PENGERANG INTEGRATED COMPLEX

Activity ID Package Activity Name Original BL1 Start BL1 Finish 2018
Duration July August ptember
09 16 23 30 06 13 20 27 03
INTEGRATED NETWORK PC&C
PC 47 15-Jul-18 31-Aug-18
Process 47 15-Jul-18 31-Aug-18
Amine IN-1000-0022 47 15-Jul-18 31-Aug-18
Milestone 38 24-Jul-18 31-Aug-18
A1060 Water Flush 4 24-Jul-18 28-Jul-18
A1070 Chemical Flush 14 29-Jul-18 12-Aug-18
A1080 Demin Water Rinsing 9 13-Aug-18 22-Aug-18
A1090 Final Rinsing 9 22-Aug-18 31-Aug-18
Water Flush 14 15-Jul-18 28-Jul-18
IN-1000-22-10 P4 Water Filling- Tanks -1610-T-001/1611-V-001 / 16 12-V-00 1 2 15-Jul-18 16-Jul-18
IN-1000-22-11 P4 Line filling- Intercntg. header P4 / P3 (Lean HP/LP Amine to Rich amine line /Bypass line) 2 17-Jul-18 18-Jul-18
IN-1000-22-12 P4-P3 Establish Circulation-Interconnecting Header ( with Bypass at SGP, DHT, CNHT) 2 19-Jul-18 20-Jul-18
IN-1000-22-13 P3-RF Lineup to packages P1 / P2 / P3 - supply and return lines to Main Rich Amine Header 4 21-Jul-18 24-Jul-18
IN-1000-22-14 P3-RF Establish Circulation with all packages 1 25-Jul-18 25-Jul-18
IN-1000-22-15 P4 Disposal of spent water 3 26-Jul-18 28-Jul-18
IN-1000-22-16 P3-RF Drain Down 3 26-Jul-18 28-Jul-18
Chemical Flush 16 29-Jul-18 13-Aug-18
IN-1000-22-17 RF Water Filling- Tanks -1610-T-001/1611-V-001 / 16 12-V-00 1 2 29-Jul-18 30-Jul-18
IN-1000-22-18 P3-P4 Line filling- Interconnecting header P4 / P3 (Lean HP/LP Amine to Rich amine line with Bypass line) 2 31-Jul-18 01-Aug-18
IN-1000-22-19 P3-P4 Establish Circulation-Interconnecting Header ( with Bypass at end of headers ) 2 02-Aug-18 03-Aug-18
IN-1000-22-20 P3-RF Lineup to packages P1 / P2 / P3 - supply and return lines to Main Rich Amine Header 3 04-Aug-18 06-Aug-18
IN-1000-22-21 P3-RF Establish Circulation with all packages 0 07-Aug-18 07-Aug-18
IN-1000-22-22 P4 Heating with LP Steam and temp achived. 0 07-Aug-18 07-Aug-18
IN-1000-22-23 P4 Chemical Injection 4 07-Aug-18 10-Aug-18
IN-1000-22-24 P4 Circulation with Chemical 4 07-Aug-18 10-Aug-18
IN-1000-22-25 P4 Sampling at each unit BL ( inlet / outlet ) by chemical cleaning agency appointed by P4 4 07-Aug-18 10-Aug-18
IN-1000-22-26 P3-RF Drain Down 2 11-Aug-18 12-Aug-18
IN-1000-22-27 P4 Disposal of spent chemical 3 11-Aug-18 13-Aug-18
IN-1000-22-28 P3-RF Preservation - N2 blanketing 2 11-Aug-18 12-Aug-18
Rinsing - Demin Water 10 13-Aug-18 22-Aug-18
IN-1000-22-29 P3-RF Water Filling- Tanks -1610-T-001/1611-V-001 / 16 12-V-00 1 2 13-Aug-18 14-Aug-18
IN-1000-22-30 P3-P4 Line filling- Interconnecting header P4 / P3 (Lean HP/LP Amine to Rich amine line with Bypass line) 2 13-Aug-18 14-Aug-18
IN-1000-22-31 P3-P4 Establish Circulation-Interconnecting Header ( with Bypass at end of headers ) 2 15-Aug-18 16-Aug-18
IN-1000-22-32 P3-RF Lineup to packages P1 / P2 / P3 - supply and return lines to Main Rich Amine Header 2 15-Aug-18 16-Aug-18
IN-1000-22-33 P3-RF Establish Circulation with all packages 3 17-Aug-18 19-Aug-18
IN-1000-22-34 P3-RF Sampling PH/FE 3 17-Aug-18 19-Aug-18
IN-1000-22-35 P3-RF Drain Down 2 20-Aug-18 21-Aug-18
IN-1000-22-36 P3-RF Disposal of spent DM Wter 3 20-Aug-18 22-Aug-18
IN-1000-22-37 P3-RF Preservation - N2 or Dry Air 3 20-Aug-18 22-Aug-18
Final Rinsing 10 22-Aug-18 31-Aug-18
IN-1000-22-38 P4 Water Filling- Tanks -1610-T-001/1611-V-001 / 16 12-V-00 1 2 22-Aug-18 23-Aug-18
IN-1000-22-39 P3-P4 Line filling- Interconnecting header P4 / P3 (Lean HP/LP Amine to Rich amine line with Bypass line) 2 22-Aug-18 23-Aug-18
IN-1000-22-40 P3-P4 Establish Circulation-Interconnecting Header ( with Bypass at end of headers ) 1 24-A ug-18 24-A ug-18
IN-1000-22-41 P3-RF Lineup to packages P1 / P2 / P3 - supply and return lines to Main Rich Amine Header 1 24-A ug-18 24-A ug-18
IN-1000-22-42 P3-RF Establish Circulation with all packages 2 25-Aug-18 26-Aug-18
IN-1000-22-43 P3-RF Sampling PH/FE 2 27-Aug-18 28-Aug-18
IN-1000-22-44 P3-RF Drain Down 2 29-Aug-18 30-Aug-18
IN-1000-22-45 P3-RF Disposal of spent DM Water 2 29-Aug-18 30-Aug-18
IN-1000-22-46 P3-RF Preservation - N2 or Dry Air 3 29-Aug-18 31-Aug-18

Milestone Date Revision Checked Approved


INTEGRATED NETWORK PC&C SCHEDULE 28-Mar-18 A
Activity  INTEGRATED AMINE DEGREASING
Critical Path DRAFT ONLY : CONFIDENTIAL