reactor Feed Heater
34 CS-140-PR-15-0025 P&ID for AntiFoaming Drum & AntiOxidant
35 CS-140-PR-15-0026 P&ID for Hydrotreater Reacter Feed Heater
36 CS-140-PR-15-0027 P&ID for Motor Instrumentation Details

1 of 4
DIESEL HYDRODESULPHURIZATION UNIT
Deliverable list
Document Number :_______

PMC REVIEW
LICENSOR
SR NO. DOC./DWG. NO. DOCUMENT DESCRIPTION Review (R) / ISSUE DATE
REVIEW
Information (I)
DISCIPLINE : PROCESS
UTILITY PIPING AND INSTRUMENT DIAGRAMS 13 nos
37 CS-140-PR-26-0001 P&ID for H.P Steam M.P Steam & BFW 18 th June
38 CS-140-PR-26-0002 P&ID for L.P Steam Distribution System
39 CS-140-PR-26-0003 P&ID for Cooling Water System
40 CS-140-PR-26-0004 P&ID for Service Water & Potable Water
41 CS-140-PR-26-0005 P&ID for Nitrogen Plant Air & Instrument Air
42 CS-140-PR-26-0006 P&ID for Fuel Gas System- K.O.Drum
43 CS-140-PR-26-0007 P&ID for Fuel Oil & Flushing Oil System
44 CS-140-PR-26-0008 P&ID for Flare System
45 CS-140-PR-26-0009 P&ID for Flare K.O. Drum
46 CS-140-PR-26-0010 P&ID for Closed Hydrocarbon Drain
47 CS-140-PR-26-0011 P&ID for Closed Hydrocarbon Drain Drum
48 CS-140-PR-26-0012 P&ID for Amine Drain/Sour Water Drain
49 CS-140-PR-26-0013 P&ID for Amine Drain Drum

METALLURGICAL FLOW DIAGRAMS (MFD) 3 nos


50 CS-140-PR-19-0001 Material & Mechanical Diagram for Feed Section 18 th June
51 CS-140-PR-19-0002 Matrial & Mechanical Diagram for Reaction Section
52 CS-140-PR-19-0003 Material & Mechanical Diagram for Stripping Section

PROCESS CAUSE & EFFECT DIAGRAM


53 CS-140-PR-24-0001 Cause & Effect diagram 30 th Dec

PROCESS EQUIPMENT DATA SHEETS 58 nos


54 CS-140-PR-30-0001 Reactor Feed /EffluentExchanger(140-EE-001 A/B/C/D) Novation item 11 th May
55 CS-140-PR-30-0002 Stripper Feed Preheater (140-EE-002) Novation item
56 CS-140-PR-30-0003 Reactor Effluent Trim Cooler (140-EE-003) Novation item
57 CS-140-PR-30-0004 Hydrogen Make Up Kick Back Cooler (140-EE-004) 11 th May
58 CS-140-PR-30-0005 Stripper Trim Condenser (140-EE-005) 11 th May
59 CS-140-PR-30-0006 Stripper Feed/Bottom Exchanger (140-EE-006 A/B/C/D) 11 th May
60 CS-140-PR-30-0007 Gas Oil Trim Cooler (140-EE-007) 11 th May
61 CS-140-PR-30-0008 Make-up Compressor Interstage Coolers (140-EE-008 A/B) Novation item
62 CS-140-PR-30-0009 Hydrogen Cooler (140-EE-009) 11 th May
63 CS-140-PR-30-0010 Hydrotreated Reactor Feed Heater (140-H-001) Novation item
64 CS-140-PR-30-0011 PDS for Hydrotreated Reactor Feed Heater Burner Data 17 th May
65 CS-140-PR-30-0012 PDS for Reactor Effluent Air Cooler (140-EA-001) 11 th May
66 CS-140-PR-30-0013 PDS for Stripper Air Condenser(140-EA-002) 11 th May
67 CS-140-PR-30-0014 PDS for Gas Oil Air Cooler (140-EA-003) 11 th May
68 CS-140-PR-30-0015 PDS for HP Amine Absorber ( 140-C-001) Novation item
69 CS-140-PR-30-0016 PDS for Stripper (140-C-002) 6 th May
70 CS-140-PR-30-0017 PDS for LP Amine Absorber ( 140-C-003) 6 th May
71 CS-140-PR-30-0018 PDS for Hydrotreater Reactor (140-R-001) Novation item
72 CS-140-PR-30-0019 PDS for Hydrogen Make up Compressor (140-K-001 A/B) Novation item
2 of 4
DIESEL HYDRODESULPHURIZATION UNIT
Deliverable list
Document Number :_______

PMC REVIEW
LICENSOR
SR NO. DOC./DWG. NO. DOCUMENT DESCRIPTION Review (R) / ISSUE DATE
REVIEW
Information (I)
DISCIPLINE : PROCESS
73 CS-140-PR-30-0020 PDS for Recycle Compressor (140-K-002) Novation item
74 CS-140-PR-30-0021 PDS for Recycle Compressor Steam Turbine (140-KT-002) Novation item
75 CS-140-PR-30-0022 PDS for Feed Surge Drum( 140-V-001) 15 th May
76 CS-140-PR-30-0023 PDS for Make-Up Gas Compressor K.O.D(140-V-002) 15 th May
77 CS-140-PR-30-0024 PDS for Make up Compressor Interstage KO drums (140-V-004) 15 th May
78 CS-140-PR-30-0025 PDS for Wash Water Drum ( 140-V-004) 15 th May
79 CS-140-PR-30-0026 PDS for Recycle Compressor K.O. Drum (140-V-005) 15 th May
80 CS-140-PR-30-0027 PDS for Separator Drum (140-V-006) Novation item
81 CS-140-PR-30-0028 PDS for HP Amine Absorber K.O. Drum (140-V-007) 15 th May
82 CS-140-PR-30-0029 PDS for Stripper Reflaux Drum ( 140-V-008) 15 th May
83 CS-140-PR-30-0030 PDS for Coalescer( 140-V-009 ) 11 th May
84 CS-140-PR-30-0031 PDS for LP Amine Absorber K.O. Drum (140-V-010) 15 th May
85 CS-140-PR-30-0032 PDS for Sulfiding Agent Drum (140-V-011) 24 th May
86 CS-140-PR-30-0033 PDS for Antifoulant Drum (140-V-012) 24 th May
87 CS-140-PR-30-0034 PDS for Anti-Foming Agent Drum (140-V-014) 24 th May
88 CS-140-PR-30-0035 PDS for Corrosion Inhibitor Drum (140-V-015) 24 th May
89 CS-140-PR-30-0036 PDS for Sour Water Flash Drum ( 140-V-017) 15 th May
90 CS-140-PR-30-0037 PDS for Off Gas K.O Drum ( 140-V-018) 15 th May
91 CS-140-PR-30-0038 PDS for Salt Dryer ( 140-V-019) Vendor Package 13 th May
92 CS-140-PR-30-0039 PDS for Antioxidant Drum (140-V-020) 24 th May
93 CS-140-PR-30-0040 PDS for Hydrocarbon Drain Drum (140-V-021) 15 th May
94 CS-140-PR-30-0041 PDS for Amine Drain Drum (140-V-022) 15 th May
95 CS-140-PR-30-0042 PDS for Flare K.O Drum (140-V-023) 15 th May
96 CS-140-PR-30-0043 PDS for Fuel Gas K.O. Drum (140-V-025) 15 th May
97 CS-140-PR-30-0044 PDS for Gas Oil Feed Pump (140-P-001A/B) 22 nd May
98 CS-140-PR-30-0045 PDS for Wash Water Pump (140-P-002A/B) 22 nd May
99 CS-140-PR-30-0046 PDS for Lean Amine Booster Pump (140-P-003A/B) 22 nd May
100 CS-140-PR-30-0047 PDS for Stripper Reflux Pump (140-P-004A/B) 22 nd May
101 CS-140-PR-30-0048 PDS for Stripper Bottoms Pump (140-P-005 A/B) 22 nd May
102 CS-140-PR-30-0049 PDS for Sulfiding Agent Injection Pump (140-P-007A/B) 24 th May
103 CS-140-PR-30-0050 PDS for Anti Foulant Injection Pump (140-P-008A/B) 24 th May
104 CS-140-PR-30-0051 PDS for Antifoaming Agent Pump (140-P-010A/B) 24 th May
105 CS-140-PR-30-0052 PDS for Corrosion Inhibitor Injection Pump(140-P-011A/B) 24 th May
106 CS-140-PR-30-0053 PDS for Antioxidant Pump (140-P-012A/B) 24 th May
107 CS-140-PR-30-0054 PDS for Closed Drain Drum Pump (140-P-013A/B) 22 nd May
108 CS-140-PR-30-0055 PDS for Amine Drain Drum Pump (140-P-014A/B) 22 nd May
109 CS-140-PR-30-0056 PDS for Flare KOD Pump (140-P-015A/B) 22 nd May
110 CS-140-PR-30-0057 PDS for Start-Up Ejector (140-J-001) 27 th May
111 CS-140-PR-30-0058 PDS for MP steam desuperheater (140-DS-001) 27 th May

PROCESS INSTRUMENT DATA SHEETS nos.


112 CS-140-PR-31-0001 PDS for Pressure Instruments 235 30 th July
113 CS-140-PR-31-0002 PDS for Temperature Instruments 233 30 th July

3 of 4
DIESEL HYDRODESULPHURIZATION UNIT
Deliverable list
Document Number :_______

PMC REVIEW
LICENSOR
SR NO. DOC./DWG. NO. DOCUMENT DESCRIPTION Review (R) / ISSUE DATE
REVIEW
Information (I)
DISCIPLINE : PROCESS
114 CS-140-PR-31-0003 PDS for Flow Instruments 60 15 th July
115 CS-140-PR-31-0004 PDS for Level Instruments 62 30 th July
116 CS-140-PR-31-0005 PDS for Analysers 8 15 th July
117 CS-140-PR-31-0006 PDS for Control Valve 55 15 th July
118 CS-140-PR-31-0007 PDS for Shutdown Valve 13 30 th July
119 CS-140-PR-31-0008 PDS for Pressure Safety Valve 43 23 rd July
120 CS-140-PR-31-0009 PDS for Motor Operated Valve 4 23 rd July
121 CS-140-PR-31-0010 PDS for Restriction Orifice 14 15 th July

PROCESS SPECIFICATIONS
122 CS-140-PR-40-0001 PDS for Feed Filter (140-F-001) 10 th May

SPECIAL PIPING ITEM DATASHEETS


123 CS-140-PR-32-0001 PDS for Special Piping Items 27 th May
124 CS-140-PR-32-0002 PDS for MP steam silencer (140-SA-001) 27 th May
125 CS-140-PR-32-0003 PDS for MP steam silencer (140-SA-002) 27 th May
126 CS-140-PR-32-0004 PDS for MP steam silencer (140-SA-003) 27 th May
127 CS-140-PR-32-0005 PDS for silencer (140-SA-004) 27 th May

PROCESS CONTROL AND SAFEGUARDING


128 CS-140-PR-45-0001 Process control and safeguarding 31 st Jan

PROCESS REPORTS/LISTINGS
130 CS-140-PR-50-0001 Equipment List 30 th June
131 CS-140-PR-50-0002 Battery limit condition summary 30 th Dec
132 CS-140-PR-50-0003 Line list 30 th Sep
133 CS-140-PR-50-0004 Catalyst and Chemical summary 30 th Dec
134 CS-140-PR-50-0005 Utility summary 30 th Dec
135 CS-140-PR-50-0006 Effluent summary 30 th Dec
136 CS-140-PR-50-0007 Flare load summary 29 th Oct

PROCESS CALCULATIONS
137 CS-140-PR-60-0001 Hydraulic report 30 th Dec

MANUALS
138 CS-140-PR-70-0001 Operating manual 30 th June

HAZOP
139 CS-140-PR-47-0001 HAZOP studies 30 th Dec

4 of 4