ATTACHMENT
#1 : Project Design Criteria
#2 : Process description
#3 : Key Milestone Schedule
#4 : Deliverable List
#5 : Environmental Regulation
2 of 14
1. APPLICATION SCOPE & PURPOSE
- Application in general work of process engineering team
- Arrangement of the job execution organization and design basis for practical use
- Establishment of design consistency and quality
PROJECT NO SO-2331
PROCESS
- Desulphurized Diesel & 1 MMTPA
- PRODUCT & CAPACITY
LICENSOR Axens
PROJECT PERIOD
2010.05.01 - 2012-01-28 Mechanical
Completion)*
Lump-sum Turn-key,
CONTRACT
EPCC (with performance test)
SCOPE OF WORK ENG. FOR PROCESS DETAIL DESIGN
PROCUREMENT SEI
CONSTRUCTION SEI
3 of 14
2.2 ENGINEERING MAN HOUR
4 of 14
2.5 PROCESS DESCRIPTION
It will follow the national standards for effluents and emission approved by the
CENTRAL POLLUTION CONTROL BOARD (CPCB).
Team Manager
Gautam Roy
Design Verifier
LE V.K. Bansal
Ketaki Adhikary
CAD Draftman
(2 No’s)
Ass. Engg.(AE)
Amrit P. Ramesh
Ankur Agarwal
Mayank Gupta(GET)
Ajay Jain (GET)
5 of 14
3.2 Process Activities
Updation of FEED Document
Hydraulic calculations for line sizing, pump data sheet and in line instrument data
sheets
Process Engg calculations
Flare header and utility header sizing checking and calculation.
PSV calculations , Control valve sizing checking and data sheet preparation
P&ID review / updation for client comments / Hazop comments incorporation
Instrument data sheets preparation
Preparation of line list
Equipment list
Support for other disciplines
Vendor Package / drawing review
MR Review of Equipments
Participation in HAZOP studies
Cause and effect diagram updation
Updation of Operating manual
Participate in 3-D model review.
Assistance to pre-commissioning and commissioning activities.
Field Engineering.
6 of 14
4-BASIS OF WORK APPROVAL
Basis of work approval in this project is same with clause of Process Team Operation
Instruction (SEM-0900E-IND).
7 of 14
5. GUIDE FOR DESIGN
VERIFICATION
DRAWING UP MATERIALS PROCESS
TERMS
1. DRAWING
1) PFD Review from BEP/FEED
2) P&ID (IFP) Essential Update from BEP/FEED
3) UDD Update from BEP/FEED
2. DATA SHEETS
8 of 14
3) B/L CONDITION Review and develop
4) SUMMARY OF UTILITY CONSUMPTION Review and update
1) GENERAL
The project will be driven by SEI who is fully aware of the Contract requirement
including the final result of clarification and technical proposal update, minutes of
kick-off meeting, P&ID screen meeting memo, licensor document regarding design and
operation, engineering manual and correspondences from and/or to NOCL/PMC and reflect
them into the process design of detail engineering. All the project design activities
shall be performed based on Project Design Criteria.
2) BASIC DESIGN ENGINEERING PACKAGE (BDP) / FRONT END ENGG PACKAGE (FEED)
M/S Axens (Licensor) has prepared the Basic design Package (BDP) which has been used by
M/S Technip for preparation of FEED Package. FEED Package will be used for detail
engineering by SEI. If there is any discrepancy between BDP and FEED and or within BDP,
and FEED ,SEI shall verify it with Licensor and PMC to avoid the design revision and to
facilitate the fast track project execution.
3) COORDINATION PROCEDURE
Forwarding of document or transmittal must follow coordination procedure which has been
agreed with NOCL/PMC .Items which are related to Licensor design must be discussed and
confirmed by AXENS, in advance and the preservation of sufficient time for review and
discussion shall be considered. SEI will inform the deviation to the Licensor/PMC.
Battery Limit Condition and battery limit schedule summary should be confirmed and
clarified by Client in the beginning of the project.
Data base for common application and activities are to be made available in a common
9 of 14
server.
Detailed design of PSV should follow API codes (RP 520,521 etc) and standards.
SEI will use the existing data of the previous DHDS projects. If no proper existing
data are available, PMC to provide the same.
5) BL CONDITION
Contract or FEED specifies the battery limit condition which shall be taken into account
for the design of equipment, instrument, piping, etc. Especially the differential head
of pump and compressor and the size of ISBL headers and battery limit conditions are
often referred.
2) SCHEDULE OBSERVANCE
As a leading team, the observance of issue schedule about process product is highly
crucial to the overall project schedule.
Refer to Attachment #3 : Key Milestone Schedule
To meet project schedule, the interaction with other teams for information change and
especially, quality control is very important. Deliberation matters are same with below
matters.
10 of 14
FEED P&ID reflects AXENS design criteria and preliminary HAZOP Level
performed between client and licensor.
P&ID screen meeting ,new design changes as addendums and technical
clarifications given by client will be reflected on the P&ID’s after
discussion with client/PMC and IFP P&ID’s are to be issued to
Licensor for review. Validation of units and hydraulics, preliminary
equipment layout and over all plot plan changes, consistency related
changes will also be included in the P&IDs for process units as well
as utility distribution P&ID.
All vendor input related with package item & rotating equipment will
be incorporated to issue IFD P&ID for Hazop. Also Inline instrument
(control valve, flowmeter), piping specialty, vendor information of
PSV will be reflected at IFD stage.
11 of 14
data before D/S issue.
SEI will follow below quality control plan for design quality to reduce field change
& schedule delay.
6.3.2.1 P&ID
12 of 14
6.3.2.3 INSTRUMENT PROCESS DATA SHEET
2) DEVIATION
No deviation against Contract is allowed by NOCL/PMC. In case the deviation is
required, the official approval from NOCL/PMC shall be acquired to avoid the
argument in the future. Procedure about all deviation (ex: removable or changeable
items) is same as below comment.
- REMOVABLE ITEM
Cost effect items must be reflected after client approval. All Items should
be specified by document.
- ADDITIONAL ITEM
When the need arises in terms of process, all items will be listed and
reflected. After list up, those items will be considered by client.
3) REWORK MINIMIZING
- SEI will always confer with resident NOCL/PMC engineer, so SEI will minimize
problems at initial stage.
- SEI will confer with resident NOCL/PMC engineer about design verification &
clarification at initial stage.
4) BUDGET MAN-HOUR
SEI will reduce rework by checking product of each stage, so SEI will control the
allotted budget MAN-HOUR. For this, weekly action list will specify instruction
about work allocation.
13 of 14
Attachment #1
Project Design Criteria
- Further development and revision of document available in FEED package will be done.
- Design requirement or philosophy of licensors will be distributed by correspondences.
Attachment #2
Process Description
Attachment #3
Key Milestone Schedule
Attachment #4
Deliverable list
Attachment #5
Environmental Regulations
14 of 14
15 of 14
DIESEL HYDRODESULPHURIZATION UNIT
Deliverable list
Document Number :_______
PMC REVIEW
LICENSOR
SR NO. DOC./DWG. NO. DOCUMENT DESCRIPTION Review (R) / ISSUE DATE
REVIEW
Information (I)
DISCIPLINE : PROCESS
PROCESS FLOW DIAGRAM (PFD) 6 nos.
1 CS-140-PR-11-0001 PFD-SOR-Feed Section Licensor review 18 th June
2 CS-140-PR-11-0002 PFD-SOR-Reaction Section
3 CS-140-PR-11-0003 PFD-SOR-Stripping Section
4 CS-140-PR-11-0004 PFD-EOR-Feed Section
5 CS-140-PR-11-0005 PFD-EOR-Reaction Section
6 CS-140-PR-11-0006 PFD-EOR-Stripping Section
1 of 4
DIESEL HYDRODESULPHURIZATION UNIT
Deliverable list
Document Number :_______
PMC REVIEW
LICENSOR
SR NO. DOC./DWG. NO. DOCUMENT DESCRIPTION Review (R) / ISSUE DATE
REVIEW
Information (I)
DISCIPLINE : PROCESS
UTILITY PIPING AND INSTRUMENT DIAGRAMS 13 nos
37 CS-140-PR-26-0001 P&ID for H.P Steam M.P Steam & BFW 18 th June
38 CS-140-PR-26-0002 P&ID for L.P Steam Distribution System
39 CS-140-PR-26-0003 P&ID for Cooling Water System
40 CS-140-PR-26-0004 P&ID for Service Water & Potable Water
41 CS-140-PR-26-0005 P&ID for Nitrogen Plant Air & Instrument Air
42 CS-140-PR-26-0006 P&ID for Fuel Gas System- K.O.Drum
43 CS-140-PR-26-0007 P&ID for Fuel Oil & Flushing Oil System
44 CS-140-PR-26-0008 P&ID for Flare System
45 CS-140-PR-26-0009 P&ID for Flare K.O. Drum
46 CS-140-PR-26-0010 P&ID for Closed Hydrocarbon Drain
47 CS-140-PR-26-0011 P&ID for Closed Hydrocarbon Drain Drum
48 CS-140-PR-26-0012 P&ID for Amine Drain/Sour Water Drain
49 CS-140-PR-26-0013 P&ID for Amine Drain Drum
PMC REVIEW
LICENSOR
SR NO. DOC./DWG. NO. DOCUMENT DESCRIPTION Review (R) / ISSUE DATE
REVIEW
Information (I)
DISCIPLINE : PROCESS
73 CS-140-PR-30-0020 PDS for Recycle Compressor (140-K-002) Novation item
74 CS-140-PR-30-0021 PDS for Recycle Compressor Steam Turbine (140-KT-002) Novation item
75 CS-140-PR-30-0022 PDS for Feed Surge Drum( 140-V-001) 15 th May
76 CS-140-PR-30-0023 PDS for Make-Up Gas Compressor K.O.D(140-V-002) 15 th May
77 CS-140-PR-30-0024 PDS for Make up Compressor Interstage KO drums (140-V-004) 15 th May
78 CS-140-PR-30-0025 PDS for Wash Water Drum ( 140-V-004) 15 th May
79 CS-140-PR-30-0026 PDS for Recycle Compressor K.O. Drum (140-V-005) 15 th May
80 CS-140-PR-30-0027 PDS for Separator Drum (140-V-006) Novation item
81 CS-140-PR-30-0028 PDS for HP Amine Absorber K.O. Drum (140-V-007) 15 th May
82 CS-140-PR-30-0029 PDS for Stripper Reflaux Drum ( 140-V-008) 15 th May
83 CS-140-PR-30-0030 PDS for Coalescer( 140-V-009 ) 11 th May
84 CS-140-PR-30-0031 PDS for LP Amine Absorber K.O. Drum (140-V-010) 15 th May
85 CS-140-PR-30-0032 PDS for Sulfiding Agent Drum (140-V-011) 24 th May
86 CS-140-PR-30-0033 PDS for Antifoulant Drum (140-V-012) 24 th May
87 CS-140-PR-30-0034 PDS for Anti-Foming Agent Drum (140-V-014) 24 th May
88 CS-140-PR-30-0035 PDS for Corrosion Inhibitor Drum (140-V-015) 24 th May
89 CS-140-PR-30-0036 PDS for Sour Water Flash Drum ( 140-V-017) 15 th May
90 CS-140-PR-30-0037 PDS for Off Gas K.O Drum ( 140-V-018) 15 th May
91 CS-140-PR-30-0038 PDS for Salt Dryer ( 140-V-019) Vendor Package 13 th May
92 CS-140-PR-30-0039 PDS for Antioxidant Drum (140-V-020) 24 th May
93 CS-140-PR-30-0040 PDS for Hydrocarbon Drain Drum (140-V-021) 15 th May
94 CS-140-PR-30-0041 PDS for Amine Drain Drum (140-V-022) 15 th May
95 CS-140-PR-30-0042 PDS for Flare K.O Drum (140-V-023) 15 th May
96 CS-140-PR-30-0043 PDS for Fuel Gas K.O. Drum (140-V-025) 15 th May
97 CS-140-PR-30-0044 PDS for Gas Oil Feed Pump (140-P-001A/B) 22 nd May
98 CS-140-PR-30-0045 PDS for Wash Water Pump (140-P-002A/B) 22 nd May
99 CS-140-PR-30-0046 PDS for Lean Amine Booster Pump (140-P-003A/B) 22 nd May
100 CS-140-PR-30-0047 PDS for Stripper Reflux Pump (140-P-004A/B) 22 nd May
101 CS-140-PR-30-0048 PDS for Stripper Bottoms Pump (140-P-005 A/B) 22 nd May
102 CS-140-PR-30-0049 PDS for Sulfiding Agent Injection Pump (140-P-007A/B) 24 th May
103 CS-140-PR-30-0050 PDS for Anti Foulant Injection Pump (140-P-008A/B) 24 th May
104 CS-140-PR-30-0051 PDS for Antifoaming Agent Pump (140-P-010A/B) 24 th May
105 CS-140-PR-30-0052 PDS for Corrosion Inhibitor Injection Pump(140-P-011A/B) 24 th May
106 CS-140-PR-30-0053 PDS for Antioxidant Pump (140-P-012A/B) 24 th May
107 CS-140-PR-30-0054 PDS for Closed Drain Drum Pump (140-P-013A/B) 22 nd May
108 CS-140-PR-30-0055 PDS for Amine Drain Drum Pump (140-P-014A/B) 22 nd May
109 CS-140-PR-30-0056 PDS for Flare KOD Pump (140-P-015A/B) 22 nd May
110 CS-140-PR-30-0057 PDS for Start-Up Ejector (140-J-001) 27 th May
111 CS-140-PR-30-0058 PDS for MP steam desuperheater (140-DS-001) 27 th May
3 of 4
DIESEL HYDRODESULPHURIZATION UNIT
Deliverable list
Document Number :_______
PMC REVIEW
LICENSOR
SR NO. DOC./DWG. NO. DOCUMENT DESCRIPTION Review (R) / ISSUE DATE
REVIEW
Information (I)
DISCIPLINE : PROCESS
114 CS-140-PR-31-0003 PDS for Flow Instruments 60 15 th July
115 CS-140-PR-31-0004 PDS for Level Instruments 62 30 th July
116 CS-140-PR-31-0005 PDS for Analysers 8 15 th July
117 CS-140-PR-31-0006 PDS for Control Valve 55 15 th July
118 CS-140-PR-31-0007 PDS for Shutdown Valve 13 30 th July
119 CS-140-PR-31-0008 PDS for Pressure Safety Valve 43 23 rd July
120 CS-140-PR-31-0009 PDS for Motor Operated Valve 4 23 rd July
121 CS-140-PR-31-0010 PDS for Restriction Orifice 14 15 th July
PROCESS SPECIFICATIONS
122 CS-140-PR-40-0001 PDS for Feed Filter (140-F-001) 10 th May
PROCESS REPORTS/LISTINGS
130 CS-140-PR-50-0001 Equipment List 30 th June
131 CS-140-PR-50-0002 Battery limit condition summary 30 th Dec
132 CS-140-PR-50-0003 Line list 30 th Sep
133 CS-140-PR-50-0004 Catalyst and Chemical summary 30 th Dec
134 CS-140-PR-50-0005 Utility summary 30 th Dec
135 CS-140-PR-50-0006 Effluent summary 30 th Dec
136 CS-140-PR-50-0007 Flare load summary 29 th Oct
PROCESS CALCULATIONS
137 CS-140-PR-60-0001 Hydraulic report 30 th Dec
MANUALS
138 CS-140-PR-70-0001 Operating manual 30 th June
HAZOP
139 CS-140-PR-47-0001 HAZOP studies 30 th Dec
4 of 4