EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) 9864.00 25-Jul-14 08:00 A 31-May-19 17:00 98.02% 96.4%
Milestone 9864.00 25-Jul-14 08:00 A 31-May-19 17:00 0% 0%
Duration 13952.00 22-Aug-14 08:00 A 31-May-19 17:00 0% 0%
E0000GEN0040 Detailed Engineering for CDU 1110 3848.00 22-Aug-14 08:00 A 28-Apr-18 08:00 100% 50%
E0000GEN0050 Detailed Engineering for Common ARDS 1210 3560.00 22-Aug-14 08:00 A 28-Apr-18 08:00 100% 50%
E0000GEN0060 Detailed Engineering for Last ARDS 1212 4800.00 22-Aug-14 08:00 A 02-May-18 17:00 100% 50%
E0000GEN0070 Detailed Engineering for HCDU 1520 3856.00 22-Aug-14 08:00 A 28-Apr-18 08:00 100% 50%
E0000GEN0080 Detailed Engineering for FOS 4550 4072.00 22-Aug-14 08:00 A 28-Apr-18 08:00 100% 50%
E0000GEN0082 Procurement for CDU 1110 4896.00 29-Oct-14 08:00 A 10-Jul-18 17:00 100% 50%
E0000GEN0083 Procurement for Common ARDS 1210 4296.00 16-Feb-15 08:00 A 10-Jul-18 17:00 100% 50%
E0000GEN0084 Procurement for Last ARDS 1212 6320.00 20-Nov-14 08:00 A 10-Jul-18 17:00 100% 50%
E0000GEN0086 Procurement for HCDU 1520 5336.00 03-Nov-14 08:00 A 28-Jun-18 17:00 100% 50%
E0000GEN0087 Procurement for FOS 4550 4320.00 18-Feb-15 08:00 A 10-Jul-18 17:00 100% 50%
E0000GEN0090 Construction for CDU 1110 7200.00 02-Nov-15 08:00 A 03-Sep-18 17:00 100% 50%
E0000GEN0100 Construction for Common ARDS 1210 5632.00 25-Apr-16 08:00 A 15-Mar-18 00:00 A 100% 100%
E0000GEN0110 Construction for Last ARDS 1212 7040.00 28-Dec-15 08:00 A 14-Aug-18 17:00 96.45% 50%
E0000GEN0120 Construction for HCDU 1520 5632.00 25-Apr-16 08:00 A 13-Aug-18 17:00 100% 50%
E0000GEN0130 Construction for FOS 4550 6408.00 17-Jan-16 08:00 A 08-Sep-18 17:00 100% 50%
E0000GEN1270 Commissioning & RFSU & Provisional Acceptance for CDU 1110 2072.00 24-Apr-18 08:00 A 02-Apr-19 17:00 2.02% 50%
E0000GEN1280 Commissioning & RFSU & Provisional Acceptance for Common ARDS 1210 2168.00 15-Aug-18 08:00 12-May-19 17:00 2.27% 0%
E0000GEN1290 Commissioning & RFSU & Provisional Acceptance for Last ARDS 1212 2240.00 15-Aug-18 08:00 21-May-19 17:00 0% 0%
E0000GEN1300 Commissioning & RFSU & Provisional Acceptance for HCDU 1520 2224.00 14-Aug-18 08:00 18-May-19 17:00 2.02% 0%
E0000GEN1310 Commissioning & RFSU & Provisional Acceptance for FOS 4550 2104.00 20-Jul-18 08:00 08-Apr-19 17:00 2.28% 0%
E0000GEN1320 Detailed Engineering for First ARDS 1211 6264.00 22-Aug-14 08:00 A 02-May-18 17:00 100% 50%
E0000GEN1330 Procurement for First ARDS 1211 6320.00 20-Nov-14 08:00 A 10-Jul-18 17:00 100% 50%
E0000GEN1340 Construction for First ARDS 1211 7048.00 23-Nov-15 08:00 A 22-Aug-18 17:00 99.67% 50%
E0000GEN1350 Commissioning & RFSU & Provisional Acceptance for First ARDS 1211 2256.00 23-Aug-18 08:00 31-May-19 17:00 0% 0%
General 9864.00 25-Jul-14 08:00 A 31-May-19 17:00 0% 0%
E0000GEN0010 LOA/Effective Date 0.00 25-Jul-14 08:00 A 100% 100%
E0000GEN0020 Commencement Date 0.00 22-Aug-14 08:00 A 100% 100%
E0000GEN0030 All Critical Equipment PO finished(reactor&makeup compressor) 0.00 21-Oct-15 17:00 A 100% 100%
E0000GEN0170 90% Foundations and concrete structures poured 0.00 15-Jan-17 17:00 A 100% 100%
E0000GEN0171 Site Access for geotech survey (earliest) 0.00 01-Sep-14 08:00 A 100% 100%
E0000GEN0172 Site Access for Temp Facilities NORTH AREA 0.00 30-Jan-15 08:00 A 100% 100%
E0000GEN0173 Availability of Camp Area 0.00 01-Apr-15 17:00 A 100% 100%
E0000GEN0174 Site Access for Temp Facilities SOUTH AREA 0.00 01-Jun-15 08:00 A 100% 100%
E0000GEN0175 Ramunia MOLF available 0.00 01-Jul-15 08:00 A 100% 100%
E0000GEN0176 Site Access for Effective Construction 0.00 01-Jul-15 08:00 A 100% 100%
E0000GEN0177 Setapa MOLF Available 0.00 30-Nov-15 08:00 A 100% 100%
E0000GEN0178 Utilities Available(Raw water/Cooling water/Instrument air, Power initial) 0.00 27-Apr-18 17:00 100% 0%
E0000GEN0179 Utilities Available(Steam, Power-full) 0.00 30-Apr-18 08:00 100% 0%
E0000GEN0190 Last ARDS reactors delivered at WORKSITE and bolted on foundation 0.00 06-May-17 17:00 A 100% 100%
E0000GEN0195 MC of CDU 1110 0.00 03-Sep-18 17:00 100% 0%
E0000GEN0200 MC of HCDU 1520 0.00 13-Aug-18 17:00 100% 0%
E0000GEN0210 MC of FOS 4550 0.00 07-Mar-18 17:00 A 100% 100%
E0000GEN0220 MC of Common ARDS 1210 0.00 16-Apr-18 17:00 A 100% 100%
E0000GEN0230 MC of Last ARDS 1212 0.00 14-Aug-18 17:00 0% 0%
E0000GEN0235 RFSU of CDU 1110 0.00 03-Sep-18 17:00 0% 0%
E0000GEN0240 RFSU of HCDU 1520 0.00 14-Sep-18 17:00 0% 0%
E0000GEN0250 RFSU of FOS 4550 0.00 08-Sep-18 17:00 0% 0%

Remaining Level of Effort Actual Work Critical Remaining ... Page 1 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

E0000GEN0260 RFSU of Common ARDS 1210 0.00 18-Oct-18 17:00 0% 0%


E0000GEN0270 RFSU of Last ARDS 1212 0.00 19-Nov-18 17:00 0% 0%
E0000GEN0280 Project MC 0.00 03-Sep-18 17:00 0% 0%
E0000GEN0290 Project RFSU 0.00 29-Nov-18 17:00 0% 0%
E0000GEN0320 Provisional Acceptance Date 0.00 31-May-19 17:00 0% 0%
E0000GEN1360 MC of First ARDS 1211 0.00 22-Aug-18 17:00 0% 0%
E0000GEN1370 RFSU of First ARDS 1211 0.00 29-Nov-18 17:00 0% 0%
E0000GEN1380 Engineering Finish of CDU 1110 0.00 27-Apr-18 17:00 100% 0%
E0000GEN1390 Engineering Finish of FOS 4550 0.00 27-Apr-18 17:00 100% 0%
E0000GEN1395 ALL Units Engineering Finish 0.00 09-May-18 17:00 100% 0%
E0000GEN1400 Engineering Finish of ARDS 1210 0.00 27-Apr-18 17:00 100% 0%
E0000GEN1410 Engineering Finish of ARDS 1211 0.00 02-May-18 17:00 100% 0%
E0000GEN1430 Engineering Finish of HCDU 1520 0.00 27-Apr-18 17:00 100% 0%
E0000GEN1440 Engineering Finish of ARDS 1212 0.00 02-May-18 17:00 100% 0%
RA Major (Critical Acti
Activities) 7632.00 07-Apr-15 08:00 A 30-Nov-18 17:00 0% 0%
Subcontractor & KOM 176.00 07-Apr-15 08:00 A 06-May-15 17:00 A 0% 0%
R0000GEN1000 LOA of Subcontractor for RA 0.00 07-Apr-15 08:00 A 100% 100%
R0000GEN1010 KOM for RA 16.00 05-May-15 08:00 A 06-May-15 17:00 A 100% 100%
Authorities 6464.00 23-Sep-15 08:00 A 26-Oct-18 17:00 0% 0%
Pejabat Daerah / Majlis
M Daerah Kota Tinggi (MDKT) 6464.00 23-Sep-15 08:00 A 26-Oct-18 17:00 0% 0%
Temporary Construction
Constr Facilities - Permit 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 0% 0%
R0000GEN1110 Consultant Submission for TCF 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 100% 100%
Accommodation Camp
C - Permit 8.00 23-Sep-15 08:00 A 23-Sep-15 17:00 A 0% 0%
R0000GEN1030 Consultant Submission for Camp 8.00 23-Sep-15 08:00 A 23-Sep-15 17:00 A 100% 100%
RAPID Package 2 Process Plant 5432.00 15-Oct-15 08:00 A 26-Oct-18 17:00 0% 0%
Development Ord
Order Submission (DO) 8.00 15-Oct-15 08:00 A 15-Oct-15 17:00 A 0% 0%
R0000GEN1040 Consultant Submission for DO 8.00 15-Oct-15 08:00 A 15-Oct-15 17:00 A 100% 100%
Earthwork Submi
Submission (EW) 8.00 15-Oct-15 08:00 A 15-Oct-15 17:00 A 0% 0%
R0000GEN1130 Consultant Submission for EW 8.00 15-Oct-15 08:00 A 15-Oct-15 17:00 A 100% 100%
Road & Drainage Submission (R&D) 8.00 30-Apr-18 08:00 30-Apr-18 17:00 0% 0%
R0000GEN1140 Submission of Document and Drawings (R&D) 8.00 30-Apr-18 08:00 30-Apr-18 17:00 100% 0%
Building Plan Submission
Sub (BP) 8.00 30-Apr-18 08:00 30-Apr-18 17:00 0% 0%
R0000GEN1060 Consultant Submission for BP 8.00 30-Apr-18 08:00 30-Apr-18 17:00 100% 0%
Certificate of Completion
Com and Compliance (CCC) 8.00 26-Oct-18 08:00 26-Oct-18 17:00 0% 0%
R0000GEN1190 Submission of Document and Drawings (CCC) 8.00 26-Oct-18 08:00 26-Oct-18 17:00 0% 0%
Department of Environment
Envi (DOE) 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 0% 0%
R0000GEN1020 EMP & ESCP Preparation (JOHOR) 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 100% 100%
Indah Water Consortium
Conso (IWK) 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 0% 0%
R0000GEN1070 Submission of Document and Drawings 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 100% 100%
Drainage & Irrigation
Irrigatio Department (JPS) 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 0% 0%
R0000GEN1090 Submission of Drainage & ESCP 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 100% 100%
Syarikat Air Johor Sdn
S Bhd (SAJ) 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 0% 0%
R0000GEN1080 Application/Submission for Construction & Temporary Facilities water supply 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 100% 100%
Telekom Malaysia (TM)
(T 8.00 01-May-18 08:00 01-May-18 17:00 0% 0%
R0000GEN1160 Application/Submission for telecommunication systems 8.00 01-May-18 08:00 01-May-18 17:00 100% 0%
Tenaga Nasional Berhad
Be (TNB) 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 0% 0%
R0000GEN1050 Application/Submission for Electricity Supply 8.00 08-Oct-15 08:00 A 08-Oct-15 17:00 A 100% 100%
Jabatan Perkhidma
Perkhidmatan Bomba Dan Penyelamat (BOMBA) 8.00 01-May-18 08:00 01-May-18 17:00 0% 0%
R0000GEN1100 Application/Submission for Fire Fighting 8.00 01-May-18 08:00 01-May-18 17:00 100% 0%
Department of Occupational
Occu Safety and Health (DOSH) 5936.00 09-Nov-15 08:00 A 04-Sep-18 17:00 0% 0%
DOSH Project Regi
Registration (JKJ 103) 8.00 09-Nov-15 08:00 A 09-Nov-15 17:00 A 0% 0%
R0000GEN1120 Consultant submission of DOSH Project Registration (JKJ 103) 8.00 09-Nov-15 08:00 A 09-Nov-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 2 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Permission to Install
Instal (PTI) Petroleum Pipeline 8.00 29-Apr-17 08:00 A 22-May-17 17:00 A 0% 0%
R0000GEN1170 Permission to Install (PTI) 8.00 29-Apr-17 08:00 A 22-May-17 17:00 A 100% 100%
Permission to Operate
Oper (PTO) Petroleum Pipeline 8.00 04-Sep-18 08:00 04-Sep-18 17:00 0% 0%
R0000GEN1180 Permission to Operate (PTO) 8.00 04-Sep-18 08:00 04-Sep-18 17:00 100% 0%
DOSH Equipment Design
D Submisstion /Approval 8.00 10-Apr-17 08:00 A 10-Apr-17 17:00 A 0% 0%
R0000GEN1150 Start of DOSH Equipment Design Submission 8.00 10-Apr-17 08:00 A 10-Apr-17 17:00 A 100% 100%
Others Tech. Department
Depart 8.00 30-Nov-18 08:00 30-Nov-18 17:00 0% 0%
Department of Environment
Envi (DOE) 8.00 30-Nov-18 08:00 30-Nov-18 17:00 0% 0%
R0000GEN1200 Operation License 8.00 30-Nov-18 08:00 30-Nov-18 17:00 0% 0%
Department of Civil Aviation (DCA) 8.00 30-Nov-18 08:00 30-Nov-18 17:00 0% 0%
R0000GEN1210 Operation License 8.00 30-Nov-18 08:00 30-Nov-18 17:00 0% 0%
Engineering 7672.00 25-Jul-14 08:00 A 09-May-18 17:00 100% 99.99%
General 7672.00 25-Jul-14 08:00 A 09-May-18 17:00 100% 99.76%
General 7672.00 25-Jul-14 08:00 A 09-May-18 17:00 100% 99.76%
Review Meeting 3240.00 19-Nov-14 08:00 A 30-Jun-16 17:00 A 0% 0%
Review Meeting 3240.00 19-Nov-14 08:00 A 30-Jun-16 17:00 A 0% 0%
PFD Review Meeting
Me 24.00 19-Nov-14 08:00 A 21-Nov-14 17:00 A 0% 0%
Risk Based Inspection
Inspe (PRBI) 1536.00 05-Jan-15 08:00 A 30-Jun-16 17:00 A 0% 0%
Constructability Reviews
R 16.00 23-Jan-15 08:00 A 26-Jan-15 17:00 A 0% 0%
PID Review (CDU,ARDS,FOS,HCDU)
(CD 160.00 12-Jan-15 08:00 A 06-Feb-15 17:00 A 0% 0%
PID Review (Uti
(Utility) 40.00 16-Mar-15 08:00 A 20-Mar-15 17:00 A 0% 0%
30% 3D Model Review
R Meeting 40.00 30-Mar-15 08:00 A 03-Apr-15 17:00 A 0% 0%
Hazop Review Meeting
M 208.00 13-Apr-15 08:00 A 19-May-15 17:00 A 0% 0%
Hazardous Area Classification Review Meeting 16.00 25-May-15 08:00 A 26-May-15 17:00 A 0% 0%
Fire Safety Assessment
Asse Review Meeting 24.00 27-May-15 08:00 A 29-May-15 17:00 A 0% 0%
IPF Review Meeting
Mee 56.00 29-Jun-15 08:00 A 07-Jul-15 17:00 A 0% 0%
HRA Review Meeting
Me 24.00 19-Aug-15 08:00 A 21-Aug-15 17:00 A 0% 0%
P-ELSOR Study 40.00 02-Nov-15 08:00 A 06-Nov-15 17:00 A 0% 0%
Elec. System RoRobustness Study(ESRS) 40.00 09-Nov-15 08:00 A 11-Nov-15 17:00 A 0% 0%
60% 3D Model Review
R Meeting 152.00 27-Oct-15 08:00 A 04-Dec-15 17:00 A 0% 0%
Alarm Rationalization
Rationaliz Review 40.00 28-Mar-16 08:00 A 08-Apr-16 17:00 A 0% 0%
Fire Protection and
a Fire and Gas Detection 3D Model Review Meeting 40.00 15-Feb-16 08:00 A 17-Feb-16 17:00 A 0% 0%
90% 3D Model Review
R Meeting 248.00 03-May-16 08:00 A 08-Jun-16 17:00 A 0% 0%
General 4768.00 25-Jul-14 08:00 A 02-Dec-16 17:00 A 100% 100%
Document 4768.00 25-Jul-14 08:00 A 02-Dec-16 17:00 A 100% 100%
Level I Schedule 2808.00 25-Jul-14 08:00 A 13-Nov-15 17:00 A 100% 100%
WBS procedure 2368.00 04-Aug-14 08:00 A 03-Nov-15 17:00 A 100% 100%
Contractor PMT Team Mobilization Plan 1608.00 04-Aug-14 08:00 A 22-May-15 17:00 A 100% 100%
120 Days Look Ahead
A Schedule 2288.00 04-Aug-14 08:00 A 17-Sep-15 17:00 A 100% 100%
The organisation chart and professional resumes of Key Personnel 944.00 04-Aug-14 08:00 A 21-Jan-15 17:00 A 100% 100%
HSSE policy statement
stat 2992.00 04-Aug-14 08:00 A 22-Oct-15 17:00 A 100% 100%
Level II Schedule 2648.00 22-Aug-14 08:00 A 13-Nov-15 17:00 A 100% 100%
Correspondence and Communication Protocol 856.00 22-Aug-14 08:00 A 26-Jan-15 17:00 A 100% 100%
List of Potential S
Subcontractors For Early Work 824.00 22-Aug-14 08:00 A 20-Jan-15 17:00 A 100% 100%
Numbering and Coding Procedure for Engineering Documents 1296.00 22-Aug-14 08:00 A 16-Apr-15 17:00 A 100% 100%
Document distrib
distribution Matrices 3128.00 22-Aug-14 08:00 A 11-Mar-16 17:00 A 100% 100%
Document mana
management procedure 2600.00 22-Aug-14 08:00 A 01-Dec-15 17:00 A 100% 100%
Project Planning,
Planning Scheduling and Control Procedure 2568.00 22-Aug-14 08:00 A 23-Oct-15 17:00 A 100% 100%
Progress Measu
Measurement Procedure 2696.00 22-Aug-14 08:00 A 04-Nov-15 17:00 A 100% 100%
Overall Deliverable
Delivera List 2800.00 22-Aug-14 08:00 A 06-Nov-15 17:00 A 100% 100%
Construction Labor
Lab Relation Plan 3592.00 22-Aug-14 08:00 A 20-May-16 17:00 A 100% 100%
Design Decision Register 712.00 22-Aug-14 08:00 A 30-Dec-14 17:00 A 100% 100%
Regulatory Appr
Approvals 2880.00 22-Aug-14 08:00 A 17-Dec-15 17:00 A 100% 100%
Detailed Engineering
Enginee Plan 2592.00 22-Aug-14 08:00 A 04-Nov-15 17:00 A 100% 100%
Project HSSE Plan
Pl 3128.00 22-Aug-14 08:00 A 10-Nov-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 3 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Invoicing procedure
proced 2992.00 22-Aug-14 08:00 A 28-Jan-16 17:00 A 100% 100%
Master Documen
Document Register 3032.00 22-Aug-14 08:00 A 29-Jan-16 17:00 A 100% 100%
Project Execution Plan 1832.00 22-Aug-14 08:00 A 21-Jul-15 17:00 A 100% 100%
Schedule Basis Memorandum
M (SBM) 3072.00 22-Aug-14 08:00 A 29-Jan-16 17:00 A 100% 100%
Worksite Waste Management Plan 2960.00 22-Aug-14 08:00 A 18-Nov-15 17:00 A 100% 100%
Environmental Management
M Plan 3736.00 22-Aug-14 08:00 A 06-Apr-16 17:00 A 100% 100%
Interface Manag
Management Plan 2880.00 22-Aug-14 08:00 A 24-Dec-15 17:00 A 100% 100%
Camp Schedule 4608.00 22-Aug-14 08:00 A 02-Dec-16 17:00 A 100% 100%
Level III Schedule
Schedu 2712.00 22-Aug-14 08:00 A 13-Nov-15 17:00 A 100% 100%
Spare Parts Procurement
Pro Procedure 1096.00 22-Aug-14 08:00 A 12-Mar-15 17:00 A 100% 100%
Quality Management
Managem Plan 1272.00 22-Aug-14 08:00 A 13-Apr-15 17:00 A 100% 100%
Project Procedures
Procedur Manual 1096.00 22-Aug-14 08:00 A 12-Mar-15 17:00 A 100% 100%
Project Worksite Rules 3368.00 22-Aug-14 08:00 A 24-Nov-15 17:00 A 100% 100%
Risk Management
Manageme Procedure 4568.00 22-Aug-14 08:00 A 10-Nov-15 17:00 A 100% 100%
Procurement Ex Execution Plan 1056.00 22-Aug-14 08:00 A 05-Mar-15 17:00 A 100% 100%
Construction Execution
Exe Plan 4320.00 22-Aug-14 08:00 A 20-May-16 17:00 A 100% 100%
Equipment & Bulk Bu Material Delivery Schedule 2176.00 18-Nov-14 08:00 A 11-Nov-15 17:00 A 100% 100%
Manpower histograms
histog 1960.00 20-Jan-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Level IV schedules
schedul 2176.00 18-Nov-14 08:00 A 13-Nov-15 17:00 A 100% 100%
Overall progress control curves 2240.00 19-Nov-14 08:00 A 13-Nov-15 17:00 A 100% 100%
Expediting Procedure
Proce 1048.00 22-Aug-14 08:00 A 04-Mar-15 17:00 A 100% 100%
Inspection Procedure
Proce 1696.00 22-Aug-14 08:00 A 26-Jun-15 17:00 A 100% 100%
Transportation and a Logistics 936.00 22-Aug-14 08:00 A 09-Feb-15 17:00 A 100% 100%
Packing and Mar Marking 752.00 22-Aug-14 08:00 A 07-Jan-15 17:00 A 100% 100%
Site Material Ma Management Procedure 768.00 22-Aug-14 08:00 A 09-Jan-15 17:00 A 100% 100%
Storage and Preservation
Pre Procedure 816.00 22-Aug-14 08:00 A 19-Jan-15 17:00 A 100% 100%
Minimum Inspec
Inspection Requirements 2944.00 21-Oct-14 08:00 A 20-Nov-15 17:00 A 100% 100%
Erosion and Sediment
Sed Control Plan 1624.00 24-Aug-15 08:00 A 27-May-16 17:00 A 100% 100%
Vendor Docume
Document Handling Procedure 2160.00 22-Aug-14 08:00 A 14-Aug-15 17:00 A 100% 100%
Process interface deliverable list 2456.00 16-Feb-15 08:00 A 06-May-16 17:00 A 100% 100%
HSE interface de deliverable list 2096.00 16-Feb-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Instrument interf
interface deliverable list 2568.00 16-Feb-15 08:00 A 27-May-16 17:00 A 100% 100%
Piping interface deliverable
d list 1936.00 16-Feb-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Electrical interfac
interface deliverable list 2352.00 16-Feb-15 08:00 A 16-Mar-16 17:00 A 100% 100%
Civil interface deliverable
de list 1336.00 16-Feb-15 08:00 A 16-Sep-15 00:00 A 100% 100%
HSSE 7176.00 27-Oct-14 08:00 A 09-May-18 17:00 100% 96.56%
Document 7176.00 27-Oct-14 08:00 A 09-May-18 17:00 100% 96.56%
3D Fire and Gas Mapping actions close-out Reports 272.00 27-Jan-16 08:00 A 01-Apr-16 17:00 A 100% 100%
3D Fire and Gas Mapping Reports 328.00 25-Jan-16 08:00 A 25-Mar-16 17:00 A 100% 100%
3D Fire and Gas Mapping Review Procedure 880.00 24-Aug-15 08:00 A 10-Dec-15 17:00 A 100% 100%
Active Fire Protection
Prote and Personnel Protection Philosophy 1808.00 03-Apr-15 08:00 A 24-Dec-15 17:00 A 100% 100%
BATTERY LIMIT INTERFACE TABLE PIPING (Fire water) 976.00 03-Apr-15 08:00 A 07-Sep-15 17:00 A 100% 100%
Critical Activity Catalog
C 3640.00 19-Aug-15 08:00 A 06-Jun-17 17:00 A 100% 100%
Design HSE Case Cas 5360.00 16-Sep-15 08:00 A 09-May-18 17:00 100% 5%
ENVID review a actions close-out report 184.00 25-Jan-16 08:00 A 27-Jan-17 00:00 A 100% 100%
FEED ENVID Re Review Close-Out Report 1056.00 24-Aug-15 08:00 A 28-Jan-16 17:00 A 100% 100%
ENVID review p procedure 584.00 20-May-15 08:00 A 28-Aug-15 17:00 A 100% 100%
ENVID review re reports 248.00 04-Jan-16 08:00 A 12-Jan-16 17:00 A 100% 100%
Environmental monitoring
m Layouts 1128.00 18-Mar-16 08:00 A 28-Sep-16 17:00 A 100% 100%
Environmental Requirements
R for Vendor 2576.00 27-Oct-14 08:00 A 31-Dec-15 17:00 A 100% 100%
Fire Safety Asse
Assessment Actions Close-out Report 1184.00 24-Dec-15 08:00 A 20-Jul-16 17:00 A 100% 100%
Fire Safety Assessment
Asse Review Precedure 1328.00 09-Feb-15 08:00 A 15-Oct-15 17:00 A 100% 100%
Fire Safety Assessment
Asse Reports 720.00 27-May-15 08:00 A 05-Nov-15 17:00 A 100% 100%
Firewater and foam fo Demand Calculation 2368.00 03-Apr-15 08:00 A 18-May-16 17:00 A 100% 100%
Fixed water spray
spra system hydraulic calculation note 1072.00 23-Mar-16 08:00 A 21-Sep-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 4 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

FW Distribution Network P&ID 2320.00 03-Apr-15 08:00 A 27-May-16 17:00 A 100% 100%
Hazard and effecteff register 5720.00 08-Jul-15 08:00 A 02-May-18 17:00 100% 85%
Hazard Remedial
Remedia Action Plan 5176.00 08-Jul-15 08:00 A 23-Jan-18 17:00 A 100% 100%
Hazardous area classification actions close-out Reports 1192.00 21-Oct-15 08:00 A 29-Jun-16 17:00 A 100% 100%
Hazardous area classification review procedure 1272.00 02-Mar-15 08:00 A 16-Oct-15 17:00 A 100% 100%
Hazardous area classification review report 800.00 27-May-15 08:00 A 05-Nov-15 17:00 A 100% 100%
HAZID Actions C Close-out Report 1584.00 15-Sep-15 08:00 A 29-Jun-16 17:00 A 100% 100%
HAZID review p procedure 1152.00 12-Jan-15 08:00 A 05-Aug-15 17:00 A 100% 100%
HAZID review re report 240.00 14-Sep-15 08:00 A 15-Oct-15 17:00 A 100% 100%
HAZOP Actions Close-out Report 2080.00 17-Jun-15 08:00 A 25-Jun-16 17:00 A 100% 100%
HAZOP Review Precedure 1296.00 12-Jan-15 08:00 A 31-Aug-15 17:00 A 100% 100%
HAZOP Review Report 456.00 20-May-15 08:00 A 06-Aug-15 17:00 A 100% 100%
Health Requirements
Requirem 2240.00 09-Feb-15 08:00 A 26-Feb-16 17:00 A 100% 100%
HRA Actions Close-out
Clo Report 1056.00 22-Sep-15 08:00 A 01-Apr-16 17:00 A 100% 100%
HRA Review Reports
Re 320.00 24-Aug-15 08:00 A 23-Sep-15 17:00 A 100% 100%
HRA Review Pre Precedure 1448.00 24-Nov-14 08:00 A 10-Aug-15 17:00 A 100% 100%
Human Factor Engineering Report 336.00 19-Aug-15 08:00 A 21-Oct-15 17:00 A 100% 100%
IPF Actions Close-out
Clos Report 3000.00 03-Sep-15 08:00 A 01-Mar-17 17:00 A 100% 100%
IPF Review Proc Procedure 1528.00 12-Jan-15 08:00 A 15-Oct-15 17:00 A 100% 100%
IPF Review Rep Reports 336.00 08-Jul-15 08:00 A 03-Sep-15 17:00 A 100% 100%
Noise study Report
Rep 5352.00 09-Sep-15 08:00 A 01-May-18 17:00 100% 85%
Personal protection
protec Equipment MTO 1096.00 19-Oct-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Personnel Prote
Protection Specification and Datasheet 1280.00 20-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Prohibited Substances
Subst List 168.00 26-Jan-15 08:00 A 27-Feb-15 17:00 A 100% 100%
Safety Sign MTO 1928.00 19-Oct-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Safety Critical Elements
El and Performance Standards 5320.00 16-Sep-15 08:00 A 02-May-18 17:00 100% 85%
SPECIFICATION SAFETY EQUIPMENT SPECIFICATIONS (FIXED AND PORTABLE FIRE FIGHTING) 1056.00 06-Apr-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Spillage & Polluti
Pollution Control 3824.00 03-Apr-15 08:00 A 23-Feb-17 17:00 A 100% 100%
FW Distribution Network UFD 1488.00 06-Apr-15 08:00 A 23-Nov-15 17:00 A 100% 100%
Electrical 5632.00 15-Feb-15 08:00 A 27-Nov-17 17:00 A 100% 100%
Document 5192.00 08-May-15 08:00 A 27-Nov-17 17:00 A 100% 100%
Cable Sizing Calculation
Cal 3040.00 08-May-15 08:00 A 04-Nov-16 17:00 A 100% 100%
Data sheet for 3.3KV
3 Cables 1096.00 08-Sep-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Data sheet for LV Cables 1160.00 08-Sep-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Data sheet for 11KV1 Cables 1160.00 08-Sep-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Data sheet for A Air Craft Warning Light 1440.00 08-Sep-15 08:00 A 25-May-16 17:00 A 100% 100%
Data sheet for E Electrical Heat Tracing 720.00 06-Jan-16 08:00 A 22-Jan-16 17:00 A 100% 100%
DATA SHEET FOR FO BULK MATERIAL 784.00 17-Feb-16 08:00 A 29-Jul-16 17:00 A 100% 100%
Electrical System Robustness Study (ESRS) 1736.00 11-Aug-15 08:00 A 19-Jan-16 17:00 A 100% 100%
Lighting Illuminat
Illumination Calculation 4328.00 12-Oct-15 08:00 A 27-Nov-17 17:00 A 100% 100%
Motor Starting A Analysis 1664.00 28-Jul-15 08:00 A 25-May-16 17:00 A 100% 100%
ELSOR Study 840.00 19-Oct-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Power Harmonic /EMC Analysis 1280.00 24-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Re-starting/Re-acceleration Analysis
Re-starting/Re-a 2936.00 24-Jun-15 08:00 A 02-Dec-16 17:00 A 100% 100%
Short Circuit Analysis
Ana 1240.00 24-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Load Flow /Voltage
/Volta Drop Analysis 1360.00 25-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Transient Stability
Stabilit Study 896.00 30-Oct-15 08:00 A 21-Jan-16 17:00 A 100% 100%
Material Take Off Of for Other Material for 1900 1016.00 23-Feb-16 08:00 A 08-Sep-16 17:00 A 100% 100%
Material Take Of Off For Cable for 1900 336.00 16-Feb-16 08:00 A 12-May-16 17:00 A 100% 100%
Material Take Of Off For Earthing and Lighting Material for 1900 1808.00 28-Jul-15 08:00 A 10-May-16 17:00 A 100% 100%
BLIT OF CABLE TRENCH for 1900 1520.00 27-Jul-15 08:00 A 03-Feb-16 17:00 A 100% 100%
BLIT OF CABLES
CABLE for 1900 1520.00 27-Jul-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Electrical Cable List
L for 1900 1632.00 27-Jul-15 08:00 A 16-Dec-15 17:00 A 100% 100%
Drawing 4088.00 15-Feb-15 08:00 A 24-Feb-17 17:00 A 100% 100%
Power Installation
Installatio Standard Drawings 1120.00 15-Feb-15 08:00 A 03-Sep-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 5 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Lightning Installation
Installa Standard Drawings 1272.00 15-Feb-15 08:00 A 21-Jul-15 17:00 A 100% 100%
Earthing and Lightning
Lig Installation Standard Drawings 864.00 15-Feb-15 08:00 A 21-Jul-15 17:00 A 100% 100%
Protective and Schematic
S Diagram 1752.00 15-Feb-15 08:00 A 25-Sep-15 17:00 A 100% 100%
Power Cable Routing
Ro Layout (Underground) for 1900 3712.00 27-Apr-15 08:00 A 24-Feb-17 17:00 A 100% 100%
Interface Drawing
Drawin of Cable Routing for 1900 2120.00 08-May-15 08:00 A 25-May-16 17:00 A 100% 100%
Earthing/Lightning Layout for 1900
Earthing/Lightnin 1592.00 27-Jul-15 08:00 A 03-Mar-16 17:00 A 100% 100%
Interface Drawing
Drawin of Earthing System for 1900 1968.00 10-Aug-15 08:00 A 29-Jul-16 17:00 A 100% 100%
Lighting Layout (Unit/Street)
( for 1900 1632.00 22-Oct-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Lighting Loop Diagram
Di for 1900 544.00 22-Feb-16 08:00 A 10-Jun-16 17:00 A 100% 100%
Civil/Structural 4992.00 10-Oct-14 08:00 A 28-Mar-17 17:00 A 100% 100%
Document 4896.00 27-Oct-14 08:00 A 28-Mar-17 17:00 A 100% 100%
Calculation For Stormwater
S Drainage 4040.00 31-Mar-15 08:00 A 28-Mar-17 17:00 A 100% 100%
Calculation For Road
R 1952.00 09-Oct-15 08:00 A 10-May-16 17:00 A 100% 100%
DESIGN CRITERIA
CRITE FOR UNDERGROUND SYSTEMS AND SITE ARRANGEMENT FACILITIES 1392.00 27-Oct-14 08:00 A 02-Jul-15 17:00 A 100% 100%
Calculation notes for AOC system 1336.00 09-Feb-15 08:00 A 02-Sep-15 17:00 A 100% 100%
Requisitions for 1900 (steel structures) 592.00 23-Jun-15 08:00 A 13-Oct-15 17:00 A 100% 100%
CALCULATION NOTES FOR ANCHOR BOLT LOAD CAPACITIES 368.00 20-Jan-15 08:00 A 27-Mar-15 17:00 A 100% 100%
Calculation For 1900-RCK
1 1120.00 17-Aug-15 08:00 A 27-Jan-16 17:00 A 100% 100%
Material Take off steel structure anchor bolts for 1900 976.00 23-Jun-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Material Take off Reinforcing Steel for 1900 664.00 17-Sep-15 08:00 A 17-Dec-15 17:00 A 100% 100%
Material Take off steel structures for 1900 952.00 17-Sep-15 08:00 A 08-Jan-16 17:00 A 100% 100%
SUPPLEMENTARY SOIL INVESTIGATION FACTUAL REPORT
SUPPLEMENTA 1464.00 27-Jan-15 08:00 A 22-Oct-15 17:00 A 100% 100%
SUPPLEMENTARY SOIL INVESTIGATION GEOTECHNICAL ASSESSMENT REPORT
SUPPLEMENTA 1424.00 27-Jan-15 08:00 A 28-Oct-15 17:00 A 100% 100%
Supplementary Soil Investigation 552.00 27-Oct-14 08:00 A 30-Jan-15 17:00 A 100% 100%
Drawing 3216.00 10-Oct-14 08:00 A 24-Feb-16 17:00 A 100% 100%
Interfaces drawing
drawin for roads and ditches 1720.00 23-Oct-14 08:00 A 26-Aug-15 17:00 A 100% 100%
FINISHED GRADE
GRA PLAN 2688.00 27-Oct-14 08:00 A 27-Jan-16 17:00 A 100% 100%
TYPICAL LAYOUT
LAYOU - PLANS OF PAVING 1640.00 27-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
LIGHT DUTY CONCRETE
C PAVING AND FOOTPATHS 1640.00 27-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
HEAVY DUTY CONCRETE
C PAVING 1640.00 27-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
TYPICAL SECTIONS
SECT OF HEAVY DUTY ROADS 1640.00 27-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
TYPICAL SECTIONS
SECT OF LIGHT DUTY ROADS 1640.00 27-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
STANDARD DITCHES
DIT AND CHANNEL 1528.00 27-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
DESANDER FOR FO STANDARD DITCH 1640.00 27-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Overall plot plan 1840.00 23-Oct-14 08:00 A 01-Sep-15 17:00 A 100% 100%
INTERFACES D DRAWING FOR UNDERGROUND PIPING 896.00 27-Apr-15 08:00 A 20-Oct-15 17:00 A 100% 100%
Underground fac facility Standard Drawing-pressure pipe connection 408.00 27-Jan-15 08:00 A 10-Apr-15 17:00 A 100% 100%
Underground fac facility Standard Drawing-clean out 408.00 27-Jan-15 08:00 A 10-Apr-15 17:00 A 100% 100%
Hydrant and mo monitor 984.00 06-Apr-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Sanitary sewer(SWW)
sewer(S manhole 984.00 06-Apr-15 08:00 A 06-Nov-15 17:00 A 100% 100%
COC manhole w with submerged inlet connection 984.00 06-Apr-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Submerged connconnection details for COC systems 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Catch basin with grating type 1 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Catch basin with grating type 2 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Catch basin with grating type 3 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Catch basin with grating type 4 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Manhole 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Double compartm
compartment manhle 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
AOC channels and a liquid gas traps 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Valve pit 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Valve pit for GRE or GRVE 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Vents for manholes
manho 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Rain water system
syste entry catch basin and discharge catch basin 984.00 06-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Anchor Bolts 264.00 20-Jan-15 08:00 A 10-Mar-15 17:00 A 100% 100%
Attachment Of Handrails
H On Concrete Structures 376.00 20-Jan-15 08:00 A 30-Mar-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 6 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Concrete Pipe Supports


S 496.00 20-Jan-15 08:00 A 20-Apr-15 17:00 A 100% 100%
Concrete Pipe Sleepers
S 528.00 10-Oct-14 08:00 A 09-Jan-15 17:00 A 100% 100%
Fastening of Apparatus
App To Fireproofed Beams 1016.00 23-Oct-14 08:00 A 23-Apr-15 17:00 A 100% 100%
Grating 464.00 23-Oct-14 08:00 A 13-Jan-15 17:00 A 100% 100%
Handrailing 464.00 23-Oct-14 08:00 A 13-Jan-15 17:00 A 100% 100%
Insert Plates 376.00 20-Jan-15 08:00 A 30-Mar-15 17:00 A 100% 100%
Installation Of Rotating
Ro Equipment Epoxy Grouting And Filling Concrete Principle 376.00 20-Jan-15 08:00 A 30-Mar-15 17:00 A 100% 100%
Ladders 328.00 20-Jan-15 08:00 A 20-Mar-15 17:00 A 100% 100%
Levelling Plates 496.00 20-Jan-15 08:00 A 20-Apr-15 17:00 A 100% 100%
Lighting Standard
Standar Foundation 520.00 10-Oct-14 08:00 A 08-Jan-15 17:00 A 100% 100%
Stairways 1016.00 23-Oct-14 08:00 A 23-Apr-15 17:00 A 100% 100%
Standard Drawing
Drawin - Concrete Works General Notes 520.00 10-Oct-14 08:00 A 08-Jan-15 17:00 A 100% 100%
Standard Drawings
Drawin - Steel Works General Notes 496.00 23-Oct-14 08:00 A 19-Jan-15 17:00 A 100% 100%
Supplementary S Soil Investigation Layout Plan 480.00 27-Oct-14 08:00 A 19-Jan-15 17:00 A 100% 100%
CIVIL & STRUCTURE
STRUC DESIGN BASIS 2960.00 10-Oct-14 08:00 A 07-Jan-16 17:00 A 100% 100%
ELECTRICAL AND AN INSTRUMENT CABLE TRENCHES 496.00 20-Jan-15 08:00 A 20-Apr-15 17:00 A 100% 100%
REINFORCED C CONCRETE FOUNDATION ON OR THROUGH PAVING 376.00 20-Jan-15 08:00 A 30-Mar-15 17:00 A 100% 100%
ROAD CROSSING
CROSSI CONDUITS FOR ELECTRICAL OR INSTRUMENT CABLES 368.00 20-Jan-15 08:00 A 27-Mar-15 17:00 A 100% 100%
PIPE TRENCHES
TRENCHE 1176.00 16-Feb-15 08:00 A 29-Jul-15 17:00 A 100% 100%
FIREPROOFING CONFIGURATIONS 1064.00 11-Oct-14 08:00 A 20-Apr-15 17:00 A 100% 100%
EQUIPMENT PLATFORMS
PL 1224.00 16-Feb-15 08:00 A 13-Aug-15 17:00 A 100% 100%
Foundation Drawings
Draw for 1900 1216.00 15-Sep-15 08:00 A 24-Feb-16 17:00 A 100% 100%
Structural Drawings
Drawi for 1900 1072.00 22-Oct-15 08:00 A 23-Feb-16 17:00 A 100% 100%
PRELIMINARY PILE P LOAD TESTS & TEST PILE LOCATIONS 320.00 01-Jun-15 08:00 A 24-Jul-15 17:00 A 100% 100%
PILE LAYOUT & PILE PLAN for 1900 840.00 12-Aug-15 08:00 A 11-Dec-15 17:00 A 100% 100%
VESSEL FOUNDATION
FOUND DRAIN 416.00 01-Jun-15 08:00 A 11-Aug-15 17:00 A 100% 100%
Architectural 1704.00 03-Feb-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Document 1704.00 03-Feb-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Building design basis
b 1704.00 03-Feb-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Piping 3960.00 27-Oct-14 08:00 A 20-Sep-16 17:00 A 100% 100%
Document 3864.00 27-Oct-14 08:00 A 20-Sep-16 17:00 A 100% 100%
Piping Stress DeDesign Basis 864.00 03-Jul-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Material Take OfOff for Insulation 1900 1352.00 05-Jan-16 08:00 A 08-Sep-16 17:00 A 100% 100%
Material Take OfOff for Piping Bulk Material 1900 1352.00 04-Jan-16 08:00 A 08-Sep-16 17:00 A 100% 100%
Material Take OfOff for Piping Painting 1900 1352.00 06-Jan-16 08:00 A 08-Sep-16 17:00 A 100% 100%
Piping Stress Calculations
Ca and analysis report for 1900 2128.00 10-Aug-15 08:00 A 26-Aug-16 17:00 A 100% 100%
30% Client 3D-Model
3D-M Review & Action Close-out Report 1900-REFINERY INTERCONNECTING UNIT 592.00 20-Apr-15 08:00 A 10-Sep-15 17:00 A 100% 100%
CRITICAL LINE LIST for REFINERY INTERCONNECTING (Unit1900) 2496.00 02-Apr-15 08:00 A 24-Jun-16 17:00 A 100% 100%
Steam Tracing L List for 1900 424.00 15-Dec-15 08:00 A 02-Mar-16 17:00 A 100% 100%
GLASS-FIBRE R REINFORCED PLASTIC PIPING Specification 1616.00 23-Mar-15 08:00 A 18-Nov-15 17:00 A 100% 100%
Piping Wall Thickness
Thick Calculation 2624.00 24-Nov-14 08:00 A 01-Feb-16 17:00 A 100% 100%
Piping Class Summary
Sum 3632.00 24-Nov-14 08:00 A 07-Sep-16 17:00 A 100% 100%
Piping Material S Specification 2880.00 27-Oct-14 08:00 A 28-Jan-16 17:00 A 100% 100%
Piping Steam TraTracing 1376.00 29-Apr-15 08:00 A 13-Oct-15 17:00 A 100% 100%
Purchasing Specification
Spec for Bolt&Nut 960.00 03-Feb-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Purchasing Specification
Spec for Fitting 960.00 03-Feb-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Purchasing Specification
Spec for Flange 960.00 03-Feb-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Purchasing Specification
Spec for Gasket 960.00 03-Feb-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Purchasing Specification
Spec for Pipe 968.00 03-Feb-15 08:00 A 27-Jul-15 17:00 A 100% 100%
Purchasing Specification
Spec for Valve 960.00 03-Feb-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Special ItemList 1416.00 16-Dec-15 08:00 A 20-Sep-16 17:00 A 100% 100%
BATTERY LIMIT INTERFACE TABLE 1900-REFINERY INTERCONNECTING UNIT 824.00 20-Jul-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Drawing 3720.00 08-Dec-14 08:00 A 14-Sep-16 17:00 A 100% 100%
Standard pipe support
su drawing 1200.00 08-Dec-14 08:00 A 10-Jul-15 17:00 A 100% 100%
Drawing of Piping
Pipin Construction Standard 2120.00 08-Jul-15 08:00 A 25-Jul-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 7 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Piping Isometric Drawings(with Materials) and list for 1900 720.00 04-Jan-16 08:00 A 25-Mar-16 17:00 A 100% 100%
1900- REFINERY
REFINER INTERCONNECTING PLOT PLAN AREA 08 2032.00 26-Jan-15 08:00 A 22-Dec-15 17:00 A 100% 100%
Above Ground PipingP Key Plan for 1900 1032.00 13-May-15 08:00 A 14-Aug-15 17:00 A 100% 100%
Piping General Arrangement
A drawings for 1900 1208.00 05-Jan-16 08:00 A 15-Aug-16 17:00 A 100% 100%
Pipe support lists(Standard
lists and Special) for 1900 2352.00 11-Aug-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Piping Interface table for 1900 1688.00 22-Apr-15 08:00 A 10-Dec-15 17:00 A 100% 100%
Instrumentation an and control 4768.00 20-May-15 08:00 A 20-Sep-17 17:00 A 100% 100%
Document 4768.00 20-May-15 08:00 A 20-Sep-17 17:00 A 100% 100%
Project Specification-
Specifica Cable Specification 2736.00 20-May-15 08:00 A 20-Jul-16 17:00 A 100% 100%
Project Specification-
Specifica Junction Box Specification 1912.00 20-May-15 08:00 A 27-Jan-16 17:00 A 100% 100%
Project Specification-
Specifica Tubing&fitting Specification 1872.00 20-May-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Project Specification-
Specifica Cabinet Specification 2520.00 20-May-15 08:00 A 15-Aug-16 17:00 A 100% 100%
Project Specifica
Specification- DCS Specification 1264.00 20-May-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Project Specifica
Specification- ESD Specification 1264.00 20-May-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Project Specifica
Specification- FGS Specification 1264.00 20-May-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Project Specification-
Specifica Advanced System Specification 4760.00 20-May-15 08:00 A 19-Sep-17 17:00 A 100% 100%
Project Specifica
Specification- MMS Specification 1416.00 20-May-15 08:00 A 28-Dec-15 17:00 A 100% 100%
Project Specification-
Specifica Control Valve Specification 1160.00 20-May-15 08:00 A 03-Dec-15 17:00 A 100% 100%
Project Specification-
Specifica Actuated Valve Specification 1312.00 20-May-15 08:00 A 22-Dec-15 17:00 A 100% 100%
Project Specification-
Specifica Temperature Instrument Specification 1160.00 20-May-15 08:00 A 19-Nov-15 17:00 A 100% 100%
Project Specification-
Specifica Electronic Instrument Specification 1160.00 20-May-15 08:00 A 19-Nov-15 17:00 A 100% 100%
Project Specification-
Specifica Flow Instrument Specification 1784.00 20-May-15 08:00 A 06-Apr-16 17:00 A 100% 100%
Project Specification-
Specifica Flow Element Specification 1288.00 20-May-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Project Specification-
Specifica Level Instrument Specification 1264.00 20-May-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Project Specification-
Specifica Analyzer and Shelter Specification 4768.00 20-May-15 08:00 A 20-Sep-17 17:00 A 100% 100%
Project Specifica
Specification- Fire & Gas Detector Specification 4768.00 20-May-15 08:00 A 20-Sep-17 17:00 A 100% 100%
Project Specification-
Specifica Construction/ installation specification 1504.00 24-Aug-15 08:00 A 12-Apr-16 17:00 A 100% 100%
Instrument, Con
Control and Safeguarding General Philosophy 2512.00 20-May-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Instrument Earth
Earthing Philosophy 2368.00 20-May-15 08:00 A 21-Apr-16 17:00 A 100% 100%
Project Procudure-
Procudur Minimum Inspection and Test Requirements for Instrumentation 1552.00 20-May-15 08:00 A 18-Jan-16 17:00 A 100% 100%
DCS Architecture 1928.00 20-May-15 08:00 A 15-Jan-16 17:00 A 100% 100%
ESD/ BMS Architecture
Archi 1928.00 20-May-15 08:00 A 15-Jan-16 17:00 A 100% 100%
FGS Architecture 1928.00 20-May-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Drawing 2200.00 24-Aug-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Instrument and ccontrol block diagrams 2200.00 24-Aug-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Heating, Ventilation & Air Conditioning (HVAC) 3248.00 20-Jan-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Document 2096.00 20-Jan-15 08:00 A 29-Dec-15 17:00 A 100% 100%
HVAC design ba basis 2096.00 20-Jan-15 08:00 A 29-Dec-15 17:00 A 100% 100%
HVAC design ph philosophy 1264.00 01-Jun-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Drawing 3248.00 20-Jan-15 08:00 A 26-Aug-16 17:00 A 100% 100%
HVAC Symbols and legend 3248.00 20-Jan-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Process 2816.00 05-Nov-14 08:00 A 29-Jan-16 17:00 A 100% 100%
Document 2360.00 26-Jan-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Process Data Sheet
Sh - Basins Unit 6300 Refinery AOC Collection Basin 3 - 6300-T-103 1992.00 09-Feb-15 08:00 A 30-Dec-15 17:00 A 100% 100%
Piping Line lists for
f REFINERY INTERCONNECTING (Unit1900) 2120.00 12-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Piping interface table
t for REFINERY INTERCONNECTING (Unit1900) 1952.00 26-Jan-15 08:00 A 10-Dec-15 17:00 A 100% 100%
Drawing 2776.00 05-Nov-14 08:00 A 29-Oct-15 17:00 A 100% 100%
P&ID for 1900 2776.00 05-Nov-14 08:00 A 29-Oct-15 17:00 A 100% 100%
CDU - Crude Distillation
Distilla Unit 6704.00 22-Aug-14 08:00 A 14-Dec-17 17:00 A 100% 100%
1110 - CDU - Crude Distillation Unit 6704.00 22-Aug-14 08:00 A 14-Dec-17 17:00 A 100% 100%
Process 6704.00 22-Aug-14 08:00 A 14-Dec-17 17:00 A 100% 100%
Document 6704.00 22-Aug-14 08:00 A 14-Dec-17 17:00 A 100% 100%
Re-Pinch Analysis
Analys Report On CDU 720.00 22-Aug-14 08:00 A 31-Dec-14 17:00 A 100% 100%
Heat and Materi
Material Balance - Crude Distillation Unit (CDU) - Unit 1110 832.00 24-Oct-14 08:00 A 24-Mar-15 17:00 A 100% 100%
Utility Consumption
Consumpt Summary - Crude Distillation Unit (CDU) - Unit 1110 872.00 16-Dec-14 08:00 A 22-May-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 8 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Relief Valves Discharge


Dis Summary - Crude Distillation Unit (CDU) - Unit 1110 648.00 26-Dec-14 08:00 A 23-Apr-15 17:00 A 100% 100%
Process Interlock Description - Crude Distillation Unit (CDU) - Unit 1110 1520.00 26-Dec-14 08:00 A 23-Oct-15 10:19 A 100% 100%
List - Piping Inter
Interface Table - Unit 1110 - Process/Utility 2192.00 26-Dec-14 08:00 A 31-Dec-15 17:00 A 100% 100%
Process and ConControl Description - Crude Distillation Unit (CDU) - Unit 1110 1944.00 26-Dec-14 08:00 A 13-Nov-15 17:00 A 100% 100%
Process Effluent List - Crude Distillation Unit (CDU) - Unit 1110 792.00 30-Dec-14 08:00 A 22-May-15 17:00 A 100% 100%
Project Equipme
Equipment List - Crude Distillation Unit (CDU) - Unit 1110 2496.00 30-Dec-14 08:00 A 25-Mar-16 17:00 A 100% 100%
Chemicals Consumption
Cons Summary - Crude Distillation Unit (CDU) - Unit 1110 120.00 19-Jan-15 08:00 A 06-Feb-15 17:00 A 100% 100%
Design Basis - Crude
C Distillation Unit (CDU) - Unit 1110 2104.00 26-Jan-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Cause and Effect
Effec Chart / Diagram - Crude Distillation Unit (CDU) - Unit 1110 1648.00 09-Feb-15 08:00 A 23-Oct-15 14:50 A 100% 100%
Piping Line List - Crude Distillation Unit 1816.00 12-Mar-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Hydraulics calcul
calculation notes 1904.00 17-Mar-15 08:00 A 23-Feb-16 17:00 A 100% 100%
Safeguarding Memorandum
Me 5056.00 19-Jun-15 08:00 A 14-Dec-17 17:00 A 100% 100%
flare system simulation
simu + report 4408.00 10-Aug-15 08:00 A 12-Oct-17 17:00 A 100% 100%
unit simulation files
fil 1264.00 10-Aug-15 08:00 A 25-Mar-16 17:00 A 100% 100%
List of alarms anand trips with set points 1488.00 24-Aug-15 08:00 A 20-May-16 17:00 A 100% 100%
Operating & maimaintenance manual 1288.00 08-Aug-16 08:00 A 28-Mar-17 17:00 A 100% 100%
Process Data Sheet
Sh - Column - CDU - Atmospheric Column 1110-C-001 872.00 22-Sep-14 08:00 A 02-Mar-15 17:00 A 100% 100%
Process Data Sheet
Sh - Heaters 1110-F-001 A/B Crude Heaters 704.00 24-Oct-14 08:00 A 02-Mar-15 17:00 A 100% 100%
Process Data Sheet
Sh - Kerosene Side Stripper and Gasoil Side Stripper (1110-C-002/003) 648.00 04-Nov-14 08:00 A 02-Mar-15 17:00 A 100% 100%
Process Data Sheet
Sh - Column (CDU) Naphtha Stabilizer Column - 1110-C-004 1200.00 04-Nov-14 08:00 A 08-Jun-15 17:00 A 100% 100%
Process Data Sheet
Sh for Exchanger 1032.00 02-Dec-14 08:00 A 05-Jun-15 17:00 A 100% 100%
Process Data Sheet
Sh - Trays (CDU) (1110-CY001/002/003/004) 1168.00 15-Dec-14 08:00 A 13-Jul-15 17:00 A 100% 100%
Process Data Sh Sheet -De-emulsifier/ Corrosion Inhibitor/ Amine Injection Package(1110-A002/003/004 ) 360.00 26-Dec-14 08:00 A 02-Mar-15 17:00 A 100% 100%
Process Data Sheet
Sh - Air-Cooled Heat Exchangers (1110-E-014/016/018/020/023/026/028/029/030) 960.00 26-Dec-14 08:00 A 18-Jun-15 17:00 A 100% 100%
Process Data Sheet
Sh - Desalter Packages 1110-A-001 A/B 1424.00 26-Dec-14 08:00 A 06-Sep-15 17:00 A 100% 100%
Process Data Sh Sheet for Large Size Drums 1016.00 12-Jan-15 08:00 A 13-Jul-15 17:00 A 100% 100%
Process Data Sh Sheet for Carbom Steel Drums 1016.00 12-Jan-15 08:00 A 13-Jul-15 17:00 A 100% 100%
Process Data Sheet
Sh - Filters - Crude Feed Filter 1110-S-001 1376.00 12-Jan-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Process Data Sheet
Sh - Control Valves - CDU Unit 1110 1584.00 01-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Process Data Sheet
Sh - On/Off Valves (CDU) Unit 1110 1536.00 09-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Process Data Sheet
Sh - Flow Elements - CDU Unit 1110 2008.00 25-May-15 08:00 A 20-May-16 17:00 A 100% 100%
Process Data Sh Sheet - Pressure Safety Valves - CDU Unit 1110 1200.00 25-May-15 08:00 A 23-Dec-15 17:00 A 100% 100%
Process Data Sheet
Sh - Analyzers- CDU Unit 1110 712.00 25-May-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Process Data Sheet
Sh - Restriction Orifices - CDU Unit 1110 1128.00 25-May-15 08:00 A 10-Dec-15 17:00 A 100% 100%
Process Data Sheet
Sh for Desuperheater (1110-M-001/002) 904.00 03-Jun-15 08:00 A 13-Oct-15 17:00 A 100% 100%
Process Data Sheet
Sh for 1110-A-101 (UV STERILIZER PACKAGE) 1144.00 17-Jul-15 08:00 A 22-Dec-15 17:00 A 0% 0%
Hydraulic calculaiton
calcula notes for U1110 1144.00 17-Jul-15 08:00 A 18-Jan-16 17:00 A 0% 0%
Cause&Effect Ch Chart/Diagram Potable Water System 1144.00 17-Jul-15 08:00 A 22-Dec-15 17:00 A 0% 0%
Drawing 4216.00 22-Aug-14 08:00 A 16-Sep-16 17:00 A 100% 100%
PFD for Process(13)
Process 3304.00 22-Aug-14 08:00 A 08-Jan-16 17:00 A 100% 100%
UFD for Process(5)
Proces 3528.00 26-Dec-14 08:00 A 16-Sep-16 17:00 A 100% 100%
P&IDs BATCH 1 for Process (55) 2397.12 04-Nov-14 08:00 A 11-Dec-15 17:00 A 100% 100%
P&IDs BATCH 2 for COC lift pit 2488.00 26-Dec-14 08:00 A 07-Sep-15 17:00 A 100% 100%
P&IDs BATCH3 for common facilities sanitary waste water 2288.00 16-Feb-15 08:00 A 29-Dec-15 17:00 A 100% 100%
UIDs BATCH 1 ffor Process (59) 2216.00 26-Dec-14 08:00 A 23-Oct-15 13:48 A 100% 100%
UIDs BATCH 2 ffor LP And Atmospheric Condensate Flash Drums/ Clean Condensate (air cooler) 2208.00 19-Jan-15 08:00 A 23-Oct-15 17:00 A 100% 100%
UIDs BATCH 3 ffor Eye washer 1360.00 10-Sep-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Material Selectio
Selection Diagram (MSD) (12) 1392.00 19-Jan-15 08:00 A 06-Nov-15 17:00 A 100% 100%
UID - Crude Distillation
Dis - Potable water 1224.00 17-Jul-15 08:00 A 29-Jan-16 17:00 A 0% 0%
Etc 80.00 04-Nov-14 08:00 A 17-Nov-14 17:00 A 0% 0%
COS 80.00 04-Nov-14 08:00 A 17-Nov-14 17:00 A 0% 0%
Material, Corrison and Inspection 4984.00 01-Apr-15 08:00 A 11-Sep-17 17:00 A 100% 100%
Document 4984.00 01-Apr-15 08:00 A 11-Sep-17 17:00 A 100% 100%
Data Sheets 1560.00 01-Apr-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Material Selection
Selectio Guide 2640.00 18-Jun-15 08:00 A 07-Oct-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 9 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Corrosion Design
Desig Basis Memorandum 2128.00 18-Sep-15 08:00 A 16-Sep-16 17:00 A 100% 100%
RBI Excution Plan
Pla 1104.00 29-Sep-15 08:00 A 08-Mar-16 17:00 A 100% 100%
Installation Specification
Spec 3401.43 07-Jan-16 15:34 A 11-Sep-17 17:00 A 100% 100%
Corrosion Documents
Docum 2944.00 06-Jan-16 08:00 A 19-Jun-17 17:00 A 100% 100%
RBI Documents 2312.00 03-Mar-16 08:00 A 21-Apr-17 17:00 A 100% 100%
Drawing 760.00 25-Mar-16 08:00 A 25-May-17 17:00 A 100% 100%
Vendor Data and Drawings 760.00 25-Mar-16 08:00 A 25-May-17 17:00 A 100% 100%
RFQ 2040.00 01-Apr-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Corrosion Monitoring
Monito System 2040.00 01-Apr-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 4048.00 26-Sep-14 08:00 A 10-Nov-16 17:00 A 100% 100%
Document 2472.00 24-Oct-14 08:00 A 12-Jan-16 17:00 A 100% 100%
Mechanical data sheet for Crude Heaters 1110-F-0001A/B 2464.00 24-Oct-14 08:00 A 28-Oct-15 08:48 A 100% 100%
Mechanical data sheet for Atmospheric Column (1110-C-001) 1792.00 04-Nov-14 08:00 A 09-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Kerosene Side Strippe (1110-C-002) 1616.00 02-Dec-14 08:00 A 09-Sep-15 17:00 A 100% 100%
Mechanical Data Sheet for Gasoil Side Stripper (1110-C-003) 1616.00 02-Dec-14 08:00 A 09-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Naphtha Stabilizer Column (1110-C-004) 1616.00 02-Dec-14 08:00 A 09-Sep-15 17:00 A 100% 100%
Mechanical Data Sheet - Packages (CDU) Amine Injection Package 1110-A-004 352.00 17-Aug-15 08:00 A 19-Oct-15 17:00 A 100% 100%
Mechanical Data Sheet - Packages (CDU) Corrosion Inhibitor Package 1110-A-003 352.00 17-Aug-15 08:00 A 19-Oct-15 17:00 A 100% 100%
Mechanical Data Sheet - Packages (CDU) De-Emulsifier Injection Package 1110-A-002 352.00 17-Aug-15 08:00 A 19-Oct-15 17:00 A 100% 100%
Mechanical Data Sheet - Desalter Package 1110-A-001A/B 2032.00 12-Jan-15 08:00 A 12-Jan-16 17:00 A 100% 100%
Mechanical data sheet for Exchangers batch 1 1200.00 20-Jan-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Mechanical data sheet for Exchangers batch 2 1200.00 20-Jan-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Mechanical data sheet for Air Cooled Heat Exchangers 1136.00 30-Jan-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Mechanical data sheet for Large Size Drums 248.00 27-Feb-15 08:00 A 09-Apr-15 17:00 A 100% 100%
Mechanical data sheet for Carbom Steel Drums 248.00 27-Feb-15 08:00 A 09-Apr-15 17:00 A 100% 100%
Drawing 3856.00 04-Nov-14 08:00 A 10-Nov-16 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Atmospheric Column (1110-C-001) 2367.60 04-Nov-14 08:00 A 31-Dec-15 16:36 A 100% 100%
General Arrangement
Arrange Drawing for Naphtha Stabilizer Column (1110-C-004) 1040.00 09-Jun-15 08:00 A 10-Dec-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Kerosene Side Stripper and Gasoil Side Stripper (1110-C-002/003) 1048.00 09-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for CS Drum 136.00 14-Jul-15 08:00 A 03-Aug-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Large Size Drum 136.00 14-Jul-15 08:00 A 03-Aug-15 17:00 A 100% 100%
Vendor Data and Drawings for Atmospheric Column (1110-C-001) (MRI-1110-3002) 1600.00 24-Sep-15 00:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for CDU Columns (1110-C-002/003/004) (MRI-1110-3002) 1600.00 24-Sep-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for Crude Heater (MRI-1110-7001) 1440.00 12-Nov-15 08:00 A 11-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Large Size Drums (MRI-1110-1004) 1360.00 29-Sep-15 00:00 A 08-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Carbon Steel Drums (MRI-1110-1007) 1360.00 28-Sep-15 00:00 A 11-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for Air Coolers (MRI-1110-2023) 1440.00 22-Sep-15 08:00 A 11-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for Exchangers (MRI-1110-2004) /(MRI-1110-2005) 1200.00 12-Oct-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Desalter Packages and De-emulsifier Injection Package (MRI-1110-9002) 1280.00 31-Oct-15 00:00 A 10-Nov-16 17:00 A 100% 100%
Vendor Data and Drawings for Corrosion Inhibitor Package & Amine Injection Package (MRI-1110-9004) 1040.00 19-Jan-16 08:00 A 10-Nov-16 17:00 A 100% 100%
RFQ 3160.00 26-Sep-14 08:00 A 22-Apr-16 17:00 A 100% 100%
Desalter Packag
Packages and De-Emulsifier Package(MRI-1110-9002) 2048.00 24-Oct-14 08:00 A 22-Oct-15 17:00 A 100% 100%
Crude Heater (MRI-1110-7001)
(M 1648.00 17-Nov-14 08:00 A 07-Sep-15 17:00 A 100% 100%
CDU Column Internals
Int (MRI-1110-7001) 1352.00 16-Dec-14 08:00 A 21-Aug-15 17:00 A 100% 100%
Atmospheric Column
Col (MRI-1110-3002) 1384.00 19-Jan-15 08:00 A 14-Aug-15 17:00 A 100% 100%
Exchangers I (MRI-1110-2004)
(M 1352.00 20-Jan-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Exchangers II (MRI-1110-2005)
(M 1368.00 20-Jan-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Corrosion Inhibitor
Inhibit Package & Amine Injection Package (MRI-1110-9004) 96.00 10-Feb-15 08:00 A 02-Mar-15 17:00 A 100% 100%
CDU Columns (MRI-1110-3002)
( 984.00 18-Feb-15 08:00 A 14-Aug-15 17:00 A 100% 100%
Air Coolers (MR
(MRI-1110-2023) 1192.00 27-Feb-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Large Size Drums
Drum (MRI-1110-1004) 920.00 09-Apr-15 08:00 A 09-Sep-15 17:00 A 100% 100%
Carbon Steel Drums
Dr (MRI-1110-1007) 920.00 09-Apr-15 08:00 A 09-Sep-15 17:00 A 100% 100%
UV Disnfection System
S (MRI-1110-7005) 3160.00 26-Sep-14 08:00 A 22-Apr-16 17:00 A 0% 0%
Etc 80.00 16-Nov-15 00:00 A 25-Dec-15 17:00 A 0% 0%
COS 80.00 16-Nov-15 00:00 A 25-Dec-15 17:00 A 0% 0%

Remaining Level of Effort Actual Work Critical Remaining ... Page 10 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Rotating Equipment 3520.08 12-Jan-15 08:00 A 10-Nov-16 17:00 A 100% 100%


Document 2056.00 12-Jan-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Mechanical data sheet for Pumps Batch 1 1864.00 12-Jan-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical data sheet for Pumps Batch 2 224.00 12-Jan-15 08:00 A 17-Feb-15 17:00 A 100% 100%
Mechanical data sheet for Pumps Batch 3- COC 1480.00 27-Apr-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Drawing 1208.00 10-Oct-15 00:00 A 10-Nov-16 17:00 A 100% 100%
Vendor Data and Drawings for Pumps Batch1 (MRI-1110-0001) 1200.00 10-Oct-15 00:00 A 10-Nov-16 17:00 A 100% 100%
Vendor Data and Drawings for Pumps Batch2 (MRI-1110-0002) 1200.00 15-Oct-15 00:00 A 10-Nov-16 17:00 A 100% 100%
RFQ 1080.00 18-Feb-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Pump Batch 1 (M (MRI-1110-0001) 1080.00 18-Feb-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Pump Batch 2 (M (MRI-1110-0002) 1080.00 18-Feb-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 3704.00 24-Nov-14 08:00 A 16-Sep-16 17:00 A 100% 100%
Document 2544.00 22-Jun-15 08:00 A 16-Sep-16 17:00 A 100% 100%
MTO for Fire Detection
De 2544.00 22-Jun-15 08:00 A 02-Sep-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices 1592.00 07-Jul-15 08:00 A 20-Apr-16 17:00 A 100% 100%
Telecommunication Cable Schedule
Telecommunicat 2040.00 15-Sep-15 08:00 A 16-Sep-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 1208.00 11-Sep-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Conduits And Accessories 1072.00 11-Sep-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Drawing 3008.00 24-Nov-14 08:00 A 27-Apr-16 17:00 A 100% 100%
Telecommunicaiton devices location layout
Telecommunicait 3008.00 24-Nov-14 08:00 A 15-Apr-16 17:00 A 100% 100%
Telecommunicaiton Cable Routing Layout
Telecommunicait 1448.00 07-Aug-15 08:00 A 27-Apr-16 17:00 A 100% 100%
RFQ 1432.00 19-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Devices (MRI-0001-1100)
(MRI-00 760.00 19-May-15 08:00 A 21-Oct-15 17:00 A 100% 100%
Detection (MRI-
(MRI-0001-1000) 1280.00 15-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Optic Fiber Cabl
Cable & Cable (MRI-0001-1200) 536.00 14-Sep-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 3688.00 24-Nov-14 08:00 A 16-Sep-16 17:00 A 100% 100%
Document 2800.00 09-Feb-15 08:00 A 29-Jun-16 17:00 A 100% 100%
Effluents inventory
invento (gaseous, liquid, solid waste) 2104.00 09-Feb-15 08:00 A 19-Jan-16 17:00 A 100% 100%
Aquatic toxicity inventory
in 1688.00 10-Mar-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Stack height calculation
calc note 2640.00 12-Mar-15 08:00 A 29-Jun-16 17:00 A 100% 100%
Hazardous area classification schedule 1776.00 13-Apr-15 08:00 A 26-Feb-16 17:00 A 100% 100%
Safety Piping LinLine List - Crude Distillation Unit 320.00 24-Apr-15 08:00 A 19-Jun-15 17:00 A 100% 100%
List of items to beb fireproofed 1160.00 27-Apr-15 08:00 A 19-Nov-15 17:00 A 100% 100%
Greenhouse gas accounting report 2216.00 22-May-15 08:00 A 24-Jun-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1448.00 08-Jul-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Material Take Off Of for fire fighting equipment 888.00 17-Aug-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Noisy equipment list 576.00 10-Sep-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Safety sign spec
specification and datasheet 1168.00 10-Oct-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Deluge Nozzle Arrangment
A Calculation Note - Crude Distillation Unit 976.00 23-Oct-15 08:00 A 29-Mar-16 17:00 A 100% 100%
Drawing 3040.00 24-Nov-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Fireproofing zone
zon layout 2296.00 24-Nov-14 08:00 A 08-Jan-16 15:24 A 100% 100%
Hazardous area classification layout 2160.00 06-Jan-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Safety Drawing- Fire Protection and Personnel Protection - Crude Distillation Unit 2168.00 12-Jan-15 08:00 A 14-Jan-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2176.00 02-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
layout for Tempo
Temporary mustering areas and escape routes 1768.00 21-Apr-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Fire water spray system P&ID 1936.00 24-Apr-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Safety shower a and eye wash station potable water 1448.00 26-Aug-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Safety sign layout 1536.00 20-Aug-15 08:00 A 08-Apr-16 17:00 A 100% 100%
RFQ 2128.00 31-Aug-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Fire water hydrant/hose
hydra box&monitor (MRI-0001-7003) 536.00 31-Aug-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Inert gas fire extinguishing
ext system (MRI-0001-7004) 600.00 31-Aug-15 08:00 A 16-Dec-15 17:00 A 100% 100%
Fire extinguisher (MRI-0001-7005) 536.00 31-Aug-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Signage for all units
u (MRI-0001-7012) 1712.00 11-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Wind socks for a all units (MRI-0001-7011) 1560.00 11-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Personal protection
protect for all units (MRI-0001-7010) 1560.00 11-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 11 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Civil/Structure 4936.00 09-Feb-15 08:00 A 19-Jun-17 17:00 A 100% 100%


Document 4936.00 09-Feb-15 08:00 A 19-Jun-17 17:00 A 100% 100%
Calculation Notes
Note for Pipe Rack 1584.00 09-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Calculation Notes
Note for Column Foundation C-004 1536.00 24-Mar-15 08:00 A 22-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for 1110-STR-1100 1400.00 28-May-15 08:00 A 21-Jan-16 17:00 A 100% 100%
Calculation Notes
Note for Drum Foundation 1360.00 05-Jun-15 08:00 A 03-Jun-16 17:00 A 100% 100%
Calculation Notes
Note for 1110-STR-1200 1352.00 05-Jun-15 08:00 A 22-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for Exchanger Foundation 1168.00 05-Jun-15 08:00 A 20-May-16 17:00 A 100% 100%
Calculation Notes
Note for Column Foundation C-001 1176.00 19-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Calculation Notes
Note for COC PIT 2216.00 25-Aug-15 08:00 A 05-Sep-16 17:00 A 100% 100%
Calculation Notes
Note for Furnace Foundation 576.00 20-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Calculation Notes
Note for Pump Foundation 1648.00 14-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Calculation Notes
Note for Filter Foundation 2360.00 23-May-16 08:00 A 19-Jun-17 17:00 A 100% 100%
Calculation Notes
Note for Desalter Package Foundation 784.00 30-Oct-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Calculation Notes
Note for Other Packages £¨1110-A-002/003/004£© 2464.00 05-Apr-16 08:00 A 19-Jun-17 17:00 A 100% 100%
Material Take Off
Of for Steel Structure Anchor Bolts 568.00 22-Jun-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Material Take Off
Of for Equipment Anchor Bolts 480.00 24-Aug-15 08:00 A 29-Aug-15 17:00 A 100% 100%
Material Take Off
Of for Reinforcing Steel 664.00 25-Sep-15 08:00 A 07-Jan-16 17:00 A 100% 100%
Material Take OfOff for Structure Steel 968.00 09-Jun-15 08:00 A 29-Jul-15 17:00 A 100% 100%
Drawing 3568.00 09-Feb-15 08:00 A 27-Sep-16 17:00 A 100% 100%
Pile Layout of 1110-C-004
11 1024.00 19-Jun-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Pile Layout of 1110-RCK-1100
11 712.00 22-Jun-15 08:00 A 20-Oct-15 08:29 A 100% 100%
Pile Layout of 1110-RCK-1200
11 712.00 22-Jun-15 08:00 A 15-Oct-15 17:00 A 100% 100%
Pile Layout of 1110-RCK-1220
11 712.00 22-Jun-15 08:00 A 16-Oct-15 08:29 A 100% 100%
Pile Layout of 1110-STR-1100
11 1088.00 06-Jul-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Pile Layout of 1110-STR-1200
11 944.00 07-Jul-15 08:00 A 22-Dec-15 17:00 A 100% 100%
Pile Layout of 1110-RCK-3100
11 808.00 22-Jun-15 08:00 A 12-Nov-15 17:00 A 100% 100%
Pile Layout of UNIT
UN 1110 1176.00 08-Jul-15 08:00 A 12-Nov-15 17:00 A 100% 100%
Pile Layout of 1110-V-003
11 1064.00 13-Jul-15 08:00 A 19-Jan-16 17:00 A 100% 100%
Pile Layout of Drum
D (1110-V-002/008) 1056.00 14-Jul-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Pile Layout of 1110-C-001,C-002/003
11 832.00 16-Jul-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Pile Layout of H Heat Exchanger (18) 952.00 17-Jul-15 08:00 A 25-Jan-16 17:00 A 100% 100%
Pile Layout of H Heat Exchanger (1110-E-024/027/031) 496.00 23-Oct-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Pile Layout of Furnace
F 400.00 20-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of 1110-K-001/002/003/004,
11 1110-KT-001B/003B 692.97 20-Nov-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Pile Layout of Drum
D (1110-V-015/016) 224.00 15-Dec-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Steel Works for RCK-3100 (Elevations/ Framing Plans) 2192.00 09-Feb-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Steel Works for RCK-1100 (Elevations/ Framing Plans) 1904.00 09-Feb-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Steel Works for RCK-1110/1200/1220 (Elevations/ Framing Plans) 2272.00 09-Feb-15 08:00 A 29-Apr-16 17:00 A 100% 100%
Structure Drawin
Drawings for 1110-STR-1100 (Elevations/ Framing Plans/Columns) 2016.00 29-May-15 08:00 A 27-May-16 17:00 A 100% 100%
Structure Drawin
Drawings for 1110-STR-1200 (Elevations/ Framing Plans/Columns) 1376.00 29-May-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1110-STR-1100 (Details) 1528.00 24-Aug-15 08:00 A 27-May-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1110-STR-1200 (Details) 1136.00 24-Aug-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for COC PIT 1792.00 26-Aug-15 08:00 A 15-Jul-16 17:00 A 100% 100%
Steel Works for RCK-1100(Columns/ Beams/ Details) 672.00 25-Sep-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Steel Works for RCK-3100(Columns/ Beams/ Details) 976.00 25-Sep-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Steel Works for RCK-1110/1200/1220(Columns/ Beams/ Details) 840.00 25-Sep-15 08:00 A 29-Apr-16 17:00 A 100% 100%
Surfacing and grading
gr finishing layout 2496.00 27-Apr-15 08:00 A 19-Jul-16 17:00 A 100% 100%
Drawing for stormwater
stor drainage network 1560.00 27-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Drawing - Drainage
Drain and Underground Piping Drawing - Refinery 04 - Unit 1110 1656.00 22-Jun-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Equipment Foun
Foundations Drawings for Column C-004 1488.00 01-Apr-15 08:00 A 22-Dec-15 17:00 A 100% 100%
Equipment Foun
Foundations Drawings for Drum 1280.00 05-Jun-15 08:00 A 27-May-16 17:00 A 100% 100%
Equipment Foun
Foundations Drawings for Heat Exchanger 1272.00 08-Jun-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Foundations Drawings
Dra for Pipe Rack£¨RCK-1100/1110/1200/1220£© 1056.00 08-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Equipment Foun
Foundations Drawings for Column C-001,C-002/003 1128.00 29-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 12 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Foundations Drawings
Dra for 1110-STR-1100 1040.00 27-Jul-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Foundations Drawings
Dra for 1110-STR-1200 1040.00 27-Jul-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Foundations Drawings
Dra for Pipe Rack£¨RCK-3100£© 616.00 24-Aug-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Foundation Layout
Layo for Unit 1110 1120.00 25-Sep-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Equipment FounFoundations Drawings for Furnace 1032.00 11-Dec-15 08:00 A 19-May-16 17:00 A 100% 100%
Equipment Foundations
Foun Drawings for Pump 1760.00 11-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Equipment FounFoundations Drawings for Filter 984.00 24-May-16 08:00 A 27-Sep-16 17:00 A 100% 100%
Equipment FounFoundations Drawings for Desalter Package 840.00 02-Nov-15 08:00 A 27-May-16 17:00 A 100% 100%
Equipment FounFoundations Drawings for Other Packages£¨1110-A-002/003/004£© 616.00 06-Apr-16 08:00 A 22-Jul-16 17:00 A 100% 100%
RFQ 568.00 08-Jun-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Requisitions for steels structures 568.00 08-Jun-15 08:00 A 29-Jul-15 17:00 A 100% 100%
Equipment anchanchor bolts 304.00 19-Jun-15 08:00 A 06-Aug-15 17:00 A 100% 100%
Steel structure a anchor bolts 304.00 22-Jun-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Piping 4296.00 22-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Document 3048.00 01-Apr-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Critical line list 1696.00 01-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Data Sheets for Flame Arrester 616.00 08-Apr-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheets for Sampler 616.00 08-Apr-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheets for Strainer (1110-S-001) 1064.00 08-Apr-15 08:00 A 18-Aug-15 17:00 A 100% 100%
Steam Tracing List L 568.00 14-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Data Sheets for Safety Valve 776.00 22-May-15 08:00 A 15-Sep-15 17:00 A 100% 100%
Data Sheets for Eyewash & Shower 1592.00 22-May-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Piping Stress Calculations
Ca and analysis report 1942.00 07-Aug-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Pipe support lists(Standard
lists and Special) 2272.00 17-Aug-15 08:00 A 19-Jan-16 17:00 A 100% 100%
Material Take Off Of for U/G pipe system 783.20 20-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Material Take Of Off for Special Item 1456.00 24-Dec-15 08:00 A 08-Sep-16 17:00 A 100% 100%
Material Take Off Of for Insulation 1456.00 24-Dec-15 08:00 A 08-Sep-16 17:00 A 100% 100%
Material Take Off Of for Piping Painting 1456.00 24-Dec-15 08:00 A 08-Sep-16 17:00 A 100% 100%
Material Take Off Of for Piping Bulk Material 592.00 24-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Spring list and data da sheet 720.00 02-Feb-16 08:00 A 13-Jun-16 17:00 A 100% 100%
Critical line list for
fo safety piping 1263.20 28-Sep-15 08:00 A 29-Jan-16 17:00 A 0% 0%
Drawing 4296.00 22-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Vendor Data and Drawings for Misc. Piping Equipment 640.00 11-Apr-16 08:00 A 08-Sep-16 17:00 A 100% 100%
CDU Unit Plot Plan P 2632.00 22-Aug-14 08:00 A 11-Dec-15 17:00 A 100% 100%
3D-Modeling/review report/action close-out-report
3D-Modeling/rev 3528.00 27-Oct-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Key Plan OF Equipment
Eq Layout 2256.00 10-Nov-14 08:00 A 18-Dec-15 17:00 A 100% 100%
Above Ground Piping P GA Key Plan 744.00 26-Dec-14 08:00 A 12-May-15 17:00 A 100% 100%
Equipment layout 1688.00 17-Feb-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Battery Limit inte
interface Table 1664.00 06-Apr-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Special Pipe Support
Sup Drawing and list 2360.00 10-Aug-15 08:00 A 07-Oct-16 00:00 A 100% 100%
ISO drawing for U/G piping and list 736.00 04-Dec-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Piping Isometric Drawings(with Materials) and list 1656.00 04-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
ISO drawing for U/G piping 728.00 20-Nov-15 00:00 A 22-Feb-16 17:00 A 100% 100%
Piping General Arrangement
A drawings 664.00 04-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
RFQ 2824.00 06-Apr-15 08:00 A 30-Aug-16 17:00 A 100% 100%
MR for Blanket Order O of Piping/Fitting/Valve 280.00 15-Apr-15 08:00 A 03-Jun-15 17:00 A 100% 100%
Safety Valves (MRI-0001-0001,0002)
(M 1408.00 25-May-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Misc. Piping Equ Equipment (Strainer/Sampler/Sighting glass/Sliencer/ Flame Arrester/ Eye Wash& Shower) 512.00 25-May-15 08:00 A 20-Aug-15 17:00 A 100% 100%
1st U/G Piping (MRI-0001-0160,8110,8210,8310)
(M 320.00 07-Jul-15 08:00 A 31-Aug-15 17:00 A 100% 100%
1st Piping Valves (MRI-0001-4610,4611,4614,4615) 224.00 10-Aug-15 08:00 A 23-Oct-15 17:00 A 100% 100%
1st Piping Support
Suppo (MRI-0001-7001) 216.00 07-Aug-15 08:00 A 23-Oct-15 17:00 A 100% 100%
U/G valves (MR (MRI-0001-8410) 568.00 26-Aug-15 08:00 A 12-Nov-15 17:00 A 100% 100%
MR for U/G GRP bulk material (MRI-0001-0160,8110,8210,8310,8410) 208.00 06-Apr-15 08:00 A 15-May-15 17:00 A 100% 100%
1st Piping/Fitting/Flange
Piping/Fitting (MRI-0001-1220,1317,1318,1319,1510,1512) 128.00 04-Dec-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Spring Hanger 184.00 07-Dec-15 08:00 A 25-Dec-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 13 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

2nd Piping/Valves/Fitting
Piping/Valve 680.00 14-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
2nd Piping Support
Supp 120.00 15-Aug-16 08:00 A 30-Aug-16 17:00 A 100% 100%
Etc 3160.00 27-Jan-15 08:00 A 18-Aug-16 17:00 A 0% 0%
COS 3160.00 27-Jan-15 08:00 A 18-Aug-16 17:00 A 0% 0%
Electrical 3632.00 30-Dec-14 08:00 A 16-Sep-16 17:00 A 100% 100%
Document 3632.00 30-Dec-14 08:00 A 09-Sep-16 17:00 A 100% 100%
Data Sheet For LV Induction Machine 1152.00 30-Dec-14 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheet For HV Induction Machine 1152.00 30-Dec-14 08:00 A 24-Jul-15 17:00 A 100% 100%
Electrical Consumer
Consum List 2488.00 15-Feb-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Electrical Cable List
L 1376.00 27-Jul-15 08:00 A 04-Feb-16 17:00 A 100% 100%
BLIT OF CABLES
CABLE 1816.00 27-Jul-15 08:00 A 15-Jan-16 17:00 A 100% 100%
BLIT OF CABLE TRENCH 1816.00 27-Jul-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Data Sheet For Cage Induction Machine - LV 1110- PM-103A/B 488.00 27-Jul-15 08:00 A 02-Sep-15 17:00 A 100% 100%
Electrical Cable Drum
D Schedule 608.00 30-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Material Take OfOff For Earthing and Lighting Material 1248.00 23-Sep-15 08:00 A 10-May-16 17:00 A 100% 100%
Material Take Off
Of For Cable 1224.00 16-Oct-15 08:00 A 24-Jun-16 17:00 A 100% 100%
Material Take OfOff For Cable Ladder And Cable Tray 1432.00 16-Oct-15 08:00 A 05-Aug-16 17:00 A 100% 100%
Material Take Off
Of for Other Material---( Including Conduit Galvanized Steel, Accessories, etc. 1896.00 10-Nov-15 08:00 A 09-Sep-16 17:00 A 100% 100%
Drawing 3176.00 12-Mar-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout (Aboveground) 2376.00 12-Mar-15 08:00 A 13-May-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout (Underground) 2048.00 27-Apr-15 08:00 A 29-Apr-16 17:00 A 100% 100%
Interface Drawing
Drawin of Cable Routing 1520.00 08-May-15 08:00 A 03-Feb-16 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 1648.00 27-Jul-15 08:00 A 20-May-16 17:00 A 100% 100%
Interface Drawing
Drawin of Earthing System 1223.20 26-Aug-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Cathodic Protection
Protect System Layout 464.00 22-Oct-15 00:00 A 22-Jan-16 17:00 A 100% 100%
Lighting Layout (Unit/Street)
( 1176.00 14-Dec-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Lighting Loop Diagram
Di 840.00 08-Jan-16 08:00 A 10-Jun-16 17:00 A 100% 100%
Wiring / Interconection
Intercon Diagram 1560.00 25-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Lighting and Small
Sm Power Distribution Panel Single Line Diagram 920.00 25-Dec-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Electrical Heat Tracing
T Layout 280.00 15-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
RFQ 1472.00 16-Oct-15 08:00 A 15-Jul-16 17:00 A 100% 100%
Cathodic Protection
Protect (MRI-0001-0700) 400.00 04-Dec-15 08:00 A 09-Dec-15 17:00 A 100% 100%
Earthing and Lightning
Lig Material (MRI-0001-0110,0210) 248.00 23-Nov-15 00:00 A 05-Jan-16 17:00 A 100% 100%
Elec. Heat Tracin
Tracing (MRI-0001-0600) 336.00 14-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Cable Ladder andan Cable Tray (MRI-0001-0300) 168.00 16-Oct-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable (MRI-000
(MRI-0001-0200,0210) 368.00 26-Oct-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Conduit And Accessories
Acc (MRI-0001-0100) 712.00 11-Mar-16 08:00 A 15-Jul-16 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch (MRI-0001-0500,0510) 328.00 07-Dec-15 08:00 A 30-Dec-15 17:00 A 100% 100%
Other Material (M(MRI-0001-0120,0230,0240,0250) 904.00 04-Jan-16 08:00 A 15-Jun-16 17:00 A 100% 100%
Lighting Fixtures (MRI-0001-0400,0410,0420,0430) 336.00 04-Jan-16 08:00 A 04-Mar-16 17:00 A 100% 100%
Etc 160.00 29-Jan-16 08:00 A 25-Mar-16 13:48 A 0% 0%
COS 160.00 29-Jan-16 08:00 A 25-Mar-16 13:48 A 0% 0%
Instrumentation anand control 3728.00 26-Dec-14 08:00 A 28-Oct-16 17:00 A 100% 100%
Document 3592.00 26-Dec-14 08:00 A 22-Sep-16 17:00 A 100% 100%
Instrument Index 296.00 26-Dec-14 08:00 A 16-Feb-15 17:00 A 100% 100%
System I/O LIST 304.00 26-Dec-14 08:00 A 17-Feb-15 17:00 A 100% 100%
Power Feeds ListLis with Power Consumption for UPS and non-UPS Consumers 376.00 15-Feb-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Instrument Air CConsumption Calculations 360.00 17-Feb-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Datasheet for Self-Actuated
Se Control Valve 1224.00 17-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for ESD
ES Ball Valve£¨Ball£© 1552.00 17-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Control
Co Valve(Rotary) 1632.00 17-Feb-15 08:00 A 16-Oct-15 17:00 A 100% 100%
Datasheet for CoControl Valve (Globe) 1632.00 17-Feb-15 08:00 A 16-Oct-15 17:00 A 100% 100%
Datasheet for Gas
G Detector 1240.00 07-Apr-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Ultrasonic
Ul Flow Meter 904.00 22-Apr-15 08:00 A 27-Oct-15 17:00 A 100% 100%
Datasheet for Thermometer
Th 1192.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 14 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Datasheet for Thermowell


Th 904.00 22-Apr-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Te Temperature Transmitter 1192.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Variable
Va Area Flow Meter 1152.00 22-Apr-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Orifice
O Plate 1152.00 22-Apr-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Level
Le Gauge 776.00 25-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Pressure
Pr Gauge 968.00 25-May-15 08:00 A 09-Nov-15 17:00 A 100% 100%
Datasheet for Displacer
Di Level Instrument 776.00 25-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Local
Lo Milliammeter 1136.00 25-May-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Datasheet for DP Transmitter 872.00 25-May-15 08:00 A 14-Oct-15 17:00 A 100% 100%
Datasheet for DP Level Transmitter 1016.00 25-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Pressure
Pr Transmitter 872.00 25-May-15 08:00 A 14-Oct-15 17:00 A 100% 100%
Datasheet for DP Flow Transmitter 976.00 25-May-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for O Oil in Water Analyzer 1024.00 25-May-15 08:00 A 23-Nov-15 17:00 A 100% 100%
Datasheet for Le Level Transmitter Radar Type 856.00 25-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Flow
Fl Element - Restriction Orifice 1016.00 25-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Deluge
De Valve 864.00 26-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Level Instrumen
Instrument Nozzel Elevations Calculation 1096.00 01-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Datasheet for W Wireless Temperature Transmitter 832.00 18-Jun-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Continuous
Co Emission Monitoring System (CEMS) 1784.00 18-Jun-15 08:00 A 06-May-16 17:00 A 100% 100%
Datasheet for De Desuperheater 1552.00 18-Jun-15 08:00 A 27-Oct-15 17:00 A 100% 100%
IPF classification
classifications, verification reports 1312.00 08-Jul-15 08:00 A 02-Mar-16 17:00 A 100% 100%
Datasheet for Differential
Di Pressure Gauge 584.00 26-May-15 08:00 A 04-Nov-15 17:00 A 100% 100%
Datasheet for Magnetic
M Level Gauge 584.00 26-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Emergency
Em Depressure Valve 1080.00 22-Jul-15 08:00 A 17-Dec-15 17:00 A 100% 100%
Instrument NamName Plate Schedules 624.00 11-Oct-15 08:00 A 16-Dec-15 17:00 A 100% 100%
Sizing Caculations
Caculation for Control Valves 856.00 04-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Intrinsically Safe(IS)
Safe( Loop Calculations 1600.00 04-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Alarm rationalisa
rationalisation study report and alarm reference data base 1696.00 04-Dec-15 08:00 A 22-Sep-16 17:00 A 100% 100%
DCS Group Displays
Disp & Reports 920.00 30-Nov-15 08:00 A 16-May-16 17:00 A 100% 100%
Configuration Data
Da for Machine Monitoring System and Performance Monitoring System 368.00 04-Dec-15 08:00 A 07-Feb-16 17:00 A 100% 100%
Analyser Sample System Transportation times 328.00 21-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable Sizing/Selection
Sizing/Sel Calculations 592.00 25-Dec-15 08:00 A 13-Apr-16 17:00 A 100% 100%
Junction Box Schedule
Sch 840.00 11-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Cable Drum Sch Schedules 760.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Instrument Cable Schedules 840.00 11-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Sizing Calculations
Calculatio for Flow Elements 916.00 29-Jul-15 08:00 A 12-Jan-16 17:00 A 100% 100%
Thermowell Wak Wake Frequency Calculations 768.00 14-Dec-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Material Take Of Off£¨Bulk Items/Cable Tray/Cable/Junction Box/Valve£© 582.40 04-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Drawing 3072.00 27-Apr-15 08:00 A 28-Oct-16 17:00 A 100% 100%
Instrument Main Cable Routing 1560.00 27-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Junction Box Wiring
Wir Diagrams 1936.00 01-Jun-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Instrument hook
hook-up drawings£¨process and pneumatic) 1776.00 01-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Graphic Display Sketches 608.00 20-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Instument Locati
Location Layouts 1104.00 26-Oct-15 00:00 A 23-Jun-16 17:00 A 100% 100%
Shutdown and LogicL Diagrams 768.00 26-Oct-15 00:00 A 08-Jan-16 17:00 A 100% 100%
Instument Air DisDistribution Layouts 624.00 27-Oct-15 00:00 A 04-May-16 17:00 A 100% 100%
Instrument Cable trays/trench layouts with cable cross section 2056.00 27-Nov-15 00:00 A 28-Oct-16 17:00 A 100% 100%
Instrument Earth
Earthing Layouts 1016.00 27-Oct-15 00:00 A 12-Jul-16 17:00 A 100% 100%
Instrument Loop Diagrams 392.00 11-Mar-16 08:00 A 20-May-16 17:00 A 100% 100%
RFQ 2216.00 26-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
MAC (INC-MRI-
(INC-MRI-0001-1001) 1456.00 26-Feb-15 08:00 A 11-Nov-15 17:00 A 100% 100%
Control Valves/o
Valves/on-off valves (MRI-0001-0501,0502,0503,0506) 1152.00 10-Mar-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Orifice Plate/ Flow
Flo /Temperature Element (MRI-0001-0101,0102,0103,0105,0106,0107,0801,0803) 1160.00 23-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Level/Gauge (INC-MRI-0001-0201,0202,0204,0205,0301)
(IN 1008.00 26-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Analysis/Transmitter (INC-MRI-0001-0302,0401,0402,0403,0404,0405)
Analysis/Transm 1000.00 27-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 15 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Desuperheater/ Deluge Valve (INC-MRI-0512/0602) 1552.00 19-Jun-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Cable Tray (INC-MRI-1110-0902)
(INC 448.00 28-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Instrument Junct
Junction Boxes (INC-MRI-1110-0903) 305.60 07-Dec-15 15:24 A 29-Jan-16 17:00 A 100% 100%
Instrument Cable (INC-MRI-1110-0901) 192.00 07-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Inst. Material (IN
(INC-MRI-1110-0904/0905/0906/0907) 192.00 25-Feb-16 08:00 A 18-Mar-16 17:00 A 100% 100%
HCDU - Hydrogen Collection
C & Distribution 6400.00 22-Aug-14 08:00 A 23-Oct-17 17:00 A 100% 100%
1520 - HCDU - Hyd Hydrogen Collection & Distribution 6400.00 22-Aug-14 08:00 A 23-Oct-17 17:00 A 100% 100%
Process 6400.00 22-Aug-14 08:00 A 23-Oct-17 17:00 A 100% 100%
Document 6400.00 22-Aug-14 08:00 A 23-Oct-17 17:00 A 100% 100%
Cause and Effect
Effec Matirx 3272.00 23-Jan-15 08:00 A 05-Sep-16 17:00 A 100% 100%
Design basis 2712.00 22-Aug-14 08:00 A 25-Dec-15 17:00 A 100% 100%
Project Equipment
Equipme List 128.00 23-Jan-15 08:00 A 13-Feb-15 17:00 A 100% 100%
Relief Valves Discharge
Dis Summary 296.00 04-Feb-15 08:00 A 31-Mar-15 17:00 A 100% 100%
Flare system simulation
sim report 1800.00 17-Feb-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Heat and Materi
Material Balance 400.00 31-Oct-14 08:00 A 09-Jan-15 17:00 A 100% 100%
Hydraulic calculation
calcula notes 976.00 15-Jun-15 08:00 A 30-Oct-15 17:00 A 100% 100%
List of alarms anand trips with set points 1784.00 12-Jun-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Operation and M Maintenance Manuals 2672.00 01-Dec-15 08:00 A 28-Mar-17 17:00 A 100% 100%
Piping interface table
t 1048.00 23-Jan-15 08:00 A 30-Jul-15 17:00 A 100% 100%
Piping Line lists 1048.00 23-Jan-15 08:00 A 30-Jul-15 17:00 A 100% 100%
Process Control Narratives 1296.00 15-Jun-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Process Data Sheet
Sh - Drums - Hydrogen Make-Up Compressor KO Drum - 1520-V-001 A/B/C/D/E 776.00 23-Jan-15 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data Sheet
Sh for Control Valves 696.00 10-Apr-15 08:00 A 11-Aug-15 17:00 A 100% 100%
Process Data Sheet
Sh for Flow Elements 960.00 10-Apr-15 08:00 A 13-Oct-15 17:00 A 100% 100%
Process Data Sh Sheet for Pressure Safety Valves 968.00 10-Apr-15 08:00 A 14-Sep-15 00:00 A 100% 100%
Process Data Sheet
Sh For Restriction Orifices Of HCDU Unit 712.00 18-Jun-15 08:00 A 13-Oct-15 17:00 A 0% 0%
Process Descriptions
Descrip 664.00 23-Jan-15 08:00 A 25-May-15 17:00 A 100% 100%
Process Interlock Description 552.00 06-Feb-15 08:00 A 19-May-15 17:00 A 100% 100%
Safeguarding Memorandum
Me 5560.00 23-Jan-15 08:00 A 23-Oct-17 17:00 A 100% 100%
Utility Consumption
Consumpt Summary 656.00 25-Nov-14 08:00 A 24-Mar-15 17:00 A 100% 100%
Drawing 3976.00 25-Aug-14 08:00 A 12-Aug-16 17:00 A 100% 100%
Material Selectio
Selection Diagrams 3480.00 25-Nov-14 08:00 A 12-Aug-16 17:00 A 100% 100%
PFD£¨H2 Make-
Make-Up Compressors ¡¢Stream Tables £© 2264.00 25-Aug-14 08:00 A 25-Sep-15 17:00 A 100% 100%
P&ID Batch 1 2776.00 25-Nov-14 08:00 A 11-Dec-15 17:00 A 100% 100%
P&ID for COC lift lif pits 2272.00 23-Jan-15 08:00 A 10-Mar-16 17:00 A 100% 100%
UIDs 1272.00 23-Jan-15 08:00 A 08-Sep-15 17:00 A 100% 100%
Etc 40.00 25-Aug-14 08:00 A 29-Aug-14 17:00 A 0% 0%
COS 40.00 25-Aug-14 08:00 A 29-Aug-14 17:00 A 0% 0%
Material, Corrison and Inspection 3864.00 30-Mar-15 08:00 A 26-Jun-17 17:00 A 100% 100%
Document 3400.00 19-Jun-15 08:00 A 26-Jun-17 17:00 A 100% 100%
RBI Excution Plan
Pla 1600.00 19-Jun-15 08:00 A 08-Mar-16 17:00 A 100% 100%
RBI Document 2304.00 04-Jan-16 08:00 A 23-Feb-17 17:00 A 100% 100%
Corrosion Design
Desig Basis Memorandum 1672.00 19-Jun-15 08:00 A 08-Mar-16 17:00 A 100% 100%
Corrosion Document
Docum 2152.00 04-Jan-16 08:00 A 26-Jun-17 17:00 A 100% 100%
RFQ 2056.00 30-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Corrosion Monitoring
Monito System 2056.00 30-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 2984.00 15-Feb-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Document 1664.00 15-Feb-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical Data Sheet for 1520-V-001ABCDE 272.00 15-Feb-15 08:00 A 07-Apr-15 17:00 A 100% 100%
Overhead Travelling
Trave Crane for 1520-K-001ABCDE 1176.00 18-May-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Drawing 2712.00 08-Apr-15 08:00 A 26-Aug-16 17:00 A 100% 100%
General Arrangement
Arrange Drawing for 1520-V-001ABCDE 664.00 08-Apr-15 08:00 A 03-Aug-15 17:00 A 100% 100%
Vendor Data Boo Book for Crane 640.00 18-Apr-16 08:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data Boo Book for Drum 1464.00 09-Sep-15 08:00 A 12-Aug-16 00:00 A 100% 100%
RFQ 1656.00 16-Feb-15 08:00 A 11-Dec-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 16 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Carbom Steel D Drums 1520-V-001A/B/C/D/E (IQ01-2015) 1144.00 16-Feb-15 08:00 A 09-Sep-15 17:00 A 100% 100%
Crane for H2 Make-Up
Ma Compressors 1520-X-001(IQ01-1009) 1168.00 19-May-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Rotating Equipment 4208.00 01-Sep-14 08:00 A 10-Nov-16 17:00 A 100% 100%
Document 1896.00 01-Sep-14 08:00 A 10-Aug-15 17:00 A 100% 100%
Mechanical data sheet for H2 MAKE-UP Compressor (IQ01-1002) 1896.00 01-Sep-14 08:00 A 10-Aug-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry for 1520-P-101A/B(IQ01-1004) 792.00 14-Nov-14 08:00 A 07-Apr-15 17:00 A 100% 100%
Drawing 1784.00 09-Oct-15 08:00 A 10-Nov-16 17:00 A 100% 100%
Vendor Data and Drawings for H2 Make-up Compressor 1472.00 30-Oct-15 08:00 A 10-Nov-16 17:00 A 100% 100%
Vendor Data and Drawings for 1520-P-101A/B 1408.00 09-Oct-15 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 2280.00 02-Sep-14 08:00 A 15-Sep-15 17:00 A 100% 100%
Requistion For Reciprocating
R Compressors (Incl. KO Drum/Interstage Cooler) (IQ01-1002) 2280.00 02-Sep-14 08:00 A 15-Sep-15 17:00 A 100% 100%
Requistion For Centrifugal
C Pump Package 1520-P-101A/B(IQ01-1004) 1568.00 17-Nov-14 08:00 A 24-Aug-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 2856.00 27-Apr-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Document 2592.00 12-Jun-15 08:00 A 16-Sep-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Conduits And Accessories 1211.20 03-Aug-15 08:00 A 22-Apr-16 11:12 A 100% 100%
MTO for Telecom
Telecommunicaiton devices 1728.00 12-Jun-15 08:00 A 20-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 1216.00 03-Aug-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Fire de detection 2432.00 10-Jul-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Telecommunication Cable Schedule
Telecommunicat 2032.00 02-Nov-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Drawing 2032.00 27-Apr-15 08:00 A 27-Apr-16 17:00 A 100% 100%
Telecommunicaiton devices location layout
Telecommunicait 2006.40 27-Apr-15 08:00 A 15-Apr-16 15:24 A 100% 100%
Telecommunicaiton Cable Routing layout
Telecommunicait 1632.00 07-Jul-15 08:00 A 27-Apr-16 17:00 A 100% 100%
RFQ 1480.00 11-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Telecommunication devices
Telecommunicat 1480.00 11-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Fire detection 1288.00 12-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Optic Fiber Cabl
Cable & Cable 280.00 02-Nov-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 2920.00 24-Nov-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Document 2208.00 02-Apr-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Safety Piping Line
Lin List - Atmospheric Residue Desulfurization Unit£¨ÐÂÔö£© 296.00 29-Apr-15 08:00 A 19-Jun-15 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1464.00 15-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Hazardous area classification schedule 1832.00 02-Apr-15 08:00 A 26-Feb-16 17:00 A 100% 100%
Noisy equipment list 656.00 10-Sep-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Safety sign spec
specification and datasheet 1376.00 21-Aug-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Deluge Nozzle Arrangment
A Calculation Note 945.60 10-Nov-15 08:00 A 23-Feb-16 17:00 A 100% 100%
Drawing 2776.00 24-Nov-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Fire Protection and
a personnel protection layout 1968.00 15-Feb-15 08:00 A 14-Jan-16 17:00 A 100% 100%
Fire water spray system P&ID 2088.00 30-Mar-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2232.00 15-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Hazardous area classification layout 2288.00 24-Nov-14 08:00 A 08-Jan-16 17:00 A 100% 100%
Temporary must
mustering areas and escape routes 1512.00 13-May-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Safety sign layout 1264.00 20-Aug-15 08:00 A 04-Mar-16 17:00 A 100% 100%
RFQ 880.00 25-Aug-15 08:00 A 16-Feb-16 17:00 A 100% 100%
spraying system(MRI-0001-7001)
system( 520.00 26-Nov-15 08:00 A 16-Feb-16 17:00 A 100% 100%
Fire water hydrant/hose
hydra box&monitor (MRI-0001-7003) 656.00 14-Sep-15 08:00 A 02-Dec-15 17:00 A 100% 100%
Portable Extinguisher(MRI-0001-7004)
Extingu 456.00 25-Aug-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Civil/Structure 4432.00 09-Feb-15 08:00 A 10-Apr-17 17:00 A 100% 100%
Document 4432.00 09-Feb-15 08:00 A 10-Apr-17 17:00 A 100% 100%
Calculation Notes
Note for Exchanger Foundation 1616.00 02-Dec-15 08:00 A 09-Sep-16 17:00 A 100% 100%
Calculation Notes
Note for Compressor Foundation 936.00 02-Dec-15 08:00 A 20-May-16 17:00 A 100% 100%
Calculation Notes
Note for RCK-1100 2616.00 09-Feb-15 08:00 A 27-May-16 17:00 A 100% 100%
Calculation Notes
Note for SHL-1100 2152.00 02-Dec-15 08:00 A 22-Dec-16 17:00 A 100% 100%
Calculation Notes
Note for 1520-STR-1100/1110/1120/1130/1140 2688.00 02-Dec-15 08:00 A 31-Mar-17 17:00 A 100% 100%
Calculation Notes
Note for 1520-STR-1200/1210/1220/1230/1240 1008.00 02-Dec-15 08:00 A 02-Jun-16 17:00 A 100% 100%
Calculation Notes
Note for Drum Foundation 2792.00 02-Dec-15 08:00 A 10-Apr-17 17:00 A 100% 100%
Calculation Notes
Note for COC PIT 1520-T-101 1248.00 22-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 17 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

MTO for Equipm


Equipment Anchor Bolts 296.00 23-Jun-15 08:00 A 12-Aug-15 17:00 A 100% 100%
MTO for Reinforcing
Reinfor Steel 424.00 07-Dec-15 08:00 A 25-Feb-16 17:00 A 100% 100%
MTO for Steel S Structure Anchor Bolts 296.00 23-Jun-15 08:00 A 12-Aug-15 17:00 A 100% 100%
MTO for Strucural
Strucur Steel 216.00 23-Jun-15 08:00 A 29-Jul-15 17:00 A 100% 100%
Drawing 3544.00 10-Feb-15 08:00 A 06-Dec-16 14:20 A 100% 100%
drawing for stormwater
storm drainage network 1560.00 27-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
surfacing and grading
gr finishing layout 2008.00 27-Apr-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Drawing - Drainage
Draina and Undeground Piping Drawing 2472.00 17-Feb-15 08:00 A 12-May-16 17:00 A 100% 100%
Equipment FounFoundations Drawings for Exchanger 1872.00 09-Dec-15 08:00 A 22-Nov-16 17:00 A 100% 100%
Equipment FounFoundations Drawings for Drum 1448.00 09-Dec-15 08:00 A 06-Dec-16 14:20 A 100% 100%
Equipment FounFoundations Drawings for Compressor 896.00 09-Dec-15 08:00 A 20-May-16 17:00 A 100% 100%
Foundations Of 1520-SHL-1100 1184.00 09-Dec-15 08:00 A 10-May-16 17:00 A 100% 100%
Foundations Of 1520-RCK-1100 1248.00 22-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Foundations Of 1520-STR-1100/1110/1120/1130/1140 1496.00 09-Dec-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Foundations Of 1520-STR-1200/1210/1220/1230/1240 1152.00 09-Dec-15 08:00 A 20-May-16 17:00 A 100% 100%
1520-RCK-1100 Steel Works£¨Columns/Beams/Details£© 912.00 24-Aug-15 08:00 A 03-Feb-16 17:00 A 100% 100%
1520-RCK-1100 Steel Works£¨Framing Plans/Elevations£© 1992.00 10-Feb-15 08:00 A 03-Feb-16 17:00 A 100% 100%
Steel Structure D Drawing For 1520-SHL-1100£¨Framing Plans/Elevations£© 712.00 30-Dec-15 08:00 A 10-May-16 17:00 A 100% 100%
Steel Structure Drawing
D For 1520-SHL-1100£¨Columns/Beams/Details) 696.00 04-Jan-16 08:00 A 10-May-16 17:00 A 0% 0%
Steel Structure Drawing
D For 1520-STR-1100/1110/1120/1130/1140£¨Framing Plans/Elevations£© 1304.00 25-Jan-16 08:00 A 02-Sep-16 17:00 A 100% 100%
Steel Structure Drawing
D For 1520-STR-1100/1110/1120/1130/1140£¨Columns/Beams/Details) 1296.00 25-Jan-16 08:00 A 02-Sep-16 17:00 A 0% 0%
Steel Structure Drawing
D For1520-STR-1200/1210/1220/1230/1240£¨Framing Plans/Elevations£© 768.00 04-Jan-16 08:00 A 25-May-16 17:00 A 100% 100%
Steel Structure Drawing
D For1520-STR-1200/1210/1220/1230/1240£¨Columns/Beams/Details) 848.00 04-Jan-16 08:00 A 15-Jul-16 17:00 A 0% 0%
COC Pit 1520-T-101
1520-T Structural Drawing 1208.00 29-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Foundation Layout
Layo for Unit 1520 2600.00 23-Jun-15 08:00 A 29-Sep-16 17:00 A 100% 100%
RFQ 304.00 22-Jun-15 08:00 A 12-Aug-15 17:00 A 100% 100%
MR for Steel Str Structure 56.00 22-Jun-15 08:00 A 30-Jun-15 17:00 A 100% 100%
equipment ancho
anchor bolts 248.00 01-Jul-15 08:00 A 12-Aug-15 17:00 A 100% 100%
steel structure an anchor bolts 248.00 01-Jul-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Architectural 1256.00 01-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Drawing 1256.00 01-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1520-SHL-1100 Elevations 848.00 01-Dec-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Compressor She Shelter 1520-SHL-1100 Ground Floor Plan 848.00 01-Dec-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Compressor She Shelter 1520-SHL-1100 Sections 848.00 01-Dec-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Compressor She Shelter 1520-SHL-1100 Roof Plan 840.00 02-Dec-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Compressor She Shelter 1520-SHL-1100 Detail Drawing 904.00 02-Feb-16 08:00 A 15-Apr-16 17:00 A 0% 0%
Piping 4576.00 25-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Document 3096.00 30-Mar-15 08:00 A 30-Dec-16 15:00 A 100% 100%
Critical line list 1176.00 30-Mar-15 08:00 A 05-Nov-15 17:00 A 100% 100%
Piping Stress Calculations
Ca and analysis report 2492.00 04-Jun-15 08:00 A 30-Dec-16 15:00 A 100% 100%
Pipe support lists(Standard
lists and Special) 720.00 12-Oct-15 08:00 A 19-Jan-16 17:00 A 100% 100%
Spring list and datasheet
da 1648.00 14-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Steam Tracing List L 624.00 21-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Data Sheets for Safety Valve 1048.00 10-Apr-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Data Sheets for sampler 600.00 10-Apr-15 08:00 A 24-Jul-15 17:00 A 100% 100%
MTO for U/G Pipe Pip System 1064.00 10-Nov-15 08:00 A 20-May-16 17:00 A 100% 100%
MTO for Piping Insulation 1416.00 24-Dec-15 08:00 A 30-Aug-16 17:00 A 100% 100%
MTO for Piping B Bulk Material 328.00 24-Dec-15 08:00 A 07-Jan-16 17:00 A 100% 100%
MTO for Piping P Painting 1416.00 24-Dec-15 08:00 A 30-Aug-16 17:00 A 100% 100%
MTO for Special Items 1424.00 24-Dec-15 08:00 A 30-Aug-16 17:00 A 100% 100%
Drawing 4576.00 25-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
3D-Model Review&Action
Revie Close-out Report 3944.00 27-Oct-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Above Ground Piping P GA Key Plan 376.00 15-Feb-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Key Plan of Equipment
Equi Layout 2656.00 10-Nov-14 08:00 A 29-Jan-16 17:00 A 100% 100%
Equipment LayoLayout(Area A/Area B/Area A Section A-A, Area B Section B-B ) 1944.00 15-Feb-15 08:00 A 01-Feb-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 18 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

ISO drawing for U/G piping and list 584.00 03-Dec-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Piping General Arrangement
A drawings 664.00 04-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Piping Isometric Drawings(with Materials) and list 1432.00 03-Dec-15 08:00 A 26-Feb-16 17:00 A 100% 100%
Piping battery limit
lim interface table 1408.00 06-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Special Pipe Support
Sup Drawing and list 2320.00 11-Oct-15 08:00 A 29-Nov-16 17:00 A 100% 100%
1520 - Hydrogen Collection And Distribution Unit - Unit Plot Plan 2920.00 25-Aug-14 08:00 A 11-Dec-15 17:00 A 100% 100%
ISO drawing for U/G piping 576.00 04-Dec-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Vendor Data and Drawings for Misc. Piping Equipment (Sampler) 584.00 01-Jul-16 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 2880.00 06-Apr-15 08:00 A 30-Aug-16 17:00 A 100% 100%
MR for Blanket Order
O of Piping/Fitting/Valve 336.00 06-Apr-15 08:00 A 03-Jun-15 17:00 A 100% 100%
Safety Valve 1640.00 13-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Misc. Piping Equ
Equipment£¨Sampler£© 736.00 14-Apr-15 08:00 A 20-Aug-15 17:00 A 100% 100%
Spring Hanger 208.00 20-Nov-15 08:00 A 25-Dec-15 17:00 A 100% 100%
1st Piping Valves 696.00 15-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
1st U/G Piping 352.00 01-Jul-15 08:00 A 31-Aug-15 17:00 A 100% 100%
MR for U/G GRP bulk material 528.00 06-Apr-15 08:00 A 15-May-15 17:00 A 100% 100%
U/G valves 552.00 25-Aug-15 08:00 A 27-Nov-15 17:00 A 100% 100%
1st Piping/Fitting/Flange
Piping/Fitting 200.00 23-Nov-15 08:00 A 25-Dec-15 17:00 A 100% 100%
1st Piping Support
Suppo 752.00 04-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
2nd Piping/Valves/Fitting
Piping/Valve 88.00 11-Apr-16 08:00 A 15-Apr-16 17:00 A 100% 100%
2nd Piping Support
Supp 120.00 15-Aug-16 08:00 A 30-Aug-16 17:00 A 100% 100%
Etc 2424.00 26-Jan-15 08:00 A 16-Aug-16 00:00 A 0% 0%
COS 2424.00 26-Jan-15 08:00 A 16-Aug-16 00:00 A 0% 0%
Electrical 3808.00 03-Nov-14 08:00 A 16-Sep-16 17:00 A 100% 100%
Document 3800.00 03-Nov-14 08:00 A 08-Sep-16 17:00 A 100% 100%
BLIT of Cables 920.00 04-Aug-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Data Sheet For Synchronous Motor For Compressors 1520-KM-001A/B/C/D/E 1528.00 03-Nov-14 08:00 A 03-Aug-15 17:00 A 100% 100%
Data Sheet For Cage Induction Machine - LV Hydrogen Collection & Disribution Unit 1520-PM-101A/B 936.00 15-Feb-15 08:00 A 03-Aug-15 17:00 A 100% 100%
Electrical Cable Drum
D Schedule 720.00 17-Nov-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Electrical Cable List
L 1504.00 22-May-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Hydrogen Collection
Collec & Distribution (1520) Electrical Consumer List 2088.00 15-Feb-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Material Take Of Off For Earthing And Lightning Material 960.00 17-Nov-15 08:00 A 10-May-16 17:00 A 100% 100%
Material Take OffOf For Cable 1224.00 17-Nov-15 08:00 A 24-Jun-16 17:00 A 100% 100%
Material Take Of Off For Cable Ladder And Cable Tray 720.00 18-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Material Take OffOf For other material 1736.00 10-Nov-15 08:00 A 08-Sep-16 17:00 A 100% 100%
Drawing 3216.00 15-Feb-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Cathodic Protection
Protect System Layout 216.00 11-Jan-16 08:00 A 22-Jan-16 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 2120.00 27-Apr-15 08:00 A 13-May-16 17:00 A 100% 100%
Electrical Heat Tracing
T Layout 256.00 04-Jan-16 08:00 A 22-Jan-16 17:00 A 100% 100%
Lighting Layout (Unit/Street)
( 880.00 04-Jan-16 08:00 A 10-Jun-16 17:00 A 100% 100%
Lighting Loop Diagram
Di 1144.00 17-Nov-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout (Underground) 2496.00 15-Feb-15 08:00 A 13-May-16 17:00 A 100% 100%
Lighting And Small
Sm Power Distribution Panel Single Line Diagram 1152.00 04-Jan-16 08:00 A 10-Jun-16 17:00 A 100% 100%
Wiring / Interconection
Intercon Diagram 1280.00 01-Feb-16 08:00 A 16-Sep-16 17:00 A 100% 100%
Interface Drawing
Drawin Of Earthing System 712.00 13-Aug-15 08:00 A 04-Dec-15 17:00 A 100% 100%
RFQ 1432.00 02-Nov-15 08:00 A 15-Jul-16 17:00 A 100% 100%
Earthing and lightning
ligh material 248.00 23-Nov-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch 152.00 10-Dec-15 08:00 A 06-Jan-16 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 408.00 19-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable 184.00 02-Nov-15 08:00 A 02-Dec-15 17:00 A 100% 100%
Conduit And Accessories
Acc 736.00 08-Mar-16 08:00 A 15-Jul-16 17:00 A 100% 100%
Cathodic Protection
Protect 312.00 04-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Elec. Heat Tracing
Tracin 280.00 04-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Lighting Fixtures 248.00 04-Jan-16 08:00 A 22-Jan-16 17:00 A 100% 100%
Other Material(Steel/
Material(S Termination Kit/Cable Joint/Cable Gland/Seal Material) 560.80 08-Mar-16 08:00 A 16-Jun-16 08:48 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 19 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Instrumentation an and control 3888.00 23-Jan-15 08:00 A 18-Oct-16 17:00 A 100% 100%
Document 3440.00 23-Jan-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Cable Drum Sch Schedules 576.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Alarm rationalisa
rationalisation study report and alarm reference data base 1576.00 24-Dec-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Analyser Sample System Transportation times 328.00 24-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Calculation for Cable
C Sizeing/Selection 616.00 25-Dec-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Configuration Data
Da for Machine Monitoring System and Performance Monitoring System 328.00 25-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Datasheet for Co Control Valve (Globe) 1632.00 17-Feb-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Datasheet for Co Control Valve (Rotary) 1632.00 17-Feb-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Datasheet for Deluge
De Valve 1776.00 25-May-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Datasheet for O Oil in Water Analyser 1024.00 25-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Displacer
Di Level Instrument 728.00 25-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for DP Flow Transmitter 976.00 25-May-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Magnetic
M Level Gauge 816.00 25-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Le Level Transmitter Radar Type 808.00 26-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Variable
Va Area Flow Meter 1088.00 26-May-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Datasheet for DP Transmitter 816.00 25-May-15 08:00 A 30-Sep-15 17:00 A 100% 100%
Datasheet for Flow
Fl Element - Restriction Orifice 880.00 17-Jun-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Fl Flow Element-Venturi Tube 1192.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Flow
Fl Element-Nozzle 1192.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Vo Votex Flow Meter 672.00 18-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
Datasheet for GasG Detector 1528.00 24-Mar-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Level
Le Gauge 816.00 25-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Orifice
O Plate 1240.00 22-Apr-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Pressure
Pr Gauge 816.00 25-May-15 08:00 A 06-Nov-15 17:00 A 100% 100%
Datasheet for Pressure
Pr Transmitter 816.00 25-May-15 08:00 A 30-Sep-15 17:00 A 100% 100%
Datasheet for Te Temperature Transmitter 1192.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Thermometer
Th 1192.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Thermowell
Th 864.00 22-Apr-15 08:00 A 23-Oct-15 17:00 A 100% 100%
DCS Group Displays
Disp & Reports 848.00 24-Dec-15 08:00 A 27-May-16 17:00 A 100% 100%
Instrument Air C Consumption Calculations 352.00 18-Feb-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Instrument Cable Schedules 576.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Instrument Index 144.00 23-Jan-15 08:00 A 16-Feb-15 17:00 A 100% 100%
Instrument NamName Plate Schedules 896.00 12-Oct-15 08:00 A 23-Feb-16 17:00 A 100% 100%
Intrinsically Safe(IS)
Safe( Loop Calculations 1520.00 25-Dec-15 08:00 A 15-Sep-16 17:00 A 100% 100%
IPF classification
classifications, verification reports 1520.00 08-Jul-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Junction Box Schedules
Sch 584.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Level Instrumen
Instrument Nozzel Elevations Caculation 1016.00 15-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Power Feeds List Lis with Power Consumption for UPS and non-UPS Consumers 368.00 08-May-15 08:00 A 10-Jul-15 17:00 A 100% 100%
Sizing Calculations
Calculatio for Control Valves 584.00 24-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Sizing Calculations
Calculatio for Flow Elements 464.00 01-Sep-15 08:00 A 12-Jan-16 17:00 A 100% 100%
System I/O LIST 152.00 23-Jan-15 08:00 A 17-Feb-15 17:00 A 100% 100%
Thermowell Wak Wake Frequency Calculations 544.00 24-Dec-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Material Take Of Off£¨Bulk Items/Cable Tray/Cable/Junction Box/Valve£© 456.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Drawing 3384.00 27-Apr-15 08:00 A 18-Oct-16 17:00 A 100% 100%
Graphic Display Sketches 648.00 20-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Instrument Cable trays/trench layouts with cable cross section 1808.00 26-Nov-15 08:00 A 18-Oct-16 17:00 A 100% 100%
Instrument Earth
Earthing Layouts 1056.00 27-Oct-15 00:00 A 12-Jul-16 17:00 A 100% 100%
Instrument hook
hook-up drawings£¨process and pneumatic) 1640.00 15-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Instrument Loop Diagrams 400.00 11-Mar-16 08:00 A 20-May-16 17:00 A 100% 100%
Instrument Main Cable Routing 1560.00 27-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Junction Box Wiring
W Diagrams 1608.00 15-Jun-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Instrument Air D Distribution Layouts 1136.00 27-Oct-15 00:00 A 20-May-16 17:00 A 100% 100%
Instrument Location
Loca Layouts 2376.00 26-Oct-15 08:00 A 23-Jun-16 17:00 A 100% 100%
Shutdown and LogicL Diagrams 928.00 22-Sep-15 08:00 A 08-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 20 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

RFQ 2256.00 18-Feb-15 08:00 A 05-Apr-16 17:00 A 100% 100%


Control Valves (INC-MRI-1520-0501/0502)
( 1032.00 18-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Orifice Plate/Flow Element/Temperature Element (INC-MRI-1520-0101/0103/0401) 1184.00 23-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Level/Gauge (INC-MRI-1520-0202/0205/0301)
(IN 1008.00 26-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Analysis/Transmitter/Deluge Valve (INC-MRI-1520-0302/0401/0804)
Analysis/Transm 1752.00 25-May-15 08:00 A 05-Apr-16 17:00 A 100% 100%
Cable Tray (INC-MRI-1520-0901)
(INC 280.00 27-Jan-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Inst. Cable (INC-MRI-1520-0902)
(INC 168.00 20-Nov-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Junction Box (INC-MRI-1520-0903)
(IN 192.00 11-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Inst. Tube&Tube Fitting/ Inst. Pipe & Fitting/Valves/ Bulk Items (INC-MRI-1520-0904/0905/0906/907 280.00 27-Jan-16 08:00 A 18-Mar-16 17:00 A 100% 100%
FOS - Fuel Oil Syste
System 6704.00 22-Aug-14 08:00 A 14-Dec-17 17:00 A 100% 100%
4550-FOS - Fuel O Oil System 6704.00 22-Aug-14 08:00 A 14-Dec-17 17:00 A 100% 100%
Process 6704.00 22-Aug-14 08:00 A 14-Dec-17 17:00 A 100% 100%
Document 6112.00 10-Dec-14 08:00 A 14-Dec-17 17:00 A 100% 100%
Hydraulic calculation
calcula notes - Unit 4550 - Fuel Oil System 2656.00 22-Jun-15 08:00 A 12-Oct-16 17:00 A 100% 100%
Process Data SheetSh - Control Valves - Unit 4550 - Fuel Oil System 1520.00 13-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Process Data SheetSh - Analyzers- Unit 4550 - Fuel Oil System 544.00 22-Jun-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Hydraulic calculation
calcula notes for pumps - Unit 4550 - Fuel Oil System 1248.00 13-Apr-15 08:00 A 08-Sep-15 17:00 A 100% 100%
Process Data SheetSh - Mixer - Unit 4550 Fuel Oil Tank Mixer 4550-M-001 1312.00 16-Feb-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Process Data SheetSh - Flow Elements- Unit 4550 - Fuel Oil System 2240.00 13-Apr-15 08:00 A 20-May-16 17:00 A 100% 100%
Process Data SheetSh - Pressure Safety Valves - Unit 4550 - Fuel Oil System 1432.00 13-Apr-15 08:00 A 23-Dec-15 17:00 A 100% 100%
Utility Consumption
Consumpt Summary - Unit 4550 - Fuel Oil System 2048.00 16-Feb-15 08:00 A 08-Oct-15 17:00 A 100% 100%
List - Piping Inter
Interface Table - Unit 4550 Process/Utility 2176.00 10-Dec-14 08:00 A 06-Jan-16 17:00 A 100% 100%
Process Effluent List - Unit 4550 - Fuel Oil System 856.00 16-Feb-15 08:00 A 21-Jul-15 17:00 A 100% 100%
Process Interlock Description - Unit 4550 - Fuel Oil System 1352.00 16-Feb-15 08:00 A 16-Oct-15 17:00 A 100% 100%
Process and Control
Con Description - Unit 4550 - Fuel Oil System 1272.00 16-Feb-15 08:00 A 07-Sep-15 17:00 A 100% 100%
Project Equipment
Equipme List - Unit 4550 - Fuel Oil System 112.00 16-Feb-15 08:00 A 11-Mar-15 17:00 A 100% 100%
Process Data SheetSh for Air Cooler PCC Atmospheric Condensate Flash Drum Condenser 4550-E-002 1424.00 16-Feb-15 08:00 A 27-Oct-15 17:00 A 100% 100%
Process Data SheetSh for Drums PCC Atmospheric Condensate Flash Drum 4550-V-002 768.00 16-Feb-15 08:00 A 06-Jul-15 17:00 A 100% 100%
Process Data SheetSh - Tanks - Unit 4550 Fuel Oil Storage Tank 4550-T-001 768.00 16-Feb-15 08:00 A 06-Jul-15 17:00 A 100% 100%
Process Data SheetSh for Heavy Slops Drain Drum 4550-V-001 768.00 16-Feb-15 08:00 A 06-Jul-15 17:00 A 100% 100%
Process Data SheetSh - Filters - Unit 4550 Fuel Oil Filters 4550-S-001A/B 1272.00 16-Feb-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Process Data SheetSh - Shell and Tube Heat Exchangers - Unit 4550 - Fuel Oil Heaters 4550-E-001A/B 1488.00 16-Feb-15 08:00 A 12-Nov-15 17:00 A 100% 100%
Process Design Basis - Unit 4550 - Fuel Oil System 1864.00 06-Mar-15 08:00 A 02-Feb-16 17:00 A 100% 100%
Relief Valves Discharge
Dis Summary - Unit 4550 - Fuel Oil System 856.00 16-Feb-15 08:00 A 21-Jul-15 17:00 A 100% 100%
Piping Line List - Fuel Oil System Unit 1808.00 16-Feb-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Cause and Effect
Effec Chart/Diagram - Unit 4550 - Fuel Oil System 1496.00 17-Mar-15 08:00 A 16-Oct-15 17:00 A 100% 100%
Process Data Sh Sheet - On/Off Valves - Fuel Oil System, Unit 4550 1520.00 13-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Safeguarding Memorandum
Me 5056.00 19-Jun-15 08:00 A 14-Dec-17 17:00 A 100% 100%
List of alarms anand trips with set points 2024.00 12-Jun-15 08:00 A 20-May-16 17:00 A 100% 100%
Operation and M Maintenance Manual 1944.00 15-Mar-16 08:00 A 28-Feb-17 17:00 A 100% 100%
Drawing 4192.00 22-Aug-14 08:00 A 15-Sep-16 17:00 A 100% 100%
UFD Batch2-FO
Batch2-FOS Atmospheric condensate 3608.00 09-Dec-14 08:00 A 15-Sep-16 17:00 A 100% 100%
PFD 2784.00 22-Aug-14 08:00 A 08-Jan-16 17:00 A 100% 100%
UFD Batch1-FOS
Batch1-FO HEAVY SLOPS DRAIN SYSTEM - DESIGN CASE 2456.00 09-Dec-14 08:00 A 26-Feb-16 17:00 A 100% 100%
PIDs 2064.00 09-Dec-14 08:00 A 11-Dec-15 17:00 A 100% 100%
UIDs 1688.00 16-Feb-15 08:00 A 14-Oct-15 17:00 A 100% 100%
Material Selectio
Selection Diagram(MSD) 912.00 16-Feb-15 08:00 A 24-Nov-15 17:00 A 100% 100%
RFQ 1688.00 03-Apr-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Requisition for Mixer 4550-M-001 760.00 03-Apr-15 08:00 A 14-Aug-15 17:00 A 100% 100%
Requisition for Mixer 4550-M-002 1240.00 23-Jun-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Etc 80.00 27-Feb-15 08:00 A 11-Mar-15 17:00 A 0% 0%
COS 80.00 27-Feb-15 08:00 A 11-Mar-15 17:00 A 0% 0%
Material, Corrison and Inspection 4304.00 13-Apr-15 08:00 A 25-May-17 17:00 A 100% 100%
Document 3368.00 11-Sep-15 08:00 A 25-May-17 17:00 A 100% 100%
Corrosion Design
Desig Basis Memorandum 552.00 07-Jan-16 08:00 A 09-Mar-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 21 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Material Selection
Selectio Guide 2096.00 14-Sep-15 08:00 A 09-Sep-16 17:00 A 100% 100%
RBI Documents 2824.00 03-Dec-15 08:00 A 26-Apr-17 17:00 A 100% 100%
RBI Excution Plan
Pla 1184.00 11-Sep-15 08:00 A 08-Mar-16 17:00 A 100% 100%
Corrosion Documents
Docum 2544.00 25-Feb-16 08:00 A 25-May-17 17:00 A 100% 100%
Drawing 1992.00 16-Oct-15 08:00 A 19-May-17 17:00 A 100% 100%
Vendor Data and Drawings 1992.00 16-Oct-15 08:00 A 19-May-17 17:00 A 100% 100%
RFQ 1480.00 13-Apr-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Corrosion Monitoring
Monito System 1480.00 13-Apr-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 3216.00 16-Feb-15 08:00 A 05-Dec-16 08:00 A 100% 100%
Document 2336.00 16-Feb-15 08:00 A 01-Feb-16 17:00 A 100% 100%
Mechanical data sheet for4550-T-001 Fuel Oil Storage Tank 1616.00 17-Feb-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Mechanical Data Sheet - Shell and Tube Heat Exchangers - Fuel Oil Heaters 4550-E-001A/B 1040.00 16-Feb-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Mechanical data sheet for Air Coolers 4550-E-002 1624.00 16-Feb-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Mechanical data sheet for Drums-Heavy Slops Drain Drum and PCC Atmospheric Condensate Flash Drum 216.00 27-Feb-15 08:00 A 03-Apr-15 17:00 A 100% 100%
Mechanical data sheet for Mixer - Unit 4550 Fuel Oil Static Mixer 4550-M-001 1656.00 22-Jun-15 08:00 A 01-Feb-16 17:00 A 100% 100%
Drawing 2968.00 06-Apr-15 08:00 A 05-Dec-16 08:00 A 100% 100%
General Arrangement
Arrange Drawing for T-001 696.00 17-Jul-15 08:00 A 28-Sep-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for V-001 1408.00 06-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for V-002 632.00 07-Jul-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Vendor Data and Drawings for Exchangers (IQ01-2020) 4550-E-001A/B 1120.00 09-Oct-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for Storage Tank4550-T-001 48.00 01-Sep-16 08:00 A 05-Dec-16 08:00 A 100% 100%
Vendor Data and Drawings for Air cooler (IQ01-2022) 4550-E-002 1200.00 22-Sep-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for Drums (IQ01-2015) 4550-V-001/002 1120.00 28-Sep-15 08:00 A 12-Aug-16 00:00 A 100% 100%
RFQ 1488.00 16-Feb-15 08:00 A 28-Sep-15 17:00 A 100% 100%
Exchanger (IQ01-2020)
(IQ0 1256.00 16-Feb-15 08:00 A 07-Sep-15 17:00 A 100% 100%
Air cooler (IQ01-2022)
(IQ01- 1456.00 27-Feb-15 08:00 A 07-Sep-15 17:00 A 100% 100%
Fuel Oil Storage Tank (IQ01-2007) 1456.00 27-Feb-15 08:00 A 28-Sep-15 17:00 A 100% 100%
Carbom Steel D Drums (IQ01-2015) 1008.00 06-Apr-15 08:00 A 09-Sep-15 17:00 A 100% 100%
Etc 56.00 23-Oct-15 08:00 A 02-Nov-15 17:00 A 0% 0%
COS 56.00 23-Oct-15 08:00 A 02-Nov-15 17:00 A 0% 0%
Rotating Equipment 2720.00 16-Feb-15 08:00 A 10-Nov-16 17:00 A 100% 100%
Document 24.00 16-Feb-15 08:00 A 18-Feb-15 17:00 A 100% 100%
Mechanical data sheet for Pump 24.00 16-Feb-15 08:00 A 18-Feb-15 17:00 A 100% 100%
Drawing 1400.00 15-Oct-15 08:00 A 10-Nov-16 17:00 A 100% 100%
Vendor Data and Drawings for Pumps ¡¾IQ01-1004¡¿ 1400.00 15-Oct-15 08:00 A 10-Nov-16 17:00 A 100% 100%
RFQ 1208.00 18-Feb-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Pump (IQ01-100
(IQ01-1004) 1208.00 18-Feb-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 3032.00 25-Mar-15 08:00 A 19-Sep-16 17:00 A 100% 100%
Document 3032.00 25-Mar-15 08:00 A 19-Sep-16 17:00 A 100% 100%
MTO for Fire de detection 2208.00 25-Mar-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices 1952.00 11-May-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 1232.00 04-Sep-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Conduits And Accessories 1072.00 09-Sep-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Telecommunication Cable Schedule
Telecommunicat 2056.00 04-Sep-15 08:00 A 19-Sep-16 17:00 A 100% 100%
Drawing 2040.00 28-Apr-15 08:00 A 27-Apr-16 17:00 A 100% 100%
layout for Teleco
Telecommunicaiton devices location 2040.00 28-Apr-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Telecommunicaiton Cable Routing layout
Telecommunicait 1632.00 07-Jul-15 08:00 A 27-Apr-16 17:00 A 100% 100%
RFQ 1472.00 26-Mar-15 08:00 A 03-Dec-15 17:00 A 100% 100%
detection 1392.00 26-Mar-15 08:00 A 30-Nov-15 17:00 A 100% 100%
devices 800.00 12-May-15 08:00 A 21-Oct-15 17:00 A 100% 100%
Cable 496.00 07-Sep-15 08:00 A 03-Dec-15 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 3040.00 28-Oct-14 08:00 A 25-Mar-16 17:00 A 100% 100%
Document 2256.00 05-Mar-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Hazardous area classification schedule 1832.00 02-Apr-15 08:00 A 26-Feb-16 17:00 A 100% 100%
List of items to be
b fireproofed 1456.00 05-Mar-15 08:00 A 19-Nov-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 22 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Fire and gas cause


cau and effect matrix 1328.00 08-Jul-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Noisy equipment list 424.00 10-Sep-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Safety sign spec
specification and datasheet 1840.00 19-May-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Effluents inventory
invento (gaseous, liquid, solid waste) 1704.00 09-Mar-15 08:00 A 21-Oct-15 17:00 A 100% 100%
Safety piping Lin
Line List 880.00 12-Jun-15 08:00 A 17-Nov-15 17:00 A 100% 100%
MTO for fire figh
fighting equipment 896.00 17-Aug-15 08:00 A 16-Feb-16 17:00 A 100% 100%
Drawing 3040.00 28-Oct-14 08:00 A 25-Mar-16 17:00 A 100% 100%
Fireproofing zone
zon layout 2721.60 28-Oct-14 08:00 A 08-Jan-16 17:00 A 100% 100%
Hazardous area classification layout 2552.00 28-Oct-14 08:00 A 28-Jan-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2224.00 16-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Temporary must
mustering areas and escape routes layout 1768.00 06-Apr-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Safety sign layout 1432.00 12-Aug-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Safety Drawing - Fire Protection and Personnel Protection 2328.00 11-Nov-14 08:00 A 19-Nov-15 17:00 A 100% 100%
RFQ 840.00 18-Aug-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Fire water monitor
monit 720.00 18-Aug-15 08:00 A 11-Nov-15 17:00 A 100% 100%
Fire Extinguisher 800.00 18-Aug-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Civil/Structure 3472.00 20-Mar-15 08:00 A 02-Dec-16 17:00 A 100% 100%
Document 3152.00 18-May-15 08:00 A 02-Dec-16 17:00 A 100% 100%
Calculation Notes
Note For 4550-SLP-1100 Foundation 2336.00 17-Aug-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Calculation Notes
Note for Mixer 4550-M-001 Foundation 544.00 16-Sep-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for Pipe Rack 1216.00 18-May-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for 4550-E-001A/B Foundation 1168.00 02-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for Underground Pit Foundation (4550-V-001) 2680.00 02-Jun-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Calculation Notes
Note for 4550-T-001 Foundation 3040.00 02-Jun-15 08:00 A 29-Nov-16 17:00 A 100% 100%
Calculation Notes
Note for 4550-STR-1100 1984.00 02-Jun-15 08:00 A 25-May-16 17:00 A 100% 100%
Calculation Notes
Note for Pump Foundation 2192.00 05-Nov-15 08:00 A 02-Dec-16 17:00 A 100% 100%
Calculation Notes
Note for Mixer and Filter 4550-M-001/S-001 FOUNDATION 784.00 16-Sep-15 08:00 A 04-Feb-16 17:00 A 100% 100%
MTO for Steel S Structure Anchor Bolts 496.00 19-May-15 08:00 A 12-Aug-15 17:00 A 100% 100%
MTO for Reinforcing
Reinfor Steel 432.00 04-Nov-15 08:00 A 11-Dec-15 11:12 A 100% 100%
MTO for Equipm
Equipment Anchor Bolts 376.00 03-Jun-15 08:00 A 06-Aug-15 17:00 A 100% 100%
MTO for Structu
Structural Steel 336.00 02-Jun-15 08:00 A 29-Jul-15 17:00 A 100% 100%
Drawing 3136.00 20-Mar-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Structure Drawings
Drawin for Structure 4550-STR-1110£¨Detail£© 1752.00 03-Jun-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Steel Works for Pipe Rack(Elevations/ Framing Plans) 1552.00 28-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of 4550
45 2640.00 03-Jun-15 08:00 A 19-Sep-16 17:00 A 100% 100%
Foundation Drawings
Draw of 4550-S-001A,001B 1808.00 02-Jun-15 08:00 A 02-Dec-15 17:00 A 100% 100%
Foundations Drawings
Dra for Pipe Rack 4550-SLP-1100 2272.00 18-Aug-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Pile Layout of 4550-T-001
45 1112.00 03-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Drawing - Drainage
Draina and Underground Piping - Unit 4550 - Fuel Oil System 1504.00 20-Mar-15 08:00 A 14-Dec-15 17:00 A 100% 100%
Foundations Drawings
Dra for Pipe Rack 1168.00 19-May-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Equipment Foun
Foundations Drawings for Heat Exchanger 1168.00 02-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Foundation of 4550-T-001
45 952.00 02-Jun-15 08:00 A 17-Nov-15 17:00 A 100% 100%
Foundation of 4550-M-001
45 1136.00 02-Jun-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Drawing for Retention
Rete Wall 1808.00 02-Jun-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Foundations Drawings
Dra for Structure 4550-STR-1110 1200.00 02-Jun-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Steel Works for Pipe Rack(Columns/ Beams/ Details) 1565.60 18-May-15 08:00 A 27-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for Structure 4550-STR-1110(Elevations/ Framing Plans/Columns) 1288.00 02-Jun-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Equipment Foundations
Foun Drawings for Pump 1848.00 06-Nov-15 08:00 A 22-Sep-16 17:00 A 100% 100%
4550-V-001 Undrground
Und Pit Drawing 1264.00 03-Nov-15 08:00 A 01-Jul-16 17:00 A 100% 100%
Surfacing and grading
gr finishing layout 1816.00 01-Jun-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Foundation Layout
Layo for Unit 4550 1016.00 01-Apr-16 08:00 A 23-Sep-16 17:00 A 100% 100%
RFQ 1040.00 18-May-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Requisition for Steel
S Structure 744.00 18-May-15 08:00 A 29-Jul-15 17:00 A 100% 100%
Equipment anch
anchor bolts 944.00 03-Jun-15 08:00 A 07-Aug-15 17:00 A 100% 100%
Steel structure a anchor bolts 712.00 03-Jun-15 08:00 A 12-Aug-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 23 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Piping 4240.00 05-Sep-14 08:00 A 17-Feb-17 17:00 A 100% 100%


Document 3344.00 16-Feb-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Data Sheets for Sampler 880.00 16-Feb-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheets for Strainer (4550-S-001A/B) 232.00 22-Jun-15 08:00 A 30-Jul-15 17:00 A 100% 100%
Data Sheets for Safety Valve 1640.00 13-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Piping Stress Calculations
Ca and analysis report 2080.00 08-Oct-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Data Sheets for Sight Glass 880.00 16-Feb-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Critical line list 976.00 13-Apr-15 08:00 A 29-Sep-15 17:00 A 100% 100%
Pipe support lists(Standard
lists and Special) 1936.00 13-Apr-15 08:00 A 19-Jan-16 17:00 A 100% 100%
Spring list and dateda sheet 1928.00 27-Oct-15 08:00 A 15-Apr-16 17:00 A 100% 100%
MTO for U/G pip pipe system 1560.00 05-Nov-15 08:00 A 11-Aug-16 17:00 A 100% 100%
Steam Tracing List L 1496.00 07-Dec-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Material Take Off Of for Insulation 592.00 19-May-16 08:00 A 30-Aug-16 17:00 A 100% 100%
Material Take Of Off for Special Item 96.00 01-Aug-16 08:00 A 31-Aug-16 17:00 A 100% 100%
Material Take Off Of for Piping Painting 592.00 19-May-16 08:00 A 30-Aug-16 17:00 A 100% 100%
Material Take Off Of for Piping Bulk Material 256.00 07-Dec-15 08:00 A 20-Jan-16 17:00 A 100% 100%
Drawing 4112.00 05-Sep-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Vendor Data and Drawings for Misc. Piping Equipment 752.00 11-May-16 08:00 A 25-Aug-16 17:00 A 100% 100%
UNIT PLOT PLAN PLA - FUEL OIL SYSTEM 2552.00 05-Sep-14 08:00 A 11-Dec-15 17:00 A 100% 100%
3D-Modeling/review report/action close-out-report
3D-Modeling/rev 3552.00 27-Oct-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Above Ground Piping P GA key plan 584.00 16-Feb-15 08:00 A 03-Jun-15 17:00 A 100% 100%
Equipment Layout
Layo 2592.00 28-Oct-14 08:00 A 01-Feb-16 17:00 A 100% 100%
Piping Battery Limit
Li Interface Table 1368.00 13-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Special Pipe Support
Sup Drawing and list 1600.00 04-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
ISO Drawing for U/G Piping and list 728.00 04-Dec-15 08:00 A 22-Feb-16 17:00 A 100% 100%
ISO Drawing for U/G Piping 544.00 04-Dec-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Piping Isometric Drawings(with Materials) and list 1640.00 04-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Piping General Arrangement
A drawings 640.00 04-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
RFQ 2664.00 13-Apr-15 08:00 A 03-Aug-16 17:00 A 100% 100%
MR for Blanket Order O of Piping/Fitting/Valve 296.00 13-Apr-15 08:00 A 03-Jun-15 17:00 A 100% 100%
Safty Valves 1632.00 14-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Misc. Piping EquEquipment 328.00 25-Jun-15 08:00 A 20-Aug-15 17:00 A 100% 100%
Spring Hanger 1032.00 07-Dec-15 08:00 A 25-Dec-15 17:00 A 100% 100%
1st Piping Valves 592.00 22-Jun-15 08:00 A 20-Aug-15 17:00 A 100% 100%
1st U/G Piping 808.00 28-Apr-15 08:00 A 31-Aug-15 17:00 A 100% 100%
MR for U/G GRP bulk material 888.00 28-Apr-15 08:00 A 15-May-15 17:00 A 100% 100%
U/G valves 1016.00 01-Jun-15 08:00 A 27-Nov-15 17:00 A 100% 100%
1st Piping/Fitting/Flange
Piping/Fitting 120.00 04-Dec-15 08:00 A 25-Dec-15 17:00 A 100% 100%
1st Piping Support
Suppo 808.00 02-Jun-15 08:00 A 23-Oct-15 17:00 A 100% 100%
2nd Piping/Valves/Fitting
Piping/Valve 680.00 14-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
2nd Piping Supp
Support/Insulation 440.00 19-May-16 08:00 A 03-Aug-16 17:00 A 100% 100%
Etc 1176.00 16-Feb-15 08:00 A 15-Sep-15 17:00 A 0% 0%
COS 1176.00 16-Feb-15 08:00 A 15-Sep-15 17:00 A 0% 0%
Electrical 3224.00 16-Feb-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Document 2976.00 16-Feb-15 08:00 A 08-Aug-16 17:00 A 100% 100%
BLIT-Electrical Cables/Civel/Electrical
C Cable Trench 1928.00 26-Feb-15 08:00 A 03-Feb-16 17:00 A 100% 100%
Data Sheet For Cage Induction Machine - 4550-PM001/PM002/PM003/E002 880.00 16-Feb-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Electrical Cable DrumD Schedule 712.00 18-Nov-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Electrical Cable ListL 998.40 31-Aug-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Electrical Consumer
Consum List 1624.00 12-Mar-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Material Take Of Off For Earthing And Lightning Material 936.00 18-Nov-15 00:00 A 10-May-16 17:00 A 100% 100%
Material Take Off Of For Cable 1192.00 18-Nov-15 08:00 A 25-May-16 17:00 A 100% 100%
Material Take Of Off For Cable Ladder And Cable Tray 1592.00 10-Aug-15 08:00 A 25-May-16 17:00 A 100% 100%
Material Take Off Of For other material 1784.00 18-Sep-15 08:00 A 08-Aug-16 17:00 A 100% 100%
Drawing 2848.00 28-Apr-15 08:00 A 14-Sep-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 24 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Cathodic Protection
Protect System Layout 1008.00 30-Dec-15 08:00 A 03-Jun-16 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 1072.00 28-Apr-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Electrical Heat Tracing
T Layout 200.00 12-Jan-16 08:00 A 22-Jan-16 17:00 A 100% 100%
Lighting Layout (Unit/Street)
( 1472.00 16-Sep-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Lighting Loop Diagram
Di 1464.00 17-Sep-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout 704.00 28-Apr-15 08:00 A 28-Aug-15 17:00 A 100% 100%
Lighting And Small
Sm Power Distribution Panel Single Line Diagram 1464.00 17-Sep-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Interface Drawing
Drawin Of Earthing System 1272.00 22-Jun-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Interface Drawing
Drawin Of Cable Routing 1414.40 22-Jun-15 08:00 A 19-Jan-16 17:00 A 100% 100%
Wiring / Interconection
Intercon Diagram 1608.00 07-Dec-15 08:00 A 14-Sep-16 17:00 A 100% 100%
RFQ 1382.80 10-Aug-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Earthing and lightning
ligh material 808.00 10-Aug-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Cable Ladder And An Cable Tray 960.00 11-Aug-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable 424.00 18-Sep-15 11:36 A 04-Dec-15 11:36 A 100% 100%
Conduit And Accessories
Acc 712.00 08-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch 664.00 08-Dec-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Cathodic Protection
Protect 344.00 29-Dec-15 08:00 A 02-Mar-16 17:00 A 100% 100%
Elec. Heat Tracing
Tracin 232.00 01-Dec-15 08:00 A 11-Jan-16 17:00 A 100% 100%
Lighting Fixtures 246.80 04-Jan-16 08:00 A 22-Jan-16 17:00 A 100% 100%
Other Material(Steel/
Material(S Termination Kit/Cable Joint/Cable Gland/Seal Material)(12-30) 573.60 04-Jan-16 08:00 A 15-Apr-16 17:00 A 100% 100%
Instrumentation an and control 3360.00 15-Feb-15 08:00 A 22-Sep-16 17:00 A 100% 100%
Document 3360.00 15-Feb-15 08:00 A 22-Sep-16 17:00 A 100% 100%
Datasheet for Coriolis
Co Flow Meter 1504.00 27-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Thermometer
Th 1504.00 27-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for W Wireless Temperature Transmitter 1000.00 27-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for O Oil in Water Analyser 1528.00 15-Feb-15 08:00 A 18-Nov-15 17:00 A 100% 100%
Datasheet for FlowFl Element - Nozzle 1200.00 21-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Co Control Valve (Single Phase)-Globe 1688.00 26-Feb-15 08:00 A 16-Oct-15 17:00 A 100% 100%
Datasheet for Self-Actuating
Se Control Valve 1200.00 25-Mar-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Datasheet for ESD ES Ball Valve£¨Ball£© 1512.00 26-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Orifice
O Plate 1160.00 21-Apr-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for FlowFl Element - Restriction Orifice 1200.00 21-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Thermowell
Th 1056.00 21-Apr-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Pressure
Pr Gauge 872.00 25-May-15 08:00 A 06-Nov-15 17:00 A 100% 100%
Datasheet for Displacer
Di Level Instrument 984.00 25-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Level
Le Gauge 984.00 25-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Le Level Transmitter Radar Type 976.00 26-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for DP Transmitter 1048.00 26-May-15 08:00 A 28-Sep-15 17:00 A 100% 100%
Datasheet for Pressure
Pr Transmitter 1048.00 26-May-15 08:00 A 30-Sep-15 17:00 A 100% 100%
Datasheet for DP Flow Transmitter 1008.00 26-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Te Temperature Transmitter 1192.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Milliammeter/Dector
M 1352.00 25-Mar-15 08:00 A 05-Nov-15 00:00 A 100% 100%
Instrument Air C Consumption Calculations 176.00 26-Mar-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Instrument Index 24.00 16-Feb-15 08:00 A 18-Feb-15 17:00 A 100% 100%
System I/O LIST 24.00 16-Feb-15 08:00 A 18-Feb-15 17:00 A 100% 100%
IPF classification
classifications, verification reports 1688.00 12-Jun-15 08:00 A 02-Mar-16 17:00 A 100% 100%
DCS Group Displays
Disp & Reports 1248.00 07-Mar-16 08:00 A 01-Sep-16 17:00 A 100% 100%
Sizing Calculations
Calculatio for Control Valves 904.00 14-Oct-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Power Feeds List Lis with Power Consumption for UPS and non-UPS Consumers 360.00 17-Feb-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Sizing Calculations
Calculatio for Flow Elements 848.00 14-Jul-15 08:00 A 12-Jan-16 17:00 A 100% 100%
Thermowell Wak Wake Frequency Calculations 368.00 26-Jan-16 08:00 A 01-Apr-16 17:00 A 100% 100%
Level Instrumen
Instrument Nozzel Elevations Calculation 1960.00 23-Sep-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Alarm rationalisa
rationalisation study report and alarm reference data base 984.00 01-Apr-16 08:00 A 22-Sep-16 17:00 A 100% 100%
Junction Box Schedules
Sch 368.00 14-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Cable Drum Sch Schedules 1256.00 07-Jul-15 08:00 A 28-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 25 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Cable Sizeing/Se
Sizeing/Selection Calculations 1552.00 07-Jul-15 08:00 A 13-Apr-16 17:00 A 100% 100%
Instrument NamName Plate Schedules 1316.00 07-Jul-15 08:00 A 18-Dec-15 12:00 A 100% 100%
Instrument Cable Schedules 1536.00 07-Jul-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Intrinsically Safe(IS)
Safe( Loop Calculations 2456.00 07-Jul-15 08:00 A 15-Sep-16 17:00 A 100% 100%
Material Take Off 328.00 14-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Drawing 2936.00 13-Apr-15 08:00 A 15-Sep-16 17:00 A 100% 100%
Instument Locati
Location Layouts 1616.00 26-Oct-15 00:00 A 02-Sep-16 17:00 A 100% 100%
Shutdown and LogicL Diagrams 840.00 19-Oct-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Instrument Main Cable Routing 1640.00 13-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Instrument Cable trays/trench layouts with cable cross section 1656.00 27-Nov-15 08:00 A 15-Sep-16 17:00 A 100% 100%
Graphic Display Sketches 840.00 20-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Instrument hook
hook-up drawings (process and pneumatic) 1336.00 22-Jun-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Instument Air Dis
Distribution Layouts 1160.00 26-Oct-15 08:00 A 23-May-16 17:00 A 100% 100%
Instrument Earth
Earthing Layouts 1448.00 26-Oct-15 08:00 A 12-Jul-16 17:00 A 100% 100%
Junction Box Wiring
Wir Diagrams 736.00 26-Oct-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Instrument Loop Diagrams 1220.00 20-Nov-15 08:00 A 23-May-16 17:00 A 100% 100%
RFQ 1840.00 22-Apr-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Control Valves/on-off
Valves/o valves (INC-MRI-0001-0501/0502/0503/0507/0601/0602) 1336.00 22-Apr-15 08:00 A 16-Dec-15 17:00 A 100% 100%
Flow/Temperature Element (INC-MRI-0001-0101/0103/0105/0107/0401/0302)
Flow/Temperatu 1192.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Level/Gauge (INC-MRI-0001-0301/0202/0203)
(IN 960.00 25-May-15 08:00 A 11-Nov-15 17:00 A 100% 100%
Analyser/Transmitter (INC-MRI-0001-0401/0302/0303/0401/0402/0403/0701/0702/0801/0802/0803)
Analyser/Transm 1144.00 16-Jun-15 08:00 A 06-Jan-16 17:00 A 100% 100%
Cable Tray 272.00 28-Jan-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Instrument Cable 928.00 07-Jul-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Instrument Junction
Junct Boxes 216.00 27-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Inst. Material 1416.00 07-Jul-15 08:00 A 18-Mar-16 17:00 A 100% 100%
ARDS - Atmospheric Residue Desulphurization 7472.00 22-Aug-14 08:00 A 02-May-18 17:00 100% 99.99%
1210 - Common ARDS AR - Common Atmospheric Residue Desulphurization 4768.00 22-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Process 4768.00 22-Aug-14 08:00 A 30-Dec-16 17:00 A 100% 100%
Document 4768.00 22-Aug-14 08:00 A 30-Dec-16 17:00 A 100% 100%
Process Data Sh Sheet - PCC Atmospheric Flash Drum 1210-V-601 392.00 05-Jun-15 08:00 A 12-Aug-15 17:00 A 100% 100%
PCC Atmospheric
Atmospher Condensates Trim Cooler 1210-E-601 840.00 18-Jun-15 08:00 A 16-Nov-15 17:00 A 100% 100%
Cause and Effect
Effec Matirx 3312.00 17-Feb-15 08:00 A 07-Oct-16 00:00 A 100% 100%
Design basis 2712.00 22-Aug-14 08:00 A 25-Dec-15 17:00 A 100% 100%
Project Equipment
Equipme List 640.00 24-Oct-14 08:00 A 13-Feb-15 17:00 A 100% 100%
Relief Valves Discharge
Dis Summary 456.00 07-Jan-15 08:00 A 31-Mar-15 17:00 A 100% 100%
Flare system simulation
sim report 1984.00 23-Mar-15 08:00 A 10-Mar-16 17:00 A 100% 100%
Heat and Materi
Material Balance 272.00 24-Nov-14 08:00 A 09-Jan-15 17:00 A 100% 100%
Hydraulic calculation
calcula notes 1096.00 01-Jul-15 08:00 A 30-Oct-15 17:00 A 100% 100%
List of alarms an
and trips with set points 1648.00 30-Jun-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Operation and M Maintenance Manuals 2256.00 09-Sep-15 08:00 A 21-Oct-16 17:00 A 100% 100%
Piping interface table
t 1200.00 26-Dec-14 08:00 A 30-Jul-15 17:00 A 0% 0%
Piping Line lists 1200.00 26-Dec-14 08:00 A 30-Jul-15 17:00 A 100% 100%
Process Control Narratives 1200.00 01-Jul-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Process Data Sheet
Sh for 1210-A-001 Hydrogen Recovery Package 1448.00 26-Aug-14 08:00 A 18-May-15 17:00 A 100% 100%
Process Data Sheet
Sh for Exchanger 1088.00 26-Dec-14 08:00 A 10-Jul-15 17:00 A 100% 100%
Process Data Sh Sheet for H2 Recovery Section Drum 928.00 26-Dec-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data Sheet
Sh for Control Valves 976.00 17-Feb-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Process Data Sheet
Sh for Flow Elements 1200.00 17-Feb-15 08:00 A 13-Oct-15 17:00 A 100% 100%
Process Data Sh Sheet for Pressure Safety Valves 1200.00 17-Feb-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Process Data Sh Sheet For Restriction Orifices Of Common ARDS Unit 1064.00 15-Jun-15 08:00 A 13-Oct-15 17:00 A 100% 100%
Process Descriptions
Descrip 808.00 29-Dec-14 08:00 A 25-May-15 17:00 A 100% 100%
Process Interlock Description 1288.00 26-Dec-14 08:00 A 14-Aug-15 17:00 A 100% 100%
Safeguarding Memorandum
Me 4080.00 26-Dec-14 08:00 A 30-Dec-16 17:00 A 100% 100%
Utility Consumption
Consumpt Summary 512.00 26-Dec-14 08:00 A 31-Mar-15 17:00 A 100% 100%
Catalyst and Chemical
Che Summary 216.00 08-Jan-15 08:00 A 13-Feb-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 26 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Process Effluent List 448.00 26-Dec-14 08:00 A 19-Mar-15 17:00 A 100% 100%
Drawing 4176.00 25-Aug-14 08:00 A 16-Sep-16 17:00 A 100% 100%
U&ID PCC atmospheric
atmo condensate flash drums 2616.00 05-Jun-15 08:00 A 16-Sep-16 17:00 A 100% 100%
PFD 3136.00 25-Aug-14 08:00 A 16-Mar-16 17:00 A 100% 100%
P&ID-Hydrogen Recovery Compressors£¨First Stage/Second Stage£© 2304.00 24-Oct-14 08:00 A 11-Dec-15 17:00 A 100% 100%
P&ID Hydrogen Recovery Unit 2304.00 24-Oct-14 08:00 A 11-Dec-15 17:00 A 100% 100%
P&ID- Detail Dw
Dwg. for Machinery (10 Pages) 1064.00 21-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
P&ID for COC lift
lif pits system 1784.00 24-Oct-14 08:00 A 08-Sep-15 17:00 A 100% 100%
P&ID for Refinery
Refiner AOC Collection Basin 3 - 6300-T-103 2384.00 24-Oct-14 08:00 A 25-Dec-15 17:00 A 100% 100%
Material Select Diagram
D 1808.00 24-Oct-14 08:00 A 29-Oct-15 17:00 A 100% 100%
UID 1784.00 24-Oct-14 08:00 A 08-Sep-15 17:00 A 100% 100%
RFQ 1672.00 03-Nov-14 08:00 A 27-Aug-15 17:00 A 100% 100%
Requisition for Hydrogen
H Recovery Package (1210-A-001) (IQ01-2026) 1672.00 03-Nov-14 08:00 A 27-Aug-15 17:00 A 100% 100%
Etc 832.00 24-Nov-14 08:00 A 22-Apr-15 17:00 A 0% 0%
COS 832.00 24-Nov-14 08:00 A 22-Apr-15 17:00 A 0% 0%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 3192.00 29-Jan-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Document 2112.00 29-Jan-15 08:00 A 25-Jan-16 17:00 A 100% 100%
Mechanical Data Sheet for 1210-V-001/ V-002 336.00 05-Feb-15 08:00 A 08-Apr-15 17:00 A 100% 100%
Mechanical data sheet for 1210-E-001/1210-E-002 160.00 29-Jan-15 08:00 A 02-Mar-15 17:00 A 100% 100%
Mechanical Data Sheet - PCC Atmospheric Flash Drum 1210-V-601 832.00 18-Jun-15 08:00 A 27-Oct-15 17:00 A 100% 100%
Overhead Travelling
Trave Crane for 1210-K-001A/B 1224.00 08-May-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical Data Sheet For Hydrogen Recovery Package 1210-A-001 616.00 19-May-15 08:00 A 02-Sep-15 17:00 A 100% 100%
Mechanical Data Sheet For AOC SLOP OIL SKIMMING AND TRANSFER PACKAGE 240.00 04-Jan-16 08:00 A 25-Jan-16 17:00 A 0% 0%
Drawing 2816.00 09-Apr-15 08:00 A 26-Aug-16 17:00 A 100% 100%
General Arrangement
Arrange Drawing for 1210-V-001/ V-002 656.00 09-Apr-15 08:00 A 03-Aug-15 17:00 A 100% 100%
General Arrangement
Arrange for - PCC Atmospheric Flash Drum 1210-V-601 1008.00 18-Jun-15 08:00 A 15-Dec-15 17:00 A 100% 100%
Vendor Data and Drawings for 1210-V-001/ V-002 1272.00 09-Sep-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for 1210-E-001 /1210-E-002 1224.00 08-Oct-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Package A-001 1280.00 09-Nov-15 00:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Crane 472.00 18-Apr-16 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 2584.00 29-Jan-15 08:00 A 10-Mar-16 17:00 A 100% 100%
Exchanger 1210-E-001/002(IQ01-2018)
1210 1192.00 29-Jan-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Carbom Steel D Drums 1210-V-001/002 (IQ01-2016) 1152.00 05-Feb-15 08:00 A 18-Sep-15 17:00 A 100% 100%
Requisition for Overhead
O Travelling Crane1210-X-001(IQ01-1009) 1224.00 08-May-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Requisition for AOC
A SLOP OIL SKIMMING AND TRANSFER PACKAGE 632.00 18-Jan-16 08:00 A 10-Mar-16 17:00 A 0% 0%
Rotating Equipment 3360.00 22-Dec-14 08:00 A 26-Aug-16 17:00 A 100% 100%
Document 1976.00 22-Dec-14 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical Data Sheet - H2 Recovery Compressor - 1210-K-001A/B (IQ01-1003, H2 Recovery Compressor) 1856.00 22-Dec-14 08:00 A 20-Nov-15 17:00 A 100% 100%
Mechanical Data Sheet-Refinery Coc Collection Pump 1210-P-101A/B 6300-P-103A/B (IQ01-1004) 264.00 16-Feb-15 08:00 A 07-Apr-15 17:00 A 100% 100%
Mechanical Data Sheet - PCC Condensates Return Pumps-1210-P-601A/B 1064.00 05-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Drawing 1456.00 16-Oct-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for 1210-K-001A/B(H2 Recovery Compressor,IQ01-1003) 1280.00 10-Nov-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for 1210-P-101A/B 1210-P-601A/B 6300-P-103A/B(IQ01-1004) 1200.00 16-Oct-15 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 1584.00 22-Dec-14 08:00 A 10-Sep-15 17:00 A 100% 100%
Requisition for reciprocation
re compressors atmospheric residue desulphurisation(unit1210)(IQ01-1003) 1584.00 22-Dec-14 08:00 A 10-Sep-15 17:00 A 100% 100%
Requisition for ce
centrifugal pump package #1 atmospheric residue desulphurisation (IQ01-1004) 1040.00 17-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 3016.00 27-Mar-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Document 2576.00 15-Jun-15 08:00 A 16-Sep-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Conduits And Accessories 1211.20 03-Aug-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices 1720.00 15-Jun-15 08:00 A 20-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 1216.00 03-Aug-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Fire dedetection 2416.00 13-Jul-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Telecommunication Cable Schedule
Telecommunicat 2032.00 02-Nov-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Drawing 2320.00 27-Mar-15 08:00 A 27-Apr-16 17:00 A 100% 100%
Telecommunicaiton devices location layout
Telecommunicait 2320.00 27-Mar-15 08:00 A 15-Apr-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 27 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Telecommunicaiton Cable Routing layout


Telecommunicait 1632.00 07-Jul-15 08:00 A 27-Apr-16 17:00 A 100% 100%
RFQ 1480.00 11-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Telecommunication devices
Telecommunicat 1480.00 11-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Fire detection 1280.00 15-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Optic Fiber Cabl
Cable & Cable 280.00 02-Nov-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 3304.00 11-Nov-14 08:00 A 29-Jun-16 17:00 A 100% 100%
Document 3040.00 26-Dec-14 08:00 A 29-Jun-16 17:00 A 100% 100%
Aquatic toxicity inventory
in 1720.00 10-Mar-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Effluents inventory
invento (gaseous, liquid, solid waste) 1976.00 26-Dec-14 08:00 A 15-Sep-15 17:00 A 100% 100%
Greenhouse gas accounting report 2632.00 10-Mar-15 08:00 A 24-Jun-16 17:00 A 100% 100%
Stack height calculation
calc note 2760.00 15-Feb-15 08:00 A 29-Jun-16 17:00 A 100% 100%
MTO for fire figh
fighting equipment 832.00 02-Sep-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Safety Piping Line
Lin List - Atmospheric Residue Desulfurization Unit 296.00 29-Apr-15 08:00 A 19-Jun-15 17:00 A 100% 100%
Hazardous area classification schedule 1952.00 02-Apr-15 08:00 A 26-Feb-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1696.00 15-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Noisy equipment list 576.00 10-Sep-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Safety sign spec
specification and datasheet 1336.00 21-Aug-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Drawing 3000.00 11-Nov-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Safety Drawing - Fire Protection and personnel protection 1984.00 15-Feb-15 08:00 A 04-Jan-16 17:00 A 100% 100%
Fire water spray system P&ID 2128.00 30-Mar-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2232.00 15-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Hazardous area classification layout 2360.00 11-Nov-14 08:00 A 08-Jan-16 17:00 A 100% 100%
Temporary must
mustering areas and escape routes layout 1752.00 24-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Safety sign layout 1320.00 20-Aug-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Deluge Nozzle Arrangment
A Calculation Note 608.00 12-Nov-15 08:00 A 23-Feb-16 17:00 A 100% 100%
RFQ 968.00 25-Aug-15 08:00 A 16-Feb-16 17:00 A 100% 100%
Fire water hydrant/hose
hydra box&monitor Req.(MRI-0001-7003) 528.00 02-Sep-15 08:00 A 02-Dec-15 17:00 A 100% 100%
Fire extinguisher Req.(MRI-0001-7004) 544.00 25-Aug-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Inert gas fire extinguishing
ext system(MRI-0001-7006) 536.00 20-Nov-15 08:00 A 16-Feb-16 17:00 A 100% 100%
Civil/Structure 3672.00 10-Feb-15 08:00 A 23-Nov-16 17:00 A 100% 100%
Document 3672.00 10-Feb-15 08:00 A 23-Nov-16 17:00 A 100% 100%
Calculation Notes
Note for 1210-A-001 Foundation 496.40 30-Nov-15 08:00 A 01-Mar-16 17:00 A 100% 100%
Calculation Notes
Note for 1210-E-001/ E-002 Foundation 1032.00 01-Jun-15 08:00 A 29-Oct-15 17:00 A 100% 100%
Calculation Notes
Note for 1210-K-001A,001B Foundation 1672.00 02-Dec-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Calculation Notes
Note for RCK-1100/1110 2608.00 10-Feb-15 08:00 A 27-May-16 17:00 A 100% 100%
Calculation Notes
Note for SHL-1100 1056.00 02-Dec-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Calculation Notes
Note for STR-1100/1200/1300 992.00 23-Nov-15 08:00 A 15-Sep-16 17:00 A 100% 100%
Calculation Notes
Note for 1210-V-001/ V-002 Foundation 2008.00 01-Jun-15 08:00 A 27-May-16 17:00 A 100% 100%
Calculation Notes
Note for AOC Basin 6300-T-103 3072.00 01-Jun-15 08:00 A 23-Nov-16 17:00 A 100% 100%
Calculation Notes
Note for COC PIT 1210-T-101 1168.00 06-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Material Take OffOf for Reinforcing Steel 424.00 08-Dec-15 08:00 A 26-Feb-16 17:00 A 100% 100%
Material Take OffOf for Steel Structural Anchor Bolts 496.00 19-May-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Material Take OffOf for Equipment Anchor Bolts 344.00 09-Jun-15 08:00 A 06-Aug-15 17:00 A 100% 100%
Material Take Of Off for Structural Steel 416.00 19-May-15 08:00 A 29-Jul-15 17:00 A 100% 100%
Drawing 3320.00 11-Feb-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Foundation Of 1210-A-001
1 1504.00 07-Dec-15 08:00 A 23-Aug-16 17:00 A 100% 100%
Foundation Of 1210-E-001/
1 E-002 1136.00 08-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Foundation Of 1 1210-K-001A,001B 1160.00 09-Dec-15 08:00 A 06-Jul-16 17:00 A 100% 100%
Foundation Of 1210-V-001/
1 V-002 1968.00 08-Jun-15 08:00 A 27-May-16 17:00 A 100% 100%
Foundation Of R RCK-1100/1110 1904.00 18-May-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Foundation Of S SHL-1100 832.00 09-Dec-15 08:00 A 10-May-16 17:00 A 100% 100%
Foundation Of S STR-1100/1200/1300 1552.00 26-Nov-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Foundation Layout
Layo For Unit 1210 2800.00 19-May-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Steel Works for RCK-1100/1110£¨Columns/Beams/Details£© 1904.00 18-May-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Steel Works for RCK-1100/1110£¨Framing Plans/Elevations£© 1960.00 11-Feb-15 08:00 A 29-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 28 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Structure Drawings
Drawin for SHL-1100£¨Framing Plans/Elevations£© 280.00 30-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Structure Drawin
Drawings for SHL-1100£¨Columns/Beams/Details£© 696.00 04-Jan-16 08:00 A 10-May-16 17:00 A 100% 100%
Structure Drawings
Drawin for STR-1100/1200/1300£¨Framing Plans/Elevations£© 488.00 25-Jan-16 08:00 A 22-Apr-16 17:00 A 100% 100%
Structure Drawings
Drawin for STR-1100/1200/1300£¨Columns/Beams/Details£© 488.00 25-Jan-16 08:00 A 22-Apr-16 17:00 A 100% 100%
COC PIT 1210-T-101
1210-T Structural Drawing 1288.00 13-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
AOC Basin 6300-T-103
6300 Structural Drawing 2664.00 08-Jun-15 08:00 A 22-Aug-16 17:00 A 100% 100%
drawing for stormwater
storm drainage network 1560.00 27-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
surfacing and grading
gr finishing layout 2520.00 27-Apr-15 08:00 A 18-Jul-16 17:00 A 100% 100%
Drawing - Drainage
Draina and Undeground Piping Drawing - Refinery 03 - Units 1210-1211-1212 2408.00 17-Feb-15 08:00 A 29-Apr-16 17:00 A 100% 100%
RFQ 1024.00 11-Feb-15 08:00 A 13-Aug-15 17:00 A 100% 100%
Steel Structure 768.00 11-Feb-15 08:00 A 30-Jun-15 17:00 A 100% 100%
Anchor bolt for MEC M 256.00 01-Jul-15 08:00 A 13-Aug-15 17:00 A 100% 100%
Anchor bolt for Structure
S 248.00 01-Jul-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Architectural 840.00 04-Jan-16 08:00 A 15-Apr-16 17:00 A 100% 100%
Drawing 840.00 04-Jan-16 08:00 A 15-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1210-SHL-1100 Elevations 832.00 04-Jan-16 08:00 A 15-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1210-SHL-1100 Ground Floor Plan 622.40 04-Jan-16 08:00 A 15-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1210-SHL-1100 Sections 832.00 04-Jan-16 08:00 A 15-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1210-SHL-1100 Roof Plan 840.00 04-Jan-16 08:00 A 15-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1210-SHL-1100 Detail Drawings 696.00 04-Jan-16 08:00 A 15-Apr-16 17:00 A 0% 0%
Piping 4272.00 26-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Document 3032.00 30-Mar-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Critical line lis 1064.00 30-Mar-15 08:00 A 05-Nov-15 17:00 A 100% 100%
Piping Stress Calculations
Ca and analysis report 2232.00 22-May-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Data Sheets for Safety Valve 1040.00 30-Mar-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Data Sheets for sampler 672.00 30-Mar-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Material Take Off Of for Insulation 328.00 17-Jun-16 08:00 A 08-Jul-16 17:00 A 100% 100%
Material Take Off Of for Piping Bulk Material 328.00 21-Dec-15 08:00 A 07-Jan-16 17:00 A 100% 100%
Material Take Off Of for Piping Painting 384.00 04-Jul-16 08:00 A 30-Aug-16 17:00 A 100% 100%
Material Take Of Off for Special Item 384.00 04-Jul-16 08:00 A 30-Aug-16 17:00 A 100% 100%
MTO for U/G pip pipe system 1224.00 13-Oct-15 08:00 A 20-May-16 17:00 A 100% 100%
Pipe support lists(Standard
lists and Special) 2360.00 27-Jul-15 08:00 A 19-Jan-16 17:00 A 100% 100%
Steam Tracing List L 600.00 21-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Spring list and datasheet
da 728.00 15-Dec-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Drawing 4272.00 26-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
3D-Model Review&Action
Revie Close-out Report 3416.00 28-Oct-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Above Ground Piping P GA Key Plan (1 of 2) 592.00 08-Jan-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Equipment layout 2160.00 08-Jan-15 08:00 A 01-Feb-16 17:00 A 100% 100%
ISO drawing for U/G piping and list 744.00 03-Dec-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Piping General Arrangement
A drawings 664.00 04-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Piping Isometric Drawings(with Materials) and list 1360.00 23-Nov-15 08:00 A 26-Feb-16 17:00 A 100% 100%
Piping battery limit
lim interface table 1408.00 06-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Special Pipe Support
Sup Drawing and list 1944.00 23-Oct-15 08:00 A 02-Sep-16 17:00 A 100% 100%
1210 - Common Atmospheric Residue Desulfurization Unit - Unit Plot Plan 2664.00 26-Aug-14 08:00 A 11-Dec-15 17:00 A 100% 100%
ISO drawing for U/G piping 736.00 04-Dec-15 08:00 A 11-Mar-16 17:00 A 100% 100%
ÐÂÔöVendor Data Da and Drawings for Misc. Piping Equipment (Sampler) 136.00 17-May-16 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 2920.00 30-Mar-15 08:00 A 30-Aug-16 17:00 A 100% 100%
MR for Blanket Order O of Piping/Fitting/Valve 280.00 15-Apr-15 08:00 A 03-Jun-15 17:00 A 100% 100%
Safety Valve 1720.00 30-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Misc. Piping EquEquipment(Sampler) 656.00 22-May-15 08:00 A 20-Aug-15 17:00 A 100% 100%
Spring Hanger 560.00 20-Nov-15 08:00 A 25-Dec-15 17:00 A 100% 100%
1st Piping Valves 504.00 01-Jul-15 08:00 A 25-Sep-15 17:00 A 100% 100%
1st U/G piping 408.00 22-Jun-15 08:00 A 31-Aug-15 17:00 A 100% 100%
MR for U/G GRP bulk materia 584.00 06-Apr-15 08:00 A 15-May-15 17:00 A 100% 100%
U/G valves 896.00 22-Jun-15 08:00 A 27-Nov-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 29 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

1st Piping/Fitting/Flange
Piping/Fitting 200.00 23-Nov-15 08:00 A 25-Dec-15 17:00 A 100% 100%
1st Piping Support
Suppo 760.00 22-May-15 08:00 A 08-Oct-15 17:00 A 100% 100%
2nd Piping/Valves/Fitting
Piping/Valve 640.00 21-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
2nd Piping Support
Supp 160.00 08-Aug-16 08:00 A 30-Aug-16 17:00 A 100% 100%
Etc 3336.00 29-Dec-14 08:00 A 12-Aug-16 17:00 A 0% 0%
COS 3336.00 29-Dec-14 08:00 A 12-Aug-16 17:00 A 0% 0%
Electrical 3216.00 15-Feb-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Document 3168.00 15-Feb-15 08:00 A 08-Sep-16 17:00 A 100% 100%
Data Sheet For Synchronous Motor 1210-KM-001A/B H2 Recovery Compressor Motor 880.00 16-Feb-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheet For Cage Induction Machine - Lv 1210-PM-101A/B Refinery Coc Collection Pump Motor 616.00 08-Apr-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheet For Cage Induction Machine - Lv 1210-PM-601A/B Pcc Condensate Return Pump Motor 248.00 12-Jun-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheet For Cage Induction Machine - LV 6300-PM-103A/B Refinery Coc Collection Pump Motor 616.00 08-Apr-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Electrical Cable Drum
D Schedule 848.00 17-Nov-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Electrical Cable List
L 1136.00 27-Jul-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Common Atmosp
Atmospheric Residue Desulphurization (1210) Electrical Consumer List 1744.00 15-Feb-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Material Take Of Off For Earthing And Lightning Material 960.00 17-Nov-15 08:00 A 10-May-16 17:00 A 100% 100%
Material Take OffOf For Cable 1224.00 17-Nov-15 08:00 A 24-Jun-16 17:00 A 100% 100%
Material Take Of Off For Cable Ladder And Cable Tray 732.80 18-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Material Take OffOf For other material 1696.00 10-Nov-15 08:00 A 08-Sep-16 17:00 A 100% 100%
BLIT of Cables 968.00 27-Jul-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Drawing 3216.00 15-Feb-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Cathodic Protection
Protect System Layout 256.00 04-Jan-16 08:00 A 22-Jan-16 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 2120.00 27-Apr-15 08:00 A 13-May-16 17:00 A 100% 100%
Electrical Heat Tracing
T Layout 256.00 04-Jan-16 08:00 A 22-Jan-16 17:00 A 100% 100%
Lighting Layout (Unit/Street)
( 880.00 04-Jan-16 08:00 A 10-Jun-16 17:00 A 100% 100%
Lighting Loop Diagram
Di 1616.00 21-Aug-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout (Underground) 2384.00 15-Feb-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Lighting And Small
Sm Power Distribution Panel Single Line Diagram 880.00 04-Jan-16 08:00 A 10-Jun-16 17:00 A 100% 100%
Wiring / Interconection
Intercon Diagram 1280.00 01-Feb-16 08:00 A 16-Sep-16 17:00 A 100% 100%
Interface Drawing
Drawin Of Earthing System 648.00 13-Aug-15 08:00 A 04-Dec-15 17:00 A 100% 100%
RFQ 1456.00 02-Nov-15 08:00 A 15-Jul-16 17:00 A 100% 100%
Earthing and lightning
ligh material 248.00 23-Nov-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 408.00 19-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable 304.00 02-Nov-15 08:00 A 03-Dec-15 17:00 A 100% 100%
Conduit And Accessories
Acc 872.00 15-Feb-16 08:00 A 15-Jul-16 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch 152.00 10-Dec-15 08:00 A 06-Jan-16 17:00 A 100% 100%
Elec. Heat Tracing
Tracin 312.00 30-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Cathodic Protection
Protect 408.00 18-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Lighting Fixtures 248.00 04-Jan-16 08:00 A 22-Jan-16 17:00 A 100% 100%
Other Material(Steel/
Material(S Termination Kit/Cable Joint/Cable Gland/Seal Material) 896.00 15-Feb-16 08:00 A 15-Jun-16 17:00 A 100% 100%
Etc 160.00 01-Aug-16 08:00 A 19-Aug-16 17:00 A 0% 0%
COS 160.00 01-Aug-16 08:00 A 19-Aug-16 17:00 A 0% 0%
Instrumentation an and control 3656.00 26-Dec-14 08:00 A 18-Oct-16 17:00 A 100% 100%
Document 3600.00 26-Dec-14 08:00 A 23-Sep-16 17:00 A 100% 100%
Cable Drum SchSchedules 568.00 28-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Alarm rationalisa
rationalisation study report and alarm reference data base 1576.00 28-Dec-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Analyser Sample System Transportation times 328.00 28-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable Sizing/Selection
Sizing/Sel Calculations 592.00 28-Dec-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Datasheet for Co Control Valve (Globe) 1496.00 17-Feb-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Datasheet for Deluge
De Valve 1576.00 29-Jun-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Datasheet for Displacer
Di Level Instrument 608.00 25-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for DP Flow Transmitter/DP Transmitter/Flow Element - Restriction Orifice 976.00 25-May-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Le Level Transmitter Radar Type/ Variable Area Flow Meter 672.00 29-Jun-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for GasG Detector 1608.00 24-Mar-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Local
Lo Milliammeter 808.00 26-May-15 08:00 A 05-Nov-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 30 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Datasheet for Magnetic


M Level Gauge 720.00 26-May-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Orifice
O Plate 1432.00 22-Apr-15 08:00 A 04-Jan-16 17:00 A 100% 100%
Datasheet for Pressure
Pr Gauge 728.00 25-May-15 08:00 A 06-Nov-15 17:00 A 100% 100%
Datasheet for Pressure
Pr Transmitter 728.00 25-May-15 08:00 A 29-Sep-15 17:00 A 100% 100%
Datasheet for Te Temperature Transmitter 1008.00 26-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Thermometer
Th 1192.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
DCS Group Displays
Disp & Reports 832.00 28-Dec-15 08:00 A 27-May-16 17:00 A 100% 100%
Instrument Air C Consumption Calculations 272.00 10-Mar-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Instrument Cable Schedules 568.00 28-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Instrument Index 296.00 26-Dec-14 08:00 A 16-Feb-15 17:00 A 100% 100%
Instrument NamName Plate Schedules 728.00 13-Oct-15 08:00 A 22-Feb-16 17:00 A 100% 100%
Intrinsically Safe(IS)
Safe( Loop Calculations 1600.00 11-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
IPF classification
classifications, verification reports 1520.00 08-Jul-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Junction Box Schedules
Sch 608.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Level Instrumen
Instrument Nozzel Elevations Caculation 1016.00 15-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Material Take Off Of for Instrument Pipe and Pipe Fitting Bulk Items 456.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Material Take Off Of for Instrument Tube and Tube Fitting Bulk Items 456.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Material Take Off Of for Bulk Items 448.00 28-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Material Take Of Off for Cable Tray 456.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Material Take Off Of for Instrument Cable 168.00 01-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Material Take Off Of for Instrument Junction Box 456.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Material Take Off Of for Instrument Valves 456.00 25-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Material Take Of Off for Cable Glands 216.00 25-Dec-15 08:00 A 02-Feb-16 17:00 A 100% 100%
Power Feeds List Lis with Power Consumption for UPS and non-UPS Consumers 272.00 10-Mar-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Sizing Calculations
Calculatio for Control Valves 816.00 13-Nov-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Sizing Calculations
Calculatio for Flow Elements 1200.00 01-Sep-15 08:00 A 08-Jan-16 17:00 A 100% 100%
System I/O LIST 376.00 29-Dec-14 08:00 A 09-Mar-15 17:00 A 100% 100%
Thermowell Wak Wake Frequency Calculations 496.00 04-Jan-16 08:00 A 01-Apr-16 17:00 A 100% 100%
Datasheet for Co Control Valve(Angle) 1656.00 17-Feb-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Datasheet for O Oil in Water Analyser 1016.00 25-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Drawing 3000.00 27-Apr-15 08:00 A 18-Oct-16 17:00 A 100% 100%
Graphic Display Sketches 696.00 12-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Instrument Cable trays/trench layouts with cable cross section 1808.00 26-Nov-15 08:00 A 18-Oct-16 17:00 A 100% 100%
Instrument Earth
Earthing Layouts 1144.00 27-Oct-15 08:00 A 20-May-16 17:00 A 100% 100%
Instrument hook
hook-up drawings£¨process and pneumatic) 1616.00 08-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Instrument Loop Diagrams 400.00 11-Mar-16 08:00 A 23-May-16 17:00 A 100% 100%
Instrument Main Cable Routing 1560.00 27-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Junction Box Wiring
Wir Diagrams 1656.00 08-Jun-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Instument Air DisDistribution Layouts 1152.00 27-Oct-15 00:00 A 20-May-16 17:00 A 100% 100%
Instument Locati
Location Layouts 1344.00 26-Oct-15 08:00 A 23-Jun-16 17:00 A 100% 100%
Shutdown and Logic L Diagrams 616.00 30-Oct-15 08:00 A 08-Jan-16 17:00 A 100% 100%
RFQ 2280.00 17-Feb-15 08:00 A 07-Apr-16 17:00 A 100% 100%
MAC (INC-MRI-
(INC-MRI-0001-1001) 1472.00 17-Feb-15 08:00 A 11-Nov-15 17:00 A 100% 100%
Control Valves (INC-MRI-1210-0502/0503)
( 1032.00 18-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Orifice Plate/Flow Element/Temperature Element (INC-MRI-1210-0101/0401) 1184.00 23-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Level/Gauge (INC-MRI-1210-0201/0205/0301/0602)
(IN 1008.00 27-May-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Analysis/Transmitter/Deluge Valve(INC-MRI-1210-0302/0401/0804)
Analysis/Transm 1568.00 29-Jun-15 08:00 A 07-Apr-16 17:00 A 100% 100%
Cable Tray (INC-MRI-1210-0901)
(INC 281.60 27-Jan-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Junction Box (INC-MRI-1210-0903)
(IN 200.00 11-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Inst. Tube&Tube Fitting/ Inst. Pipe & Fitting/Valves/ Bulk Items (INC-MRI-1210-0904/0905/0906/0907) 184.00 20-Feb-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Inst. Cable (INC-MRI-1210-0902)
(INC 192.00 01-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
1211 - ARDS - Atmospheric
Atmo Residue Desulphurization 7472.00 22-Aug-14 08:00 A 02-May-18 17:00 100% 99.99%
Process 6120.00 22-Aug-14 08:00 A 30-Aug-17 17:00 A 100% 100%
Document 6120.00 22-Aug-14 08:00 A 30-Aug-17 17:00 A 100% 100%
Process Data SheetSh for Heat Exchangers - 1211-E-601 - Blowdown cooling exchanger 1464.00 25-Dec-14 08:00 A 31-Aug-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 31 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Process Data Sheet


Sh for blowdown drum 1211-V-601 792.00 26-Mar-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Process Data Sheet
Sh for LP Clean Condensate Flash Drum 1211-V-602 696.00 13-Apr-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Cause and Effect
Effec Matrix 5440.00 25-Dec-14 08:00 A 30-Aug-17 17:00 A 100% 100%
Hydraulic calculation
calcula notes for pumps 1008.00 20-May-15 08:00 A 18-Sep-15 17:00 A 100% 100%
Hydraulic calculation
calcula notes 664.00 03-Aug-15 08:00 A 05-Nov-15 17:00 A 100% 100%
List of alarms an
and trips with set points 2288.00 30-Jun-15 08:00 A 15-Mar-16 17:00 A 100% 100%
Piping Lines lists 1872.00 26-Feb-15 08:00 A 04-Jan-16 17:00 A 100% 100%
Process Data Sheet
Sh for C001/002/003 1240.00 03-Nov-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data Sheet
Sh for 1211-C-101 (201) (HP H2S Absorber) 1736.00 22-Aug-14 08:00 A 03-Jul-15 17:00 A 100% 100%
Process Data Sheet
Sh for Large Sizes Drum 1608.00 25-Aug-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data Sh Sheet for HP Drum 1616.00 22-Aug-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data Sh Sheet for CS Drum 1240.00 03-Nov-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data Sheet
Sh for Cladding Drum 1240.00 03-Nov-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data Sheet
Sh for Cr-Mo Drum 1240.00 22-Aug-14 08:00 A 07-Apr-15 17:00 A 100% 100%
Process Data Sheet
Sh for HP Centrifugal Separator 1632.00 03-Sep-14 08:00 A 26-Jun-15 17:00 A 100% 100%
Process Data Sheet
Sh for SM Heat Exchanger 1400.00 03-Nov-14 08:00 A 10-Jul-15 17:00 A 100% 100%
Process Data Sheet
Sh for HP Heat Exchanger 1392.00 02-Dec-14 08:00 A 07-Aug-15 17:00 A 100% 100%
Process Data Sheet
Sh for DSS Air Cooler 1352.00 02-Dec-14 08:00 A 31-Jul-15 17:00 A 100% 100%
Process Data Sheet
Sh for Air Cooler 1216.00 25-Dec-14 08:00 A 31-Jul-15 17:00 A 100% 100%
Process Data Sh Sheet for Common Heat Exchanger 1280.00 25-Dec-14 08:00 A 12-Aug-15 17:00 A 100% 100%
Process Data Sheet
Sh for 1211-S-101/201 (Fresh Feed Filter) 1416.00 22-Aug-14 08:00 A 08-May-15 17:00 A 100% 100%
Process Data Sheet
Sh for Control Valves 1712.00 22-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Process Data Sh Sheet for On-off Valves 1288.00 21-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Process Data Sh Sheet for Flow Elements 1400.00 25-May-15 08:00 A 03-Dec-15 17:00 A 100% 100%
Process Data Sheet
Sh for Restriction Orifices 960.00 14-Jul-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Process Data Sh Sheet for Pressure Safety Valves 2000.00 30-Jan-15 08:00 A 11-Nov-15 17:00 A 100% 100%
Process Data Sheet
Sh for Analyzers 1352.00 16-Feb-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Process Data Sheet
Sh for Desuperheater 1752.00 16-Feb-15 08:00 A 29-Sep-15 17:00 A 100% 100%
Drawing 3440.00 22-Aug-14 08:00 A 16-Mar-16 17:00 A 100% 100%
PFD 3440.00 22-Aug-14 08:00 A 16-Mar-16 17:00 A 100% 100%
UFD BATCH 1 2992.00 24-Oct-14 08:00 A 19-Aug-15 17:00 A 100% 100%
UFD BATCH 2 2992.00 24-Oct-14 08:00 A 19-Aug-15 17:00 A 100% 100%
P&ID BATCH 1 2984.00 24-Oct-14 08:00 A 11-Dec-15 17:00 A 100% 100%
UID BATCH 1 2344.00 27-Oct-14 08:00 A 08-Sep-15 17:00 A 100% 100%
P&ID BATCH 2 2848.00 24-Oct-14 08:00 A 18-Dec-15 17:00 A 100% 100%
UID BATCH 2 2336.00 27-Oct-14 08:00 A 25-Sep-15 17:00 A 100% 100%
P&ID BATCH 3 ((P&ID for COC lift pits) 2256.00 20-Nov-14 08:00 A 10-Oct-15 17:00 A 100% 100%
Material Selectio
Selection Diagram 1960.00 24-Oct-14 08:00 A 29-Oct-15 17:00 A 100% 100%
RFQ 1608.00 17-Nov-14 08:00 A 31-Aug-15 17:00 A 100% 100%
Fresh Feed Filte
Filter (1211-S-101/201£©(IQ01-2028) 1608.00 17-Nov-14 08:00 A 31-Aug-15 17:00 A 100% 100%
Etc 464.00 03-Nov-14 08:00 A 22-Jan-15 17:00 A 0% 0%
COS 464.00 03-Nov-14 08:00 A 22-Jan-15 17:00 A 0% 0%
Material, Corrison and Inspection 6288.00 30-Mar-15 08:00 A 02-May-18 17:00 100% 98.8%
Document 6288.00 30-Mar-15 08:00 A 02-May-18 17:00 100% 98.47%
RBI Excution Plan
Pla 2264.00 13-Apr-15 08:00 A 08-Mar-16 17:00 A 100% 100%
MATERIAL SELECTION
SELE GUIDE 880.00 03-Aug-15 08:00 A 16-Feb-16 17:00 A 100% 100%
RBI Risk Manag
Management Report 2992.00 22-Jun-15 08:00 A 01-Dec-16 17:00 A 100% 100%
RBI Inspection R Reference Plan 3704.00 24-Jun-15 08:00 A 21-Apr-17 17:00 A 100% 100%
RBI MANUAL 5808.00 23-Jun-15 08:00 A 02-May-18 17:00 100% 70%
Corrosion Design
Desig Basis Memorandum 2616.00 24-Jun-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Corrosion Management
Mana Plan 2056.00 09-Oct-15 08:00 A 25-Jan-16 17:00 A 100% 100%
Corrosion Execu
Execution Plan 1552.00 25-Jun-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Corrosion study plan 1448.00 15-Oct-15 08:00 A 08-Mar-16 17:00 A 100% 100%
Corrosion Preve
Prevention Program 3008.00 15-Oct-15 08:00 A 10-Apr-17 17:00 A 100% 100%
Data Sheets 1616.00 30-Mar-15 08:00 A 05-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 32 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Installation Specification
Spec 3688.00 19-Nov-15 08:00 A 11-Sep-17 17:00 A 100% 100%
Drawing 1152.00 29-Jan-16 08:00 A 18-May-17 17:00 A 100% 100%
Vendor Data and Drawings 1152.00 29-Jan-16 08:00 A 18-May-17 17:00 A 100% 100%
RFQ 2048.00 31-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Corrosion Monitoring
Monito System 2048.00 31-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 3768.00 24-Oct-14 08:00 A 10-Nov-16 08:00 A 100% 100%
Document 2656.00 03-Nov-14 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical data sheet for Heat Exchangers 1211-E-601 - Blowdown cooling exchanger 1008.00 18-May-15 08:00 A 22-Sep-15 17:00 A 100% 100%
Mechanical data sheet for blowdown drum 1211-V-601 1808.00 06-Apr-15 08:00 A 09-Dec-15 17:00 A 100% 100%
Mechanical data sheet for LP Clean Condensate Flash Drum 1211-V-602 896.00 08-Jun-15 08:00 A 27-Oct-15 17:00 A 100% 100%
Mechanical data sheet for First Reactor 1192.00 18-May-15 08:00 A 13-Oct-15 17:00 A 100% 100%
Mechanical data sheet for Second Reactor / Third Reactor / Fourth Reactor 1176.00 18-May-15 08:00 A 13-Oct-15 17:00 A 100% 100%
Mechanical data sheet for Column 672.00 04-Nov-14 08:00 A 05-Mar-15 17:00 A 100% 100%
Mechanical data sheet for Clading Drum 520.00 25-Dec-14 08:00 A 31-Mar-15 17:00 A 100% 100%
Mechanical data sheet for HP Equipment 1608.00 03-Nov-14 08:00 A 17-Aug-15 17:00 A 100% 100%
Mechanical data sheet for CS Drums 992.00 03-Nov-14 08:00 A 29-Apr-15 17:00 A 100% 100%
Mechanical data sheet for Large sizeDrums 496.00 25-Dec-14 08:00 A 26-Mar-15 17:00 A 100% 100%
Mechanical data sheet for Cr-Mo Drum 1136.00 05-Feb-15 08:00 A 27-Aug-15 17:00 A 100% 100%
Mechanical data sheet for DSS Air Cooler 1496.00 25-Dec-14 08:00 A 07-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Air Cooler 552.00 04-Nov-14 08:00 A 09-Feb-15 17:00 A 100% 100%
Mechanical data sheet for SM Exchanger 640.00 04-Nov-14 08:00 A 28-Feb-15 17:00 A 100% 100%
Mechanical data sheet for Common Exchanger 640.00 02-Feb-15 08:00 A 28-May-15 17:00 A 100% 100%
Mechanical data sheet for HP Exchangers 1104.00 05-Feb-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Mechanical data sheet for Fired-heater 2296.00 29-Dec-14 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical Data Sheet for Waste Heat boiler package(1211-A-610) 1272.00 09-Jan-15 08:00 A 25-Aug-15 17:00 A 100% 100%
Drawing 3760.00 27-Oct-14 08:00 A 10-Nov-16 08:00 A 100% 100%
General Arrangement
Arrange Drawing for Cr-Mo Drum 448.00 01-Jul-15 08:00 A 11-Sep-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for HP Drum 2840.00 03-Nov-14 08:00 A 07-Sep-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for HP Centrifugal Separator 1328.00 25-Dec-15 08:00 A 19-Apr-16 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Large Sizes Drum 624.00 14-Apr-15 08:00 A 31-Jul-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for LP Clean Condensate Flash Drum 1211-V-602 1992.00 09-Jun-15 08:00 A 20-Nov-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Column C-002 1368.00 09-Mar-15 08:00 A 02-Sep-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Column (C-001/003) 1488.00 31-Mar-15 08:00 A 15-Dec-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for blowdown drum 1211-V-601 1680.00 07-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for HP Column (C101/201 ) 2272.00 03-Nov-14 08:00 A 02-Sep-15 17:00 A 100% 100%
General Drawing for 1211-R-101/201 First Reactor 2304.00 27-Oct-14 08:00 A 02-Sep-15 17:00 A 100% 100%
General Drawing for Second Reactor / Third Reactor / Fourth Reactor 2304.00 27-Oct-14 08:00 A 02-Sep-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Cladding Drum 176.00 01-Sep-15 09:36 A 13-Oct-15 09:36 A 100% 100%
General Arrangement
Arrange Drawing for CS Drum 176.00 01-Oct-15 11:12 A 13-Oct-15 11:12 A 100% 100%
Vendor Data and Drawings for Common Exchangers ( IQ01-2018) 1440.00 08-Oct-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for DSS Air Coolers (1211-E-002/107/207) IQ01-2009 1216.00 29-Oct-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for Air Coolers(1211-E-005/009) IQ01-2021 1440.00 15-Sep-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for Column (C001/002/003 ) IQ01-2023 1664.00 24-Sep-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for HP Equipment(1211-V-104/106/204/206¡¢1211-C-101/201)-IQ01-2010 1312.00 10-Jul-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for ARDS Reactor(1211-R-101/102/103/104) IQ01-2001 2520.00 16-Apr-15 08:00 A 13-Jul-15 17:00 A 100% 100%
Vendor Data and Drawings for Cr-Mo Drums(1211-V-102/103/202/203)IQ01-2008 1240.00 04-Jul-15 00:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for Clading Drums (1211-V-004/005/006/008/101/201) IQ01-2012 1280.00 09-Sep-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for Large Size Drums(1211-V-003/007/013)IQ01-2013 1136.00 29-Sep-15 08:00 A 12-Aug-16 00:00 A 100% 100%
Vendor Data and Drawings for HP Centrifugal Separator(1211-V-105/205)IQ01-2014 992.00 12-Nov-15 08:00 A 26-Aug-16 08:00 A 100% 100%
Vendor Data and Drawings for Carbon Steel Drums (IQ01-2016) 1032.00 28-Sep-15 08:00 A 26-Aug-16 08:00 A 100% 100%
Vendor Data and Drawings for Column Internals (IQ01-2027) 1440.00 09-Sep-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Furnace (including Waste heat Boiler Package)IQ01-2006 1360.00 06-Nov-15 08:00 A 10-Nov-16 08:00 A 100% 100%
Vendor Data and Drawings for Fresh Feed Filter (1211-S-101/201)IQ01-2028 1200.00 12-Jan-16 08:00 A 23-Sep-16 08:00 A 100% 100%
Vendor Data and Drawings for HP Exchangers 1211-E-104A/B;105A~C;106£»E-204A/B;205A~C;206 £»IQ01- 1504.00 08-Oct-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Special Material Exchangers(1211-E-001/004A/B/008/011)IQ01-2017 1304.00 15-Sep-15 08:00 A 12-Aug-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 33 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

RFQ 2344.00 24-Oct-14 08:00 A 18-Sep-15 17:00 A 100% 100%


ARDS Reactor (IQ01-2001)
( 1384.00 24-Oct-14 08:00 A 30-Jun-15 17:00 A 100% 100%
HP Exchanger ((IQ01-2005) 1664.00 27-Oct-14 08:00 A 19-Aug-15 17:00 A 100% 100%
DSS Air Cooler (IQ01-2009)
( 1984.00 26-Dec-14 08:00 A 09-Sep-15 17:00 A 100% 100%
SM Exchanger ((IQ01-2017) 1240.00 29-Jan-15 08:00 A 11-Sep-15 17:00 A 100% 100%
High Pressure Equipment
E (IQ01-2010) Z-X 1608.00 04-Nov-14 08:00 A 18-Aug-15 17:00 A 100% 100%
Column Tray (IQ(IQ01-2027) 1736.00 03-Nov-14 08:00 A 02-Sep-15 17:00 A 100% 100%
HP Centrifugel Sepertator
S (IQ01-2014) 1792.00 29-Oct-14 08:00 A 18-Sep-15 17:00 A 100% 100%
Air Cooler (IQ01
(IQ01-2021) 1416.00 25-Dec-14 08:00 A 09-Sep-15 17:00 A 100% 100%
Common Exchan
Exchanger (IQ01-2018) 1208.00 03-Feb-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Cr-Mo Drum (IQ (IQ01-2008) 2112.00 03-Nov-14 08:00 A 18-Sep-15 17:00 A 100% 100%
Column (C101-0
(C101-001/002/003, IQ01-2023) 1064.00 06-Mar-15 08:00 A 18-Sep-15 17:00 A 100% 100%
Heater (IQ01-2006)
(IQ01-20 1360.00 30-Dec-14 08:00 A 31-Jul-15 08:00 A 100% 100%
Large Size Drum (IQ01-2013) 944.00 27-Mar-15 08:00 A 18-Sep-15 17:00 A 100% 100%
Cladding Drum ((IQ01-2012) 944.00 01-Apr-15 08:00 A 03-Sep-15 17:00 A 100% 100%
CS Drum (IQ01-
(IQ01-2016) 1200.00 06-Feb-15 08:00 A 02-Sep-15 17:00 A 100% 100%
Waste Heat Boiler
Boil package (1211-A-610£© 1536.00 12-Jan-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Etc 8.00 02-Nov-15 08:00 A 02-Nov-15 17:00 A 0% 0%
COS 8.00 02-Nov-15 08:00 A 02-Nov-15 17:00 A 0% 0%
Rotating Equipment 3824.00 30-Oct-14 08:00 A 26-Sep-16 17:00 A 100% 100%
Document 3224.00 30-Oct-14 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - K101/201(Recycle Gas Compressor, IQ01-1001) 1888.00 30-Oct-14 08:00 A 15-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - K001A/B (FRAC Off Gas Compressor, IQ01-1006) 1400.00 23-Jan-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - 1st Level Pump (IQ01-1005) 1336.00 25-Dec-14 08:00 A 21-Aug-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - 2nd Level Pump (IQ01-1004/) 392.00 23-Jan-15 08:00 A 06-Apr-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - P-002A/B(Injection Water Pumps) 1384.00 23-Jan-15 08:00 A 15-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry -Overhead Travelling Crane for 1211-K-001A/B 1416.00 16-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry -Overhead Travelling Crane for 1211-K-101/201 1960.00 16-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Drawing 2040.00 14-Sep-15 08:00 A 26-Sep-16 17:00 A 100% 100%
Vendor Data and Drawings for K101/201(Recycle Gas Compressor, IQ01-1001) 1280.00 15-Sep-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for K001 (Face Off Gas Compressor, IQ01-1006) 1280.00 27-Nov-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for 1st Level Pump(IQ01-1005) 1280.00 14-Sep-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for 2nd Level Pump (IQ01-1004/1011) 1200.00 25-Dec-15 08:00 A 26-Sep-16 17:00 A 100% 100%
Vendor Data and Drawings for Crane 1120.00 18-Dec-15 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 2288.00 31-Oct-14 08:00 A 11-Dec-15 17:00 A 100% 100%
K101/201(Recycle Gas Compressor, IQ01-1001)
K101/201(Recyc 1984.00 31-Oct-14 08:00 A 15-Sep-15 17:00 A 100% 100%
K001 (Face Off Gas Compressor, IQ01-1006) 1296.00 26-Jan-15 08:00 A 15-Sep-15 17:00 A 100% 100%
1st level Pump(REACTOR
Pump(R FEED PUMPS AND HP LEAN PUMPSIQ01-1005) 1208.00 26-Dec-14 08:00 A 31-Jul-15 17:00 A 100% 100%
2nd Level Pump/FRAC
Pump BOTTOMS PUMP/IQ01-1004/1011) 1176.00 26-Jan-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Injection Water Pump(IQ01-1012)
P 1808.00 23-Jan-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Compressor oveoverhead travelling crane 1024.00 17-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 2936.00 24-Apr-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Document 2840.00 13-May-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Telecommunication Cable Schedule
Telecommunicat 1600.00 02-Nov-15 08:00 A 14-Sep-16 17:00 A 100% 100%
MTO for Fire de detection 1880.00 13-May-15 08:00 A 15-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices 2064.00 15-May-15 08:00 A 20-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 2056.00 03-Aug-15 08:00 A 02-Sep-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Conduits And Accessories 1952.00 03-Aug-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Drawing 2544.00 24-Apr-15 08:00 A 27-Apr-16 17:00 A 100% 100%
layout for Teleco
Telecommunicaiton devices location 2440.00 24-Apr-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Telecommunicaiton Cable Routing layout
Telecommunicait 2144.00 06-Jul-15 08:00 A 27-Apr-16 17:00 A 100% 100%
RFQ 1952.00 14-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
detection 1952.00 14-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
devices 1568.00 18-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Cable 136.00 11-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 34 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Health, Safety, Env


Environmental and Security 3648.00 27-Oct-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Document 2712.00 16-Feb-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Safety Piping Lin
Line List 680.00 16-Feb-15 08:00 A 19-Jun-15 17:00 A 100% 100%
MTO for fire figh
fighting equipment 1352.00 24-Aug-15 08:00 A 26-Feb-16 17:00 A 100% 100%
Hazardous area classification schedule 2032.00 24-Mar-15 08:00 A 26-Feb-16 17:00 A 100% 100%
List of items to be
b fireproofed 1848.00 25-Mar-15 08:00 A 19-Nov-15 17:00 A 100% 100%
Noisy equipment list 848.00 01-Sep-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Safety sign spec
specification and datasheet 1696.00 19-Aug-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Drawing 3648.00 27-Oct-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Safety Drawing - Fire Protection and personnel protection 2176.00 25-Dec-14 08:00 A 21-Jan-16 17:00 A 100% 100%
Fire water spray system P&ID 2536.00 30-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 2216.00 13-May-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2728.00 10-Apr-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Hazardous area classification layout 2776.00 27-Oct-14 08:00 A 28-Jan-16 17:00 A 100% 100%
Fireproofing zone
zon drawings 1312.00 20-May-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Temporary must
mustering areas and escape routes layout 2048.00 13-May-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Safety sign layout 1680.00 20-Aug-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Deluge Nozzle Arrangment
A Calculation Note 1520.00 20-Aug-15 08:00 A 26-Feb-16 17:00 A 100% 100%
RFQ 896.00 01-Jul-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Hydro/ Hose box / Fire monitor 896.00 01-Jul-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Civil/Structure 3632.00 06-Feb-15 08:00 A 16-Dec-16 17:00 A 100% 100%
Document 3632.00 06-Feb-15 08:00 A 16-Dec-16 17:00 A 100% 100%
Calculation Notes
Note for RCK-1110 1328.00 06-Feb-15 08:00 A 15-Oct-15 17:00 A 100% 100%
Calculation Notes
Note for RCK-1100/1200/1210/1220/1230/1240 1328.00 06-Feb-15 08:00 A 15-Oct-15 17:00 A 100% 100%
Calculation Notes
Note for 1211-STR-1100/1200 1872.00 03-Jun-15 08:00 A 09-Feb-16 17:00 A 100% 100%
Calculation Notes
Note for 1211-STR-1300/1400 1216.00 03-Jun-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for 1211-STR-1500/1600 1168.00 03-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for Column Foundation 1211-C-002 1392.00 30-Apr-15 08:00 A 30-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for Column Foundation 1211-C-001/003 1392.00 30-Apr-15 08:00 A 30-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for Column Foundation 1211-C-101/201 1392.00 30-Apr-15 08:00 A 30-Dec-15 17:00 A 100% 100%
Calculation Notes
Note for Drum Foundation 1352.00 21-May-15 08:00 A 27-May-16 17:00 A 100% 100%
Calculation Notes
Note for Heat Exchanger Foundation 1624.00 21-May-15 08:00 A 20-May-16 17:00 A 100% 100%
Calculation Notes
Note for Pump Foundation 2048.00 13-Nov-15 08:00 A 16-Dec-16 17:00 A 100% 100%
Calculation Notes
Note for Filter Foundation 1211-S-101 /201 1872.00 17-Sep-15 08:00 A 27-May-16 17:00 A 100% 100%
Calculation Notes
Note for Furnace Foundation 656.00 03-Nov-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Calculation Notes
Note for Compressor Foundation 1211-K-001A/B 1232.00 11-Dec-15 08:00 A 19-May-16 17:00 A 100% 100%
Calculation Notes
Note for Compressor Foundation 1211-K-101/201 1432.00 02-Nov-15 08:00 A 19-May-16 17:00 A 100% 100%
Calculation Notes
Note for 1211-SHL-1100 1016.00 03-Aug-15 08:00 A 20-May-16 17:00 A 100% 100%
Calculation Notes
Note for 1211-SHL-1200 1472.00 03-Aug-15 08:00 A 20-May-16 17:00 A 100% 100%
Calculation Notes
Note for COC PIT 1211-T-101/102 1496.00 22-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
MTO for Reinforcing
Reinfor Steel 544.00 17-Dec-15 08:00 A 26-Feb-16 17:00 A 100% 100%
MTO for Structu
Structure Steel 800.00 12-May-15 08:00 A 12-Aug-15 17:00 A 100% 100%
MTO for Equipm
Equipment Anchor Bolts 544.00 05-May-15 08:00 A 06-Aug-15 17:00 A 100% 100%
MTO for Steel S Structure Anchor Bolts 632.00 06-May-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Drawing 3360.00 16-Feb-15 08:00 A 30-Sep-16 17:00 A 100% 100%
Drawing - Drainage
Draina and Undeground Piping Drawing 1768.00 08-Jun-15 08:00 A 06-Apr-16 17:00 A 100% 100%
PILE LAYOUT O OF 1211-RCK-1110 792.00 08-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-RCK-1100 728.00 08-Jun-15 08:00 A 02-Nov-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-RCK-1200 728.00 08-Jun-15 08:00 A 02-Nov-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-RCK-1210 688.00 08-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-RCK-1220 728.00 08-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-RCK-1230 728.00 08-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-RCK-1240 728.00 08-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-STR-1100 744.00 04-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-STR-1200 744.00 04-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 35 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

PILE LAYOUT O OF 1211-STR-1300 736.00 04-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-STR-1400 736.00 04-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-STR-1500 1304.00 04-Jun-15 08:00 A 18-Dec-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-STR-1600 744.00 04-Jun-15 08:00 A 15-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1211-SHL-1100 1600.00 04-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1211-K-101 1464.00 22-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1211-K-201 1464.00 22-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1211-SHL-1200 1448.00 22-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1211-K-001A, 001B 1448.00 22-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1211-C-101 1296.00 21-May-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Pile Layout Of 1211-C-201
12 1296.00 21-May-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Pile Layout Of 1211-C-002
12 1296.00 21-May-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Pile Layout Of 11211-C-003 1296.00 21-May-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Pile Layout Of 11211-V-007 1512.00 22-May-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Pile Layout Of 11211-V-013 1736.00 22-May-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Pile Layout Of 1211-F-001
12 624.00 12-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Pile Layout OF 11211-F-101/201 664.00 09-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout For Unit
U 1211 1216.00 05-Nov-15 08:00 A 19-May-16 17:00 A 100% 100%
Pile Layout Of EExchangers 1544.00 19-Jun-15 08:00 A 15-Feb-16 17:00 A 100% 100%
Equipment Foun
Foundations Drawings forColumn-1211-C-101/201 1784.00 04-May-15 08:00 A 30-Dec-15 17:00 A 100% 100%
Foundations Of Column-1211-C-002 1464.00 04-May-15 08:00 A 30-Dec-15 17:00 A 100% 100%
Foundations Of Column-1211-C-003 1608.00 04-May-15 08:00 A 30-Dec-15 17:00 A 100% 100%
Foundations Of Drum 1776.00 22-May-15 08:00 A 30-May-16 17:00 A 100% 100%
Foundations Of Heat Exchanger 1920.00 21-May-15 08:00 A 20-May-16 17:00 A 100% 100%
Foundations Of 1st Pump 1760.00 16-Nov-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Foundations Of 2st Pump /injection pump 1824.00 16-Nov-15 08:00 A 30-Sep-16 17:00 A 100% 100%
Foundations Of Furnace 1152.00 04-Nov-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Foundations Of Compressor 1211 K-001A/B 1016.00 14-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Foundations Of Compressor--1211 K-101/201 968.00 03-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Foundations Of RCK-1100/1200/1210/1220/1230/1240/1250/1260 1560.00 30-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Foundations Of RCK-1110 1752.00 30-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Foundations Of 1211-STR-1100/1200 1616.00 04-Jun-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Foundations Of1211-STR-1300/1400
Of1 1616.00 04-Jun-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Foundations Of 1211-STR-1500/1600 1592.00 04-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Foundations Of 1211-SHL-1100 680.00 18-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Foundations Of 1211-SHL-1200 1088.00 08-Oct-15 08:00 A 29-Jan-16 17:00 A 100% 100%
General Layout - Drawing for stormwater drainage network 2512.00 27-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
General Layout - Surfacing and grading finishing layout 2168.00 27-Apr-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Drawing - Drainage
Draina and Undeground Piping Drawing - Refinery 03 - Units 1211 2936.00 16-Feb-15 08:00 A 29-Feb-16 17:00 A 100% 100%
Equipment Foun
Foundations Drawings for Filter 1552.00 18-Sep-15 08:00 A 27-May-16 17:00 A 100% 100%
COC PIT 1211-T-101/201
1211-T STRUCTURAL DRAWING 1816.00 23-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-SHL-1100(Elevation ¡¢ Framing Plans) 512.00 12-Nov-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-SHL-1100(Columns¡¢Details) 480.00 01-Dec-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-STR-1500/1600(Framing Plans ¡¢Elevation) 1192.00 04-Jun-15 08:00 A 29-Dec-15 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-STR-1500/1600( Details¡¢ Columns) 1000.00 19-Aug-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-SHL-1200(Elevation ¡¢Framing Plans) 512.00 12-Nov-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-SHL-1200(Columns¡¢Details) 480.00 10-Nov-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-STR-1100/1200(Elevation ¡¢Framing Plans) 1200.00 03-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-STR-1100/1200(Columns ¡¢Details) 1312.00 18-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-STR-1300/1400 (Elevation ¡¢Framing Plans) 1200.00 03-Jun-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Structure Drawings
Drawin for 1211-STR-1300/1400( Columns¡¢Details) 1352.00 11-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
SD for RCK-1100/1200/1210/1220/1230/1240/1250/1260
RCK-110 (Elevation ¡¢Framing Plans) 1504.00 30-Apr-15 08:00 A 18-Jan-16 17:00 A 100% 100%
SD for RCK-1100/1200/1210/1220/1230/1240/1250/1260(Columns
RCK-110 ¡¢Details) 1456.00 12-May-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Structure Drawin
Drawings for RCK-1110(Elevation ¡¢ Framing Plans) 1784.00 30-Apr-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Structure Drawin
Drawings for RCK-1110(Columns ¡¢Details) 1600.00 12-May-15 08:00 A 18-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 36 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Foundation Layout
Layo for Unit 1211 1824.00 31-Aug-15 08:00 A 21-Jul-16 17:00 A 100% 100%
RFQ 984.00 07-May-15 08:00 A 14-Aug-15 17:00 A 100% 100%
Requisition for st structural steel 160.00 08-Jun-15 08:00 A 03-Jul-15 17:00 A 100% 100%
Requisitions for equipment
e anchor bolts 728.00 22-Jun-15 08:00 A 06-Aug-15 17:00 A 100% 100%
Requisitions for steels structure anchor bolts 984.00 07-May-15 08:00 A 14-Aug-15 17:00 A 100% 100%
Architectural 2136.00 17-Jun-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Drawing 2136.00 17-Jun-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Compressor She Shelter 1 Elevations 1616.00 16-Sep-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Compressor She Shelter 1 Sections 1608.00 17-Sep-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Compressor She Shelter 1 Roof Plan 1592.00 21-Sep-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Compressor She Shelter 1 Ground Floor Plan 1600.00 18-Sep-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Compressor She Shelter 2 Elevations 1720.00 17-Jun-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Compressor She Shelter 2 Sections 1704.00 19-Jun-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Compressor She Shelter 2 Roof Plan 1712.00 18-Jun-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Compressor She Shelter 2 Ground Floor Plan 1496.00 22-Jun-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Piping 4568.00 25-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Document 3072.00 30-Mar-15 08:00 A 19-Oct-16 17:00 A 100% 100%
Critical line list 1720.00 30-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Piping Stress Calculations
Ca and analysis report 3032.00 06-Apr-15 08:00 A 19-Oct-16 17:00 A 100% 100%
Pipe support lists(Standard
lists and Special) 144.00 18-Dec-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Spring list and datasheet
da 2512.00 19-May-15 08:00 A 13-Jun-16 17:00 A 100% 100%
Steam Tracing List L 176.00 01-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
MTO for U/G Pipe Pip System 808.00 27-Apr-15 08:00 A 30-Oct-15 16:50 A 100% 100%
Data Sheet for S Safety Valve 1144.00 30-Mar-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Data Sheet for S Silencer 904.00 30-Mar-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheet for S Sampler 704.00 13-Apr-15 08:00 A 13-Aug-15 17:00 A 100% 100%
Material Take Off Of for Insulation 56.00 01-Jun-16 08:00 A 31-Aug-16 17:00 A 100% 100%
Material Take Off Of for Piping Bulk Material 184.00 07-Dec-15 08:00 A 07-Jan-16 17:00 A 100% 100%
Material Take Off Of for Piping Painting 96.00 01-Jun-16 08:00 A 31-Aug-16 17:00 A 100% 100%
Material Take Of Off for Special Item 88.00 01-Jul-16 08:00 A 31-Aug-16 17:00 A 100% 100%
Drawing 4568.00 25-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Above Ground Piping P GA Key Plan 3344.00 25-Dec-14 08:00 A 24-Apr-15 17:00 A 100% 100%
Key Plan of Equipment
Equi Layout 2872.00 27-Oct-14 08:00 A 29-Jan-16 17:00 A 100% 100%
ARDS 1211 Unit Plot Plan 2680.00 25-Aug-14 08:00 A 11-Dec-15 17:00 A 100% 100%
Special Pipe Support
Sup Drawing and list 1984.00 23-Nov-15 08:00 A 10-Oct-16 17:00 A 100% 100%
Piping battery limit
lim interface table 2048.00 06-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
ISO drawing for U/G piping and list 936.00 23-Nov-15 08:00 A 11-Mar-16 17:00 A 100% 100%
Piping General Arrangement
A drawings 1720.00 23-Nov-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Equipment layout 1920.00 18-Feb-15 08:00 A 29-Jan-16 17:00 A 100% 100%
3D-Modeling/review report/action close-out-report
3D-Modeling/rev 3632.00 27-Oct-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Piping Isometric Drawings(with Materials) and list 1640.00 23-Nov-15 08:00 A 25-Mar-16 17:00 A 100% 100%
RFQ 2928.00 31-Mar-15 08:00 A 31-Aug-16 17:00 A 100% 100%
MR for Blanket Order O of Piping/Fitting/Valve 352.00 06-Apr-15 08:00 A 05-Jun-15 17:00 A 100% 100%
Misc. Piping EquEquipment 512.00 21-May-15 08:00 A 20-Aug-15 17:00 A 100% 100%
1st Piping Support
Suppo 952.00 17-Aug-15 08:00 A 20-Oct-15 17:00 A 100% 100%
1st U/G Piping 664.00 28-Apr-15 08:00 A 21-Aug-15 17:00 A 100% 100%
MR for U/G GRP Bulk Material 656.00 29-Apr-15 08:00 A 21-Aug-15 17:00 A 100% 100%
U/G Valves 896.00 24-Aug-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Safety Valve 1712.00 31-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
1st Pipes & Tubes
Tube 136.00 23-Nov-15 08:00 A 25-Dec-15 17:00 A 100% 100%
1st Piping Valves 504.00 01-Jul-15 08:00 A 25-Sep-15 17:00 A 100% 100%
2nd Piping/Valves/Fitting
Piping/Valve 832.00 18-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
MR of Spring Ha Hanger 376.00 01-Jul-15 08:00 A 17-Jul-15 17:00 A 100% 100%
2st Piping Supp
Support/Insulation 1408.00 18-Dec-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Etc 1712.00 25-Dec-14 08:00 A 11-Dec-15 17:00 A 0% 0%

Remaining Level of Effort Actual Work Critical Remaining ... Page 37 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

COS 1712.00 25-Dec-14 08:00 A 11-Dec-15 17:00 A 0% 0%


Electrical 3688.00 25-Dec-14 08:00 A 19-Sep-16 17:00 A 100% 100%
Document 3592.00 25-Dec-14 08:00 A 02-Sep-16 08:00 A 100% 100%
Electrical Consumer
Consum List 2400.00 27-Mar-15 08:00 A 25-Dec-15 17:00 A 100% 100%
List / Schedule for
fo Electrical Cable List 1760.00 05-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Electrical Cable Drum
D Schedule 936.00 04-Jan-16 08:00 A 25-Mar-16 17:00 A 100% 100%
MTO for Cable 1968.00 29-Sep-15 08:00 A 24-Jun-16 17:00 A 100% 100%
MTO for Other M Material(Steel/Termination Kit/Calbe Joint/Cable Gland/Seal Material) 2048.00 29-Sep-15 08:00 A 02-Sep-16 08:00 A 100% 100%
MTO for Cable T Tray 2464.00 05-Jun-15 08:00 A 01-Aug-16 17:00 A 100% 100%
MTO for Earthin
Earthing and Lighting Material 2016.00 13-Jul-15 08:00 A 10-May-16 17:00 A 100% 100%
MTO for Lighting Fixtures 720.00 24-Dec-15 08:00 A 10-May-16 17:00 A 100% 100%
MTO for Conduit 1928.00 29-Sep-15 08:00 A 22-Jul-16 17:00 A 100% 100%
MTO for Explosi
Explosion-proof materila/Explosion-proof control switch/Socket Outlets/Panel 760.00 15-Feb-16 08:00 A 15-Apr-16 17:00 A 100% 100%
MTO for Cathod
Cathodic Protection 448.00 13-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
MTO for Elec. H Heat Tracing 424.00 19-Feb-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Data Sheet For LV Induction Motor 1176.00 25-Dec-14 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheet For HV Induction Motor 1168.00 26-Dec-14 08:00 A 24-Jul-15 17:00 A 100% 100%
Drawing 3016.00 27-Apr-15 08:00 A 14-Sep-16 17:00 A 100% 100%
INTERFACE DRAWING
DR OF CABLE ROUTING 1520.00 27-May-15 08:00 A 25-Feb-16 17:00 A 100% 100%
INTERFACE DRAWING
DR OF EARTHING SYSTEM 2792.00 28-May-15 08:00 A 01-Jun-16 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 1792.00 27-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
BLIT OF CABLES
CABLE 2120.00 28-Apr-15 08:00 A 15-Jan-16 17:00 A 100% 100%
BLIT OF CABLESTRENCH
CABLE 2104.00 29-Apr-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Cathodic Protection
Protect System Layout 1472.00 18-Sep-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Lighting Layout (Unit/Street)
( 1464.00 17-Sep-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Lighting Loop Diagram
Di 1728.00 18-Sep-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout (Aboveground) 2648.00 27-Apr-15 08:00 A 01-Aug-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout (Underground) 2768.00 27-Apr-15 08:00 A 15-Jun-16 17:00 A 100% 100%
Wiring / Interconection
Intercon Diagram 1264.00 25-Dec-15 15:24 A 14-Sep-16 17:00 A 100% 100%
Small Power DisDistribution Panel Single Line Diagram 1280.00 23-Oct-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Electrical Heat Tracing
T Layout 1016.00 30-Nov-15 08:00 A 19-Feb-16 17:00 A 100% 100%
RFQ 1768.00 29-Sep-15 08:00 A 15-Jul-16 17:00 A 100% 100%
Earthing and Lighting
Lig Material 248.00 02-Nov-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Cable Tray 800.00 29-Sep-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Cable 176.00 26-Oct-15 08:00 A 02-Dec-15 17:00 A 100% 100%
Conduit 872.00 01-Mar-16 08:00 A 15-Jul-16 17:00 A 100% 100%
Lighting Fixtures 176.00 01-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch/Socket Outlets/Panel 264.00 16-Nov-15 08:00 A 30-Dec-15 17:00 A 100% 100%
Cathodic Protection
Protect 312.00 22-Dec-15 08:00 A 14-Jan-16 17:00 A 100% 100%
Elec. Heat Tracing
Tracin 256.00 02-Nov-15 08:00 A 01-Dec-15 17:00 A 100% 100%
Other Material(Steel/Termination
Material(S Kit/Calbe Joint/Cable Gland/Seal Material) 768.00 25-Dec-15 08:00 A 09-May-16 17:00 A 100% 100%
Etc 88.00 01-Sep-16 08:00 A 19-Sep-16 17:00 A 0% 0%
COS 88.00 01-Sep-16 08:00 A 19-Sep-16 17:00 A 0% 0%
Instrumentation anand control 4152.00 22-Oct-14 08:00 A 31-Oct-16 17:00 A 100% 100%
Document 4152.00 25-Dec-14 08:00 A 18-Oct-16 17:00 A 100% 100%
Instrument Index 296.00 25-Dec-14 08:00 A 15-Feb-15 17:00 A 100% 100%
System I/O LIST 376.00 26-Dec-14 08:00 A 06-Mar-15 17:00 A 100% 100%
Power Feeds ListLis with Power Consumption for UPS and non-UPS Consumers 128.00 03-Apr-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Instrument Air C Consumption Calculations 416.00 09-Feb-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Datasheet for Integral
In Orifice D/P Flow Transmitter 1768.00 17-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for H H2 Analyser/Sulfur Analyzer 2464.00 16-Feb-15 08:00 A 06-May-16 17:00 A 100% 100%
Datasheet for lContinuous
lC Emission Monitoring System (CEMS) 2464.00 16-Feb-15 08:00 A 06-May-16 17:00 A 100% 100%
Data Sheet for C Control Valve (Globe) 1664.00 16-Feb-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Data Sheet for D Deluge Valve 2640.00 16-Feb-15 08:00 A 23-Mar-16 17:00 A 100% 100%
Datasheet for Displacer
Di Level Instrument 1576.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 38 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Data Sheet for D DP Flow /Level Transmitter 1744.00 16-Feb-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for DP Transmitter 1576.00 16-Feb-15 08:00 A 29-Sep-15 17:00 A 100% 100%
Datasheet for W Wireless Temperature Transmitter 1776.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for E Elec. Motorized Valves (Gate/ORBIT/Y-Patten) 1584.00 16-Feb-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Data Sheet for C Control Valve (Angle) 1856.00 16-Feb-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Datasheet for Control
Co Valve(Antisurge) 2104.00 08-Oct-15 08:00 A 18-Oct-16 17:00 A 100% 100%
Data Sheet for E Emergency Depressure Valve 2016.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for P Process ESD Ball Valve(Ball) 2024.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for O Oil in Water Analyser 1784.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Flow
Fl Element- Restriction Orifice 1776.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Flow
Fl Element- Venturi Tube 1776.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Flow
Fl Element- Nozzle 1736.00 16-Feb-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Data Sheet for G Gas Detector 2040.00 16-Feb-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Datasheet for Level
Le Gauge 1400.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Le Level Transmitter Radar Type 1400.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Local
L Milliammeter 1288.00 16-Feb-15 08:00 A 05-Nov-15 17:00 A 100% 100%
Datasheet for Magnetic
M Level Gauge 1400.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for O Orifice Plate 1816.00 16-Feb-15 08:00 A 04-Jan-16 17:00 A 100% 100%
Datasheet for Pressure
Pr Gauge 664.00 01-Jun-15 08:00 A 06-Nov-15 17:00 A 100% 100%
Data Sheet for P Pressure Transmitter 1400.00 16-Feb-15 08:00 A 29-Sep-15 17:00 A 100% 100%
Data Sheet for P Process On-off Valve (Ball) 1360.00 16-Feb-15 08:00 A 22-Oct-15 17:00 A 100% 100%
Data Sheet for S Self-Actuating Control Valve 1232.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Data Sheet for Temperature
T Skin 1288.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Te Temperature Transmitter 1608.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Thermometer
Th 1608.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for T Thermowell 1608.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for Reactor
R Bed Mutipoint Thermocouples 1400.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Variable
Va Area Flow Meter 2064.00 16-Feb-15 08:00 A 18-Nov-15 17:00 A 100% 100%
Datasheet for Se Self-Actuating Flow Regulator 1368.00 17-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Co Conductivity Analyser 1584.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Cable Drum Sch Schedules 1256.00 08-Dec-15 08:00 A 25-Jan-16 17:00 A 100% 100%
Alarm rationalisa
rationalisation study report and alarm reference data base 1680.00 30-Nov-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Analyser Sample System Transportation times 792.00 08-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable Sizing/Selection
Sizing/Sel Calculations 992.00 08-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Configuration Data
Da for Machine Monitoring System and Performance Monitoring System 376.00 11-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
DCS Group Displays
Disp & Reports 1728.00 30-Nov-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Instrument Cable Schedules 672.00 04-Dec-15 08:00 A 25-Jan-16 17:00 A 100% 100%
Instrument NamName Plate Schedules 208.00 04-Dec-15 08:00 A 16-Dec-15 17:00 A 100% 100%
Intrinsically Safe(IS)
Safe( Loop Calculations 1680.00 23-Nov-15 08:00 A 16-Sep-16 17:00 A 100% 100%
IPF classification
classifications, verification reports 2496.00 01-Jul-15 08:00 A 08-Feb-16 17:00 A 100% 100%
Junction Box Schedules
Sch 464.00 08-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Instrument Nozz
Nozzel Elevations Caculation 1296.00 06-Jul-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Calculation for Control
C Valves 608.00 11-Dec-15 08:00 A 28-Mar-16 17:00 A 100% 100%
Sizing Calculations
Calculatio for Flow Elements 3232.00 11-Jun-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Thermowell Wak Wake Frequency Calculations 584.00 07-Dec-15 08:00 A 05-Apr-16 17:00 A 100% 100%
MTO 176.00 04-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Drawing 3072.00 27-Apr-15 08:00 A 31-Oct-16 17:00 A 100% 100%
Shutdown and LogicL Diagrams 1696.00 03-Aug-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Instrument Main Cable Routing 2120.00 27-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Instrument Cable trays/trench Layouts 1864.00 23-Nov-15 08:00 A 31-Oct-16 17:00 A 100% 100%
Instument Locati
Location Layout 2000.00 23-Oct-15 08:00 A 23-Jun-16 17:00 A 100% 100%
Instrument hook
hook-up Drawings 1120.00 23-Oct-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Junction Box Wiring
Wir Diagrams 1056.00 26-Oct-15 00:00 A 22-Jan-16 17:00 A 100% 100%
Graphic Display Sketches 656.00 18-Nov-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Instrument Earth
Earthing Layouts 1928.00 26-Oct-15 08:00 A 12-Jul-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 39 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Instument Air DisDistribution Layouts 1568.00 26-Oct-15 00:00 A 03-May-16 17:00 A 100% 100%
Instrument Loop Diagrams 1168.00 11-Mar-16 08:00 A 23-May-16 17:00 A 100% 100%
RFQ 2400.00 22-Oct-14 08:00 A 18-Mar-16 17:00 A 100% 100%
MAC (INC-MRI-
(INC-MRI-0001-0001) 1496.00 16-Feb-15 08:00 A 11-Nov-15 17:00 A 100% 100%
Control Valves/o
Valves/on-off valves (MRI-0001-0501,0502,0503,0504,0505,0506,0507,0508,0509,0510) 1264.00 17-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Orifice Plate/Flow Element/Temperature Element(MRI-0001-0102,0105,0106,0107,0108,0109) 1632.00 17-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Level/Gauge (INC-MRI-0001-0201,0202,0203,0204,0205,0301)
(IN 1528.00 17-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Analysis (INC-MRI-0001-0302,0303,0401,0402,0403,0404,0405)
(INC-M 1888.00 17-Feb-15 08:00 A 07-Jan-16 17:00 A 100% 100%
Transmitter (INC(INC-MRI-0001-0302,0303,0401,0402,0403,0404,0405) 1928.00 22-Oct-14 08:00 A 20-Nov-15 17:00 A 0% 0%
Instrument Junct
Junction Boxes (INC-MRI-1110-0903) 432.00 08-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Instrument Cable (INC-MRI-1110-0901) 224.00 07-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Cable Tray (INC-MRI-1110-0902)
(INC 600.00 08-Jan-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Inst. Material (IN
(INC-MRI-1110-0904/0905/0906/0907) 344.00 08-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
1212 - ARDS - Atmospheric
Atm Residue Desulphurization 7472.00 22-Aug-14 08:00 A 02-May-18 17:00 100% 99.99%
Process 6192.00 22-Aug-14 08:00 A 12-Sep-17 17:00 A 100% 100%
Document 6192.00 22-Aug-14 08:00 A 12-Sep-17 17:00 A 100% 100%
Process Data SheetSh for Heat Exchangers - 1212-E-601 - Blowdown cooling exchanger 1464.00 25-Dec-14 08:00 A 31-Aug-15 17:00 A 100% 100%
Process Data SheetSh for blowdown drum 1212-V-601 792.00 26-Mar-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Process Data Sh Sheet for LP Clean Condensate Flash Drum 1212-V-602 696.00 13-Apr-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Cause and Effect
Effec Matrix 5512.00 25-Dec-14 08:00 A 12-Sep-17 17:00 A 100% 100%
Hydraulic calculation
calcula notes for pumps 1008.00 20-May-15 08:00 A 18-Sep-15 17:00 A 100% 100%
Hydraulic calculation
calcula notes 720.00 03-Aug-15 08:00 A 18-Jan-16 17:00 A 100% 100%
List of alarms anand trips with set points 4488.00 30-Jun-15 08:00 A 12-Sep-17 17:00 A 100% 100%
Piping Lines lists 3320.00 26-Feb-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Process Data SheetSh for C001/002/003 1240.00 03-Nov-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data SheetSh for 1212-C-101 (201) (HP H2S Absorber) 1736.00 22-Aug-14 08:00 A 03-Jul-15 17:00 A 100% 100%
Process Data SheetSh for Large Sizes Drum 1608.00 25-Aug-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data Sh Sheet for HP Drum 1616.00 22-Aug-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data Sh Sheet for CS Drum 1240.00 03-Nov-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data SheetSh for Cladding Drum 1240.00 03-Nov-14 08:00 A 12-Jun-15 17:00 A 100% 100%
Process Data SheetSh for Cr-Mo Drum 1240.00 22-Aug-14 08:00 A 07-Apr-15 17:00 A 100% 100%
Process Data SheetSh for HP Centrifugal Separator 1632.00 03-Sep-14 08:00 A 26-Jun-15 17:00 A 100% 100%
Process Data SheetSh for SM Heat Exchanger 1400.00 03-Nov-14 08:00 A 10-Jul-15 17:00 A 100% 100%
Process Data SheetSh for HP Heat Exchanger 1392.00 02-Dec-14 08:00 A 07-Aug-15 17:00 A 100% 100%
Process Data SheetSh for DSS Air Cooler 1352.00 02-Dec-14 08:00 A 31-Jul-15 17:00 A 100% 100%
Process Data SheetSh for Air Cooler 1216.00 25-Dec-14 08:00 A 31-Jul-15 17:00 A 100% 100%
Process Data Sh Sheet for Common Heat Exchanger 1280.00 25-Dec-14 08:00 A 12-Aug-15 17:00 A 100% 100%
Process Data SheetSh for 1212-S-101/201 (Fresh Feed Filter) 1416.00 22-Aug-14 08:00 A 08-May-15 17:00 A 100% 100%
Process Data SheetSh for Control Valves 1408.00 22-Apr-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Process Data Sh Sheet for On-off Valves 2864.00 21-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Process Data Sh Sheet for Flow Elements 1408.00 25-May-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Process Data SheetSh for Restriction Orifices 960.00 14-Jul-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Process Data Sh Sheet for Pressure Safety Valves 3472.00 30-Jan-15 08:00 A 27-Sep-16 17:00 A 100% 100%
Process Data SheetSh for Analyzers 1352.00 16-Feb-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Process Data SheetSh for Desuperheater 1752.00 16-Feb-15 08:00 A 29-Sep-15 17:00 A 100% 100%
Drawing 4272.00 22-Aug-14 08:00 A 16-Sep-16 17:00 A 100% 100%
PFD 3440.00 22-Aug-14 08:00 A 16-Mar-16 17:00 A 100% 100%
UFD BATCH 1 2688.00 24-Oct-14 08:00 A 31-Aug-15 17:00 A 100% 100%
UFD BATCH 2 3344.00 24-Oct-14 08:00 A 17-Jun-16 17:00 A 100% 100%
P&ID BATCH 1 2952.00 24-Oct-14 08:00 A 08-Mar-16 17:00 A 100% 100%
UID BATCH 1 2512.00 27-Oct-14 08:00 A 08-Sep-15 17:00 A 100% 100%
P&ID BATCH 2 2968.00 24-Oct-14 08:00 A 08-Mar-16 17:00 A 100% 100%
UID BATCH 2 3936.00 27-Oct-14 08:00 A 16-Sep-16 17:00 A 100% 100%
P&ID BATCH 3 ((P&ID for COC lift pits) 2472.00 20-Nov-14 08:00 A 08-Sep-15 17:00 A 100% 100%
Material Selectio
Selection Diagram 1960.00 24-Oct-14 08:00 A 03-Nov-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 40 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

RFQ 1608.00 17-Nov-14 08:00 A 31-Aug-15 17:00 A 100% 100%


Fresh Feed Filte
Filter (1212-S-101/201£©(IQ01-2028) 1608.00 17-Nov-14 08:00 A 31-Aug-15 17:00 A 100% 100%
Etc 464.00 03-Nov-14 08:00 A 22-Jan-15 17:00 A 0% 0%
COS 464.00 03-Nov-14 08:00 A 22-Jan-15 17:00 A 0% 0%
Material, Corrison and Inspection 6288.00 30-Mar-15 08:00 A 02-May-18 17:00 100% 98.8%
Document 6288.00 30-Mar-15 08:00 A 02-May-18 17:00 100% 98.47%
RBI Excution Plan
Pla 2264.00 13-Apr-15 08:00 A 08-Mar-16 17:00 A 100% 100%
MATERIAL SELECTION
SELE GUIDE 952.00 03-Aug-15 08:00 A 16-Feb-16 17:00 A 100% 100%
RBI Risk Manag
Management Report 2992.00 22-Jun-15 08:00 A 29-Nov-16 17:00 A 100% 100%
RBI Inspection R Reference Plan 3560.00 24-Jun-15 08:00 A 28-Mar-17 17:00 A 100% 100%
RBI MANUAL 5808.00 23-Jun-15 08:00 A 02-May-18 17:00 100% 70%
Corrosion Design
Desig Basis Memorandum 2640.00 24-Jun-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Corrosion Management
Mana Plan 2104.00 09-Oct-15 08:00 A 25-Jan-16 17:00 A 100% 100%
Corrosion Execu
Execution Plan 1472.00 25-Jun-15 08:00 A 25-Jan-16 17:00 A 100% 100%
Corrosion study plan 1688.00 15-Oct-15 08:00 A 08-Mar-16 17:00 A 100% 100%
Corrosion Preve
Prevention Program 488.00 15-Oct-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Data Sheets 1648.00 30-Mar-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Installation Specification
Spec 3696.00 19-Nov-15 08:00 A 12-Sep-17 17:00 A 100% 100%
Drawing 1264.00 29-Jan-16 08:00 A 18-May-17 17:00 A 100% 100%
Vendor Data and Drawings 1264.00 29-Jan-16 08:00 A 18-May-17 17:00 A 100% 100%
RFQ 2048.00 31-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Corrosion Monitoring
Monito System 2048.00 31-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 3768.00 24-Oct-14 08:00 A 10-Nov-16 08:00 A 100% 100%
Document 2736.00 03-Nov-14 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical data sheet for Heat Exchangers 1212-E-601 - Blowdown cooling exchanger 1008.00 18-May-15 08:00 A 22-Sep-15 17:00 A 100% 100%
Mechanical data sheet for blowdown drum 1212-V-601 1776.00 06-Apr-15 08:00 A 09-Dec-15 17:00 A 100% 100%
Mechanical data sheet for LP Clean Condensate Flash Drum 1212-V-602 896.00 08-Jun-15 08:00 A 27-Oct-15 17:00 A 100% 100%
Mechanical data sheet for First Reactor 1192.00 18-May-15 08:00 A 13-Oct-15 17:00 A 100% 100%
Mechanical data sheet for Second Reactor / Third Reactor / Fourth Reactor 1176.00 18-May-15 08:00 A 13-Oct-15 17:00 A 100% 100%
Mechanical data sheet for Column 672.00 04-Nov-14 08:00 A 05-Mar-15 17:00 A 100% 100%
Mechanical data sheet for Clading Drum 520.00 25-Dec-14 08:00 A 31-Mar-15 17:00 A 100% 100%
Mechanical data sheet for HP Equipment 1608.00 03-Nov-14 08:00 A 17-Aug-15 17:00 A 100% 100%
Mechanical data sheet for CS Drums 992.00 03-Nov-14 08:00 A 29-Apr-15 17:00 A 100% 100%
Mechanical data sheet for Large sizeDrums 496.00 25-Dec-14 08:00 A 26-Mar-15 17:00 A 100% 100%
Mechanical data sheet for Cr-Mo Drum 1136.00 05-Feb-15 08:00 A 27-Aug-15 17:00 A 100% 100%
Mechanical data sheet for DSS Air Cooler 1496.00 25-Dec-14 08:00 A 07-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Air Cooler 552.00 04-Nov-14 08:00 A 09-Feb-15 17:00 A 100% 100%
Mechanical data sheet for SM Exchanger 640.00 04-Nov-14 08:00 A 28-Feb-15 17:00 A 100% 100%
Mechanical data sheet for Common Exchanger 640.00 02-Feb-15 08:00 A 28-May-15 17:00 A 100% 100%
Mechanical data sheet for HP Exchangers 1104.00 05-Feb-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Mechanical data sheet for Fired-heater 2416.00 29-Dec-14 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical Data Sheet for Waste Heat boiler package(1212-A-610) 1272.00 09-Jan-15 08:00 A 25-Aug-15 17:00 A 100% 100%
Drawing 3760.00 27-Oct-14 08:00 A 10-Nov-16 08:00 A 100% 100%
General Arrangement
Arrange Drawing for Cr-Mo Drum 448.00 01-Jul-15 08:00 A 14-Sep-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for HP Drum 2840.00 03-Nov-14 08:00 A 07-Sep-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for HP Centrifugal Separator 1336.00 25-Dec-15 08:00 A 19-Apr-16 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Large Sizes Drum 624.00 14-Apr-15 08:00 A 31-Jul-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for LP Clean Condensate Flash Drum 1212-V-602 1992.00 09-Jun-15 08:00 A 20-Nov-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Column C-002 1368.00 09-Mar-15 08:00 A 02-Sep-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Column (C-001/003) 1560.00 31-Mar-15 08:00 A 15-Dec-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for blowdown drum 1212-V-601 1680.00 07-Apr-15 08:00 A 20-Nov-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for HP Column (C101/201 ) 2272.00 03-Nov-14 08:00 A 02-Sep-15 17:00 A 100% 100%
General Drawing for 1212-R-101/201 First Reactor 2304.00 27-Oct-14 08:00 A 02-Sep-15 17:00 A 100% 100%
General Drawing for Second Reactor / Third Reactor / Fourth Reactor 2304.00 27-Oct-14 08:00 A 02-Sep-15 17:00 A 100% 100%
General Arrangement
Arrange Drawing for Cladding Drum 176.00 01-Sep-15 10:24 A 13-Oct-15 10:24 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 41 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

General Arrangement
Arrange Drawing for CS Drum 176.00 01-Oct-15 10:24 A 13-Oct-15 10:24 A 100% 100%
Vendor Data and Drawings for Common Exchangers ( IQ01-2018) 1440.00 08-Oct-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for DSS Air Coolers (1212-E-002/107/207) IQ01-2009 1216.00 29-Oct-15 08:00 A 12-Aug-16 08:00 A 100% 100%
Vendor Data and Drawings for Air Coolers(1212-E-005/009) IQ01-2021 1440.00 15-Sep-15 08:00 A 12-Aug-16 08:00 A 100% 100%
Vendor Data and Drawings for Column (C001/002/003 ) IQ01-2023 1664.00 08-Oct-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for HP Equipment(1212-V-104/106/204/206¡¢1212-C-101/201)-IQ01-2010 1312.00 10-Jul-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for ARDS Reactor(1212-R-101/102/103/104) IQ01-2001 2520.00 16-Apr-15 08:00 A 13-Jul-15 17:00 A 100% 100%
Vendor Data and Drawings for Cr-Mo Drums(1212-V-102/103/202/203)IQ01-2008 1240.00 04-Jul-15 00:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Clading Drums (1212-V-004/005/006/008/101/201) IQ01-2012 1280.00 09-Sep-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Large Size Drums(1212-V-003/007/013)IQ01-2013 1136.00 29-Sep-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for HP Centrifugal Separator(1212-V-105/205)IQ01-2014 992.00 12-Nov-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Carbon Steel Drums (IQ01-2016) 1032.00 28-Sep-15 08:00 A 12-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for Column Internals (IQ01-2027) 1440.00 09-Sep-15 08:00 A 12-Aug-16 08:00 A 100% 100%
Vendor Data and Drawings for Furnace (including Waste heat Boiler Package)IQ01-2006 1360.00 06-Nov-15 08:00 A 10-Nov-16 08:00 A 100% 100%
Vendor Data and Drawings for Fresh Feed Filter (1212-S-101/201)IQ01-2028 1000.00 12-Jan-16 08:00 A 23-Sep-16 17:00 A 100% 100%
Vendor Data and Drawings for HP Exchangers 1212-E-104A/B;105A~C;106£»E-204A/B;205A~C;206 1504.00 08-Oct-15 08:00 A 26-Aug-16 08:00 A 100% 100%
Vendor Data and Drawings for Special Material Exchangers(1211-E-001/004A/B/008/011) 1304.00 15-Sep-15 08:00 A 26-Aug-16 08:00 A 100% 100%
RFQ 2344.00 24-Oct-14 08:00 A 18-Sep-15 17:00 A 100% 100%
ARDS Reactor (IQ01-2001)
( 1384.00 24-Oct-14 08:00 A 30-Jun-15 17:00 A 100% 100%
HP Exchanger ((IQ01-2005) 1664.00 27-Oct-14 08:00 A 19-Aug-15 17:00 A 100% 100%
DSS Air Cooler (IQ01-2009)
( 1984.00 26-Dec-14 08:00 A 09-Sep-15 17:00 A 100% 100%
SM Exchanger ((IQ01-2017) 1240.00 29-Jan-15 08:00 A 11-Sep-15 17:00 A 100% 100%
High Pressure Equipment
E (IQ01-2010) 1608.00 04-Nov-14 08:00 A 18-Aug-15 17:00 A 100% 100%
Column Tray (IQ(IQ01-2027) 1736.00 03-Nov-14 08:00 A 02-Sep-15 17:00 A 100% 100%
HP Centrifugel Sepertator
S (IQ01-2014) 1792.00 29-Oct-14 08:00 A 18-Sep-15 17:00 A 100% 100%
Air Cooler (IQ01
(IQ01-2021) 1416.00 25-Dec-14 08:00 A 09-Sep-15 17:00 A 100% 100%
Common Exchan
Exchanger (IQ01-2018) 1208.00 03-Feb-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Cr-Mo Drum (IQ (IQ01-2008) 2112.00 03-Nov-14 08:00 A 18-Sep-15 17:00 A 100% 100%
Column (C101-0
(C101-001/002/003, IQ01-2023) 1064.00 06-Mar-15 08:00 A 18-Sep-15 17:00 A 100% 100%
Heater (IQ01-2006)
(IQ01-20 1360.00 30-Dec-14 08:00 A 31-Aug-15 17:00 A 100% 100%
Large Size Drum (IQ01-2013) 944.00 27-Mar-15 08:00 A 18-Sep-15 17:00 A 100% 100%
Cladding Drum ((IQ01-2012) 944.00 01-Apr-15 08:00 A 03-Sep-15 17:00 A 100% 100%
CS Drum (IQ01-
(IQ01-2016) 1200.00 06-Feb-15 08:00 A 02-Sep-15 17:00 A 100% 100%
Waste Heat Boiler
Boil package (1212-A-610£© 1536.00 12-Jan-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Etc 8.00 02-Nov-15 08:00 A 02-Nov-15 17:00 A 0% 0%
COS 8.00 02-Nov-15 08:00 A 02-Nov-15 17:00 A 0% 0%
Rotating Equipment 3824.00 30-Oct-14 08:00 A 27-Sep-16 17:00 A 100% 100%
Document 2880.00 30-Oct-14 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - K101/201(Recycle Gas Compressor, IQ01-1001) 1880.00 30-Oct-14 08:00 A 15-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - K001A/B (FRAC Off Gas Compressor, IQ01-1006) 1400.00 23-Jan-15 08:00 A 11-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - 1st Level Pump (IQ01-1005) 1336.00 25-Dec-14 08:00 A 21-Aug-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - 2nd Level Pump (IQ01-1004/) 392.00 23-Jan-15 08:00 A 06-Apr-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry - P-002A/B(Injection Water Pumps) 1384.00 23-Jan-15 08:00 A 15-Sep-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry -Overhead Travelling Crane for 1212-K-001A/B 1376.00 16-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Mechanical data sheet for Inquiry -Overhead Travelling Crane for 1212-K-101/201 1616.00 16-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Drawing 1712.00 15-Sep-15 08:00 A 27-Sep-16 17:00 A 100% 100%
Vendor Data and Drawings for K101/201(Recycle Gas Compressor, IQ01-1001) 1280.00 15-Sep-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for K001 (Face Off Gas Compressor, IQ01-1006) 1280.00 27-Nov-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for 1st Level Pump(IQ01-1005) 1280.00 15-Sep-15 08:00 A 26-Aug-16 17:00 A 100% 100%
Vendor Data and Drawings for 2nd Level Pump (IQ01-1004/1011) 1200.00 25-Dec-15 08:00 A 27-Sep-16 17:00 A 100% 100%
Vendor Data and Drawings for Crane 1120.00 18-Dec-15 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 2288.00 31-Oct-14 08:00 A 11-Dec-15 17:00 A 100% 100%
K101/201(Recycle Gas Compressor, IQ01-1001)
K101/201(Recyc 1984.00 31-Oct-14 08:00 A 15-Sep-15 17:00 A 100% 100%
K001 (Face Off Gas Compressor, IQ01-1006) 1296.00 26-Jan-15 08:00 A 15-Sep-15 17:00 A 100% 100%
1st level Pump(REACTOR
Pump(R FEED PUMPS AND HP LEAN PUMPSIQ01-1005) 1208.00 26-Dec-14 08:00 A 31-Jul-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 42 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

2nd Level Pump/FRAC


Pump BOTTOMS PUMP/IQ01-1004/1011) 1176.00 26-Jan-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Injection Water Pump(IQ01-1012)
P 1760.00 23-Jan-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Compressor ove overhead travelling crane 1024.00 17-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 3000.00 24-Apr-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Document 2904.00 13-May-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Telecommunication Cable Schedule
Telecommunicat 1608.00 01-Dec-15 08:00 A 14-Sep-16 17:00 A 100% 100%
MTO for Fire de detection 1880.00 13-May-15 08:00 A 15-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices 2056.00 15-May-15 08:00 A 20-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 2056.00 03-Aug-15 08:00 A 02-Sep-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Conduits And Accessories 2128.00 03-Aug-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Drawing 2856.00 24-Apr-15 08:00 A 14-Sep-16 17:00 A 100% 100%
layout for Teleco
Telecommunicaiton devices location 2184.00 24-Apr-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Telecommunicaiton Cable Routing layout
Telecommunicait 2456.00 06-Jul-15 08:00 A 14-Sep-16 17:00 A 100% 100%
RFQ 1624.00 14-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
detection 1624.00 14-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
devices 1568.00 18-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Cable 136.00 11-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 3824.00 27-Oct-14 08:00 A 31-Aug-16 17:00 A 100% 100%
Document 2712.00 16-Feb-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Safety Piping Lin
Line List 680.00 16-Feb-15 08:00 A 19-Jun-15 17:00 A 100% 100%
MTO for fire figh
fighting equipment 1352.00 24-Aug-15 08:00 A 26-Feb-16 17:00 A 100% 100%
Hazardous area classification schedule 2032.00 24-Mar-15 08:00 A 26-Feb-16 17:00 A 100% 100%
List of items to be
b fireproofed 1848.00 25-Mar-15 08:00 A 19-Nov-15 17:00 A 100% 100%
Noisy equipment list 848.00 01-Sep-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Safety sign spec
specification and datasheet 1696.00 19-Aug-15 08:00 A 21-Mar-16 17:00 A 100% 100%
Drawing 3824.00 27-Oct-14 08:00 A 31-Aug-16 17:00 A 100% 100%
Safety Drawing - Fire Protection and personnel protection 2920.00 25-Dec-14 08:00 A 10-Mar-16 17:00 A 100% 100%
Fire water spray system P&ID 2976.00 30-Mar-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1648.00 13-May-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2728.00 10-Apr-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Hazardous area classification layout 2640.00 27-Oct-14 08:00 A 28-Jan-16 17:00 A 100% 100%
Fireproofing zone
zon drawings 1312.00 20-May-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Temporary must
mustering areas and escape routes layout 2136.00 13-May-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Safety sign layout 1680.00 20-Aug-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Deluge Nozzle Arrangment
A Calculation Note 2152.00 20-Aug-15 08:00 A 31-Aug-16 17:00 A 100% 100%
RFQ 888.00 01-Jul-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Hydro/ Hose box / Fire monitor 888.00 01-Jul-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Civil/Structure 3584.00 06-Feb-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Document 3584.00 06-Feb-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Calculation Notes
Note for RCK-1110 2656.00 06-Feb-15 08:00 A 02-Jun-16 17:00 A 100% 100%
Calculation Notes
Note for RCK-1100/1200/1210/1220/1230/1240 1328.00 06-Feb-15 08:00 A 15-Oct-15 17:00 A 100% 100%
Calculation Notes
Note for 1212-STR-1100/1200 2024.00 03-Jun-15 08:00 A 27-May-16 17:00 A 100% 100%
Calculation Notes
Note for 1212-STR-1300/1400 2020.00 03-Jun-15 08:00 A 17-May-16 17:00 A 100% 100%
Calculation Notes
Note for 1212-STR-1500/1600 2024.00 03-Jun-15 08:00 A 17-May-16 17:00 A 100% 100%
Calculation Notes
Note for Column Foundation 1212-C-002 2248.00 30-Apr-15 08:00 A 25-May-16 17:00 A 100% 100%
Calculation Notes
Note for Column Foundation 1212-C-001/003 2208.00 30-Apr-15 08:00 A 25-May-16 17:00 A 100% 100%
Calculation Notes
Note for Column Foundation 1212-C-101/201 2208.00 30-Apr-15 08:00 A 27-May-16 17:00 A 100% 100%
Calculation Notes
Note for Drum Foundation 2216.00 21-May-15 08:00 A 27-May-16 17:00 A 100% 100%
Calculation Notes
Note for Heat Exchanger Foundation 1688.00 21-May-15 08:00 A 20-May-16 17:00 A 100% 100%
Calculation Notes
Note for Pump Foundation 2000.00 13-Nov-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Calculation Notes
Note for Filter Foundation 1212-S-101 /201 1888.00 17-Sep-15 08:00 A 27-May-16 17:00 A 100% 100%
Calculation Notes
Note for Furnace Foundation 640.00 03-Nov-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Calculation Notes
Note for Compressor Foundation 1212-K-001A/B 1232.00 11-Dec-15 08:00 A 19-May-16 17:00 A 100% 100%
Calculation Notes
Note for Compressor Foundation 1212-K-101/201 1432.00 02-Nov-15 08:00 A 19-May-16 17:00 A 100% 100%
Calculation Notes
Note for 1212-SHL-1100 1432.00 03-Aug-15 08:00 A 20-May-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 43 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Calculation Notes
Note for 1212-SHL-1200 1472.00 03-Aug-15 08:00 A 20-May-16 17:00 A 100% 100%
Calculation Notes
Note for COC PIT 1212-T-101/102 1496.00 22-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
MTO for Reinforcing
Reinfor Steel 864.00 17-Dec-15 08:00 A 02-Mar-16 17:00 A 100% 100%
MTO for Structu
Structure Steel 800.00 12-May-15 08:00 A 12-Aug-15 17:00 A 100% 100%
MTO for Equipm
Equipment Anchor Bolts 544.00 05-May-15 08:00 A 06-Aug-15 17:00 A 100% 100%
MTO for Steel S Structure Anchor Bolts 632.00 06-May-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Drawing 3360.00 02-Mar-15 08:00 A 30-Sep-16 17:00 A 100% 100%
Drawing - Drainage
Draina and Undeground Piping Drawing 1784.00 08-Jun-15 08:00 A 20-Apr-16 17:00 A 100% 100%
PILE LAYOUT O OF 1212-RCK-1110 792.00 08-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-RCK-1100 728.00 08-Jun-15 08:00 A 16-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-RCK-1200 1088.00 08-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-RCK-1210 688.00 08-Jun-15 08:00 A 22-Sep-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-RCK-1220 728.00 08-Jun-15 08:00 A 22-Sep-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-RCK-1230 1208.00 08-Jun-15 08:00 A 09-Dec-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-RCK-1240 1328.00 08-Jun-15 08:00 A 18-Dec-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-STR-1100 744.00 04-Jun-15 08:00 A 15-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-STR-1200 744.00 04-Jun-15 08:00 A 15-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-STR-1300 736.00 04-Jun-15 08:00 A 14-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-STR-1400 736.00 04-Jun-15 08:00 A 14-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-STR-1500 744.00 04-Jun-15 08:00 A 15-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-STR-1600 744.00 04-Jun-15 08:00 A 15-Oct-15 17:00 A 100% 100%
PILE LAYOUT O OF 1212-SHL-1100 1592.00 04-Jun-15 08:00 A 12-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1212-K-101 1464.00 22-Jun-15 08:00 A 12-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1212-K-201 1464.00 22-Jun-15 08:00 A 12-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1212-SHL-1200 1448.00 22-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1212-K-001A, 001B 1448.00 22-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
PILE LAYOUT O OF 1212-C-101 1584.00 08-Jun-15 08:00 A 12-Jan-16 17:00 A 100% 100%
Pile Layout Of 1212-C-201
12 1584.00 08-Jun-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Pile Layout Of 1212-C-002
12 1584.00 08-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Pile Layout Of 11212-C-003 1584.00 08-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Pile Layout Of 11212-V-007 1704.00 22-May-15 08:00 A 24-Feb-16 17:00 A 100% 100%
Pile Layout Of 11212-V-013 1672.00 22-May-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Pile Layout Of 1212-F-001
12 624.00 12-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Pile Layout OF 11212-F-101/201 656.00 09-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout For Unit
U 1212 1104.00 05-Nov-15 08:00 A 19-May-16 17:00 A 100% 100%
Pile Layout Of EExchangers 1480.00 19-Jun-15 08:00 A 09-May-16 17:00 A 100% 100%
Equipment Foun
Foundations Drawings forColumn-1212-C-101/201 2208.00 05-May-15 08:00 A 03-Jun-16 17:00 A 100% 100%
Foundations Of Column-1212-C-002 2208.00 04-May-15 08:00 A 27-May-16 17:00 A 100% 100%
Foundations Of Column-1212-C-003 2224.00 04-May-15 08:00 A 27-May-16 17:00 A 100% 100%
Foundations Of Drum 2184.00 22-May-15 08:00 A 30-May-16 08:00 A 100% 100%
Foundations Of Heat Exchanger 2056.00 21-May-15 08:00 A 20-May-16 17:00 A 100% 100%
Foundations Of 1st Pump 1792.00 16-Nov-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Foundations Of 2st Pump /injection pump 1824.00 16-Nov-15 08:00 A 30-Sep-16 17:00 A 100% 100%
Foundations Of Furnace 1152.00 04-Nov-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Foundations Of Compressor 1212 K-001A/B 1056.00 14-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Foundations Of Compressor--1212 K-101/201 896.00 14-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Foundations Of RCK-1100/1200/1210/1220/1230/1240/1250/1260 1632.00 30-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Foundations Of RCK-1110 2016.00 30-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Foundations Of 1212-STR-1100/1200 2040.00 03-Aug-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Foundations Of 1212-STR-1300/1400 1592.00 03-Aug-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Foundations Of 1212-STR-1500/1600 1584.00 03-Aug-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Foundations Of 1212-SHL-1100 648.00 18-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Foundations Of 1212-SHL-1200 1240.00 08-Oct-15 08:00 A 29-Jan-16 17:00 A 100% 100%
General Layout - Drawing for stormwater drainage network 2280.00 27-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
General Layout - Surfacing and grading finishing layout 2496.00 27-Apr-15 08:00 A 22-Apr-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 44 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Drawing - Drainage
Draina and Undeground Piping Drawing - Refinery 03 - Units 1212 3184.00 02-Mar-15 08:00 A 04-Apr-16 17:00 A 100% 100%
Equipment FounFoundations Drawings for Filter 1952.00 18-Sep-15 08:00 A 27-May-16 17:00 A 100% 100%
COC PIT 1212-T-101/201
1212-T STRUCTURAL DRAWING 1648.00 03-Aug-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Structure Drawin
Drawings for 1212-SHL-1100(Elevation ¡¢ Framing Plans) 1144.00 12-Nov-15 08:00 A 20-May-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1212-SHL-1100(Columns¡¢Details) 520.00 01-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1212-STR-1500/1600(Framing Plans ¡¢Elevation) 1864.00 04-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1212-STR-1500/1600( Details¡¢ Columns) 960.00 19-Aug-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Structure Drawin
Drawings for 1212-SHL-1200(Elevation ¡¢Framing Plans) 1152.00 04-Nov-15 08:00 A 20-May-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1212-SHL-1200(Columns¡¢Details) 1104.00 10-Nov-15 08:00 A 20-May-16 17:00 A 100% 100%
Structure Drawin
Drawings for 1212-STR-1100/1200(Elevation ¡¢Framing Plans) 1584.00 02-Jun-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Structure Drawings
Drawin for 1212-STR-1100/1200(Columns ¡¢Details) 1312.00 18-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Structure Drawin
Drawings for 1212-STR-1300/1400 (Elevation ¡¢Framing Plans) 1312.00 03-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Structure Drawings
Drawin for 1212-STR-1300/1400( Columns¡¢Details) 1352.00 11-Jun-15 08:00 A 15-Jan-16 17:00 A 100% 100%
SD for RCK-1100/1200/1210/1220/1230/1240/1250/1260
RCK-110 (Elevation ¡¢Framing Plans) 1504.00 30-Apr-15 08:00 A 18-Jan-16 17:00 A 100% 100%
SD for RCK-1100/1200/1210/1220/1230/1240/1250/1260(Columns
RCK-110 ¡¢Details) 1456.00 12-May-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Structure Drawin
Drawings for RCK-1110(Elevation ¡¢ Framing Plans) 1840.00 30-Apr-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Structure Drawin
Drawings for RCK-1110(Columns ¡¢Details) 1544.00 12-May-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Foundation Layout
Layo for Unit 1212 1824.00 31-Aug-15 08:00 A 22-Jul-16 17:00 A 100% 100%
RFQ 984.00 07-May-15 08:00 A 14-Aug-15 17:00 A 100% 100%
Requisition for st structural steel 160.00 03-Jun-15 08:00 A 03-Jul-15 17:00 A 100% 100%
Requisitions for equipment
e anchor bolts 728.00 22-Jun-15 08:00 A 06-Aug-15 17:00 A 100% 100%
Requisitions for steels structure anchor bolts 984.00 07-May-15 08:00 A 14-Aug-15 17:00 A 100% 100%
Architectural 2128.00 17-Jun-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Drawing 2128.00 17-Jun-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1 Elevations 1608.00 16-Sep-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1 Sections 1600.00 17-Sep-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1 Roof Plan 1584.00 21-Sep-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Compressor She Shelter 1 Ground Floor Plan 1592.00 18-Sep-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Compressor She Shelter 2 Elevations 1792.00 17-Jun-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Compressor She Shelter 2 Sections 1776.00 19-Jun-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Compressor She Shelter 2 Roof Plan 1784.00 18-Jun-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Compressor She Shelter 2 Ground Floor Plan 1768.00 22-Jun-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Piping 4568.00 25-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Document 3272.00 30-Mar-15 08:00 A 17-Feb-17 17:00 A 100% 100%
Critical line list 3136.00 30-Mar-15 08:00 A 05-Nov-15 17:00 A 100% 100%
Piping Stress Calculations
Ca and analysis report 3232.00 06-Apr-15 08:00 A 17-Feb-17 17:00 A 100% 100%
Pipe support lists(Standard
lists and Special) 144.00 18-Dec-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Spring list and datasheet
da 2672.00 19-May-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Steam Tracing List L 176.00 01-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
MTO for U/G Pipe Pip System 808.00 27-Apr-15 08:00 A 30-Oct-15 10:24 A 100% 100%
Data Sheet for S Safety Valve 1144.00 30-Mar-15 08:00 A 10-Sep-15 17:00 A 100% 100%
Data Sheet for S Silencer 904.00 30-Mar-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheet for S Sampler 704.00 13-Apr-15 08:00 A 24-Jul-15 17:00 A 100% 100%
Material Take Off Of for Insulation 56.00 01-Jun-16 08:00 A 31-Aug-16 17:00 A 100% 100%
Material Take Off Of for Piping Bulk Material 184.00 07-Dec-15 08:00 A 07-Jan-16 17:00 A 100% 100%
Material Take Off Of for Piping Painting 96.00 01-Jun-16 08:00 A 31-Aug-16 17:00 A 100% 100%
Material Take Of Off for Special Item 88.00 01-Jul-16 08:00 A 31-Aug-16 17:00 A 100% 100%
Drawing 4568.00 25-Aug-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Above Ground Piping P GA Key Plan 3344.00 25-Dec-14 08:00 A 24-Apr-15 17:00 A 100% 100%
Key Plan of Equipment
Equi Layout 3168.00 27-Oct-14 08:00 A 01-Feb-16 17:00 A 100% 100%
ARDS 1211 Unit Plot Plan 2680.00 25-Aug-14 08:00 A 11-Dec-15 17:00 A 100% 100%
Special Pipe Support
Sup Drawing and list 1984.00 23-Nov-15 08:00 A 10-Oct-16 17:00 A 100% 100%
Piping battery limit
lim interface table 2048.00 06-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
ISO drawing for U/G piping and list 928.00 23-Nov-15 08:00 A 18-Mar-16 12:00 A 100% 100%
Piping General Arrangement
A drawings 1984.00 23-Nov-15 08:00 A 28-Sep-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 45 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Equipment layout 2208.00 18-Feb-15 08:00 A 29-Jan-16 17:00 A 100% 100%


3D-Modeling/review report/action close-out-report
3D-Modeling/rev 3672.00 27-Oct-14 08:00 A 17-Feb-17 17:00 A 100% 100%
Piping Isometric Drawings(with Materials) and list 1464.00 23-Nov-15 08:00 A 08-Jun-16 17:00 A 100% 100%
RFQ 2928.00 31-Mar-15 08:00 A 30-Aug-16 17:00 A 100% 100%
MR for Blanket Order
O of Piping/Fitting/Valve 352.00 06-Apr-15 08:00 A 05-Jun-15 17:00 A 100% 100%
Misc. Piping Equ
Equipment 512.00 21-May-15 08:00 A 18-Aug-15 17:00 A 100% 100%
1st Piping Support
Suppo 352.00 17-Aug-15 08:00 A 20-Oct-15 17:00 A 100% 100%
1st U/G Piping 664.00 28-Apr-15 08:00 A 21-Aug-15 17:00 A 100% 100%
MR for U/G GRP Bulk Material 656.00 29-Apr-15 08:00 A 21-Aug-15 17:00 A 100% 100%
U/G Valves 896.00 24-Aug-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Safety Valve 1712.00 31-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
1st Pipes & Tubes
Tube 136.00 23-Nov-15 08:00 A 25-Dec-15 17:00 A 100% 100%
1st Piping Valves 504.00 01-Jul-15 08:00 A 25-Sep-15 17:00 A 100% 100%
2nd Piping/Valves/Fitting
Piping/Valve 464.00 18-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
MR of Spring Ha Hanger 376.00 01-Jul-15 08:00 A 17-Jul-15 17:00 A 100% 100%
2st Piping Supp
Support/Insulation 1408.00 18-Dec-15 08:00 A 30-Aug-16 17:00 A 100% 100%
Etc 1712.00 25-Dec-14 08:00 A 10-Dec-15 17:00 A 0% 0%
COS 1712.00 25-Dec-14 08:00 A 10-Dec-15 17:00 A 0% 0%
Electrical 3680.00 25-Dec-14 08:00 A 14-Sep-16 17:00 A 100% 100%
Document 3512.00 25-Dec-14 08:00 A 02-Sep-16 17:00 A 100% 100%
Electrical Consumer
Consum List 2400.00 27-Mar-15 08:00 A 25-Dec-15 17:00 A 100% 100%
List / Schedule for
fo Electrical Cable List 1760.00 05-Jun-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Electrical Cable Drum
D Schedule 936.00 08-Jan-16 08:00 A 25-Mar-16 17:00 A 100% 100%
MTO for Cable 1968.00 29-Sep-15 08:00 A 24-Jun-16 17:00 A 100% 100%
MTO for Other M Material(Steel/Termination Kit/Calbe Joint/Cable Gland/Seal Material) 1928.00 29-Sep-15 08:00 A 02-Sep-16 17:00 A 100% 100%
MTO for Cable T Tray 2416.00 05-Jun-15 08:00 A 01-Aug-16 17:00 A 100% 100%
MTO for Earthin
Earthing and Lighting Material 2016.00 13-Jul-15 08:00 A 10-May-16 17:00 A 100% 100%
MTO for Lighting Fixtures 1000.00 24-Dec-15 08:00 A 10-May-16 17:00 A 100% 100%
MTO for Conduit 1920.00 29-Sep-15 08:00 A 22-Jul-16 17:00 A 100% 100%
MTO for Explosi
Explosion-proof materila/Explosion-proof control switch/Socket Outlets/Panel 760.00 15-Feb-16 08:00 A 15-Apr-16 17:00 A 100% 100%
MTO for Cathod
Cathodic Protection 448.00 13-Nov-15 08:00 A 01-Feb-16 17:00 A 100% 100%
MTO for Elec. H Heat Tracing 424.00 01-Feb-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Data Sheet For LV Induction Motor 1176.00 25-Dec-14 08:00 A 24-Jul-15 17:00 A 100% 100%
Data Sheet For HV Induction Motor 1168.00 26-Dec-14 08:00 A 24-Jul-15 17:00 A 100% 100%
Drawing 3016.00 27-Apr-15 08:00 A 14-Sep-16 17:00 A 100% 100%
INTERFACE DRAWING
DR OF CABLE ROUTING 2752.00 27-May-15 08:00 A 25-May-16 17:00 A 100% 100%
INTERFACE DRAWING
DR OF EARTHING SYSTEM 2792.00 28-May-15 08:00 A 01-Jun-16 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 2768.00 27-Apr-15 08:00 A 15-Jun-16 17:00 A 100% 100%
BLIT OF CABLES
CABLE 2120.00 28-Apr-15 08:00 A 15-Jan-16 17:00 A 100% 100%
BLIT OF CABLESTRENCH
CABLE 2096.00 29-Apr-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Cathodic Protection
Protect System Layout 1472.00 18-Sep-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Lighting Layout (Unit/Street)
( 1736.00 17-Sep-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Lighting Loop Diagram
Di 1456.00 18-Sep-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout (Aboveground) 2296.00 27-Apr-15 08:00 A 16-May-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout (Underground) 2528.00 27-Apr-15 08:00 A 13-May-16 17:00 A 100% 100%
Wiring / Interconection
Intercon Diagram 1264.00 25-Dec-15 15:24 A 14-Sep-16 17:00 A 100% 100%
Small Power Dis Distribution Panel Single Line Diagram 1280.00 23-Oct-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Electrical Heat Tracing
T Layout 1016.00 01-Dec-15 08:00 A 19-Feb-16 17:00 A 100% 100%
RFQ 1768.00 29-Sep-15 08:00 A 15-Jul-16 17:00 A 100% 100%
Earthing and Lighting
Lig Material 248.00 02-Nov-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Cable Tray 800.00 29-Sep-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Cable 176.00 26-Oct-15 08:00 A 02-Dec-15 17:00 A 100% 100%
Conduit 872.00 01-Mar-16 08:00 A 15-Jul-16 17:00 A 100% 100%
Lighting Fixtures 176.00 01-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch/Socket Outlets/Panel 264.00 16-Nov-15 08:00 A 30-Dec-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 46 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Cathodic Protection
Protect 312.00 22-Dec-15 08:00 A 14-Jan-16 17:00 A 100% 100%
Elec. Heat Tracing
Tracin 256.00 02-Nov-15 08:00 A 01-Dec-15 17:00 A 100% 100%
Other Material(Steel/Termination
Material(S Kit/Calbe Joint/Cable Gland/Seal Material) 968.00 25-Dec-15 08:00 A 09-May-16 17:00 A 100% 100%
Etc 88.00 19-May-16 08:00 A 18-Jul-16 17:00 A 0% 0%
COS 88.00 19-May-16 08:00 A 18-Jul-16 17:00 A 0% 0%
Instrumentation anand control 3856.00 25-Dec-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Document 3856.00 25-Dec-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Instrument Index 296.00 25-Dec-14 08:00 A 15-Feb-15 17:00 A 100% 100%
System I/O LIST 384.00 26-Dec-14 08:00 A 09-Mar-15 17:00 A 100% 100%
Power Feeds ListLis with Power Consumption for UPS and non-UPS Consumers 128.00 03-Apr-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Instrument Air C Consumption Calculations 416.00 09-Feb-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Datasheet for Integral
In Orifice D/P Flow Transmitter 1768.00 17-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for H H2 Analyser/Sulfur Analyzer 2688.00 16-Feb-15 08:00 A 06-May-16 17:00 A 100% 100%
Datasheet for lContinuous
lC Emission Monitoring System (CEMS) 2688.00 16-Feb-15 08:00 A 06-May-16 17:00 A 100% 100%
Data Sheet for C Control Valve (Globe) 1936.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for D Deluge Valve 2776.00 16-Feb-15 08:00 A 30-Mar-16 17:00 A 100% 100%
Datasheet for Displacer
Di Level Instrument 1576.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Data Sheet for D DP Flow /Level Transmitter 1776.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for DP Transmitter 1576.00 16-Feb-15 08:00 A 29-Sep-15 17:00 A 100% 100%
Datasheet for W Wireless Temperature Transmitter 1776.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for E Elec. Motorized Valves (Gate/ORBIT/Y-Patten) 1776.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for C Control Valve (Angle) 2264.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Control
Co Valve(Antisurge) 2296.00 08-Oct-15 08:00 A 18-Nov-16 17:00 A 100% 100%
Data Sheet for E Emergency Depressure Valve 2016.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for P Process ESD Ball Valve(Ball) 2016.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for O Oil in Water Analyser 1784.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Flow
Fl Element- Restriction Orifice 1776.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Flow
Fl Element- Venturi Tube 1776.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Flow
Fl Element- Nozzle 1776.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for G Gas Detector 2080.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Level
Le Gauge 1400.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for LeLevel Transmitter Radar Type 1400.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Local
L Milliammeter 1608.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Magnetic
M Level Gauge 1400.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for O Orifice Plate 1696.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Pressure
Pr Gauge 656.00 01-Jun-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for P Pressure Transmitter 1400.00 16-Feb-15 08:00 A 29-Sep-15 17:00 A 100% 100%
Data Sheet for P Process On-off Valve (Ball) 1552.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for S Self-Actuating Control Valve 1560.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for Temperature
T Skin 1288.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for TeTemperature Transmitter 1608.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for Thermometer
Th 1608.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for T Thermowell 1608.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Data Sheet for Reactor
R Bed Mutipoint Thermocouples 1400.00 16-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for Variable
Va Area Flow Meter 2064.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Datasheet for SeSelf-Actuating Flow Regulator 1368.00 17-Feb-15 08:00 A 23-Oct-15 17:00 A 100% 100%
Datasheet for CoConductivity Analyser 1584.00 16-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Cable Drum SchSchedules 1504.00 09-Dec-15 08:00 A 25-Jan-16 17:00 A 100% 100%
Alarm rationalisa
rationalisation study report and alarm reference data base 1664.00 30-Nov-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Analyser Sample System Transportation times 488.00 28-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Cable Sizing/Selection
Sizing/Sel Calculations 880.00 28-Dec-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Configuration Data
Da for Machine Monitoring System and Performance Monitoring System 376.00 11-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
DCS Group Displays
Disp & Reports 1560.00 30-Nov-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Instrument Cable Schedules 920.00 04-Dec-15 08:00 A 26-Jan-16 17:00 A 100% 100%
Instrument Nam
Name Plate Schedules 480.00 04-Dec-15 08:00 A 16-Dec-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 47 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Intrinsically Safe(IS)
Safe( Loop Calculations 1672.00 23-Nov-15 08:00 A 16-Sep-16 17:00 A 100% 100%
IPF classification
classifications, verification reports 2448.00 08-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Junction Box Schedules
Sch 424.00 08-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Instrument Nozz
Nozzel Elevations Caculation 1296.00 06-Jul-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Calculation for Control
C Valves 536.00 11-Dec-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Sizing Calculations
Calculatio for Flow Elements 1184.00 11-Jun-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Thermowell Wak Wake Frequency Calculations 584.00 04-Jan-16 08:00 A 05-Apr-16 17:00 A 100% 100%
MTO 176.00 04-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Drawing 3072.00 27-Apr-15 08:00 A 31-Oct-16 17:00 A 100% 100%
Shutdown and LogicL Diagrams 1696.00 03-Aug-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Instrument Main Cable Routing 2768.00 27-Apr-15 08:00 A 20-May-16 17:00 A 100% 100%
Instrument Cable trays/trench Layouts 1864.00 23-Nov-15 08:00 A 31-Oct-16 17:00 A 100% 100%
Instument Locati
Location Layout 2000.00 23-Oct-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Instrument hook
hook-up Drawings 1120.00 23-Oct-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Junction Box Wiring
Wir Diagrams 1120.00 26-Oct-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Graphic Display Sketches 656.00 18-Nov-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Instrument Earth
Earthing Layouts 1632.00 26-Oct-15 08:00 A 12-Jul-16 17:00 A 100% 100%
Instument Air DisDistribution Layouts 1760.00 26-Oct-15 08:00 A 10-Jun-16 17:00 A 100% 100%
Instrument Loop Diagrams 1168.00 11-Mar-16 08:00 A 23-May-16 17:00 A 100% 100%
RFQ 2400.00 16-Feb-15 08:00 A 18-Mar-16 17:00 A 100% 100%
MAC (INC-MRI-
(INC-MRI-0001-0001) 1480.00 16-Feb-15 08:00 A 11-Nov-15 17:00 A 100% 100%
Control Valves/o
Valves/on-off valves (MRI-0001-0501,0502,0503,0504,0505,0506,0507,0508,0509,0510) 1264.00 17-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Orifice Plate/Flow Element/Temperature Element(MRI-0001-0102,0105,0106,0107,0108,0109) 1528.00 17-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Level/Gauge (INC-MRI-0001-0201,0202,0203,0204,0205,0301)
(IN 1528.00 17-Feb-15 08:00 A 20-Nov-15 17:00 A 100% 100%
Analysis (INC-MRI-0001-0302,0303,0401,0402,0403,0404,0405)
(INC-M 2224.00 17-Feb-15 08:00 A 07-Jan-16 17:00 A 100% 100%
Transmitter (INC
(INC-MRI-0001-0302,0303,0401,0402,0403,0404,0405) 1928.00 18-Feb-15 08:00 A 20-Nov-15 17:00 A 0% 0%
Instrument Junction
Junct Boxes 432.00 08-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Instrument Cable 224.00 07-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Cable Tray 600.00 08-Jan-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Inst. Material 344.00 08-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Electrical Substation 4360.00 27-Oct-14 08:00 A 18-Nov-16 17:00 A 100% 100%
6850-SUB-111 3880.00 31-Dec-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Electrical 3880.00 31-Dec-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Document 3448.00 11-Mar-15 08:00 A 18-Nov-16 17:00 A 100% 100%
Data sheet For ENMCS 1216.00 04-May-15 08:00 A 02-Sep-15 17:00 A 100% 100%
Calculation for DCD UPS and battery up 1560.00 18-Jun-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Interface ENMCS
ENMC I/O List 2328.00 26-Aug-15 08:00 A 15-Sep-16 17:00 A 100% 100%
Schedule For 11KV11 Switchgear 1744.00 27-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Schedule For 3.3KV
3.3 Switchgear 1768.00 27-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Schedule For LV Switchgear 2904.00 04-May-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Data sheet For 1 11/0.42KV Transformer 928.00 13-Mar-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data sheet For 1 11/3.45KV Transformer 928.00 13-Mar-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data sheet For 3 33/11.5KV Transformer 928.00 13-Mar-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Equipment List 984.00 05-Jun-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Electrical Consumer
Consum List 1624.00 12-Mar-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Earthing Calculation
Calcula 1840.00 07-May-15 08:00 A 01-Apr-16 17:00 A 100% 100%
ENMCS I/O List 816.00 25-Aug-15 08:00 A 19-Jan-16 17:00 A 100% 100%
MTO For Earthin
Earthing And Lightning Material 1512.00 07-Aug-15 08:00 A 10-May-16 17:00 A 100% 100%
MTO For Cable 1192.00 30-Nov-15 08:00 A 01-Jul-16 17:00 A 100% 100%
MTO For Cable Ladder And Cable Tray 1976.00 10-Aug-15 08:00 A 01-Aug-16 17:00 A 100% 100%
MTO For other material 1752.00 03-Nov-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Data Sheet For 0.4kv Switchgear 936.00 12-Mar-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For 11kv Switchgear 936.00 12-Mar-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For 3.3kv Switchgear 936.00 12-Mar-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For Dc Ups Up 648.00 04-May-15 08:00 A 24-Aug-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 48 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Data Sheet For Lv Vsds 872.00 12-Mar-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Data Sheet For Neutral Earthing Resistor 1280.00 10-Apr-15 08:00 A 25-Nov-15 17:00 A 100% 100%
Data Sheet For 11kv Bus Ducts 1200.00 12-May-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Data Sheet For 0.42kv Bus Ducts 1200.00 12-May-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Electrical Load Schedule/Power
S Balance 1328.00 04-May-15 08:00 A 24-Dec-15 17:00 A 100% 100%
Relay Coordinat
Coordination studies and reports including setting tables 2240.00 14-Oct-15 08:00 A 18-Nov-16 17:00 A 100% 100%
Elec. Cable List 2968.00 28-Apr-15 08:00 A 23-Sep-16 17:00 A 100% 100%
List / Schedule for
fo Electrical Cable Drum 1288.00 31-Aug-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Equipment Heat Dissipation for HVAC Sizing 1016.00 11-Mar-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Drawing 3608.00 31-Dec-14 08:00 A 29-Sep-16 17:00 A 100% 100%
Single Line Diagram
Diag For DC UPS 992.00 18-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Electrical Panel Single
S Line Diagram 1248.00 04-May-15 08:00 A 22-Jan-16 17:00 A 100% 100%
11kV Single Line and Logic Diagram 560.00 04-May-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Key Single Line Diagram
D 1800.00 31-Dec-14 08:00 A 20-Nov-15 17:00 A 100% 100%
3.3kV Single Line
Lin and Logic Diagram 560.00 04-May-15 08:00 A 08-Jan-16 17:00 A 100% 100%
0.4kV Single Line
Lin and Logic Diagram 560.00 04-May-15 08:00 A 29-Jan-16 17:00 A 100% 100%
ENMCS Architecture
Architec Diagrams 784.00 01-Jun-15 08:00 A 31-Aug-15 17:00 A 100% 100%
Substation Equipment
Equi Layout 1664.00 02-Feb-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 1816.00 27-Apr-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout 2008.00 27-Apr-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Wiring / Interconnection
Intercon Diagrams 1616.00 25-Dec-15 08:00 A 29-Sep-16 17:00 A 100% 100%
Substation Floor
Floo Cut-Outs/Steel Frame Layout 632.00 29-Jan-16 08:00 A 25-May-16 17:00 A 100% 100%
RFQ 3504.00 12-Mar-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Transformer 1336.00 17-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Switchgear 1472.00 12-Mar-15 08:00 A 30-Nov-15 17:00 A 100% 100%
UPS System & B Batteries 1824.00 05-May-15 08:00 A 15-Mar-16 17:00 A 100% 100%
Bus Duct 1248.00 04-May-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Capacitor 2464.00 04-May-15 08:00 A 19-Jul-16 17:00 A 100% 100%
ENMCS 2472.00 03-Sep-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 952.00 27-Nov-15 08:00 A 12-May-16 17:00 A 100% 100%
Cable 1240.00 28-Apr-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Other Material 2184.00 04-Nov-15 08:00 A 02-Aug-16 17:00 A 100% 100%
Civil/Structure 1544.00 29-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Document 1544.00 29-Jul-15 08:00 A 18-Jan-16 17:00 A 100% 100%
General Notes 1016.00 23-Sep-15 08:00 A 29-Dec-15 17:00 A 100% 100%
Calculation Notes
Note For SUB-111 960.00 29-Jul-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Drawing 1400.00 29-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of SUB111
SU 856.00 29-Jul-15 08:00 A 29-Dec-15 17:00 A 100% 100%
Building Foundations
Founda Drawings 656.00 23-Sep-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Columns/Beams 1056.00 28-Sep-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Details/Framing Plans 1044.00 29-Sep-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Architecture 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Drawing 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Ground Floor PlanPl 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
First Floor Plan 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Roof Plan 1584.00 11-Mar-15 08:00 A 17-Dec-15 17:00 A 100% 100%
Elevations&Sections
Elevations&Sect 1584.00 11-Mar-15 08:00 A 17-Dec-15 17:00 A 100% 100%
DETAIL DRAWINGS
DRAWIN 1984.00 25-Mar-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Finishing & Door Schedule 2112.00 12-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Heating, Ventilation & Air Conditioning (HVAC) 3008.00 13-May-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Document 3008.00 13-May-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Calculation note for SUB-111 1264.00 13-May-15 08:00 A 23-Dec-15 17:00 A 100% 100%
Data Sheet for H HVAC Equipment 2304.00 14-May-15 08:00 A 01-Jul-16 17:00 A 100% 100%
Equipment list and
an MTO for HVAC system 2736.00 30-Jun-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Drawing 2832.00 14-May-15 08:00 A 30-Sep-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 49 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

layout for HVAC DIDS 2832.00 14-May-15 08:00 A 30-Sep-16 17:00 A 100% 100%
layout for Equipment,ducting
Equipm 2464.00 29-Jun-15 08:00 A 13-Sep-16 17:00 A 100% 100%
RFQ 2096.00 22-Jun-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Air conditioner/Air
conditioner/A duct 2096.00 22-Jun-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 2368.00 11-Mar-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Document 1696.00 19-Jun-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Datasheet for In Inert gas fire extinguishing system 624.00 12-Oct-15 08:00 A 18-Feb-16 17:00 A 100% 100%
Material Take Off 1464.00 19-Jun-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1560.00 22-Jun-15 08:00 A 29-Mar-16 17:00 A 100% 100%
Drawing 2368.00 11-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Layout for Fire and
a gas detection and alarming devices 2368.00 11-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Fire Extinguishers
Extinguisher Layout 1800.00 25-Mar-15 08:00 A 15-Feb-16 17:00 A 100% 100%
RFQ 896.00 03-Aug-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Fire Hydrant/ Fire
Fir Extinguisher 896.00 03-Aug-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 2320.00 19-Mar-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Document 2080.00 23-Apr-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Fire de detection 1528.00 21-Jul-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Teleco
Telecommunicaiton Conduits And Accessories 2024.00 23-Apr-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 2040.00 23-Apr-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices 2080.00 23-Apr-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Drawing 2320.00 19-Mar-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Fire Alarm System
Syste layout 768.00 20-Jul-15 08:00 A 03-Dec-15 17:00 A 100% 100%
layout for Teleco
Telecommunicaiton devices location 2320.00 19-Mar-15 08:00 A 15-Apr-16 17:00 A 100% 100%
RFQ 1760.00 23-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Devices 1000.00 24-Apr-15 08:00 A 21-Oct-15 17:00 A 100% 100%
Detection 1136.00 23-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Cable 1752.00 24-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
6850-SUB-121 4192.00 27-Oct-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Electrical 4192.00 27-Oct-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Document 3568.00 13-Feb-15 08:00 A 18-Nov-16 17:00 A 100% 100%
Data sheet For ENMCS 1216.00 04-May-15 08:00 A 02-Sep-15 17:00 A 100% 100%
Calculation for DCD UPS and battery up 1560.00 18-Jun-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Interface ENMCS
ENMC I/O List 2600.00 09-Jul-15 08:00 A 15-Sep-16 17:00 A 100% 100%
Schedule For 11KV
11 Switchgear 1744.00 27-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Schedule For 3.3KV
3.3 Switchgear 1768.00 27-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Schedule For LV Switchgear 2944.00 04-May-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Data sheet For 1 11/0.42KV Transformer 1056.00 15-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data sheet For 1 11/3.45KV Transformer 1056.00 15-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data sheet For 3 33/11.5KV Transformer 1056.00 15-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Equipment List 936.00 15-Jun-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Electrical Consumer
Consum List 1752.00 13-Feb-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Earthing Calculation
Calcula 1840.00 07-May-15 08:00 A 01-Apr-16 17:00 A 100% 100%
ENMCS I/O List 1088.00 08-Jul-15 08:00 A 19-Jan-16 17:00 A 100% 100%
MTO For Earthin
Earthing And Lightning Material 1432.00 21-Aug-15 08:00 A 10-May-16 17:00 A 100% 100%
MTO For Cable 1192.00 30-Nov-15 08:00 A 01-Jul-16 17:00 A 100% 100%
MTO For Cable Ladder And Cable Tray 1896.00 24-Aug-15 08:00 A 01-Aug-16 17:00 A 100% 100%
MTO For other material 1976.00 21-Sep-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Data Sheet For 0.4kv Switchgear 904.00 18-Mar-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For 11kv Switchgear 1064.00 13-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For 3.3kv Switchgear 1064.00 13-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For DC UPS UP 1064.00 13-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For LV Vsds 840.00 18-Mar-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Data Sheet For Neutral Earthing Resistor 1248.00 16-Apr-15 08:00 A 25-Nov-15 17:00 A 100% 100%
Data Sheet For 0.42kv Bus Ducts 1224.00 04-May-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Electrical Load Schedule/Power
S Balance 1328.00 04-May-15 08:00 A 24-Dec-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 50 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Relay Coordinat
Coordination studies and reports including setting tables 2336.00 23-Sep-15 08:00 A 18-Nov-16 17:00 A 100% 100%
Elec. Cable List 1536.00 11-Jan-16 08:00 A 23-Sep-16 17:00 A 100% 100%
List / Schedule for
fo Electrical Cable Drum 552.00 12-Jan-16 08:00 A 25-Mar-16 17:00 A 100% 100%
Equipment Heat Dissipation for HVAC Sizing 936.00 11-Mar-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Drawing 3936.00 27-Oct-14 08:00 A 23-Sep-16 17:00 A 100% 100%
Single Line Diagram
Diag For DC UPS 996.00 18-Jun-15 08:00 A 11-Dec-15 12:00 A 100% 100%
Electrical Panel Single
S Line Diagram 1248.00 04-May-15 08:00 A 22-Jan-16 17:00 A 100% 100%
11kV Single Line Diagram 1456.00 04-May-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Key Single Line Diagram
D 2176.00 27-Oct-14 08:00 A 20-Nov-15 17:00 A 100% 100%
3.3kV Single Line
Lin Diagram 1536.00 04-May-15 08:00 A 08-Jan-16 17:00 A 100% 100%
0.4kV Single Line
Lin Diagram 1944.00 04-May-15 08:00 A 29-Jan-16 17:00 A 100% 100%
ENMCS Architecture
Architec Diagrams 784.00 01-Jun-15 08:00 A 31-Aug-15 17:00 A 100% 100%
Substation Equipment
Equi Layout 2216.00 28-Oct-14 08:00 A 30-Nov-15 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 1496.00 27-Apr-15 08:00 A 19-Jan-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout 2928.00 27-Apr-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Wiring / Interconnection
Intercon Diagrams 1536.00 25-Dec-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Substation Floor
Floo Cut-Outs/Steel Frame Layout 1120.00 11-Jan-16 08:00 A 13-Jul-16 17:00 A 100% 100%
RFQ 3136.00 19-Mar-15 08:00 A 13-Sep-16 17:00 A 100% 100%
Transformer 1336.00 17-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Switchgear 1432.00 19-Mar-15 08:00 A 30-Nov-15 17:00 A 100% 100%
UPS System & B Batteries 1536.00 18-Jun-15 08:00 A 15-Mar-16 17:00 A 100% 100%
Bus Duct 1248.00 04-May-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Capacitor 2464.00 04-May-15 08:00 A 19-Jul-16 17:00 A 100% 100%
ENMCS/Panels 2184.00 03-Sep-15 08:00 A 13-Sep-16 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 2104.00 28-Apr-15 08:00 A 12-May-16 17:00 A 100% 100%
Cable 1240.00 28-Apr-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Other Material 1120.00 04-Nov-15 08:00 A 25-May-16 17:00 A 100% 100%
Civil/Structure 1448.00 29-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Document 997.60 29-Jul-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Calculation For SUB-121
S 997.60 29-Jul-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Drawing 1448.00 29-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of SUB121
SU 848.00 29-Jul-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Building Foundations
Founda Drawings 840.00 23-Sep-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Columns/Beams 616.00 17-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Details/Framing Plans 604.00 18-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Architecture 2320.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Drawing 2320.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
DETAIL DRAWINGS
DRAWIN 2200.00 01-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Ground Floor PlanPl 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
First Floor Plan 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Roof Plan 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Elevations&Sections
Elevations&Sect 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Finishing Schedule
Schedu 2112.00 12-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Heating, Ventilation & Air Conditioning (HVAC) 3088.00 28-Apr-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Document 3088.00 28-Apr-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Calculation 1344.00 28-Apr-15 08:00 A 23-Dec-15 17:00 A 100% 100%
Data Sheet for H HVAC Equipment 2392.00 29-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Equipment list and
an MTO for HVAC system 2736.00 30-Jun-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Drawing 2912.00 29-Apr-15 08:00 A 30-Sep-16 17:00 A 100% 100%
layout for HVAC DIDS 2912.00 29-Apr-15 08:00 A 30-Sep-16 17:00 A 100% 100%
layout for Equipment,ducting
Equipm 2464.00 29-Jun-15 08:00 A 13-Sep-16 17:00 A 100% 100%
RFQ 2096.00 22-Jun-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Air conditioner/Air
conditioner/A duct 2096.00 22-Jun-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 2248.00 01-Apr-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Document 1560.00 22-Jun-15 08:00 A 29-Mar-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 51 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Datasheet for In Inert gas fire extinguishing system 512.00 20-Aug-15 08:00 A 18-Feb-16 17:00 A 100% 100%
Material Take Off 1216.00 27-Jul-15 08:00 A 03-Mar-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1560.00 22-Jun-15 08:00 A 29-Mar-16 17:00 A 100% 100%
Drawing 2248.00 01-Apr-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Fire Extinguishers
Extinguisher Layout 2088.00 01-Apr-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Layout for Fire and
a gas detection and alarming devices 2248.00 01-Apr-15 08:00 A 01-Apr-16 17:00 A 100% 100%
RFQ 848.00 28-Jul-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Fire Hydrant/ Fire
Fir Extinguisher 848.00 28-Jul-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 2296.00 01-Apr-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Document 2000.00 15-May-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices 1904.00 15-May-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 1920.00 15-May-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Teleco
Telecommunicaiton Conduits And Accessories 1904.00 15-May-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Fire de detection 1960.00 22-May-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Drawing 2296.00 01-Apr-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Fire Alarm System
Syste layout 1104.00 21-May-15 08:00 A 03-Dec-15 17:00 A 100% 100%
layout for Teleco
Telecommunicaiton devices location 2296.00 01-Apr-15 08:00 A 15-Apr-16 17:00 A 100% 100%
RFQ 1632.00 18-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Devices 1440.00 18-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Detection 1400.00 25-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Cable 1632.00 18-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
6850-SUB-122 4192.00 27-Oct-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Electrical 4192.00 27-Oct-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Document 3560.00 15-Feb-15 08:00 A 18-Nov-16 17:00 A 100% 100%
Data sheet For ENMCS 1216.00 04-May-15 08:00 A 02-Sep-15 17:00 A 100% 100%
Calculation for DCD UPS and battery up 1552.00 19-Jun-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Interface ENMCS
ENMC I/O List 2584.00 14-Jul-15 08:00 A 14-Sep-16 17:00 A 100% 100%
Schedule For 11KV
11 Switchgear 2088.00 28-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Schedule For 3.3KV
3.3 Switchgear 1920.00 28-Apr-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Schedule For LV Switchgear 2896.00 05-May-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Data sheet For 1 11/0.42KV Transformer 1056.00 16-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data sheet For 1 11/3.45KV Transformer 1056.00 16-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data sheet For 3 33/11.5KV Transformer 1056.00 16-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Equipment List 936.00 15-Jun-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Electrical Consumer
Consum List 1744.00 15-Feb-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Earthing Calculation
Calcula 1872.00 07-May-15 08:00 A 08-Apr-16 17:00 A 100% 100%
ENMCS I/O List 1064.00 13-Jul-15 08:00 A 19-Jan-16 17:00 A 100% 100%
MTO For Earthin
Earthing And Lightning Material 1432.00 21-Aug-15 08:00 A 10-May-16 17:00 A 100% 100%
MTO For Cable 1192.00 30-Nov-15 08:00 A 01-Jul-16 17:00 A 100% 100%
MTO For Cable Ladder And Cable Tray 1896.00 24-Aug-15 08:00 A 01-Aug-16 17:00 A 100% 100%
MTO For other material 2584.00 05-Jun-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Data Sheet For Soft Starter 1624.00 20-Mar-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Data Sheet For 0.4kv Switchgear 888.00 20-Mar-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For 11kv Switchgear 1056.00 15-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For 3.3kv Switchgear 1056.00 15-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For DC UPS Up 1056.00 15-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For LV Vsds 816.00 23-Mar-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Data Sheet For Neutral Earthing Resistor 1240.00 21-Apr-15 08:00 A 25-Nov-15 17:00 A 100% 100%
Data Sheet For 11kv Bus Ducts 1120.00 21-May-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Data Sheet For 0.42kv Bus Ducts 1120.00 21-May-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Electrical Load Schedule/Power
S Balance 1328.00 04-May-15 08:00 A 24-Dec-15 17:00 A 100% 100%
Relay Coordinat
Coordination studies and reports including setting tables 2352.00 21-Sep-15 08:00 A 18-Nov-16 17:00 A 100% 100%
Elec. Cable List 1816.00 27-Nov-15 08:00 A 23-Sep-16 17:00 A 100% 100%
List / Schedule for
fo Electrical Cable Drum 1008.00 27-Nov-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Equipment Heat Dissipation for HVAC Sizing 1288.00 11-Mar-15 08:00 A 21-Aug-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 52 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Drawing 4016.00 27-Oct-14 08:00 A 30-Sep-16 17:00 A 100% 100%


Single Line Diagram
Diag For DC UPS 984.00 19-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Electrical Panel Single
S Line Diagram 1248.00 04-May-15 08:00 A 22-Jan-16 17:00 A 100% 100%
11kV Single Line Diagram 1456.00 04-May-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Key Single Line Diagram
D 2216.00 27-Oct-14 08:00 A 27-Nov-15 17:00 A 100% 100%
3.3kV Single Line
Lin Diagram 1536.00 04-May-15 08:00 A 08-Jan-16 17:00 A 100% 100%
0.4kV Single Line
Lin Diagram 1944.00 04-May-15 08:00 A 29-Jan-16 17:00 A 100% 100%
ENMCS Architecture
Architec Diagrams 784.00 01-Jun-15 08:00 A 31-Aug-15 17:00 A 100% 100%
Substation Equipment
Equi Layout 1904.00 28-Oct-14 08:00 A 30-Sep-15 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 1520.00 27-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout 3008.00 27-Apr-15 08:00 A 03-Aug-16 17:00 A 100% 100%
Wiring / Interconnection
Intercon Diagrams 1592.00 25-Dec-15 08:00 A 30-Sep-16 17:00 A 100% 100%
Substation Floor
Floo Cut-Outs/Steel Frame Layout 1096.00 28-Dec-15 08:00 A 13-Jul-16 17:00 A 100% 100%
RFQ 3128.00 20-Mar-15 08:00 A 13-Sep-16 17:00 A 100% 100%
Transformer 1336.00 17-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Switchgear 1424.00 20-Mar-15 08:00 A 30-Nov-15 17:00 A 100% 100%
UPS System & B Batteries 1488.00 19-Jun-15 08:00 A 15-Mar-16 17:00 A 100% 100%
Starter 616.00 23-Oct-15 08:00 A 16-Nov-15 17:00 A 100% 100%
Bus Duct 1240.00 05-May-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Capacitor 2456.00 05-May-15 08:00 A 19-Jul-16 17:00 A 100% 100%
ENMCS/Panels 2184.00 03-Sep-15 08:00 A 13-Sep-16 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 2104.00 28-Apr-15 08:00 A 12-May-16 17:00 A 100% 100%
Cable 1240.00 28-Apr-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Other Material 1296.00 30-Sep-15 08:00 A 25-May-16 17:00 A 100% 100%
Civil/Structure 1448.00 29-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Document 992.00 29-Jul-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Calculation For SUB-122
S 992.00 29-Jul-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Drawing 1448.00 29-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of SUB122
SU 848.00 29-Jul-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Building Structure
Structur Drawings for Columns/Beams 608.00 17-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Foundations
Founda Drawings 840.00 23-Sep-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Details/Framing Plans 604.00 18-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Architecture 2320.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Drawing 2320.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
DETAIL DRAWINGS
DRAWIN 2240.00 25-Mar-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Ground Floor PlanPl 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
First Floor Plan 2112.00 12-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Roof Plan 2112.00 12-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Elevations&Sections
Elevations&Sect 2112.00 12-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Finishing Schedule
Schedu 2104.00 13-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Heating, Ventilation & Air Conditioning (HVAC) 3080.00 29-Apr-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Document 3080.00 29-Apr-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Calculation 1336.00 29-Apr-15 08:00 A 23-Dec-15 17:00 A 100% 100%
Data Sheet for H HVAC Equipment 2384.00 30-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Equipment list and
an MTO for HVAC system 2736.00 30-Jun-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Drawing 2904.00 30-Apr-15 08:00 A 30-Sep-16 17:00 A 100% 100%
layout for HVAC DIDS 2904.00 30-Apr-15 08:00 A 30-Sep-16 17:00 A 100% 100%
layout for Equipment,ducting
Equipm 2464.00 29-Jun-15 08:00 A 13-Sep-16 17:00 A 100% 100%
RFQ 2096.00 22-Jun-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Air conditioner/Air
conditioner/A duct 2096.00 22-Jun-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 2296.00 25-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Document 1560.00 22-Jun-15 08:00 A 29-Mar-16 17:00 A 100% 100%
Datasheet for In Inert gas fire extinguishing system 504.00 20-Aug-15 08:00 A 18-Feb-16 17:00 A 100% 100%
Material Take Off 856.00 17-Aug-15 08:00 A 03-Mar-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1560.00 22-Jun-15 08:00 A 29-Mar-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 53 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Drawing 2296.00 25-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%


Fire Extinguishers
Extinguisher Layout 2176.00 25-Mar-15 08:00 A 15-Mar-16 17:00 A 100% 100%
Layout for Fire and
a gas detection and alarming devices 2296.00 25-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
RFQ 720.00 17-Aug-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Fire Hydrant/ Fire
Fir Extinguisher 720.00 17-Aug-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 2336.00 25-Mar-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Document 2000.00 15-May-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices 1904.00 15-May-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 1920.00 15-May-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Teleco
Telecommunicaiton Conduits And Accessories 1904.00 15-May-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Fire de detection 1960.00 22-May-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Drawing 2336.00 25-Mar-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Fire Alarm System
Syste layout 1096.00 21-May-15 08:00 A 02-Dec-15 17:00 A 100% 100%
layout for Teleco
Telecommunicaiton devices location 2336.00 25-Mar-15 08:00 A 15-Apr-16 17:00 A 100% 100%
RFQ 1632.00 18-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Devices 1440.00 18-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Detection 1400.00 25-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Cable 1632.00 18-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
6850-SUB-152 4360.00 27-Oct-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Electrical 4360.00 27-Oct-14 08:00 A 18-Nov-16 17:00 A 100% 100%
Document 3728.00 15-Feb-15 08:00 A 18-Nov-16 17:00 A 100% 100%
Data sheet For ENMCS 1216.00 04-May-15 08:00 A 02-Sep-15 17:00 A 100% 100%
Calculation for DC
D UPS and battery up 1560.00 18-Jun-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Interface ENMCS
ENMC I/O List 2576.00 14-Jul-15 08:00 A 15-Sep-16 17:00 A 100% 100%
Schedule For 11KV
11 Switchgear 1520.00 05-Jun-15 08:00 A 08-Jan-16 17:00 A 100% 100%
Schedule For LV Switchgear 2816.00 04-May-15 08:00 A 16-Sep-16 17:00 A 100% 100%
Data sheet For 1 11/0.42KV Transformer 1048.00 16-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data sheet For 3 33/11.5KV Transformer 1048.00 16-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Equipment List 1056.00 25-May-15 08:00 A 27-Nov-15 17:00 A 100% 100%
Electrical Consumer
Consum List 1744.00 15-Feb-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Earthing Calculation
Calcula 1840.00 07-May-15 08:00 A 01-Apr-16 17:00 A 100% 100%
ENMCS I/O List 1064.00 13-Jul-15 08:00 A 19-Jan-16 17:00 A 100% 100%
MTO For Earthin
Earthing And Lightning Material 1432.00 21-Aug-15 08:00 A 10-May-16 17:00 A 100% 100%
MTO For Cable 1192.00 30-Nov-15 08:00 A 01-Jul-16 17:00 A 100% 100%
MTO For Cable Ladder And Cable Tray 1936.00 24-Aug-15 08:00 A 01-Aug-16 17:00 A 100% 100%
MTO For other material 2088.00 01-Sep-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Data Sheet For Soft Starter 1904.00 15-Feb-15 08:00 A 25-Jan-16 17:00 A 100% 100%
Data Sheet For 0.4kv Switchgear 1056.00 15-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For 11kv Switchgear 1056.00 15-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For Dc Ups Up 1056.00 15-Feb-15 08:00 A 24-Aug-15 17:00 A 100% 100%
Data Sheet For Lv Vsds 992.00 15-Feb-15 08:00 A 12-Aug-15 17:00 A 100% 100%
Data Sheet For Neutral Earthing Resistor 1504.00 20-Mar-15 08:00 A 25-Nov-15 17:00 A 100% 100%
Data Sheet For 11kv Bus Ducts 1464.00 20-Mar-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Data Sheet For 0.42kv Bus Ducts 1464.00 20-Mar-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Electrical Load Schedule/Power
S Balance 1328.00 04-May-15 08:00 A 24-Dec-15 17:00 A 100% 100%
Relay Coordinat
Coordination studies and reports including setting tables 2520.00 21-Sep-15 08:00 A 18-Nov-16 17:00 A 100% 100%
Elec. Cable List 1848.00 23-Nov-15 08:00 A 23-Sep-16 17:00 A 100% 100%
List / Schedule for
fo Electrical Cable Drum 824.00 24-Nov-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Equipment Heat Dissipation for HVAC Sizing 936.00 11-Mar-15 08:00 A 21-Aug-15 17:00 A 100% 100%
Drawing 4016.00 27-Oct-14 08:00 A 30-Sep-16 17:00 A 100% 100%
Single Line Diagram
Diag For DC UPS 992.00 18-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Electrical Panel Single
S Line Diagram 1248.00 04-May-15 08:00 A 22-Jan-16 17:00 A 100% 100%
11kV Single Line Diagram 1536.00 04-May-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Key Single Line Diagram
D 2176.00 27-Oct-14 08:00 A 20-Nov-15 17:00 A 100% 100%
0.4kV Single Line
Lin Diagram 1768.00 04-May-15 08:00 A 29-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 54 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

ENMCS Architecture
Architec Diagrams 784.00 01-Jun-15 08:00 A 31-Aug-15 17:00 A 100% 100%
Substation Equipment
Equi Layout 1360.00 02-Feb-15 08:00 A 30-Sep-15 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 1520.00 27-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout 3008.00 27-Apr-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Wiring / Interconnection
Intercon Diagrams 1584.00 25-Dec-15 08:00 A 30-Sep-16 17:00 A 100% 100%
Substation Floor
Floo Cut-Outs/Steel Frame Layout 936.00 11-Jan-16 08:00 A 28-Jun-16 17:00 A 100% 100%
RFQ 3656.00 16-Feb-15 08:00 A 13-Sep-16 17:00 A 100% 100%
Transformer 1336.00 17-Apr-15 08:00 A 11-Dec-15 17:00 A 100% 100%
Switchgear 1584.00 16-Feb-15 08:00 A 30-Nov-15 17:00 A 100% 100%
UPS System & B Batteries 1496.00 18-Jun-15 08:00 A 15-Mar-16 17:00 A 100% 100%
Starter 512.00 22-Oct-15 08:00 A 13-Nov-15 17:00 A 100% 100%
Bus Duct 1248.00 04-May-15 08:00 A 07-Dec-15 17:00 A 100% 100%
Capacitor 2464.00 04-May-15 08:00 A 19-Jul-16 17:00 A 100% 100%
ENMCS/Panels 2080.00 03-Sep-15 08:00 A 13-Sep-16 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 2104.00 28-Apr-15 08:00 A 12-May-16 17:00 A 100% 100%
Cable 1240.00 28-Apr-15 08:00 A 04-Dec-15 17:00 A 100% 100%
Other Material 2224.00 04-Nov-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Civil/Structure 1528.00 29-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Document 1008.00 29-Jul-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Calculation For SUB-152
S 1008.00 29-Jul-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Drawing 1528.00 29-Jul-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of SUB152
SU 896.00 29-Jul-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Building Structure
Structur Drawings for Columns/Beams 1048.00 28-Sep-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Foundations
Founda Drawings 840.00 23-Sep-15 08:00 A 15-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Details/Framing Plans 1048.00 29-Sep-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Architecture 2320.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Drawing 2320.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
DETAIL DRAWINGS
DRAWIN 2200.00 01-Apr-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Ground Floor PlanPl 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
First Floor Plan 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Roof Plan 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Elevations&Sections
Elevations&Sect 2120.00 11-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Finishing Schedule
Schedu 2112.00 12-Mar-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Heating, Ventilation & Air Conditioning (HVAC) 3088.00 28-Apr-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Document 3088.00 28-Apr-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Calculation 1344.00 28-Apr-15 08:00 A 23-Dec-15 17:00 A 100% 100%
Data Sheet for H HVAC Equipment 2392.00 29-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Equipment list and
an MTO for HVAC system 2736.00 30-Jun-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Drawing 2912.00 29-Apr-15 08:00 A 30-Sep-16 17:00 A 100% 100%
layout for HVAC DIDS 2912.00 29-Apr-15 08:00 A 30-Sep-16 17:00 A 100% 100%
layout for Equipment,ducting
Equipm 2464.00 29-Jun-15 08:00 A 13-Sep-16 17:00 A 100% 100%
RFQ 2096.00 22-Jun-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Air conditioner/Air
conditioner/A duct 2096.00 22-Jun-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 2288.00 25-Mar-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Document 1696.00 22-Jun-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Datasheet for In Inert gas fire extinguishing system 968.00 24-Aug-15 08:00 A 18-Feb-16 17:00 A 100% 100%
Material Take Off 1496.00 27-Jul-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1560.00 22-Jun-15 08:00 A 29-Mar-16 17:00 A 100% 100%
Drawing 2288.00 25-Mar-15 08:00 A 01-Apr-16 17:00 A 100% 100%
Fire Extinguishers
Extinguisher Layout 1800.00 25-Mar-15 08:00 A 15-Feb-16 17:00 A 100% 100%
Layout for Fire and
a gas detection and alarming devices 2248.00 01-Apr-15 08:00 A 01-Apr-16 17:00 A 100% 100%
RFQ 848.00 28-Jul-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Fire Hydrant/ Fire
Fir Extinguisher 848.00 28-Jul-15 08:00 A 30-Nov-15 17:00 A 100% 100%
Navigation and Telecommunications
Te 2600.00 15-Feb-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Document 2600.00 15-Feb-15 08:00 A 26-Apr-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 55 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

MTO for Telecom


Telecommunicaiton devices 2024.00 23-Apr-15 08:00 A 22-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton Cable 2240.00 23-Apr-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Fire de detection 2480.00 15-Feb-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Teleco
Telecommunicaiton Conduits And Accessories 2024.00 23-Apr-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Drawing 2320.00 19-Mar-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Fire Alarm System
Syste layout 632.00 12-Aug-15 08:00 A 03-Dec-15 17:00 A 100% 100%
layout for Teleco
Telecommunicaiton devices location 2320.00 19-Mar-15 08:00 A 15-Apr-16 17:00 A 100% 100%
RFQ 1760.00 23-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Devices 1568.00 24-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Detection 1576.00 23-Apr-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable 1752.00 24-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Field Auxiliary Rooms 3752.00 26-Dec-14 08:00 A 03-Nov-16 17:00 A 100% 100%
6750-FAR-111 3744.00 29-Dec-14 08:00 A 03-Nov-16 17:00 A 100% 100%
Instrumentation an and control 3392.00 29-Dec-14 08:00 A 31-Aug-16 17:00 A 100% 100%
Document 3200.00 02-Feb-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Electrical & Instrument
Instru Interface List Including IRP 328.00 28-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for ENMCS 192.00 04-Jan-16 08:00 A 04-Feb-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for MMS 208.00 30-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for MCC 192.00 04-Jan-16 08:00 A 04-Feb-16 17:00 A 100% 100%
Material Take OffOf For Bulk Items in FAR-111 168.00 07-Mar-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Material Take OffOf for Instrument Cable/Cable Tray in FAR-111 168.00 07-Mar-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Power Feeds List Lis with Power Consumption for UPS and non-UPS Consumers 480.00 02-Feb-15 08:00 A 29-Apr-15 17:00 A 100% 100%
Wireless HART coverage study report 1384.00 25-Dec-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Drawing 2696.00 29-Dec-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Cable Entry Layouts
Layo for FAR-111 568.00 25-Dec-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Cable Trench an and Tray Layout Routing Drawing in FAR-111 568.00 28-Dec-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Instrument Earth
Eartheing Layouts for FAR-111 648.00 04-Jan-16 08:00 A 08-Apr-16 17:00 A 100% 100%
Instrument Equip
Equipment Layouts for FAR-111 2576.00 29-Dec-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Power Distribution
Distributio Board Single Line Diagrams for UPS and non-UPS CONSUMERS 328.00 28-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
RFQ 200.00 07-Mar-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Req for Cable Tray/Instrument
Tr Cable/Bulk 200.00 07-Mar-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Electrical 3304.00 12-Mar-15 08:00 A 07-Sep-16 17:00 A 100% 100%
Document 3304.00 12-Mar-15 08:00 A 07-Sep-16 17:00 A 100% 100%
Far(6750) Electrical
Electr Cable Drum Schedule For 6750-Far-111 1160.00 22-Sep-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Far(6750) Electrical
Electr Cable List For 6750-Far-111 1816.00 22-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Far(6750) Electrical
Electr Consumer List For 6750-Far-111 1648.00 12-Mar-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Material Take Of Off For Earthing And Lightning Material 1336.00 08-Sep-15 08:00 A 10-May-16 17:00 A 100% 100%
Material Take OffOf For Cable 1456.00 04-Nov-15 08:00 A 13-Jun-16 17:00 A 100% 100%
Material Take Of Off For Cable Ladder And Cable Tray 2032.00 04-Nov-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Material Take Of Off For Distribution Panel (Non-Ex Type) 880.00 04-Nov-15 08:00 A 27-Jan-16 17:00 A 100% 100%
Material Take OffOf For other material 1560.00 19-Jan-16 08:00 A 02-Sep-16 17:00 A 100% 100%
Far (6750) Data Sheet For AC UPS UP-111-V-01 656.00 08-May-15 08:00 A 31-Aug-15 17:00 A 100% 100%
Far(6750) Interface
Interf Enmcs I/O List 6750-Far-111 2872.00 08-May-15 08:00 A 07-Sep-16 17:00 A 100% 100%
Calculation For AC A Ups And Battery Up-111-V-01, Up-121-V-01, Up-122-V-01 2600.00 18-Jun-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Drawing 1976.00 08-May-15 08:00 A 28-Apr-16 17:00 A 100% 100%
Far(6750) Earthing/Lightning
Earth Layout For 6750-Far-111 1104.00 08-May-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Far(6750) Electrical
Electr Panel Single Line Diagram For 6750-Far-111 576.00 19-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Far(6750) Power
Powe Cable Routing Layout 6750-Far-111 768.00 10-Dec-15 08:00 A 28-Apr-16 17:00 A 100% 100%
FAR(6750) Single
Sing Line Diagram For AC UPS For 6750-Far-111 1144.00 18-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
RFQ 2912.00 08-May-15 08:00 A 02-Sep-16 17:00 A 100% 100%
AC UPS 2480.00 08-May-15 08:00 A 27-Jul-16 17:00 A 100% 100%
Panel 1416.00 01-Dec-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Earthing And Lightning
Lig Material 248.00 23-Nov-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Cable Ladder And An Cable Tray 168.00 04-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable 232.00 20-Nov-15 08:00 A 18-Dec-15 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 56 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Elec. Bulk Material


Mater 464.00 20-Jan-16 08:00 A 14-Apr-16 17:00 A 100% 100%
Civil/Structure 2088.00 25-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Document 1344.00 25-Mar-15 08:00 A 03-Nov-15 17:00 A 100% 100%
Calculation 1344.00 25-Mar-15 08:00 A 03-Nov-15 17:00 A 100% 100%
General Notes Of O Field Auxiliary Room Far-6750-111/121/122 736.00 26-Mar-15 08:00 A 03-Aug-15 17:00 A 100% 100%
Drawing 1344.00 04-Aug-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Foundations
Founda Drawings 696.00 04-Aug-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Columns/Beams 944.00 16-Oct-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Details/Framing Plans 536.00 28-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of FAR-6750-111
FA 584.80 04-Aug-15 08:00 A 18-Nov-15 17:00 A 100% 100%
Architactural 2576.00 02-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Drawing 2576.00 02-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-111 ELEVATION B,C,D 2240.00 02-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-111 FINISHING & DOOR SCHEDULES 2152.00 16-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-111 GROUND FLOOR PLAN 2240.00 02-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-111 SECTION A & ELEVATION A 2240.00 02-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-111 ROOF PLAN 2240.00 02-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-111 REFLECTED CEILING PLAN 1808.00 13-May-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-111 DETAIL DRAWINGS 2032.00 13-May-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Heating, Ventilation & Air Conditioning (HVAC) 3280.00 25-Mar-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Document 3280.00 25-Mar-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Calculation note for FAR-111 1536.00 25-Mar-15 08:00 A 23-Dec-15 17:00 A 100% 100%
HVAC Equipment
Equipmen data sheet for FAR-111 2592.00 25-Mar-15 08:00 A 04-Jul-16 17:00 A 100% 100%
HVAC Equipment
Equipmen list for FAR-111 1816.00 11-Dec-15 08:00 A 03-Nov-16 17:00 A 100% 100%
MTO for HVAC ssystem for FAR-111 1536.00 01-Feb-16 08:00 A 03-Nov-16 17:00 A 100% 100%
Drawing 3112.00 26-Mar-15 08:00 A 07-Sep-16 17:00 A 100% 100%
Plumbing drawing
drawin 968.00 11-Dec-15 08:00 A 06-Jun-16 17:00 A 100% 100%
Equipment,ducting layouts
Equipment,ductin 1504.00 11-Dec-15 08:00 A 07-Sep-16 17:00 A 100% 100%
HVAC Flow Diagram
Diag 3112.00 26-Mar-15 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 2592.00 25-Mar-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Requisitions of Air
A conditioner/Air duct/ventilation equipment 2592.00 25-Mar-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Requisitions of HVAC
H bulk material 840.00 02-Feb-16 08:00 A 04-Jul-16 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 2928.00 25-Mar-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Document 1712.00 15-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Material Take Off 1712.00 15-Jun-15 08:00 A 17-Feb-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1424.00 22-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Drawing 2024.00 25-Mar-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2024.00 25-Mar-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Fire Extinguishers
Extinguisher Layout 1744.00 25-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
RFQ 1688.00 02-Nov-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Fire Hydrant/Fire Extinguisher 1688.00 02-Nov-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Navigation and Telecommunications
Te 2600.00 03-Feb-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Document 2256.00 17-Mar-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Bulk Material
Ma 1232.00 03-Aug-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices/Fire detection 2224.00 17-Mar-15 08:00 A 20-Apr-16 17:00 A 100% 100%
Drawing 2600.00 03-Feb-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Telecommunicaiton devices location layout
Telecommunicait 2600.00 03-Feb-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Fire Alarm System
Syste layout 1656.00 22-Jun-15 08:00 A 15-Apr-16 17:00 A 100% 100%
RFQ 1784.00 17-Mar-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Telecommunication devices
Telecommunicat 1784.00 17-Mar-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Fire detection 1280.00 15-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Optic Fiber Cabl
Cable & Cable 112.00 01-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
6750-FAR-121 3752.00 26-Dec-14 08:00 A 03-Nov-16 17:00 A 100% 100%
Instrumentation anand control 3400.00 26-Dec-14 08:00 A 31-Aug-16 17:00 A 100% 100%
Document 3200.00 02-Feb-15 08:00 A 31-Aug-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 57 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Electrical & Instrument


Instru Interface List Including IRP 328.00 28-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for ENMCS 192.00 04-Jan-16 08:00 A 04-Feb-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for 1211-K101 & 201 224.00 02-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for MMS 296.00 15-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for MCC 192.00 04-Jan-16 08:00 A 04-Feb-16 17:00 A 100% 100%
Material Take Off(
Of Bulk Items/ Instrument Cable/ Cable Tray) 168.00 07-Mar-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Power Feeds List Lis with Power Consumption for UPS and non-UPS Consumers 456.00 02-Feb-15 08:00 A 24-Apr-15 17:00 A 100% 100%
Wireless HART coverage study report 1384.00 25-Dec-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Drawing 2584.00 26-Dec-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Cable Entry Layouts
Layo for FAR-121 560.00 28-Dec-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Cable Trench an and Tray Layout Routing Drawing in FAR-121 560.00 28-Dec-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Instrument Earth
Eartheing Layouts for FAR-121 528.00 04-Jan-16 08:00 A 08-Apr-16 17:00 A 100% 100%
Instrument Equip
Equipment Layouts for FAR-121 2584.00 26-Dec-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Power Distribution
Distributio Board Single Line Diagrams for UPS and non-UPS CONSUMERS 328.00 28-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
RFQ 2392.00 02-Feb-15 08:00 A 18-Mar-16 17:00 A 100% 100%
MMS 2240.00 02-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
Req for Cable Tray/Instrument
Tr Cable/Bulk 200.00 07-Mar-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Electrical 3600.00 05-Jan-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Document 3600.00 05-Jan-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Far(6750) Electrical
Electr Cable Drum Schedule For 6750-Far-121 1272.00 08-Sep-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Far(6750) Electrical
Electr Cable List For 6750-Far-121 2736.00 05-Jan-15 08:00 A 13-May-16 17:00 A 100% 100%
Far(6750) Electrical
Electr Consumer List For 6750-Far-121 1400.00 27-Apr-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Material Take Of Off For Earthing And Lightning Material 1336.00 08-Sep-15 08:00 A 10-May-16 17:00 A 100% 100%
Material Take OffOf For Cable 1968.00 02-Nov-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Material Take Of Off For Cable Ladder And Cable Tray 1960.00 02-Nov-15 08:00 A 01-Aug-16 17:00 A 100% 100%
Material Take Of Off For Distribution Panel (Non-Ex Type) 872.00 02-Nov-15 08:00 A 27-Jan-16 17:00 A 100% 100%
Material Take OffOf For other material 1472.00 20-Jan-16 08:00 A 02-Sep-16 17:00 A 100% 100%
FAR (6750) Data Sheet For AC UPS UP-121-V-01 664.00 08-May-15 08:00 A 31-Aug-15 17:00 A 100% 100%
Far(6750) Interface
Interf Enmcs I/O List 6750-Far-121 2872.00 08-May-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Drawing 2056.00 08-May-15 08:00 A 13-May-16 17:00 A 100% 100%
Far(6750) Earthing/Lightning
Earth Layout For 6750-Far-121 1128.00 08-May-15 08:00 A 25-Nov-15 17:00 A 100% 100%
Far(6750) Electrical
Electr Panel Single Line Diagram For 6750-Far-121 624.00 11-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Far(6750) Power
Powe Cable Routing Layout 6750-Far-121 792.00 21-Dec-15 08:00 A 13-May-16 17:00 A 100% 100%
Far(6750)Single Line Diagram For Ac Ups For 6750-Far-121 1152.00 18-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
RFQ 2912.00 08-May-15 08:00 A 02-Sep-16 17:00 A 100% 100%
AC UPS 2480.00 08-May-15 08:00 A 27-Jul-16 17:00 A 100% 100%
Panel 1424.00 01-Dec-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Earthing And Lightning
Lig Material 400.00 02-Nov-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Cable Ladder And An Cable Tray 168.00 04-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Cable 240.00 20-Nov-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Elec. Bulk Material
Mater 456.00 21-Jan-16 08:00 A 14-Apr-16 17:00 A 100% 100%
Civil/Structure 2136.00 31-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Document 1312.00 31-Mar-15 08:00 A 03-Nov-15 17:00 A 100% 100%
Calculation 1312.00 31-Mar-15 08:00 A 03-Nov-15 17:00 A 100% 100%
Drawing 1672.00 22-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Foundations
Founda Drawings 696.00 10-Aug-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Columns/Beams 1024.00 16-Oct-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Details/Framing Plans 512.00 02-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of FAR-6750-121
FA 832.80 22-Jun-15 08:00 A 18-Nov-15 17:00 A 100% 100%
Architactural 2536.00 02-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Drawing 2536.00 02-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-121 ELEVATION B,C,D 1992.00 02-Feb-15 08:00 A 22-Jan-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-121 FINISHING & DOOR SCHEDULES 1992.00 16-Feb-15 08:00 A 22-Jan-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-121 GROUN D FLOOR PLAN 1992.00 02-Feb-15 08:00 A 22-Jan-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-121 SECTIO N A & ELEVATION A 1968.00 03-Feb-15 08:00 A 22-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 58 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-121 ROOF PLAN 1968.00 03-Feb-15 08:00 A 22-Jan-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-121 REFLEC TED CEILING PLAN 1808.00 13-May-15 08:00 A 22-Jan-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-121 DETAIL DRAWINGS 1992.00 13-May-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Heating, Ventilation & Air Conditioning (HVAC) 3248.00 31-Mar-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Document 3248.00 31-Mar-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Calculation note for FAR-121 1504.00 31-Mar-15 08:00 A 23-Dec-15 17:00 A 100% 100%
HVAC Equipment
Equipmen data sheet for FAR-121 2552.00 01-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
HVAC Equipment
Equipmen list for FAR-121 1816.00 11-Dec-15 08:00 A 03-Nov-16 17:00 A 100% 100%
MTO for HVAC ssystem for FAR-121 1536.00 01-Feb-16 08:00 A 03-Nov-16 17:00 A 100% 100%
Drawing 3088.00 31-Mar-15 08:00 A 07-Sep-16 17:00 A 100% 100%
Plumbing drawing
drawin 1096.00 17-Dec-15 08:00 A 04-Jul-16 17:00 A 100% 100%
layout for Equipment,ducting
Equipm 1504.00 11-Dec-15 08:00 A 07-Sep-16 17:00 A 100% 100%
HVAC Flow Diagram
Diag 3088.00 31-Mar-15 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 2552.00 01-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Requisitions of Air
A conditioner/Air duct/ventilation equipment 1120.00 01-Apr-15 08:00 A 19-Oct-15 17:00 A 100% 100%
Requisitions of HVAC
H bulk material 840.00 02-Feb-16 08:00 A 04-Jul-16 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 2896.00 31-Mar-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Document 1712.00 15-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Material Take Off 1712.00 15-Jun-15 08:00 A 17-Feb-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1424.00 22-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Drawing 2084.00 31-Mar-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2084.00 31-Mar-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Fire Extinguishers
Extinguisher Layout 1344.00 31-Mar-15 08:00 A 11-Sep-15 17:00 A 100% 100%
RFQ 1688.00 02-Nov-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Fire Hydrant/Fire Extinguisher 1688.00 02-Nov-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Navigation and Telecommunications
Te 2476.80 03-Feb-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Document 2064.00 20-Apr-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Bulk Material
Ma 1232.00 03-Aug-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices/Fire detection 2032.00 20-Apr-15 08:00 A 20-Apr-16 17:00 A 100% 100%
Drawing 2476.80 03-Feb-15 08:00 A 15-Apr-16 15:24 A 100% 100%
Telecommunicaiton devices location layout
Telecommunicait 2476.80 03-Feb-15 08:00 A 15-Apr-16 13:48 A 100% 100%
Fire Alarm System
Syste layout 1662.40 22-Jun-15 08:00 A 15-Apr-16 15:24 A 100% 100%
RFQ 1592.00 20-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Telecommunication devices
Telecommunicat 1592.00 20-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Fire detection 1584.00 21-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Optic Fiber Cabl
Cable & Cable 168.00 01-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
6750-FAR-122 3752.00 26-Dec-14 08:00 A 03-Nov-16 17:00 A 100% 100%
Instrumentation anand control 3400.00 26-Dec-14 08:00 A 31-Aug-16 17:00 A 100% 100%
Document 3208.00 30-Jan-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Electrical & Instrument
Instru Interface List Including IRP 384.00 28-Dec-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for ENMCS 192.00 04-Jan-16 08:00 A 04-Feb-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for 1212-K101 & 201 224.00 28-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for MMS 208.00 30-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
Subsystems Serial
Ser Interface Mapping Details for MCC 192.00 04-Jan-16 08:00 A 04-Feb-16 17:00 A 100% 100%
Power Feeds ListLis with Power Consumption for UPS and non-UPS Consumers 456.00 30-Jan-15 08:00 A 23-Apr-15 17:00 A 100% 100%
Wireless HART coverage study report 1376.00 28-Dec-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Material Take Off(
Of Bulk Items/ Instrument Cable/ Cable Tray) 168.00 07-Mar-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Drawing 2584.00 26-Dec-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Cable Entry Layouts
Layo for FAR-122 560.00 28-Dec-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Cable Trench an and Tray Layout Routing Drawing in FAR-122 559.20 28-Dec-15 08:00 A 08-Apr-16 17:00 A 100% 100%
Instrument Earth
Eartheing Layouts for FAR-122 528.00 04-Jan-16 08:00 A 08-Apr-16 17:00 A 100% 100%
Instrument Equip
Equipment Layouts for FAR-122 2584.00 26-Dec-14 08:00 A 08-Apr-16 17:00 A 100% 100%
Power Distribution
Distributio Board Single Line Diagram for UPS and non-UPS Consumers 328.00 28-Dec-15 08:00 A 29-Jan-16 17:00 A 100% 100%
RFQ 200.00 08-Mar-16 08:00 A 18-Mar-16 17:00 A 100% 100%
Req for Cable Tray/Instrument
Tr Cable/Bulk 200.00 08-Mar-16 08:00 A 18-Mar-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 59 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Electrical 3040.00 27-Apr-15 08:00 A 07-Sep-16 17:00 A 100% 100%


Document 3040.00 27-Apr-15 08:00 A 07-Sep-16 17:00 A 100% 100%
Far(6750) Electrical
Electr Cable Drum Schedule For 6750-Far-122 1264.00 09-Sep-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Far(6750) Electrical
Electr Cable List For 6750-Far-122 1979.20 22-May-15 08:00 A 13-May-16 17:00 A 100% 100%
Far(6750) Electrical
Electr Consumer List For 6750-Far-122 1392.00 27-Apr-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Material Take Of Off For Earthing And Lightning Material 1328.00 09-Sep-15 08:00 A 10-May-16 17:00 A 100% 100%
Material Take OffOf For Cable 1656.00 21-Dec-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Material Take Of Off For Cable Ladder And Cable Tray 1712.00 21-Dec-15 08:00 A 02-Sep-16 17:00 A 100% 100%
Material Take Of Off For Distribution Panel (Non-Ex Type) 560.00 21-Dec-15 08:00 A 27-Jan-16 17:00 A 100% 100%
Material Take OffOf For other material 1864.00 11-Nov-15 08:00 A 23-Aug-16 17:00 A 100% 100%
FAR (6750) Data Sheet For AC UPS UP-122-V-01 656.00 08-May-15 08:00 A 31-Aug-15 17:00 A 100% 100%
Far(6750) Interface
Interf Enmcs I/O List 6750-Far-122 2928.00 08-May-15 08:00 A 07-Sep-16 17:00 A 100% 100%
Drawing 2056.00 08-May-15 08:00 A 13-May-16 17:00 A 100% 100%
Far(6750) Earthing/Lightning
Earth Layout For 6750-Far-122 1336.00 08-May-15 08:00 A 31-Dec-15 17:00 A 100% 100%
Far(6750) Electrical
Electr Panel Single Line Diagram For 6750-Far-122 656.00 19-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Far(6750) Power
Powe Cable Routing Layout 6750-Far-122 960.00 20-Nov-15 08:00 A 13-May-16 17:00 A 100% 100%
Far(6750) Single Line Diagram For Ac Ups For 6750-Far-122 1144.00 18-Jun-15 08:00 A 11-Dec-15 17:00 A 100% 100%
RFQ 2912.00 08-May-15 08:00 A 27-Jul-16 17:00 A 100% 100%
AC UPS 2480.00 08-May-15 08:00 A 27-Jul-16 17:00 A 100% 100%
Earthing And Lightning
Lig Material 248.00 23-Nov-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Cable 232.00 20-Nov-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 164.80 04-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Panel 1416.00 02-Dec-15 08:00 A 12-Jul-16 17:00 A 100% 100%
Elec. Bulk Material
Mater 848.00 12-Nov-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Civil/Structure 2136.00 31-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Document 1312.00 31-Mar-15 08:00 A 03-Nov-15 17:00 A 100% 100%
Calculation 1312.00 31-Mar-15 08:00 A 03-Nov-15 17:00 A 100% 100%
Drawing 1672.00 22-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Foundations
Founda Drawings 808.00 10-Aug-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Columns/Beams 1000.00 21-Oct-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Details/Framing Plans 912.00 05-Nov-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of FAR-6750-122
FA 838.40 22-Jun-15 08:00 A 18-Nov-15 17:00 A 100% 100%
Architactural 2360.00 30-Jan-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Drawing 2360.00 30-Jan-15 08:00 A 25-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-122 ELEVATION B,C,D 2248.00 30-Jan-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-122 FINISHING & DOOR SCHEDULES 1936.00 31-Mar-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-122 GROUN D FLOOR PLAN 2248.00 30-Jan-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-122 SECTIO N A & ELEVATION A 2240.00 02-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-122 ROOF PLAN 2240.00 02-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-122 REFLEC TED CEILING PLAN 1808.00 13-May-15 08:00 A 14-Mar-16 17:00 A 100% 100%
FIELD AUXILIARY
AUXILIAR ROOM 6750-FAR-122 DETAIL DRAWINGS 1768.00 13-May-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Heating, Ventilation & Air Conditioning (HVAC) 3248.00 31-Mar-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Document 3248.00 31-Mar-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Calculation note for FAR-122 1504.00 31-Mar-15 08:00 A 23-Dec-15 17:00 A 100% 100%
HVAC Equipment
Equipmen data sheet for FAR-122 2559.20 01-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
HVAC Equipment
Equipmen list for FAR-122 1816.00 11-Dec-15 08:00 A 03-Nov-16 17:00 A 100% 100%
MTO for HVAC ssystem for FAR-122 1536.00 01-Feb-16 08:00 A 03-Nov-16 17:00 A 100% 100%
Drawing 2936.00 31-Mar-15 08:00 A 07-Sep-16 17:00 A 100% 100%
Plumbing drawing
drawin 1432.00 17-Dec-15 08:00 A 31-Aug-16 17:00 A 100% 100%
layout for Equipment,ducting
Equipm 1504.00 11-Dec-15 08:00 A 07-Sep-16 17:00 A 100% 100%
HVAC Flow Diagram
Diag 2872.00 31-Mar-15 08:00 A 26-Aug-16 17:00 A 100% 100%
RFQ 2544.00 02-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Requisitions of Air
A conditioner/Air duct/ventilation equipment 2544.00 02-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Requisitions of HVAC
H bulk material 840.00 02-Feb-16 08:00 A 04-Jul-16 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 2896.00 31-Mar-15 08:00 A 31-Aug-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 60 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Document 1672.00 22-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%


Material Take Off 1080.00 17-Aug-15 08:00 A 17-Feb-16 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1424.00 22-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Drawing 2000.00 31-Mar-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2000.00 31-Mar-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Fire Extinguishers
Extinguisher Layout 1712.00 31-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
RFQ 1584.00 20-Nov-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Fire Hydrant/Fire Extinguisher 1584.00 20-Nov-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Navigation and Telecommunications
Te 2608.00 02-Feb-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Document 2064.00 20-Apr-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Bulk Material
Ma 1232.00 03-Aug-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices/Fire detection 2032.00 20-Apr-15 08:00 A 20-Apr-16 17:00 A 100% 100%
Drawing 2608.00 02-Feb-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Telecommunicaiton devices location layout
Telecommunicait 2608.00 02-Feb-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Fire Alarm System
Syste layout 1656.00 22-Jun-15 08:00 A 15-Apr-16 17:00 A 100% 100%
RFQ 1592.00 20-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Telecommunication devices
Telecommunicat 1592.00 20-Apr-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Fire detection 1288.00 12-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Optic Fiber Cabl
Cable & Cable 168.00 01-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Operating Shelter Building
Bu 3552.00 02-Feb-15 08:00 A 03-Nov-16 17:00 A 100% 100%
6760-OSB-101 3552.00 02-Feb-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Instrumentation anand control 3296.00 02-Feb-15 08:00 A 05-Jul-16 17:00 A 100% 100%
Document 3296.00 02-Feb-15 08:00 A 12-May-16 17:00 A 100% 100%
Operator Shelter
Shelte Building 101( 6760) Mini Laboratory Design Basis 2016.00 02-Feb-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Operator Shelter
Shelte Building 101 (6760) Mini Laboratory Equipment List 96.00 23-Apr-15 08:00 A 11-May-15 17:00 A 100% 100%
Operator Shelter
Shelte Building 101 (6760) Mini Laboratory Testing Equipment Specification 1312.00 23-Apr-15 08:00 A 14-Dec-15 17:00 A 100% 100%
Material Take OfOff For Bulk Items in OSB-101(INC) 1464.00 29-Dec-15 08:00 A 12-May-16 17:00 A 100% 100%
Material Take Off
Of for Instrument Cable(INC) 168.00 20-Nov-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Material Take OfOff for Cable Tray(INC) 648.00 23-Nov-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Drawing 2432.00 23-Apr-15 08:00 A 05-Jul-16 17:00 A 100% 100%
Operator Shelter
Shelte Building 101 (6760) Mini Laboratory Equipment Layout 1232.00 23-Apr-15 08:00 A 22-Sep-15 17:00 A 100% 100%
Cable Trench an and Tray Layout Routing Drawing in OSB-101(INC) 672.00 28-Dec-15 08:00 A 19-Apr-16 17:00 A 100% 100%
Instrument Earth
Eartheing Layouts for OSB-101(INC) 504.00 07-Apr-16 08:00 A 05-Jul-16 17:00 A 100% 100%
Instrument Equip
Equipment Layouts for OSB-101(INC) 544.00 28-Dec-15 08:00 A 06-Apr-16 17:00 A 100% 100%
REQ 1832.00 23-Apr-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Req for Inst. Bulk
Bul Material 424.00 31-Dec-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Furniture 1336.00 23-Apr-15 08:00 A 17-Dec-15 17:00 A 100% 100%
Testing Equipment/Consumption
Equipme 872.00 15-Jul-15 08:00 A 17-Dec-15 17:00 A 100% 100%
Electrical 3280.00 12-Mar-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Document 3280.00 12-Mar-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Electrical Cable Drum
D Schedule 1192.00 23-Sep-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Electrical Cable List
L 2864.00 22-May-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Electrical Consumer
Consum List 1632.00 12-Mar-15 08:00 A 25-Dec-15 17:00 A 100% 100%
Material Take Off
Of For Bulk Material ------ (Include Lighting, Socket, Cables, Etc.) 1416.00 15-Feb-16 08:00 A 17-Aug-16 17:00 A 100% 100%
Drawing 2816.00 08-May-15 08:00 A 23-Sep-16 17:00 A 100% 100%
Earthing/Lightning Layout
Earthing/Lightnin 1704.00 08-May-15 08:00 A 10-Mar-16 17:00 A 100% 100%
Electrical Panel Single
S Line Diagram 568.00 20-Nov-15 08:00 A 22-Jan-16 17:00 A 100% 100%
Power Cable Routing
Ro Layout 1424.00 13-Jan-16 08:00 A 23-Sep-16 17:00 A 100% 100%
REQ 1816.00 20-Nov-15 08:00 A 09-Aug-16 17:00 A 100% 100%
Earthing And Lightning
Lig Material 248.00 23-Nov-15 08:00 A 05-Jan-16 17:00 A 100% 100%
Cable 232.00 20-Nov-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 168.00 04-Jan-16 08:00 A 29-Jan-16 17:00 A 100% 100%
Panel 1416.00 01-Dec-15 08:00 A 09-Aug-16 17:00 A 100% 100%
Elec. Bulk Material
Mater 264.00 25-Feb-16 08:00 A 12-Apr-16 17:00 A 100% 100%
Civil/Structure 2168.00 25-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 61 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Document 1176.00 25-Mar-15 08:00 A 03-Nov-15 15:24 A 100% 100%


Calculation 1176.00 25-Mar-15 08:00 A 03-Nov-15 15:24 A 100% 100%
General Notes Of O Operator Shelter Building Osb-6760-101 736.00 26-Mar-15 08:00 A 03-Aug-15 17:00 A 100% 100%
Drawing 1672.00 22-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Foundations
Founda Drawings 648.00 10-Aug-15 08:00 A 18-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Columns/Beams 640.00 11-Oct-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Building Structure
Structur Drawings for Details/Framing Plans 976.00 26-Oct-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Pile Layout of OSB-6760-101
OS 844.00 22-Jun-15 08:00 A 19-Nov-15 12:00 A 100% 100%
Architactural 2408.00 03-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
Drawing 2408.00 03-Feb-15 08:00 A 25-Mar-16 17:00 A 100% 100%
OPERATOR SH SHELTER BUILDING 6760-OSB-101 GROUND FLOOR PLAN 2232.00 03-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
OPERATOR SH SHELTER BUILDING 6760-OSB-101 ELEVATIONS 2232.00 03-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
OPERATOR SH SHELTER BUILDING 6760-OSB-101 FINISHING & DOOR SCHEDULES 1976.00 24-Mar-15 08:00 A 14-Mar-16 17:00 A 100% 100%
OPERATOR SH SHELTER BUILDING 6760-OSB-101 ROOF PLAN & SECTION A 2232.00 03-Feb-15 08:00 A 14-Mar-16 17:00 A 100% 100%
OPERATOR SH SHELTER BUILDING 6760-OSB-101 REFLECTED CEILING PLAN 1816.00 22-May-15 08:00 A 14-Mar-16 17:00 A 100% 100%
OPERATOR SH SHELTER BUILDING 6760-OSB-101 DETAIL DRAWING S 1720.00 22-May-15 08:00 A 25-Mar-16 17:00 A 0% 0%
Heating, Ventilation & Air Conditioning (HVAC) 3248.00 31-Mar-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Document 3248.00 31-Mar-15 08:00 A 03-Nov-16 17:00 A 100% 100%
Calculation note 1504.00 31-Mar-15 08:00 A 23-Dec-15 17:00 A 100% 100%
HVAC Equipment
Equipmen data sheet 2552.00 01-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
HVAC Equipment
Equipmen list 1672.00 07-Dec-15 08:00 A 14-Sep-16 17:00 A 100% 100%
MTO for HVAC ssystem 1600.00 20-Jan-16 08:00 A 03-Nov-16 17:00 A 100% 100%
Drawing 2896.00 31-Mar-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Plumbing drawing
drawin 1776.00 19-Oct-15 08:00 A 31-Aug-16 17:00 A 100% 100%
layout for Equipment,ducting
Equipm 1680.00 16-Oct-15 08:00 A 12-Aug-16 17:00 A 100% 100%
HVAC Flow Diagram
Diag 2480.00 31-Mar-15 08:00 A 20-Jun-16 17:00 A 100% 100%
RFQ 2544.00 02-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Air conditioner/Air
conditioner/A duct/ventilation equipment 2544.00 02-Apr-15 08:00 A 04-Jul-16 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 2928.00 25-Mar-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Document 1464.00 15-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Material Take Off 1072.00 15-Jun-15 08:00 A 01-Dec-15 17:00 A 100% 100%
Fire and gas cause
cau and effect matrix 1424.00 22-Jun-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Drawing 2568.00 25-Mar-15 08:00 A 29-Jun-16 17:00 A 100% 100%
Fire and gas detection
det and alarming devices layout 2568.00 25-Mar-15 08:00 A 29-Jun-16 17:00 A 100% 100%
Fire Extinguishers
Extinguisher Layout 1744.00 25-Mar-15 08:00 A 29-Jan-16 17:00 A 100% 100%
RFQ 1696.00 09-Nov-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Fire Hydrant/Fire Extinguisher 1696.00 09-Nov-15 08:00 A 31-Aug-16 17:00 A 100% 100%
Navigation and Telecommunications
Te 2464.00 04-Feb-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Document 1936.00 13-May-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Bulk Material
Ma 1232.00 03-Aug-15 08:00 A 26-Apr-16 17:00 A 100% 100%
MTO for Telecom
Telecommunicaiton devices/Fire detection 1936.00 13-May-15 08:00 A 26-Apr-16 17:00 A 100% 100%
Drawing 2452.80 04-Feb-15 08:00 A 15-Apr-16 13:48 A 100% 100%
Telecommunicaiton devices location layout
Telecommunicait 2452.80 04-Feb-15 08:00 A 15-Apr-16 13:48 A 100% 100%
Fire Alarm System
Syste layout 1649.60 22-Jun-15 08:00 A 15-Apr-16 09:36 A 100% 100%
RFQ 1464.00 13-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Telecommunication devices
Telecommunicat 1464.00 13-May-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Fire detection 1280.00 15-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Optic Fiber Cabl
Cable & Cable 168.00 01-Dec-15 08:00 A 18-Dec-15 17:00 A 100% 100%
Piping 1912.00 26-Mar-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Document 1912.00 26-Mar-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Data Sheets for Eyewash & Shower 1912.00 26-Mar-15 08:00 A 04-Mar-16 17:00 A 100% 100%
Procurement 7512.00 22-Aug-14 08:00 A 03-Aug-18 17:00 100% 98.77%
CDU - Crude Distillation
Distilla Unit 7120.00 22-Aug-14 08:00 A 10-Jul-18 17:00 100% 98.97%
1110 - CDU - Crude Distillation Unit 7120.00 22-Aug-14 08:00 A 10-Jul-18 17:00 100% 98.97%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 7120.00 29-Oct-14 08:00 A 02-May-18 17:00 100% 99.6%

Remaining Level of Effort Actual Work Critical Remaining ... Page 62 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Equipment 7120.00 29-Oct-14 08:00 A 02-May-18 17:00 100% 99.6%


Atmospheric Column
Col (1110-C-001) 6192.00 10-Mar-15 08:00 A 26-Feb-18 17:00 A 100% 100%
Columns (1110-C
(1110-C-002/004/003) 3784.00 11-Mar-15 08:00 A 19-Jan-17 17:00 A 100% 100%
Large Size Drums£¨1110-V-002/003/004/005/008£©
Drum 6184.00 15-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Carbom Steel D Drums £¨1110-V-001/006/007/009/0010/011/012/013/014£© 3744.00 15-Apr-15 08:00 A 24-Feb-18 17:00 A 100% 100%
Exchangers Batch1(1110-E-012A-H/003A-H/022A-C/009AB/024/010A-D/011AB/013AB/015/032/017)
Batc 4328.00 30-Jan-15 08:00 A 06-Oct-17 00:00 A 100% 100%
Exchangers Batch2(1110-E-006A-D/007A-D/021A-D/025/001AB/002AB/004AB/005AB/008A-D/019/027/031)
Batc 4216.00 03-Feb-15 08:00 A 31-Mar-17 17:00 A 100% 100%
Air Coolers (1110
(1110-E-014/016/018/020/023/026/028/029/030) 5664.00 11-Mar-15 08:00 A 24-Feb-18 10:40 A 100% 100%
Crude Heater£¨1110-F-001AB£©
Heater£¨ 4096.00 08-Jan-15 08:00 A 23-Dec-16 17:00 A 100% 100%
Internals (1110-CY-001/002/003/004)
(1110-C 6624.00 26-Jan-15 08:00 A 02-May-18 17:00 100% 95%
Desalter Packag
Package (1110-A-001AB/002,1110-V-015AB/016AB) 4320.00 02-Dec-14 08:00 A 18-Jan-17 17:00 A 100% 100%
Inhibitor Package & Amine Injection Package (1110-A-003/004) 6064.00 03-Mar-15 08:00 A 26-Feb-18 17:00 A 100% 100%
UV Disnfection System
S (MRI-1110-7005) 7112.00 29-Oct-14 08:00 A 01-May-18 17:00 0% 0%
Rotating 6280.00 30-Mar-15 08:00 A 01-May-18 17:00 100% 95.21%
Equipment 6280.00 30-Mar-15 08:00 A 01-May-18 17:00 100% 95.21%
Crude Distillation Pumps Batch 1 (1110-P-001ABC/004ABC/005AB/006AB/011AB/012AB/015ABC) 6280.00 30-Mar-15 08:00 A 01-May-18 17:00 100% 95%
Crude Distillation Pumps Batch 2 (1110-P-002ABC/003AB/007AB/008AB/003AB/010AB/013AB etc. ) 5064.00 30-Mar-15 08:00 A 30-Apr-18 17:00 100% 95.69%
Navigation and Telecommunications
Te 5608.00 13-Jun-15 08:00 A 01-May-18 17:00 100% 97.25%
Equipment 5608.00 13-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Devices (NVT-MRI-0001-1000)
(NVT-M 5608.00 13-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Detection (NVT-
(NVT-MRI-0001-1100) 5608.00 06-Jul-15 08:00 A 01-May-18 17:00 100% 95%
Material 3800.00 21-Dec-15 08:00 A 03-Nov-17 17:00 A 100% 100%
Cable (NVT-MR
(NVT-MRI-0001-1200) 3800.00 21-Dec-15 08:00 A 03-Nov-17 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 4736.00 21-Sep-15 08:00 A 02-May-18 17:00 100% 94.9%
Equipment 4736.00 21-Sep-15 08:00 A 02-May-18 17:00 100% 94.9%
Fire water hydra
hydrant/hose box&monitor (HSE-MRI-0001-7003) 4736.00 21-Sep-15 08:00 A 02-May-18 17:00 100% 94.9%
Extinguisher (HSE-MRI-0001-7004,7005)
(HS 4736.00 29-Oct-15 08:00 A 02-May-18 17:00 100% 94.9%
Personal protection/
protect wind socks/ signage (HSE-MRI-0001-7010,7011,7012) 4200.00 11-Apr-16 08:00 A 02-May-18 17:00 100% 94.9%
Steel Structure 2864.00 29-Jun-15 08:00 A 11-Jul-17 17:00 A 100% 100%
Material 2864.00 29-Jun-15 08:00 A 11-Jul-17 17:00 A 100% 100%
Blanket Order of Steel Structure 864.00 29-Jun-15 08:00 A 20-Nov-15 17:00 A 100% 100%
1st Steel Structure£¨RCK-3100£©
Structu 1512.00 07-Dec-15 08:00 A 15-Sep-16 17:00 A 100% 100%
2nd Steel Structu
Structure£¨STR£© 2048.00 23-Nov-15 08:00 A 11-Jul-17 17:00 A 100% 100%
3rd Steel Structure£¨RCK-1110/1200/1220£©
Structu 1824.00 07-Dec-15 08:00 A 16-Sep-16 17:00 A 100% 100%
4th Steel Structure£¨RCK-1100£©
Structu 960.00 07-Dec-15 08:00 A 15-Sep-16 17:00 A 100% 100%
Anchor bolt for MECM 1160.00 27-Jul-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Anchor bolt for Structure
S 1016.00 31-Jul-15 08:00 A 29-Feb-16 17:00 A 100% 100%
Piping 5912.00 15-May-15 08:00 A 07-Jun-18 17:00 100% 99.76%
Material 5912.00 15-May-15 08:00 A 07-Jun-18 17:00 100% 99.76%
Blanket Order of Piping/Fitting/Valves 1304.00 04-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
Misc. Piping EquEquipment 5816.00 22-Jun-15 08:00 A 02-May-18 17:00 100% 94.6%
Safety Valves (PIP-MRI-0001-0001,0002)
(P 4336.00 07-Jul-15 08:00 A 07-Jun-18 17:00 100% 95.55%
1st Piping Support
Suppo (PIP-MRI-0001-7001) 1184.00 20-Nov-15 08:00 A 22-Jun-16 17:00 A 100% 100%
Spring Hanger 3696.00 01-Feb-16 08:00 A 05-Jan-18 17:00 A 100% 100%
1st Valves (PIP-MRI-0001-4610,4611,4614,4615)
(PIP-M 1744.00 11-Jan-16 08:00 A 30-Nov-16 17:00 A 100% 100%
1st Piping & Tubes
Tub (PIP-MRI-0001-1220,1317,1318,1319,1510,1512) 1008.00 31-Dec-15 08:00 A 28-Oct-16 17:00 A 100% 100%
U/G Bulk Materia
Material (PIP-MRI-0001-0160,8110,8210,8310,8410) 1976.00 15-May-15 08:00 A 04-Dec-16 17:00 A 100% 100%
1st U/G piping (PIP-MRI-0001-0160,8110,8210,8310)
(P 1352.00 01-Sep-15 08:00 A 12-Oct-16 17:00 A 100% 100%
U/G Valves (PIP(PIP-MRI-0001-8410) 5000.00 13-Nov-15 08:00 A 01-May-18 17:00 100% 95%
2nd Piping/valves/fitting
Piping/valve 1000.00 15-Apr-16 08:00 A 30-Apr-18 17:00 100% 99.44%
2nd Piping Support
Supp (PIP-MRI-0001-7001) 2472.00 01-Sep-16 08:00 A 05-Jan-18 17:00 A 100% 100%
Electrical 3688.00 09-Dec-15 08:00 A 06-Jun-18 17:00 100% 99.97%
Material 3688.00 09-Dec-15 08:00 A 06-Jun-18 17:00 100% 99.97%
Earthing and Lighting
Lig Material (ELE-MRI-0001-0110,0210) 1604.80 06-Jan-16 08:00 A 02-Nov-16 17:00 A 100% 100%
Cable Tray (ELE
(ELE-MRI-0001-0300) 2152.00 01-Feb-16 08:00 A 14-Jul-17 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 63 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Cathodic Protection
Protect (ELE-MRI-0001-0700) 1768.00 10-Dec-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Elec. Heat Tracin
Tracing (ELE-MRI-0001-0600) 2072.00 25-Jan-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Lighting Fixtures (ELE-MRI-0001-0400,0410,0420,0430) 2200.00 07-Mar-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Conduit (ELE-MRI-0001-0100)
(ELE-M 1704.00 18-Jul-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Cable (ELE-MR
(ELE-MRI-0001-0200,0210) 2912.00 09-Dec-15 08:00 A 18-Feb-17 17:00 A 100% 100%
Other Material (E(ELE-MRI-0001-0120,0230,0240,0250) 2648.00 16-Jun-16 08:00 A 06-Jun-18 17:00 100% 99.2%
Explosion-proof materila/Explosion-proof control switch (ELE-MRI-0001-0500,0510) 3416.00 31-Dec-15 08:00 A 22-Nov-17 17:00 A 100% 100%
Instrumentation anand Control 5224.00 22-Aug-14 08:00 A 10-Jul-18 17:00 100% 98.08%
Material 5224.00 22-Aug-14 08:00 A 10-Jul-18 17:00 100% 98.08%
Desuperheater/ Deluge Valve (INC-MRI-0512/0602) 4072.00 21-Jul-15 08:00 A 25-Nov-17 17:00 A 100% 100%
Control Valves/o
Valves/on-off valves (MRI-0001-0501,0502,0503,0506) 5224.00 22-Aug-14 08:00 A 30-Apr-18 17:00 100% 96.82%
Orifice Plate/ Flow
Flo Element (MRI-0001-0101,0102,0103,0105,0106,0107,0801,0803) 3824.00 04-Jun-15 08:00 A 17-Oct-17 00:00 A 100% 100%
Level/Gauge (INC-MRI-0001-0201,0202,0204,0205,0301)
(IN 4152.00 17-Jun-15 08:00 A 03-Nov-17 17:00 A 100% 100%
Analysis/Transmitter (INC-MRI-0001-0302,0401,0402,0403,0404,0405)
Analysis/Transm 3904.00 17-Jun-15 08:00 A 28-Jun-18 17:00 100% 99.1%
Cable Tray (INC-MRI-0001-0902)
(INC 2384.00 28-Mar-16 08:00 A 25-Aug-17 17:00 A 100% 100%
Inst. Cable (INC-MRI-0001-0901)
(INC 2793.60 21-Dec-15 15:24 A 06-Oct-17 00:00 A 100% 100%
Junction Box (INC-MRI-0001-0903)
(IN 3496.00 01-Feb-16 08:00 A 05-Jan-18 17:00 A 100% 100%
Inst. Material (IN
(INC-MRI-0001-0904,0905,0906,0907) 2432.00 25-Mar-16 08:00 A 10-Jul-18 17:00 100% 99.1%
HCDU - Hydrogen Collection
C & Distribution 7488.00 03-Nov-14 08:00 A 10-Jul-18 17:00 100% 99.88%
1520 - HCDU - Hyd Hydrogen Collection & Distribution 7488.00 03-Nov-14 08:00 A 10-Jul-18 17:00 100% 99.88%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 6064.00 15-Apr-15 08:00 A 10-Apr-18 17:00 A 100% 100%
Equipment 6064.00 15-Apr-15 08:00 A 10-Apr-18 17:00 A 100% 100%
Carbom Steel D Drums 1520-V-001A/B/C/D/E(IQ01-2015) 6064.00 15-Apr-15 08:00 A 10-Apr-18 17:00 A 100% 100%
Crane for H2 Make-Up
Ma Compressors 1520-X-001(IQ01-1009) 5584.00 01-Jul-15 08:00 A 26-Feb-18 17:00 A 100% 100%
Rotating 5776.00 03-Nov-14 08:00 A 21-Jul-17 17:00 A 100% 100%
Equipment 5776.00 03-Nov-14 08:00 A 21-Jul-17 17:00 A 100% 100%
H2 MAKE-UP C Compressors 1520-K-001A/B/C/D/E(IQ01-1002) 5400.00 03-Nov-14 08:00 A 30-Jun-17 17:00 A 100% 100%
PUMPS 1520-P-
1520-P-101A/B(IQ01-1004) 4904.00 09-Apr-15 08:00 A 21-Jul-17 17:00 A 100% 100%
Navigation and Telecommunications
Te 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 97.25%
Equipment 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Telecommunication devices
Telecommunicat 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Fire detection 5696.00 10-Jul-15 08:00 A 01-May-18 17:00 100% 95%
Material 3800.00 21-Dec-15 08:00 A 24-Nov-17 17:00 A 100% 100%
Cable/Optic Fiber 3800.00 21-Dec-15 08:00 A 03-Nov-17 17:00 A 100% 100%
Galvanized pipe 3800.00 21-Dec-15 08:00 A 24-Nov-17 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 4728.00 04-Jan-16 08:00 A 02-May-18 17:00 100% 94.9%
Equipment 4728.00 04-Jan-16 08:00 A 02-May-18 17:00 100% 94.9%
Portable Extinguisher
Extingu 4728.00 04-Jan-16 08:00 A 02-May-18 17:00 100% 94.9%
Steel Structure 5032.00 16-Jan-15 08:00 A 11-Jul-17 17:00 A 100% 100%
Material 5032.00 16-Jan-15 08:00 A 11-Jul-17 17:00 A 100% 100%
Steel Structure 1336.00 01-Jul-15 08:00 A 20-Nov-15 17:00 A 100% 100%
1st Steel Structure£¨RCK£©
Structu 2664.00 07-Dec-15 08:00 A 05-May-17 17:00 A 100% 100%
2nd Steel Structu
Structure£¨STR/SHL£© 2928.00 01-Feb-16 08:00 A 11-Jul-17 17:00 A 100% 100%
Anchor bolt for MEC
M 2360.00 16-Jan-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Anchor bolt for Structure
S 1152.00 03-Aug-15 08:00 A 29-Feb-16 17:00 A 100% 100%
Piping 6304.00 15-May-15 08:00 A 10-Jul-18 17:00 100% 98.78%
Material 6304.00 15-May-15 08:00 A 10-Jul-18 17:00 100% 98.78%
Blanket Order of Piping/Fitting/Valve 1282.80 04-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
1st U/G piping 2072.00 01-Sep-15 08:00 A 11-Nov-16 17:00 A 100% 100%
U/G Bulk Material 1912.00 15-May-15 08:00 A 26-Aug-16 17:00 A 100% 100%
1st Piping/Fitting/Flange
Piping/Fitting 776.00 10-Jan-16 08:00 A 12-Aug-16 17:00 A 100% 100%
1st Piping Support
Suppo 1056.00 23-Nov-15 08:00 A 29-Jun-16 17:00 A 100% 100%
2nd Piping/valves/fitting
Piping/valve 1136.00 15-Apr-16 08:00 A 11-May-18 17:00 100% 99.44%
2nd Piping Supp
Support/Insulation 2432.00 01-Sep-16 08:00 A 05-Jan-18 17:00 A 100% 100%
U/G Valves 5000.00 04-Dec-15 08:00 A 22-May-18 17:00 100% 94.6%

Remaining Level of Effort Actual Work Critical Remaining ... Page 64 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

1st Piping Valves 4688.00 10-Jan-16 08:00 A 04-May-18 17:00 100% 94.06%
Spring Hanger 3568.00 11-Jan-16 08:00 A 05-Jan-18 17:00 A 100% 100%
Safety Valve 4328.00 07-Jul-15 08:00 A 08-Jun-18 17:00 100% 95.6%
Misc. Piping Equ
Equipment 6208.00 22-Jun-15 08:00 A 10-Jul-18 17:00 100% 94.6%
Electrical 3536.00 07-Dec-15 08:00 A 22-Nov-17 17:00 A 100% 100%
Material 3536.00 07-Dec-15 08:00 A 22-Nov-17 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch 3360.00 07-Jan-16 08:00 A 22-Nov-17 17:00 A 100% 100%
Earthing and lighting
ligh material 1600.00 06-Jan-16 08:00 A 02-Nov-16 17:00 A 100% 100%
Conduit and Accessories
Acc 1664.00 18-Jul-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Lighting Fixtures 1980.00 07-Mar-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Elec. Heat Tracing
Tracin 1240.00 25-Jan-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Cable 2928.00 07-Dec-15 08:00 A 18-Feb-17 17:00 A 100% 100%
Cable ladder/Cable
ladder/Ca Tray 2136.00 01-Feb-16 08:00 A 14-Jul-17 17:00 A 100% 100%
Cathodic Protection
Protect 576.00 01-Feb-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Instrumentation an and Control 6128.00 24-Apr-15 08:00 A 06-Jul-18 17:00 100% 99.07%
Material 6128.00 24-Apr-15 08:00 A 06-Jul-18 17:00 100% 99.07%
Analysis/Transmitter
Analysis/Transm 4096.00 14-Aug-15 08:00 A 28-Jun-18 17:00 100% 99.1%
Control Valves 6128.00 24-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Orifice Plate/Flow Element 3584.00 22-Jul-15 08:00 A 17-Oct-17 17:00 A 100% 100%
Level/Gauge 4088.00 17-Jun-15 08:00 A 03-Nov-17 17:00 A 100% 100%
Cable Tray 2552.00 21-Mar-16 08:00 A 25-Aug-17 17:00 A 100% 100%
Inst. Cable 3296.00 21-Dec-15 08:00 A 06-Oct-17 00:00 A 100% 100%
Junction Box 3128.00 01-Feb-16 08:00 A 05-Jan-18 17:00 A 100% 100%
Inst. Tube&Tube Fitting/ Inst. Pipe & Fitting/Valves/ Bulk Items 2904.00 21-Mar-16 08:00 A 06-Jul-18 17:00 100% 99.1%
FOS - Fuel Oil Syste
System 6480.00 18-Feb-15 08:00 A 10-Jul-18 17:00 100% 97.94%
4550 - FOS - Fuel O Oil System 6480.00 18-Feb-15 08:00 A 10-Jul-18 17:00 100% 97.94%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 6472.00 18-Feb-15 08:00 A 01-May-18 17:00 100% 99.42%
Equipment 6472.00 18-Feb-15 08:00 A 01-May-18 17:00 100% 99.42%
Tank (4550-T-001)
(4550-T-00 5808.00 22-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Carbom Steel D Drums (4550-V-001/002) 3712.00 15-Apr-15 08:00 A 14-Feb-17 17:00 A 100% 100%
Exchangers (4550-E-001)
(455 4048.00 18-Feb-15 08:00 A 13-Jan-17 17:00 A 100% 100%
Air Cooler (4550-E-002)
(4550 4360.00 11-Mar-15 08:00 A 04-Apr-17 17:00 A 100% 100%
Rotating 6272.00 30-Mar-15 08:00 A 30-Apr-18 17:00 100% 95%
Equipment 6272.00 30-Mar-15 08:00 A 30-Apr-18 17:00 100% 95%
Pumps 6272.00 30-Mar-15 08:00 A 30-Apr-18 17:00 100% 95%
Navigation and Telecommunications
Te 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 97.25%
Equipment 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Devices 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
FGS(Field Detection)
Detec 5688.00 13-Jul-15 08:00 A 01-May-18 17:00 100% 95%
Material 2744.00 08-Oct-15 08:00 A 08-Nov-16 17:00 A 100% 100%
Cable/OF/galvanized pipe
Cable/OF/galvan 2744.00 08-Oct-15 08:00 A 08-Nov-16 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 4864.00 21-Sep-15 08:00 A 30-Apr-18 17:00 100% 99.5%
Equipment 4864.00 21-Sep-15 08:00 A 30-Apr-18 17:00 100% 99.5%
Fire Hydrant/ Fire
Fir Extinguisher 4864.00 21-Sep-15 08:00 A 30-Apr-18 17:00 100% 99.5%
Steel Structure 3688.00 03-Jun-15 08:00 A 02-May-17 17:00 A 100% 100%
Material 3688.00 03-Jun-15 08:00 A 02-May-17 17:00 A 100% 100%
Blanket Order of Steel Structure 960.00 03-Jun-15 08:00 A 20-Nov-15 17:00 A 100% 100%
1st Steel Structure£¨RCK£©
Structu 2050.40 23-Nov-15 08:00 A 25-Nov-16 17:00 A 100% 100%
2nd Steel Structu
Structure£¨STR£© 2440.00 23-Nov-15 08:00 A 02-May-17 17:00 A 100% 100%
Anchor bolt for MEC
M 1232.00 07-Aug-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Anchor bolt for Structure
S 1112.00 29-Jul-15 08:00 A 18-Feb-16 17:00 A 100% 100%
Piping 6016.00 18-May-15 08:00 A 18-May-18 17:00 100% 99.48%
Material 6016.00 18-May-15 08:00 A 18-May-18 17:00 100% 99.48%
Blanket Order of Piping/Fitting/Valves 1344.00 04-Jun-15 08:00 A 31-Dec-15 17:00 A 100% 100%
1st U/G piping 1792.00 01-Sep-15 08:00 A 16-Dec-16 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 65 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

U/G Bulk Material 2688.00 18-May-15 08:00 A 31-Aug-16 17:00 A 100% 100%
1st Piping & Tubes
Tub 576.00 31-Dec-15 08:00 A 18-Aug-16 08:00 A 100% 100%
1st Piping Support
Suppo 2528.00 26-Oct-15 08:00 A 16-Dec-16 17:00 A 100% 100%
2nd Piping/valves/fitting
Piping/valve 1760.00 15-Apr-16 08:00 A 26-May-17 17:00 A 100% 100%
2nd Piping Supp
Support/Insulation 440.00 04-Aug-16 08:00 A 18-Aug-16 08:00 A 100% 100%
U/G Valves 3000.00 30-Nov-15 08:00 A 20-Oct-17 10:38 A 100% 100%
1st Valves 3240.00 24-Aug-15 08:00 A 09-Dec-16 17:00 A 100% 100%
Spring list 3392.00 28-Dec-15 08:00 A 05-Jan-18 17:00 A 100% 100%
Safety Valves 5720.00 07-Jul-15 08:00 A 01-May-18 17:00 100% 95%
Misc. Piping Equ
Equipment 5024.00 11-Nov-15 08:00 A 18-May-18 17:00 100% 94.6%
Electrical 3864.00 07-Dec-15 08:00 A 20-Jun-18 17:00 100% 99.98%
Material 3864.00 07-Dec-15 08:00 A 20-Jun-18 17:00 100% 99.98%
Elec. Heat Tracing
Tracin 1792.00 12-Jan-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Cable 2440.00 07-Dec-15 08:00 A 20-Oct-17 17:00 A 100% 100%
Conduit and Accessories
Acc 1752.00 18-Apr-16 08:00 A 17-Jan-17 17:00 A 100% 100%
Other Material 3144.00 18-Apr-16 08:00 A 20-Jun-18 17:00 100% 99.55%
Earthing and lighting
ligh material 1556.80 04-Jan-16 08:00 A 04-May-17 17:00 A 100% 100%
Lighting Fixtures 2592.00 25-Jan-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Cable Tray 2168.00 01-Feb-16 08:00 A 25-Jul-17 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch 3512.00 04-Jan-16 08:00 A 29-May-18 17:00 100% 99.9%
Cathodic Protection
Protect 1920.00 03-Mar-16 08:00 A 26-Aug-16 17:00 A 100% 100%
Instrumentation an and Control 5016.00 04-Jun-15 08:00 A 10-Jul-18 17:00 100% 98.16%
Material 5016.00 04-Jun-15 08:00 A 10-Jul-18 17:00 100% 98.16%
Control Valves 4928.00 19-Jun-15 08:00 A 30-May-18 17:00 100% 96.02%
Transmitter 3880.00 17-Aug-15 08:00 A 20-Jun-18 17:00 100% 99.8%
Flow Element - Restriction
R Orifice/Orifice Plate 3744.00 04-Jun-15 08:00 A 14-Jun-18 17:00 100% 99.1%
Level/Gauge 4176.00 17-Jun-15 08:00 A 30-Oct-17 17:00 A 100% 100%
Cable Tray 2208.00 21-Mar-16 08:00 A 25-Aug-17 17:00 A 100% 100%
Junction Box 3216.00 01-Feb-16 08:00 A 26-Jul-17 17:00 A 100% 100%
Inst. Cable 2680.00 21-Dec-15 08:00 A 06-Oct-17 00:00 A 100% 100%
Inst. Tube&Tube Fitting/ Inst. Pipe & Fitting/Valves/ Bulk Items 2520.00 21-Mar-16 08:00 A 10-Jul-18 17:00 100% 99.1%
ARDS - Atmospheric Residue Desulphurization 7384.00 20-Nov-14 08:00 A 10-Jul-18 17:00 100% 98.87%
1210 - Common ARDSAR - Common Atmospheric Residue Desulphurization 6888.00 16-Feb-15 08:00 A 10-Jul-18 17:00 100% 98.25%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 6408.00 06-Mar-15 08:00 A 01-May-18 17:00 100% 99.53%
Equipment 6408.00 06-Mar-15 08:00 A 01-May-18 17:00 100% 99.53%
Drum 1210-V-0
1210-V-001/002 (IQ01-2016) 3600.00 15-Apr-15 08:00 A 20-Jan-17 17:00 A 100% 100%
Crane 1210-X-001(IQ01-1009)
1210-X-0 5752.00 01-Jul-15 08:00 A 01-May-18 17:00 100% 95%
Exchanger 1210-E-001/002(IQ01-2018)
1210 6408.00 06-Mar-15 08:00 A 01-May-18 17:00 100% 95%
Hydrogen Recovery
Recov Package 1210-A-001(IQ01-2026) 5400.00 27-Apr-15 08:00 A 09-Nov-17 17:00 A 100% 100%
AOC SLOP OIL SKIMMING AND TRANSFER PACKAGE 4536.00 04-Feb-16 08:00 A 01-May-18 17:00 0% 0%
Rotating 4936.00 16-Feb-15 08:00 A 30-Apr-18 17:00 100% 97.5%
Equipment 4936.00 16-Feb-15 08:00 A 30-Apr-18 17:00 100% 97.5%
H2 Recovery Compressor
Co 1210-K-001A/B(IQ01-1003) 4072.00 16-Feb-15 08:00 A 30-Apr-18 17:00 100% 97.5%
Centrifugal Pumps
Pum 1210-P-101A/B¡¢1210-P-601A/B¡¢6300-P-103A/B (IQ01-1004) 4664.00 09-Apr-15 08:00 A 30-Apr-18 17:00 100% 98.33%
Navigation and Telecommunications
Te 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 97.25%
Equipment 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Telecommunication devices
Telecommunicat 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Fire detection 5688.00 13-Jul-15 08:00 A 01-May-18 17:00 100% 95%
Material 3824.00 21-Dec-15 08:00 A 22-Nov-17 17:00 A 100% 100%
Cable/OF/galvanized pipe
Cable/OF/galvan 3824.00 21-Dec-15 08:00 A 22-Nov-17 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 4328.00 29-Dec-15 08:00 A 30-Apr-18 17:00 100% 99.5%
Equipment 4328.00 29-Dec-15 08:00 A 30-Apr-18 17:00 100% 99.5%
Fire Hydrant/ Fire
Fir Extinguisher 4328.00 29-Dec-15 08:00 A 30-Apr-18 17:00 100% 99.5%
Steel Structure 3728.00 01-Jul-15 08:00 A 05-May-17 17:00 A 100% 100%
Material 3728.00 01-Jul-15 08:00 A 05-May-17 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 66 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Steel Structure 1416.00 01-Jul-15 08:00 A 20-Nov-15 17:00 A 100% 100%


1st Steel Structure£¨RCK£©
Structu 2784.00 07-Dec-15 08:00 A 04-May-17 17:00 A 100% 100%
2nd Steel Structu
Structure£¨STR/SHL£© 2928.00 23-Nov-15 08:00 A 05-May-17 17:00 A 100% 100%
Anchor bolt for MEC
M 1304.00 27-Jul-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Anchor bolt for Structure
S 1152.00 03-Aug-15 08:00 A 29-Feb-16 17:00 A 100% 100%
Piping 6304.00 15-May-15 08:00 A 10-Jul-18 17:00 100% 98.91%
Material 6304.00 15-May-15 08:00 A 10-Jul-18 17:00 100% 98.91%
Blanket Order of Piping/Fitting/Valves 1344.00 04-Jun-15 08:00 A 29-Jan-16 17:00 A 100% 100%
1st U/G piping 1568.00 01-Sep-15 08:00 A 14-Nov-16 17:00 A 100% 100%
U/G Bulk Material 1696.00 15-May-15 08:00 A 26-Aug-16 17:00 A 100% 100%
1st Piping & Tubes
Tub 760.00 10-Jan-16 08:00 A 12-Aug-16 17:00 A 100% 100%
1st Piping Support
Suppo 1176.00 20-Nov-15 08:00 A 21-Jun-16 17:00 A 100% 100%
2nd Piping/valves/fitting
Piping/valve 1104.00 29-Apr-16 08:00 A 11-Aug-17 17:00 A 100% 100%
2nd Piping Support
Supp 2320.00 01-Sep-16 08:00 A 30-Apr-18 17:00 100% 100%
U/G Valves 4928.00 30-Nov-15 08:00 A 03-May-18 17:00 100% 94.6%
1st Piping Valves 4880.00 11-Jan-16 08:00 A 11-Jun-18 17:00 100% 94.06%
Spring Hanger 1840.00 10-Jan-16 08:00 A 05-Jan-18 17:00 A 100% 100%
Safety Valve 4336.00 07-Jul-15 08:00 A 30-Apr-18 17:00 100% 95.6%
Misc. Piping Equ
Equipment 6208.00 22-Jun-15 08:00 A 10-Jul-18 17:00 100% 94.6%
Electrical 3584.00 06-Dec-15 08:00 A 27-Jun-18 17:00 100% 99.98%
Material 3584.00 06-Dec-15 08:00 A 27-Jun-18 17:00 100% 99.98%
Explosion-proof materila/Explosion-proof control switch 3360.00 07-Jan-16 08:00 A 22-Nov-17 17:00 A 100% 100%
Lighting Lamps 2200.00 07-Mar-16 08:00 A 27-Jun-18 17:00 100% 100%
Earthing and Lighting
Lig Material 1624.00 06-Jan-16 08:00 A 02-Nov-16 17:00 A 100% 100%
Conduit and Accessories
Acc 1600.00 18-Jul-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 2160.00 01-Feb-16 08:00 A 14-Jul-17 17:00 A 100% 100%
Elec. Heat Tracing
Tracin 240.00 25-Jan-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Cable 2904.00 06-Dec-15 08:00 A 18-Feb-17 17:00 A 100% 100%
Cathodic Protection
Protect 192.00 25-Jan-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Other Material(Conduit/Accessories/Steel/Termination
Material(C Kit/Calbe Joint/Cable Gland/Seal Material/) 2528.00 16-Jun-16 08:00 A 16-May-18 17:00 100% 99.2%
Instrumentation anand Control 5216.00 27-Apr-15 08:00 A 10-Jul-18 17:00 100% 97.13%
Material 5216.00 27-Apr-15 08:00 A 10-Jul-18 17:00 100% 97.13%
Analysis/Transmitter
Analysis/Transm 4096.00 14-Aug-15 08:00 A 28-Jun-18 17:00 100% 99.1%
Control Valves 5216.00 27-Apr-15 08:00 A 30-Apr-18 17:00 100% 95%
Flow Element 4192.00 04-Jun-15 08:00 A 28-Aug-17 17:00 A 100% 100%
Level/Gauge 3920.00 17-Jun-15 08:00 A 30-Oct-17 17:00 A 100% 100%
Cable Tray 2552.00 21-Mar-16 08:00 A 25-Aug-17 11:12 A 100% 100%
Inst. Cable 3272.00 21-Dec-15 08:00 A 06-Oct-17 00:00 A 100% 100%
Junction Box 3128.00 01-Feb-16 08:00 A 05-Jan-18 17:00 A 100% 100%
Inst. Material 2832.00 21-Mar-16 08:00 A 10-Jul-18 17:00 100% 99.1%
1211 - ARDS - Atmospheric
Atmo Residue Desulphurization 7224.00 20-Nov-14 08:00 A 10-Jul-18 17:00 100% 98.91%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 6984.00 20-Nov-14 08:00 A 04-May-18 17:00 100% 99%
Equipment 6984.00 20-Nov-14 08:00 A 04-May-18 17:00 100% 99%
Cr-Mo Drums 3992.00 12-Jan-15 08:00 A 30-Nov-16 08:00 A 100% 100%
High Pressure Equipment
E 3640.00 09-Feb-15 08:00 A 28-Oct-16 17:00 A 100% 100%
HP Centrifugal Separator
S 4104.00 12-Feb-15 08:00 A 24-Feb-17 17:00 A 100% 100%
Large Size Drums
Drum 6192.00 14-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Clading Drums 6088.00 17-Apr-15 08:00 A 30-Apr-18 17:00 100% 97.5%
Carbom Steel Drums
D 3872.00 07-Apr-15 08:00 A 04-May-18 17:00 100% 96.25%
Common Exchan
Exchangers 5352.00 11-May-15 08:00 A 30-Apr-18 17:00 100% 95.83%
Special Material Exchangers 5680.00 09-Mar-15 08:00 A 21-Dec-17 17:00 A 100% 100%
HP Exchangers 6832.00 17-Dec-14 08:00 A 01-May-18 17:00 100% 95%
DSS Air Coolers 4048.00 26-Jan-15 08:00 A 23-Nov-16 17:00 A 100% 100%
Air Coolers 5792.00 29-Jan-15 08:00 A 07-Dec-17 17:00 A 100% 100%
ARDS Reactors(with
Reactors( internals) 4744.00 20-Nov-14 08:00 A 03-Aug-17 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 67 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Columns 6272.00 31-Mar-15 08:00 A 01-May-18 17:00 100% 95%


Internals 3952.00 17-Feb-15 08:00 A 31-Dec-16 17:00 A 100% 100%
Fresh Feed Filter 6128.00 24-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Furnace (including
(includin Waste heat Boiler Package)£¨1211-F-001/101/201£© 4192.00 11-Mar-15 08:00 A 30-Apr-18 17:00 100% 98.5%
Rotating 6696.00 12-Jan-15 08:00 A 08-Jun-18 17:00 100% 97.92%
Equipment 6696.00 12-Jan-15 08:00 A 08-Jun-18 17:00 100% 97.92%
Frac Off Gas Compressor
Co (K-001A/B) 3952.00 27-Apr-15 08:00 A 30-Apr-18 17:00 100% 97.5%
Injection Water Pump
P 3480.00 17-Jun-15 08:00 A 07-Mar-17 17:00 A 100% 100%
Recycle Gas Compressor
Co 4296.00 12-Jan-15 08:00 A 23-Dec-16 17:00 A 100% 100%
1st level pump 6480.00 17-Feb-15 08:00 A 01-May-18 17:00 100% 95%
2nd level pump/FRAC
pump/F BOTTOMS PUMPS 5072.00 08-Apr-15 08:00 A 08-Jun-18 17:00 100% 96.75%
Compressor Ov Overhead Travelling Crane 3224.00 11-Aug-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Navigation and Telecommunications
Te 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 97.25%
Equipment 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Detection 5688.00 13-Jul-15 08:00 A 01-May-18 17:00 100% 95%
Devices 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Material 2232.00 01-Jan-16 08:00 A 22-Nov-17 17:00 A 100% 100%
Cable/OF/galvanized pipe
Cable/OF/galvan 2232.00 01-Jan-16 08:00 A 22-Nov-17 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 5296.00 21-Sep-15 08:00 A 02-May-18 17:00 100% 94.9%
Equipment 5296.00 21-Sep-15 08:00 A 02-May-18 17:00 100% 94.9%
Fire Hydrant/ Fire
Fir Extinguisher 5296.00 21-Sep-15 08:00 A 02-May-18 17:00 100% 94.9%
Steel Structure 3376.00 06-Jul-15 08:00 A 11-Jul-17 17:00 A 100% 100%
Material 3376.00 06-Jul-15 08:00 A 11-Jul-17 17:00 A 100% 100%
Blanket Order of Steel Structure 848.00 06-Jul-15 08:00 A 20-Nov-15 17:00 A 100% 100%
1st Steel Structure(RCK)
Structu 1392.00 26-Oct-15 08:00 A 18-Nov-16 17:00 A 100% 100%
2nd Steel Structure(STR/RCK)
Structu 1600.00 01-Jan-16 08:00 A 04-May-17 08:24 A 100% 100%
3nd Steel Structure(SHL)
Structu 1568.00 25-May-16 08:00 A 11-Jul-17 17:00 A 100% 100%
Anchor bolt for MEC
M 1544.00 03-Aug-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Anchor bolt for Structure
S 1488.00 03-Aug-15 08:00 A 31-Mar-16 17:00 A 100% 100%
Piping 6128.00 08-Jun-15 08:00 A 12-Jun-18 17:00 100% 99.8%
Material 6128.00 08-Jun-15 08:00 A 12-Jun-18 17:00 100% 99.8%
Blanket Order of Piping/Fitting/Valves 1320.00 08-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Safety Valves 4160.00 01-Jul-15 08:00 A 25-May-18 17:00 100% 95.6%
Misc. Piping Equ
Equipment 5984.00 02-Jul-15 08:00 A 12-Jun-18 17:00 100% 94.6%
Spring List 3904.00 20-Jul-15 08:00 A 05-Jan-18 17:00 A 100% 100%
1st Piping Support
Suppo 1944.00 09-Nov-15 08:00 A 05-Aug-16 17:00 A 100% 100%
1st Valves 2920.00 31-Dec-15 08:00 A 30-Apr-18 17:00 100% 99.47%
1st U/G piping 1808.00 25-Aug-15 08:00 A 11-May-16 17:00 A 100% 100%
U/G Bulk Material 1972.00 24-Aug-15 08:00 A 13-Sep-16 17:00 A 100% 100%
1st Piping & Tubes
Tub 744.00 08-Jan-16 08:00 A 12-Oct-16 17:00 A 100% 100%
U/G Valves 1856.00 30-Nov-15 08:00 A 18-May-18 17:00 100% 97.5%
2nd Piping/valves/fitting
Piping/valve 1288.00 15-Apr-16 08:00 A 01-May-18 17:00 100% 99.87%
2nd Piping Supp
Support/Insulation 592.00 26-Feb-16 08:00 A 20-Sep-16 17:00 A 100% 100%
Electrical 3408.00 02-Dec-15 08:00 A 01-Jun-18 17:00 100% 100%
Material 3408.00 02-Dec-15 08:00 A 01-Jun-18 17:00 100% 100%
Cable 2280.00 09-Dec-15 08:00 A 18-Feb-17 17:00 A 100% 100%
Other Material(Steel/Termination
Material(S Kit/Calbe Joint/Cable Gland/Seal Material) 2568.00 10-May-16 08:00 A 01-Jun-18 17:00 100% 99.45%
Cable Tray 2176.00 25-Jan-16 08:00 A 26-Jul-17 17:00 A 100% 100%
Earthing and Lighting
Lig Material 2272.00 11-Jan-16 08:00 A 04-Aug-16 17:00 A 100% 100%
Lighting Fixtures 2232.00 27-Jan-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Conduit 1256.00 18-Jul-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch/Socket Outlets/Panel 2224.00 12-May-16 08:00 A 21-Nov-17 17:00 A 100% 100%
Cathodic Protection
Protect 2512.00 15-Jan-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Elec. Heat Tracing
Tracin 1928.00 02-Dec-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Instrumentation anand Control 5552.00 23-Apr-15 08:00 A 10-Jul-18 17:00 100% 98.12%

Remaining Level of Effort Actual Work Critical Remaining ... Page 68 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Material 5552.00 23-Apr-15 08:00 A 10-Jul-18 17:00 100% 98.12%


Control /On Off valves (INC-IQ01-0001-6018.6019,6020,6021,6022,6024,6025,6026,6027,6028,6029) 5552.00 23-Apr-15 08:00 A 30-Apr-18 17:00 100% 96.82%
Flow Element (INC-IQ01-6001.6004,6006,6015,6016,6018)
(IN 4152.00 03-Jun-15 08:00 A 17-Oct-17 00:00 A 100% 100%
Analysis/Transmitter (INC-MRI-0001-0302,0303,0401,0402,0403,0404,0405)
Analysis/Transm 4056.00 11-Aug-15 08:00 A 28-Jun-18 17:00 100% 99.1%
Level/Gauge (INC-MRI-0001-0201,0202,0203,0204,0205,0301)
(IN 3992.00 15-Jul-15 08:00 A 31-Oct-17 17:00 A 100% 100%
Cable Tray (INC-MRI-0001-0902)
(INC 1744.00 01-Apr-16 08:00 A 13-Jan-17 17:00 A 100% 100%
Inst. Cable (INC-MRI-0001-0901)
(INC 3144.00 23-Dec-15 08:00 A 06-Oct-17 00:00 A 100% 100%
Junction Box (INC-MRI-0001-0903)
(IN 3016.00 29-Jan-16 08:00 A 05-Jan-18 17:00 A 100% 100%
Inst. Material (IN
(INC-MRI-0001-0904,0905,0906,0907) 2808.00 01-Feb-16 08:00 A 10-Jul-18 17:00 100% 99.1%
1212 - ARDS - Atmospheric
Atm Residue Desulphurization 6992.00 20-Nov-14 08:00 A 10-Jul-18 17:00 100% 98.88%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 6984.00 20-Nov-14 08:00 A 24-May-18 17:00 100% 98.91%
Equipment 6984.00 20-Nov-14 08:00 A 24-May-18 17:00 100% 98.91%
Cr-Mo Drums 3992.00 12-Jan-15 08:00 A 30-Nov-16 17:00 A 100% 100%
Clading Drums 6088.00 17-Apr-15 08:00 A 30-Apr-18 17:00 100% 96.75%
High Pressure Equipment
E 3640.00 09-Feb-15 08:00 A 27-Oct-16 17:00 A 100% 100%
HP Centrifugal Separator
S 4104.00 12-Feb-15 08:00 A 24-Feb-17 17:00 A 100% 100%
Large Size Drums
Drum 6192.00 14-Apr-15 08:00 A 01-May-18 17:00 100% 95%
HP Exchangers 6832.00 17-Dec-14 08:00 A 01-May-18 17:00 100% 95%
Carbom Steel Drums
D 3840.00 07-Apr-15 08:00 A 24-May-18 17:00 100% 96.25%
Special Material Exchangers 5600.00 09-Mar-15 08:00 A 07-Dec-17 17:00 A 100% 100%
Common Exchan
Exchangers 5352.00 11-May-15 08:00 A 30-Apr-18 17:00 100% 95.83%
DSS Air Coolers 4048.00 26-Jan-15 08:00 A 23-Nov-16 17:00 A 100% 100%
Air Coolers 5792.00 29-Jan-15 08:00 A 07-Dec-17 17:00 A 100% 100%
ARDS Reactors(with
Reactors( internals) 4744.00 20-Nov-14 08:00 A 14-Jul-17 17:00 A 100% 100%
Columns 6272.00 31-Mar-15 08:00 A 01-May-18 17:00 100% 95%
Internals 4024.00 17-Feb-15 08:00 A 31-Dec-16 17:00 A 100% 100%
Fresh Feed Filter 6128.00 24-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Furnace (including
(includin Waste heat Boiler Package)£¨1211-F-001/101/201£© 4264.00 11-Mar-15 08:00 A 30-Apr-18 17:00 100% 97.5%
Rotating 6696.00 12-Jan-15 08:00 A 08-Jun-18 17:00 100% 97.92%
Equipment 6696.00 12-Jan-15 08:00 A 08-Jun-18 17:00 100% 97.92%
Frac Off Gas Compressor
Co (K-001A/B) 3952.00 27-Apr-15 08:00 A 30-Apr-18 17:00 100% 97.5%
Injection Water Pump
P 3480.00 17-Jun-15 08:00 A 07-Mar-17 17:00 A 100% 100%
Recycle Gas Compressor
Co 4312.00 12-Jan-15 08:00 A 23-Dec-16 17:00 A 100% 100%
1st level pump 6480.00 17-Feb-15 08:00 A 01-May-18 17:00 100% 95%
2nd level pump/FRAC
pump/F BOTTOMS PUMPS 5064.00 08-Apr-15 08:00 A 08-Jun-18 17:00 100% 96.75%
Compressor Ov Overhead Travelling Crane 3224.00 11-Aug-15 08:00 A 30-Dec-16 17:00 A 100% 100%
Navigation and Telecommunications
Te 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 97.25%
Equipment 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Detection 5688.00 13-Jul-15 08:00 A 01-May-18 17:00 100% 95%
Devices 5848.00 15-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Material 2232.00 01-Jan-16 08:00 A 22-Nov-17 17:00 A 100% 100%
Cable/OF/galvanized pipe
Cable/OF/galvan 2232.00 01-Jan-16 08:00 A 22-Nov-17 17:00 A 100% 100%
Health, Safety, Env
Environmental and Security 5280.00 21-Sep-15 08:00 A 30-Apr-18 17:00 100% 94.9%
Equipment 5280.00 21-Sep-15 08:00 A 30-Apr-18 17:00 100% 94.9%
Fire Hydrant/ Fire
Fir Extinguisher 5280.00 21-Sep-15 08:00 A 30-Apr-18 17:00 100% 94.9%
Steel Structure 2992.00 06-Jul-15 08:00 A 11-Jul-17 17:00 A 100% 100%
Material 2992.00 06-Jul-15 08:00 A 11-Jul-17 17:00 A 100% 100%
Blanket Order of Steel Structure 848.00 06-Jul-15 08:00 A 20-Nov-15 17:00 A 100% 100%
1st Steel Structure(RCK)
Structu 1672.00 26-Oct-15 08:00 A 18-Nov-16 08:10 A 100% 100%
2nd Steel Structure(STR/RCK)
Structu 1584.00 01-Jan-16 08:00 A 20-Jan-17 08:24 A 100% 100%
3nd Steel Structure(SHL)
Structu 1184.00 25-May-16 08:00 A 11-Jul-17 17:00 A 100% 100%
Anchor bolt for MEC
M 1560.00 03-Aug-15 08:00 A 18-Mar-16 17:00 A 100% 100%
Anchor bolt for Structure
S 1416.00 03-Aug-15 08:00 A 31-Mar-16 17:00 A 100% 100%
Piping 5896.00 08-Jun-15 08:00 A 08-Jun-18 17:00 100% 99.83%
Material 5896.00 08-Jun-15 08:00 A 08-Jun-18 17:00 100% 99.83%

Remaining Level of Effort Actual Work Critical Remaining ... Page 69 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Blanket Order of Piping/Fitting/Valves 1320.00 08-Jun-15 08:00 A 28-Jan-16 17:00 A 100% 100%
Safety Valves 4208.00 01-Jul-15 08:00 A 24-May-18 17:00 100% 95.6%
Misc. Piping Equ
Equipment 5752.00 02-Jul-15 08:00 A 18-May-18 17:00 100% 94.6%
Spring List 3904.00 01-Jul-15 08:00 A 05-Jan-18 17:00 A 100% 100%
1st Piping Support
Suppo 2096.00 09-Nov-15 08:00 A 05-Aug-16 17:00 A 100% 100%
1st Valves 2920.00 31-Dec-15 08:00 A 08-Jun-18 17:00 100% 99.65%
1st U/G piping 1808.00 24-Aug-15 08:00 A 11-May-16 17:00 A 100% 100%
U/G Bulk Material 1976.00 24-Aug-15 08:00 A 13-Sep-16 17:00 A 100% 100%
1st Piping & Tubes
Tub 784.00 11-Jan-16 08:00 A 12-Oct-16 17:00 A 100% 100%
U/G Valves 2000.00 30-Nov-15 08:00 A 07-Jun-18 17:00 100% 97.1%
2nd Piping/valves/fitting
Piping/valve 1136.00 15-Apr-16 08:00 A 03-May-18 17:00 100% 99.88%
2nd Piping Supp
Support/Insulation 752.00 29-Feb-16 08:00 A 20-Sep-16 17:00 A 100% 100%
Electrical 3376.00 02-Dec-15 08:00 A 06-Jul-18 17:00 100% 99.98%
Material 3376.00 02-Dec-15 08:00 A 06-Jul-18 17:00 100% 99.98%
Cable 2280.00 07-Dec-15 08:00 A 18-Feb-17 17:00 A 100% 100%
Other Material(Steel/Termination
Material(S Kit/Calbe Joint/Cable Gland/Seal Material) 2176.00 01-Aug-16 08:00 A 06-Jul-18 17:00 100% 99.45%
Cable Tray 2176.00 01-Feb-16 08:00 A 14-Jul-17 17:00 A 100% 100%
Earthing and Lighting
Lig Material 2272.00 11-Jan-16 08:00 A 05-Aug-16 17:00 A 100% 100%
Lighting Fixtures 2232.00 26-Jan-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Conduit 1184.00 01-Aug-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Explosion-proof materila/Explosion-proof control switch/Socket Outlets/Panel 2232.00 12-May-16 08:00 A 07-Jun-18 17:00 100% 99.9%
Cathodic Protection
Protect 2512.00 15-Jan-16 08:00 A 19-Feb-16 17:00 A 100% 100%
Elec. Heat Tracing
Tracin 1928.00 02-Dec-15 08:00 A 19-Feb-16 17:00 A 100% 100%
Instrumentation anand Control 5560.00 23-Apr-15 08:00 A 10-Jul-18 17:00 100% 98.12%
Material 5560.00 23-Apr-15 08:00 A 10-Jul-18 17:00 100% 98.12%
Control /On Off valves (INC-IQ01-0001-6018.6019,6020,6021,6022,6024,6025,6026,6027,6028,6029) 5560.00 23-Apr-15 08:00 A 30-Apr-18 17:00 100% 96.82%
Flow Element (INC-IQ01-6001.6004,6006,6015,6016,6018)
(IN 4032.00 03-Jun-15 08:00 A 17-Oct-17 00:00 A 100% 100%
Analysis/Transmitter (INC-MRI-0001-0302,0303,0401,0402,0403,0404,0405)
Analysis/Transm 4056.00 11-Aug-15 08:00 A 28-Jun-18 17:00 100% 99.1%
Level/Gauge (INC-MRI-0001-0201,0202,0203,0204,0205,0301)
(IN 3992.00 15-Jul-15 08:00 A 31-Oct-17 17:00 A 100% 100%
Cable Tray (INC-MRI-0001-0902)
(INC 1864.00 01-Apr-16 08:00 A 13-Jan-17 17:00 A 100% 100%
Inst. Cable (INC-MRI-0001-0901)
(INC 3288.00 23-Dec-15 08:00 A 06-Oct-17 00:00 A 100% 100%
Junction Box (INC-MRI-0001-0903)
(IN 3088.00 29-Jan-16 08:00 A 05-Jan-18 17:00 A 100% 100%
Inst. Material (IN
(INC-MRI-0001-0904,0905,0906,0907) 2768.00 01-Mar-16 08:00 A 10-Jul-18 17:00 100% 99.1%
Electrical Substation 6152.00 22-Apr-15 08:00 A 02-May-18 17:00 100% 95.58%
6850-SUB-111 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95.18%
Health, Safety, Env
Environmental and Security 4904.00 01-Dec-15 08:00 A 01-May-18 17:00 100% 94.9%
Equipment 4904.00 01-Dec-15 08:00 A 01-May-18 17:00 100% 94.9%
Fire Hydrant/ Fire
Fir Extinguisher 4904.00 01-Dec-15 08:00 A 01-May-18 17:00 100% 94.9%
Electrical 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95.2%
Equipment 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95.13%
Transformer 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Switchgear 6088.00 04-May-15 08:00 A 01-May-18 17:00 100% 95%
UPS System & B Batteries 5008.00 26-Jun-15 08:00 A 13-Dec-17 17:00 A 100% 100%
Bus Duct 5816.00 19-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Capacitor 5136.00 08-Oct-15 08:00 A 01-May-18 17:00 100% 95%
ENMCS/Panels 4360.00 10-Mar-16 08:00 A 01-May-18 17:00 100% 95%
Material 4832.00 15-Jun-15 08:00 A 30-Apr-18 17:00 100% 99.98%
Cable 3952.00 15-Jun-15 08:00 A 08-Nov-17 17:00 A 100% 100%
Cable Ladder AndAn Cable Tray 3232.00 01-Feb-16 08:00 A 14-Jul-17 17:00 A 100% 100%
Other Material 3352.00 09-Mar-16 08:00 A 30-Apr-18 17:00 100% 99.9%
Heating, Ventilation & Air Conditioning (HVAC) 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
Equipment 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
Ventialation Equipment/Air
Equi Conditioner/Air Duct 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
6850-SUB-121 6152.00 22-Apr-15 08:00 A 02-May-18 17:00 100% 95.2%
Health, Safety, Env
Environmental and Security 4912.00 01-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%

Remaining Level of Effort Actual Work Critical Remaining ... Page 70 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Equipment 4912.00 01-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%


Fire Hydrant/ Fire
Fir Extinguisher 4912.00 01-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Electrical 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95.24%
Equipment 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95.17%
Transformer 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Switchgear 6088.00 04-May-15 08:00 A 01-May-18 17:00 100% 95%
UPS System & B Batteries 5008.00 26-Jun-15 08:00 A 13-Dec-17 17:00 A 100% 100%
Bus Duct 5816.00 19-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Capacitor 5136.00 08-Oct-15 08:00 A 01-May-18 17:00 100% 95%
ENMCS/Panels 4360.00 10-Mar-16 08:00 A 01-May-18 17:00 100% 95%
Material 4920.00 15-Jun-15 08:00 A 30-Apr-18 17:00 100% 99.98%
Cable 3952.00 15-Jun-15 08:00 A 07-Nov-17 17:00 A 100% 100%
Cable Ladder And
An Cable Tray 2952.00 01-Feb-16 08:00 A 14-Jul-17 17:00 A 100% 100%
Other Material 3440.00 09-Mar-16 08:00 A 30-Apr-18 17:00 100% 99.9%
Heating, Ventilation & Air Conditioning (HVAC) 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
Equipment 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
Ventialation Equipment/Air
Equi Conditioner/Air Duct 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
6850-SUB-122 6152.00 22-Apr-15 08:00 A 02-May-18 17:00 100% 95.66%
Health, Safety, Env
Environmental and Security 4912.00 01-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Equipment 4912.00 01-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Fire Hydrant/ Fire
Fir Extinguisher 4912.00 01-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Electrical 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95.76%
Equipment 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95.71%
Transformer 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Switchgear 6080.00 05-May-15 08:00 A 01-May-18 17:00 100% 95%
UPS System & B Batteries 5000.00 29-Jun-15 08:00 A 13-Dec-17 17:00 A 100% 100%
Bus Duct 5816.00 01-Jul-15 08:00 A 01-May-18 17:00 100% 95%
Starter 2064.00 29-Oct-15 08:00 A 26-Oct-16 17:00 A 100% 100%
Capacitor 5128.00 08-Oct-15 08:00 A 01-May-18 17:00 100% 95%
ENMCS/Panels 4360.00 10-Mar-16 08:00 A 01-May-18 17:00 100% 95%
Material 5104.00 15-Jun-15 08:00 A 30-Apr-18 17:00 100% 99.98%
Cable 3920.00 15-Jun-15 08:00 A 08-Nov-17 17:00 A 100% 100%
Cable Ladder And
An Cable Tray 2952.00 01-Feb-16 08:00 A 14-Jul-17 17:00 A 100% 100%
Other Material 3624.00 09-Mar-16 08:00 A 30-Apr-18 17:00 100% 99.9%
Heating, Ventilation & Air Conditioning (HVAC) 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
Equipment 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
Ventialation Equipment/Air
Equi Conditioner/Air Duct 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
6850-SUB-152 6152.00 22-Apr-15 08:00 A 02-May-18 17:00 100% 96.36%
Health, Safety, Env
Environmental and Security 4800.00 01-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Equipment 4800.00 01-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Fire Hydrant/ Fire
Fir Extinguisher 4800.00 01-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Electrical 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 96.67%
Equipment 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 96.64%
Transformer 6144.00 22-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Switchgear 6088.00 04-May-15 08:00 A 01-May-18 17:00 100% 95%
Starter 2048.00 28-Oct-15 08:00 A 31-Oct-16 17:00 A 100% 100%
UPS System & B Batteries 5008.00 26-Jun-15 08:00 A 13-Dec-17 17:00 A 100% 100%
Bus Duct 5816.00 19-Jun-15 08:00 A 01-May-18 17:00 100% 95%
Capacitor 5136.00 08-Oct-15 08:00 A 01-May-18 17:00 100% 95%
ENMCS/Panels 4360.00 10-Mar-16 08:00 A 01-May-18 17:00 100% 95%
Material 5032.00 15-Jun-15 08:00 A 30-Apr-18 17:00 100% 99.97%
Cable 4000.00 15-Jun-15 08:00 A 09-Nov-17 17:00 A 100% 100%
Cable Ladder And
An Cable Tray 2952.00 01-Feb-16 08:00 A 14-Jul-17 17:00 A 100% 100%
Other Material 3552.00 09-Mar-16 08:00 A 30-Apr-18 17:00 100% 99.8%
Heating, Ventilation & Air Conditioning (HVAC) 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%

Remaining Level of Effort Actual Work Critical Remaining ... Page 71 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Equipment 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%


Ventialation Equipment/Air
Equi Conditioner/Air Duct 4888.00 03-Dec-15 08:00 A 01-May-18 17:00 100% 95%
Field Auxiliary Rooms 6416.00 06-Mar-15 08:00 A 03-Aug-18 17:00 100% 95.81%
6750-FAR-111 6416.00 06-Mar-15 08:00 A 22-Jun-18 17:00 100% 95.81%
Health, Safety, Env
Environmental and Security 4880.00 07-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Equipment 4880.00 07-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Fire Hydrant/ Fire
Fir Extinguisher 4880.00 07-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Electrical 3760.00 20-Dec-15 08:00 A 30-Apr-18 17:00 100% 100%
Material 3760.00 20-Dec-15 08:00 A 30-Apr-18 17:00 100% 100%
Cable Ladder And
An Cable Tray 2944.00 01-Feb-16 08:00 A 20-Oct-17 17:00 A 100% 100%
Cable 2520.00 20-Dec-15 08:00 A 20-Oct-17 17:00 A 100% 100%
Panel/UPS 2784.00 07-Mar-16 08:00 A 20-Oct-17 08:00 A 100% 100%
Elec. Bulk Material
Mater 3200.00 15-Apr-16 08:00 A 30-Apr-18 17:00 100% 99.8%
Instrumentation an
and Control 6408.00 06-Mar-15 08:00 A 22-Jun-18 17:00 100% 95.2%
Equipment 6408.00 06-Mar-15 08:00 A 01-May-18 17:00 100% 95%
Main Automation Contractor 6408.00 06-Mar-15 08:00 A 01-May-18 17:00 100% 95%
Material 2696.00 21-Mar-16 08:00 A 22-Jun-18 17:00 100% 99.1%
Instrument Bulk Material 2696.00 21-Mar-16 08:00 A 22-Jun-18 17:00 100% 99.1%
Heating, Ventilation & Air Conditioning (HVAC) 5568.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Equipment 5568.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Ventialation Equipment/Air
Equi Conditioner/Air Duct 5568.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
6750-FAR-121 6144.00 23-Apr-15 08:00 A 06-Jul-18 17:00 100% 95.81%
Health, Safety, Env
Environmental and Security 4896.00 03-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Equipment 4896.00 03-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Fire Hydrant/ Fire
Fir Extinguisher 4896.00 03-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Electrical 3512.00 21-Dec-15 08:00 A 18-May-18 17:00 100% 99.99%
Material 3512.00 21-Dec-15 08:00 A 18-May-18 17:00 100% 99.99%
Cable Ladder And
An Cable Tray 2904.00 01-Feb-16 08:00 A 20-Oct-17 17:00 A 100% 100%
Cable 2464.00 21-Dec-15 08:00 A 20-Oct-17 17:00 A 100% 100%
Panel/UPS 2784.00 07-Mar-16 08:00 A 20-Oct-17 17:00 A 100% 100%
Elec. Bulk Material
Mater 2880.00 15-Apr-16 08:00 A 18-May-18 17:00 100% 99.1%
Instrumentation an
and Control 6136.00 23-Apr-15 08:00 A 06-Jul-18 17:00 100% 95.2%
Equipment 6136.00 23-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Main Automation Contractor 6136.00 23-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Machine Monitoring
Monitor System 5952.00 27-May-15 08:00 A 01-May-18 17:00 100% 95%
Material 2840.00 25-Mar-16 08:00 A 06-Jul-18 17:00 100% 99.1%
Instrument Bulk Material 2840.00 25-Mar-16 08:00 A 06-Jul-18 17:00 100% 99.1%
Heating, Ventilation & Air Conditioning (HVAC) 5568.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Equipment 5568.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Ventialation Equipment/Air
Equi Conditioner/Air Duct 5568.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
6750-FAR-122 6144.00 23-Apr-15 08:00 A 03-Aug-18 17:00 100% 95.8%
Health, Safety, Env
Environmental and Security 4888.00 04-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Equipment 4888.00 04-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Fire Hydrant/ Fire
Fir Extinguisher 4888.00 04-Dec-15 08:00 A 02-May-18 17:00 100% 94.9%
Electrical 3504.00 21-Dec-15 08:00 A 11-May-18 17:00 100% 99.99%
Material 3504.00 21-Dec-15 08:00 A 11-May-18 17:00 100% 99.99%
Cable Ladder And
An Cable Tray 2904.00 01-Feb-16 08:00 A 20-Oct-17 17:00 A 100% 100%
Cable 2464.00 21-Dec-15 08:00 A 20-Oct-17 17:00 A 100% 100%
Panel 2784.00 07-Mar-16 08:00 A 20-Oct-17 17:00 A 100% 100%
Elec. Bulk Material
Mater 2872.00 15-Apr-16 08:00 A 11-May-18 17:00 100% 99.1%
Instrumentation an
and Control 6136.00 23-Apr-15 08:00 A 03-Aug-18 17:00 100% 95.2%
Equipment 6136.00 23-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Main Automation Contractor 6136.00 23-Apr-15 08:00 A 01-May-18 17:00 100% 95%
Machine Monitoring
Monitor System 5952.00 27-May-15 08:00 A 01-May-18 17:00 100% 95%
Material 3088.00 25-Mar-16 08:00 A 03-Aug-18 17:00 100% 99.1%

Remaining Level of Effort Actual Work Critical Remaining ... Page 72 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Instrument Bulk Material 3088.00 25-Mar-16 08:00 A 03-Aug-18 17:00 100% 99.1%
Heating, Ventilation & Air Conditioning (HVAC) 5240.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Equipment 5240.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Ventialation Equipment/Air
Equi Conditioner/Air Duct 5240.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Operating Shelter Building
Bu 5568.00 03-Aug-15 08:00 A 20-Jul-18 17:00 100% 97.35%
6760-OSB-101 5568.00 03-Aug-15 08:00 A 20-Jul-18 17:00 100% 97.35%
Electrical 3920.00 21-Dec-15 08:00 A 03-May-18 17:00 100% 99.77%
Material 3920.00 21-Dec-15 08:00 A 03-May-18 17:00 100% 99.77%
Panel 2784.00 07-Mar-16 08:00 A 20-Oct-17 17:00 A 100% 100%
Cable Ladder And
An Cable Tray 2712.00 01-Feb-16 08:00 A 20-Oct-17 17:00 A 100% 100%
Cable 2464.00 21-Dec-15 08:00 A 20-Oct-17 17:00 A 100% 100%
Elec. Bulk Material
Mater 3304.00 13-Apr-16 08:00 A 03-May-18 17:00 100% 99.07%
Instrumentation an
and Control 2472.00 21-Mar-16 08:00 A 20-Jul-18 17:00 100% 99.1%
Material 2472.00 21-Mar-16 08:00 A 20-Jul-18 17:00 100% 99.1%
Instrument Bulk Material 2472.00 21-Mar-16 08:00 A 20-Jul-18 17:00 100% 99.1%
Heating, Ventilation & Air Conditioning (HVAC) 5568.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Equipment 5568.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Ventialation Equipment/Air
Equi Conditioner/Air Duct 5568.00 03-Aug-15 08:00 A 01-May-18 17:00 100% 95%
Construction 8128.00 11-Nov-14 08:00 A 03-Sep-18 17:00 99.97% 97.09%
General 4984.00 11-Nov-14 08:00 A 03-Mar-17 17:00 A 100% 100%
General 4984.00 11-Nov-14 08:00 A 03-Mar-17 17:00 A 100% 100%
General 4984.00 11-Nov-14 08:00 A 03-Mar-17 17:00 A 100% 100%
C0001GEN7028 General(Manhours) 3008.00 11-Nov-14 08:00 A 10-Aug-16 17:00 A 100% 100%
General 4984.00 11-Nov-14 08:00 A 03-Mar-17 17:00 A 100% 100%
Geotech Survey 1288.00 20-Apr-15 08:00 A 18-Sep-15 00:00 A 100% 100%
Construction Subcontracting
Sub 6160.00 11-Nov-14 08:00 A 03-Mar-17 17:00 A 100% 100%
Camp 2368.00 13-Jul-15 08:00 A 21-Oct-16 17:00 A 100% 100%
Temporary Facilities
Facil 1760.00 01-Aug-15 08:00 A 09-Sep-16 17:00 A 100% 100%
CDU - Crude Distillation
Distilla Unit 7360.00 23-Oct-15 08:00 A 03-Sep-18 17:00 100% 98.05%
1110 - CDU - Crude Distillation Unit 7360.00 23-Oct-15 08:00 A 03-Sep-18 17:00 100% 98.05%
CVS-Civil Works 6392.00 23-Oct-15 08:00 A 29-May-18 17:00 100% 99.87%
C1110CVS0000 CVS - Civil Works(Manhours) 6392.00 02-Nov-15 08:00 A 16-Jan-18 00:00 A 100% 100%
Soil Improvement 1048.00 23-Oct-15 08:00 A 29-Apr-16 17:00 A 100% 100%
Piling 1048.00 23-Oct-15 08:00 A 15-Apr-16 17:00 A 100% 100%
Test 312.00 12-Jan-16 08:00 A 29-Apr-16 17:00 A 100% 100%
Foundation 2584.00 11-Mar-16 08:00 A 19-May-17 17:00 A 100% 100%
Foundation for Piperacks
P 800.00 11-Mar-16 08:00 A 04-Feb-17 17:00 A 100% 100%
Foundation for Heater
H 480.00 20-Jun-16 08:00 A 16-Dec-16 17:00 A 100% 100%
Foundation for Column
C 680.00 23-May-16 08:00 A 11-Aug-16 17:00 A 100% 100%
Foundation for Drum
D 744.00 10-Aug-16 08:00 A 15-Feb-17 17:00 A 100% 100%
Foundation for RC
R Structure 384.00 29-Jun-16 08:00 A 24-Oct-16 17:00 A 100% 100%
Foundation for Pump
P 608.00 24-Sep-16 00:00 A 08-Feb-17 17:00 A 100% 100%
Foundation for Exchanger
E 1632.00 25-Apr-16 08:00 A 29-Dec-16 17:00 A 100% 100%
Foundation for Filter
F 120.00 01-Feb-17 08:00 A 19-May-17 17:00 A 100% 100%
Foundation for Package
P 856.00 08-Oct-16 08:00 A 22-Dec-16 17:00 A 100% 100%
Foundation for Blower
B 224.00 11-Feb-17 08:00 A 17-Mar-17 17:00 A 100% 100%
Road,Yards,Paving
Road,Yards,Pavin 3376.00 24-Sep-16 08:00 A 29-May-18 17:00 100% 99.48%
Road 3024.00 24-Sep-16 08:00 A 29-May-18 17:00 100% 93.33%
Heavy Duty Paving
Pav 2696.00 02-Jan-17 08:00 A 15-Mar-18 17:00 A 100% 100%
Light Duty Paving 2360.00 01-Dec-16 08:00 A 16-Jan-18 17:00 A 100% 100%
Pool,Drainage,Cable Trench/Slab, Fire Proofing
Pool,Drainage,Ca 3732.00 01-Oct-16 08:00 A 14-Dec-17 17:00 A 100% 100%
Drainage Pit 1688.00 01-Oct-16 08:00 A 19-Sep-17 17:00 A 100% 100%
Cable Trench/Sla
Trench/Slab (E&I) 592.00 16-Jan-17 08:00 A 06-Nov-17 00:00 A 100% 100%
DC Trench 160.00 26-Nov-16 08:00 A 05-Sep-17 17:00 A 100% 100%
Fire Proofing For
Fo Steel Structure and Equipment 1220.00 01-May-17 00:00 A 14-Dec-17 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 73 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

CVS-Steel Structure
Structu 2768.00 06-Jun-16 08:00 A 08-Dec-17 17:00 A 100% 100%
C1110CVS9000 CVS - Steel Structure(Manhours) 2768.00 06-Jun-16 08:00 A 08-Dec-17 00:00 A 100% 100%
Erection of Main SSteel Structure 1992.00 06-Jun-16 08:00 A 14-Aug-17 17:00 A 100% 100%
Erection of STR Steel Structure 1008.00 11-Oct-16 13:48 A 23-Jun-17 08:00 A 100% 100%
Erection of RCK Steel Work 1736.00 06-Jun-16 08:00 A 14-Aug-17 17:00 A 100% 100%
Erection of Light Steel
S Structure(stair,ladder,platform,handrail) 1464.00 15-Sep-16 08:00 A 08-Dec-17 17:00 A 100% 100%
Erection of Light Steel Structure(stair,ladder,platform,handrail) 1464.00 15-Sep-16 08:00 A 08-Dec-17 17:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 3512.00 27-Sep-16 08:00 A 23-Mar-18 17:00 A 100% 100%
C1110MEC0000 Mechanical/Machinery/Heaters & Boilers(Manhours) 1728.00 17-Dec-16 08:00 A 23-Mar-18 17:00 A 100% 100%
Equipment Installation
Installa 2432.00 27-Sep-16 08:00 A 10-Nov-17 17:00 A 100% 100%
Heater 680.00 30-Dec-16 08:00 A 10-Nov-17 17:00 A 100% 100%
Column 872.00 27-Dec-16 08:00 A 15-Aug-17 17:00 A 100% 100%
Drum 1448.00 27-Sep-16 08:00 A 14-Oct-17 17:00 A 100% 100%
Heat Exchanger 850.00 28-Jan-17 08:00 A 18-Oct-17 17:00 A 100% 100%
Packages 1856.00 28-Jan-17 08:00 A 14-Oct-17 17:00 A 100% 100%
Filter 192.00 07-Oct-17 08:00 A 13-Oct-17 17:00 A 100% 100%
Air Cooler 528.00 02-May-17 08:00 A 09-Sep-17 17:00 A 100% 100%
Trays & Internals 1520.00 28-Aug-17 00:00 A 23-Mar-18 17:00 A 100% 100%
Trays & Internals 1520.00 28-Aug-17 00:00 A 23-Mar-18 17:00 A 100% 100%
Rotating 1287.53 18-Mar-17 00:00 A 04-Jul-18 17:00 100% 99.85%
C1110ROT0000 Rotating(Manhours) 544.00 15-Jul-17 08:00 A 18-Dec-17 00:00 A 100% 100%
Rotating 1287.53 18-Mar-17 00:00 A 04-Jul-18 17:00 100% 99.85%
Blower 464.00 15-Jul-17 08:00 A 04-Jul-18 17:00 100% 99.58%
Pump 1287.53 18-Mar-17 00:00 A 23-Mar-18 00:00 A 100% 100%
Piping 4128.00 20-Jul-16 08:00 A 09-Jul-18 17:00 100% 99.77%
C1110PIP0000 Piping(Manhours) 3632.00 26-Jul-16 08:00 A 15-Jun-18 17:00 100% 0%
U/G Piping 2670.00 29-Aug-16 08:00 A 04-Nov-17 00:00 A 100% 100%
Accidently Oily Contaminated
C 2510.00 21-Sep-16 08:00 A 10-Oct-17 00:00 A 100% 100%
Continuous Oily Contaminated 1296.00 23-Oct-16 00:00 A 20-Jun-17 00:00 A 100% 100%
Fire Fighting Water
Wa 1944.00 29-Aug-16 08:00 A 04-Nov-17 00:00 A 100% 100%
PCV 976.00 04-Mar-17 08:00 A 05-Aug-17 00:00 A 100% 100%
A/G Piping 4128.00 20-Jul-16 08:00 A 15-Jun-18 17:00 100% 99.81%
Carbon Steel Piping
Pip 3744.00 20-Jul-16 08:00 A 15-Jun-18 17:00 100% 99.81%
Alloy Steel Piping 2408.00 04-Dec-16 08:00 A 15-Jun-18 17:00 100% 99.81%
Stainless Steel Piping
P 2112.00 20-Apr-17 00:00 A 15-Jun-18 17:00 100% 99.81%
Piping Support 3112.00 02-Dec-16 08:00 A 09-Jul-18 17:00 100% 98%
Piping Support 3112.00 02-Dec-16 08:00 A 09-Jul-18 17:00 100% 98%
Electrical 2896.00 31-Oct-16 08:00 A 25-Apr-18 17:00 A 100% 100%
C1110ELE0000 Electrical(Manhours) 2896.00 31-Oct-16 08:00 A 21-Jul-17 17:00 A 100% 100%
Electrical 2872.00 31-Oct-16 08:00 A 25-Apr-18 17:00 A 100% 100%
Cable Ladder 160.00 04-Mar-17 08:00 A 29-Nov-17 17:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 808.00 15-Apr-17 00:00 A 14-Apr-18 17:00 A 100% 100%
Wiring 696.00 03-Oct-17 00:00 A 23-Mar-18 17:00 A 100% 100%
Elec. Field Equipment
Equip 1720.00 04-Apr-17 00:00 A 23-Mar-18 17:00 A 100% 100%
Lighting System 1112.00 04-Apr-17 00:00 A 25-Apr-18 17:00 A 100% 100%
Earthing System 2496.00 31-Oct-16 08:00 A 22-Dec-17 17:00 A 100% 100%
Cathodic Protection
Protect System 232.00 11-Feb-17 08:00 A 20-Jul-17 17:00 A 100% 100%
Heat Tracing 416.00 24-Jun-17 00:00 A 21-Jul-17 17:00 A 100% 100%
Instrumentation an
and Control 2848.00 18-Feb-17 08:00 A 07-Aug-18 17:00 100% 95.26%
C1110INC0000 Instrumentation and Control(Manhours) 2416.00 18-Feb-17 08:00 A 25-Apr-18 00:00 A 100% 100%
Instrumentation a
and Control 2848.00 18-Feb-17 08:00 A 07-Aug-18 17:00 100% 95.26%
Cable Tray 840.00 18-Feb-17 08:00 A 27-Jul-18 17:00 100% 99.25%
Cabling 1392.00 21-May-17 00:00 A 07-Aug-18 17:00 100% 99.99%
Junction Boxes 1328.00 25-Feb-17 08:00 A 05-Oct-17 00:00 A 100% 100%
Field Instrument 1640.00 14-Jun-17 00:00 A 10-Jul-18 17:00 100% 82.79%

Remaining Level of Effort Actual Work Critical Remaining ... Page 74 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Wiring 1064.00 01-Sep-17 00:00 A 25-Apr-18 00:00 A 100% 100%


PIP/MEC Insulation 1784.00 02-May-17 08:00 A 27-Aug-18 17:00 100% 93.21%
C1110INS0000 PIP/MEC Insulation(Manhours) 1624.00 02-May-17 08:00 A 27-Aug-18 17:00 100% 0%
Insulation of Equip
Equipment 880.00 02-May-17 08:00 A 16-Nov-17 17:00 A 100% 100%
Insulation of Equipment
Equ 880.00 02-May-17 08:00 A 16-Nov-17 17:00 A 100% 100%
Insulation of Pipes 1088.00 12-Jun-17 08:00 A 27-Aug-18 17:00 100% 90.66%
Insulation of Pipes
Pipe 1088.00 12-Jun-17 08:00 A 27-Aug-18 17:00 100% 90.66%
Navigation and Telecommunications
Te 1064.00 18-Jul-17 08:00 A 30-Aug-18 17:00 100% 70.82%
Navigation and Telecommunications
Te 1064.00 18-Jul-17 08:00 A 30-Aug-18 17:00 100% 70.82%
Navigation and Telecommunications
T 1064.00 18-Jul-17 08:00 A 30-Aug-18 17:00 100% 70.82%
Precommissioning 2424.00 29-May-17 08:00 A 03-Sep-18 17:00 100% 73.5%
C1110GEN0000 Pre Commissioning(Manhours) 1320.00 24-Apr-18 08:00 A 03-Sep-18 17:00 100% 61.67%
Precommissioning 2272.00 29-May-17 08:00 A 03-Sep-18 17:00 100% 73.5%
Pre Commissioning
Commission for 1110 2272.00 29-May-17 08:00 A 03-Sep-18 17:00 100% 73.5%
MC for 1110 (P4
(P40,T0+45,2018/4/30) 0.00 03-Sep-18 17:00 03-Sep-18 17:00 0% 0%
HCDU - Hydrogen Collection
C & Distribution 5864.00 25-Apr-16 08:00 A 13-Aug-18 17:00 100% 96.44%
1520-HCDU - Hydrogen
Hydr Collection & Distribution 5864.00 25-Apr-16 08:00 A 13-Aug-18 17:00 100% 96.44%
CVS-Civil Works 4608.00 25-Apr-16 08:00 A 26-May-18 17:00 100% 99.07%
C1520CVS0000 CVS-Civil Works(Manhours) 4112.00 25-Apr-16 08:00 A 26-May-18 17:00 100% 0%
Foundation 2488.00 25-Apr-16 08:00 A 05-Aug-17 17:00 A 100% 100%
Foundation for Piperacks
P 560.00 25-Apr-16 08:00 A 19-Aug-16 17:00 A 100% 100%
Foundation for Drum
D 336.00 25-Feb-17 08:00 A 05-Aug-17 17:00 A 100% 100%
Foundation for Exchange
E 368.00 25-Feb-17 08:00 A 10-Mar-17 17:00 A 100% 100%
Foundations Of 1520-STR-1100/1110/1120/1130/1140 912.00 10-Dec-16 08:00 A 17-Feb-17 17:00 A 100% 100%
Foundation for Compressor/Shelter
C 768.00 17-Aug-16 08:00 A 30-Dec-16 17:00 A 100% 100%
Foundations Of 1520-STR-1200/1210/1220/1230/1240 688.00 10-Dec-16 08:00 A 05-Aug-17 17:00 A 100% 100%
Road,Yards,Paving
Road,Yards,Pavin 2478.00 04-Feb-17 08:00 A 20-Jan-18 00:00 A 100% 100%
Heavy Duty Paving
Pav 750.00 25-Oct-17 08:00 A 20-Jan-18 00:00 A 100% 100%
Light Duty Paving 912.00 18-Mar-17 08:00 A 19-Dec-17 17:00 A 100% 100%
Road 1000.00 04-Feb-17 08:00 A 10-Aug-17 17:00 A 100% 100%
Pool,Drainage,Cable Trench/Slab, Fire Proofing
Pool,Drainage,Ca 3120.00 28-Nov-16 08:00 A 26-May-18 17:00 100% 96.73%
Drainage Pit 1048.00 28-Nov-16 08:00 A 15-May-17 00:00 A 100% 100%
COC Pit 1520-T-101
1520-T 240.00 01-May-17 08:00 A 19-May-17 17:00 A 100% 100%
Cable Trench/Sla
Trench/Slab (E&I) 264.00 14-Sep-17 08:00 A 18-Dec-17 17:00 A 100% 100%
Fire Proofing 200.00 08-Dec-17 08:00 A 26-May-18 17:00 100% 93.91%
CVS-Steel Structure
Structu 1736.00 01-Jan-17 08:00 A 08-Dec-17 17:00 A 100% 100%
C1520CVS9000 CVS-Steel Structure(Manhours) 1504.00 30-Jan-17 08:00 A 08-Dec-17 00:00 A 100% 100%
Erection of STR S Steel Structure 1736.00 01-Jan-17 08:00 A 08-Dec-17 17:00 A 100% 100%
Erection of Steel Work(RCK) 1112.00 30-Jan-17 08:00 A 19-Jul-17 17:00 A 100% 100%
Erection of Steel Structure 720.00 01-Apr-17 00:00 A 08-Dec-17 17:00 A 100% 100%
Erection of Shelter
Shelt 1488.00 01-Jan-17 08:00 A 11-Jul-17 17:00 A 100% 100%
Erection of Light Steel
S Structure(stair,ladder,platform,handrail) 1128.00 04-Jan-17 08:00 A 08-Dec-17 00:00 A 100% 100%
Erection of Light Steel Structure 1128.00 04-Jan-17 08:00 A 08-Dec-17 00:00 A 100% 100%
Mechanical/Machinery
Mechanical/Machin 576.00 02-May-17 08:00 A 20-Oct-17 17:00 A 100% 100%
C1520MEC0000 Mechanical/Machinery(Manhours) 0.00 16-Jun-17 08:00 A 07-Oct-17 17:00 A 100% 100%
Equipment Installation
Installa 576.00 02-May-17 08:00 A 20-Oct-17 17:00 A 100% 100%
Drum 360.00 07-Aug-17 08:00 A 20-Oct-17 17:00 A 100% 100%
Heat Exchanger 280.00 07-Oct-17 08:00 A 20-Oct-17 17:00 A 100% 100%
Crane 240.00 02-May-17 08:00 A 16-Jun-17 17:00 A 100% 100%
Rotating 1200.00 25-Mar-17 08:00 A 28-Mar-18 17:00 A 100% 100%
Rotating 1200.00 25-Mar-17 08:00 A 28-Mar-18 17:00 A 100% 100%
Compressor 1200.00 25-Mar-17 08:00 A 28-Mar-18 17:00 A 100% 100%
Pump 72.00 21-Aug-17 08:00 A 08-Dec-17 17:00 A 100% 100%
Piping 3704.00 17-Aug-16 08:00 A 10-Jul-18 17:00 100% 99.72%
C1520PIP0000 Piping(Manhours) 304.00 08-Dec-16 08:00 A 02-Jun-17 08:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 75 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

U/G Piping 1136.00 05-Sep-16 08:00 A 10-Sep-17 00:00 A 100% 100%


Accidently Oily Contaminated
C 720.00 21-Sep-16 08:00 A 10-Aug-17 00:00 A 100% 100%
Continuous Oily Contaminated 560.00 06-Sep-16 08:00 A 10-Sep-17 00:00 A 100% 100%
Cooling Water Return
R / Cooling Water Supply 720.00 05-Sep-16 08:00 A 23-Dec-16 17:00 A 100% 100%
Fire Fighting Water
Wa 528.00 21-Sep-16 08:00 A 10-Aug-17 00:00 A 100% 100%
A/G Piping 3472.00 17-Aug-16 08:00 A 29-Jun-18 17:00 100% 99.82%
Carbon Steel Piping
Pip 3472.00 17-Aug-16 08:00 A 22-Jun-18 17:00 100% 99.82%
Stainless Steel Piping
P 2256.00 17-Aug-16 08:00 A 29-Jun-18 17:00 100% 99.86%
Piping Support 2384.00 08-Dec-16 08:00 A 10-Jul-18 17:00 100% 97.89%
Piping Support 2384.00 08-Dec-16 08:00 A 10-Jul-18 17:00 100% 97.89%
Electrical 3080.00 03-Dec-16 08:00 A 27-Jul-18 17:00 100% 99.9%
C1520ELE0000 Electrical(Manhours) 3080.00 17-Dec-16 08:00 A 08-Sep-17 17:00 A 100% 100%
Electrical 3080.00 03-Dec-16 08:00 A 27-Jul-18 17:00 100% 99.9%
Earthing System 1424.00 17-Dec-16 08:00 A 22-Dec-17 17:00 A 100% 100%
Cable Ladder 60.00 15-Mar-17 08:00 A 29-Nov-17 17:00 A 100% 100%
Wiring 140.00 08-Nov-17 08:00 A 25-Apr-18 17:00 A 100% 100%
Elec. Field Equipment
Equip 568.00 15-May-17 08:00 A 25-Apr-18 08:00 A 100% 100%
Lighting System 1512.00 20-Mar-17 08:00 A 27-Jul-18 17:00 100% 97.5%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 720.00 20-Mar-17 08:00 A 15-Nov-17 17:00 A 100% 100%
Cathodic Protection
Protect System 568.00 03-Dec-16 08:00 A 25-Jul-17 17:00 A 100% 100%
Heat Tracing 480.00 01-Jul-17 08:00 A 08-Sep-17 17:00 A 100% 100%
Instrumentation an
and Control 2016.00 10-May-17 08:00 A 04-Aug-18 17:00 100% 94.5%
C1520INC0000 Instrumentation and Control(Manhours) 1984.00 10-May-17 08:00 A 28-Apr-18 08:00 100% 0%
Instrumentation a
and Control 2016.00 10-May-17 08:00 A 04-Aug-18 17:00 100% 94.5%
Cable Tray 72.00 10-May-17 08:00 A 17-Apr-18 00:00 A 100% 100%
Wiring 992.00 24-Nov-17 08:00 A 16-Feb-18 00:00 A 100% 100%
Cabling 1360.00 13-Jul-17 08:00 A 14-Jul-18 17:00 100% 97.94%
Junction Boxes 920.00 10-May-17 08:00 A 16-Feb-18 00:00 A 100% 100%
Field Instrument 672.00 17-Jun-17 08:00 A 04-Aug-18 17:00 100% 74.34%
PIP/MEC Insulation 1104.00 16-Oct-17 08:00 A 21-Jun-18 17:00 100% 25.19%
C1520INS0000 PIP/MEC Insulation(Manhours) 288.00 20-Nov-17 08:00 A 21-Jun-18 17:00 100% 0%
Insulation of Equip
Equipment 536.00 20-Nov-17 08:00 A 23-Mar-18 17:00 A 100% 100%
Insulation of Equipment
Equ 536.00 20-Nov-17 08:00 A 23-Mar-18 17:00 A 100% 100%
Insulation of Pipes 1104.00 16-Oct-17 08:00 A 21-Jun-18 17:00 100% 4.5%
Insulation of Pipes
Pipe 1104.00 16-Oct-17 08:00 A 21-Jun-18 17:00 100% 4.5%
Navigation and Telecommunications
Te 552.00 28-Sep-17 08:00 A 17-Jul-18 17:00 100% 70.15%
Navigation and Telecommunications
Te 552.00 28-Sep-17 08:00 A 17-Jul-18 17:00 100% 70.15%
Navigation and Telecommunications
T 552.00 28-Sep-17 08:00 A 17-Jul-18 17:00 100% 70.15%
Precommissioning 2224.00 26-May-17 08:00 A 13-Aug-18 17:00 100% 76.01%
C1520GEN0000 Precommissioning(Manhours) 1560.00 26-May-17 08:00 A 13-Aug-18 17:00 100% 0%
Precommissioning 2224.00 26-May-17 08:00 A 13-Aug-18 17:00 100% 76.01%
Pre Commissioning
Commission for 1520 2224.00 26-May-17 08:00 A 13-Aug-18 17:00 100% 76.01%
MC for 1520 (P4
(P40,T0+45,2018/4/30) 0.00 13-Aug-18 17:00 13-Aug-18 17:00 0% 0%
FOS - Fuel Oil Syste
System 6440.00 17-Jan-16 08:00 A 31-Aug-18 17:00 100% 99.42%
4550 - FOS - Fuel O
Oil System 6440.00 17-Jan-16 08:00 A 31-Aug-18 17:00 100% 99.42%
CVS-Civil 5232.00 17-Jan-16 08:00 A 07-Mar-18 00:00 A 100% 100%
C4550CVS0000 CVS-Civil(Manhours) 5048.00 17-Jan-16 08:00 A 07-Mar-18 00:00 A 100% 100%
Soil Improvement 272.00 17-Jan-16 08:00 A 04-Jul-16 17:00 A 100% 100%
Piling 192.00 17-Jan-16 08:00 A 08-Feb-16 17:00 A 100% 100%
Test 176.00 25-Feb-16 00:00 A 04-Jul-16 17:00 A 100% 100%
Foundation 1640.00 24-Oct-16 08:00 A 30-Jun-17 17:00 A 100% 100%
Foundation for Drum
D 344.00 10-Dec-16 08:00 A 03-Mar-17 17:00 A 100% 100%
Foundation for Piperacks
P 1640.00 24-Oct-16 08:00 A 30-Jun-17 17:00 A 100% 100%
Foundation for Tank
T 296.00 10-Nov-16 08:00 A 16-Dec-16 17:00 A 100% 100%
Foundation for RC
R Structure 480.00 24-Oct-16 08:00 A 06-Jan-17 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 76 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Foundation for Exchanger


E 200.00 04-Feb-17 08:00 A 10-Feb-17 17:00 A 100% 100%
Foundation for Filter
F 312.00 11-Feb-17 08:00 A 17-Feb-17 17:00 A 100% 100%
Foundation for Pump
P 160.00 08-Jan-17 08:00 A 04-Feb-17 17:00 A 100% 100%
Foundation for Mixer
M 376.00 18-Mar-17 08:00 A 24-Mar-17 17:00 A 100% 100%
Road,Yards,Paving
Road,Yards,Pavin 2064.00 02-May-17 08:00 A 07-Mar-18 00:00 A 100% 100%
Road 1824.00 19-Jun-17 08:00 A 06-Mar-18 00:00 A 100% 100%
Light duty paving 1504.00 02-May-17 08:00 A 14-Feb-18 00:00 A 100% 100%
Heavy duty paving
pavi 888.00 04-May-17 08:00 A 07-Mar-18 00:00 A 100% 100%
Pool,Drainage,Cable Trench/Slab, Fire Proofing
Pool,Drainage,Ca 2928.00 26-Nov-16 08:00 A 11-Dec-17 17:00 A 100% 100%
DC: CLOSE DRAIN
DR 640.00 17-Dec-16 08:00 A 23-Jun-17 17:00 A 100% 100%
Pool-4550-V-001 144.00 26-Nov-16 08:00 A 08-Feb-17 17:00 A 100% 100%
Drainage Pit 1072.00 16-Jan-17 08:00 A 30-Jun-17 17:00 A 100% 100%
Cable Trench/Sla
Trench/Slab(El & IN) 272.00 05-Dec-17 08:00 A 11-Dec-17 17:00 A 100% 100%
Fire Proofing 336.00 01-Dec-17 08:00 A 05-Dec-17 17:00 A 100% 100%
CVS-Steel Structure
Structu 136.00 28-Jan-17 08:00 A 08-Dec-17 00:00 A 100% 100%
C4550CVS9000 CVS-Steel Structure(Manhours) 136.00 28-Jan-17 08:00 A 08-Dec-17 00:00 A 100% 100%
Erection of STR S Steel Structure 96.00 28-Jan-17 08:00 A 12-Jul-17 17:00 A 100% 100%
Erection of RCK Steel Structure 96.00 28-Jan-17 08:00 A 19-May-17 17:00 A 100% 100%
Erection of STR Steel Structure 96.00 28-Jan-17 08:00 A 12-Jul-17 17:00 A 100% 100%
Erection of Light Steel
S Structure(stair,ladder,platform,handrail) 136.00 28-Jan-17 08:00 A 08-Dec-17 00:00 A 100% 100%
Erection of Light Steel Structure(stair,ladder,platform,handrail) 136.00 28-Jan-17 08:00 A 08-Dec-17 00:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 1464.00 09-Feb-17 08:00 A 05-Mar-18 17:00 A 100% 100%
C4550MEC0000 Mechanical/Machinery/Heaters & Boilers(Manhours) 480.00 24-Jul-17 00:00 A 05-Mar-18 17:00 A 100% 100%
Equipment Installation
Installa 1464.00 09-Feb-17 08:00 A 05-Mar-18 17:00 A 100% 100%
Filter 144.00 11-Sep-17 00:00 A 22-Feb-18 00:00 A 100% 100%
Heat Exchanger 160.00 09-Feb-17 08:00 A 03-Mar-17 17:00 A 100% 100%
Air Cooler 368.00 04-Sep-17 00:00 A 13-Oct-17 00:00 A 100% 100%
Drum 328.00 24-Jul-17 00:00 A 08-Nov-17 17:00 A 100% 100%
Cylindrical Tank 440.00 06-Mar-17 08:00 A 05-Mar-18 17:00 A 100% 100%
Rotating 456.00 05-Jun-17 08:00 A 16-Sep-17 17:00 A 100% 100%
Rotating 456.00 05-Jun-17 08:00 A 16-Sep-17 17:00 A 100% 100%
Pumps 456.00 05-Jun-17 08:00 A 16-Sep-17 17:00 A 100% 100%
Piping 3816.00 27-Jul-16 08:00 A 05-Mar-18 17:00 A 100% 100%
C4550PIP0000 Piping(Manhours) 1600.00 25-Mar-17 08:00 A 12-Feb-18 08:00 A 100% 100%
U/G Piping 1296.00 14-Jan-17 08:00 A 07-May-17 17:00 A 100% 100%
DC Piping 160.00 25-Mar-17 08:00 A 07-Apr-17 17:00 A 100% 100%
Accidently Oily Contaminated
C 440.00 14-Jan-17 08:00 A 07-Apr-17 17:00 A 100% 100%
Fire Fighting Water
Wa 592.00 01-Apr-17 08:00 A 07-May-17 17:00 A 100% 100%
A/G Piping 3816.00 27-Jul-16 08:00 A 05-Mar-18 17:00 A 100% 100%
Carbon Steel Piping
Pip 3816.00 27-Jul-16 08:00 A 05-Mar-18 17:00 A 100% 100%
Piping Support 2008.00 04-Jan-17 08:00 A 02-Sep-17 17:00 A 100% 100%
Piping Support 2008.00 04-Jan-17 08:00 A 02-Sep-17 17:00 A 100% 100%
Electrical 2544.00 25-Feb-17 08:00 A 06-Mar-18 17:00 A 100% 100%
C4550ELE0000 Electrical(Manhours) 1424.00 25-Feb-17 08:00 A 13-Sep-17 00:00 A 100% 100%
Electrical 2544.00 25-Feb-17 08:00 A 06-Mar-18 17:00 A 100% 100%
Wiring 360.00 18-Oct-17 00:00 A 15-Dec-17 17:00 A 100% 100%
Earthing System 670.00 25-Feb-17 08:00 A 22-Dec-17 17:00 A 100% 100%
Elec. Field Equipment
Equip 200.00 02-May-17 00:00 A 06-Mar-18 17:00 A 100% 100%
Lighting System 232.00 03-May-17 00:00 A 06-Mar-18 17:00 A 100% 100%
Cathodic Protection
Protect System 192.00 25-Feb-17 08:00 A 17-Jun-17 17:00 A 100% 100%
Cabling(LV,Control,Lighting)
Cabling(LV,Cont 920.00 01-Jul-17 00:00 A 15-Dec-17 00:00 A 100% 100%
Heat Tracing 216.00 01-Jul-17 00:00 A 13-Sep-17 00:00 A 100% 100%
Instrumentation 2072.00 01-May-17 00:00 A 07-Mar-18 00:00 A 100% 100%
C4550INC0000 Instrumentation(Manhours) 1216.00 01-May-17 00:00 A 06-Mar-18 00:00 A 100% 100%
Instrumentation 2072.00 01-May-17 00:00 A 07-Mar-18 00:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 77 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Wiring 424.00 10-Jan-18 00:00 A 07-Mar-18 00:00 A 100% 100%


Cable Tray 480.00 10-May-17 00:00 A 06-Mar-18 00:00 A 100% 100%
Cabling 472.00 29-Nov-17 00:00 A 07-Mar-18 00:00 A 100% 100%
Junction Boxes 440.00 01-May-17 00:00 A 07-Feb-18 17:00 A 100% 100%
Field Instrument 480.00 30-Jun-17 00:00 A 07-Mar-18 00:00 A 100% 100%
PIP/MEC Insulation 880.00 16-Oct-17 00:00 A 31-Aug-18 17:00 100% 89.6%
C4550INS0000 PIP/MEC Insulation(Manhours) 112.00 23-Oct-17 08:00 A 31-Aug-18 17:00 100% 0%
Insulation of Equip
Equipment 128.00 23-Oct-17 08:00 A 06-Mar-18 17:00 A 100% 100%
Insulation of Equipment
Equ 128.00 23-Oct-17 08:00 A 06-Mar-18 17:00 A 100% 100%
Insulation of Pipes 584.00 16-Oct-17 00:00 A 31-Aug-18 17:00 100% 77.87%
Insulation of Pipes
Pipe 584.00 16-Oct-17 00:00 A 31-Aug-18 17:00 100% 77.87%
Navigation and Telecommunications
Te 240.00 18-Sep-17 00:00 A 06-Mar-18 17:00 A 100% 100%
Navigation and Telecommunications
Te 240.00 18-Sep-17 00:00 A 06-Mar-18 17:00 A 100% 100%
Navigation and Telecommunications
T 240.00 18-Sep-17 00:00 A 06-Mar-18 17:00 A 100% 100%
Precommissioning 1816.00 30-May-17 08:00 A 19-Jul-18 17:00 100% 85.9%
C4550GEN0000 Precommissioning(Manhours) 752.00 12-Oct-17 08:00 A 19-Jul-18 17:00 100% 0%
Precommissioning 1816.00 30-May-17 08:00 A 07-Jul-18 17:00 100% 85.9%
Precommissioning
Precommissionin 1816.00 30-May-17 08:00 A 07-Jul-18 17:00 100% 85.9%
MC for 4550 (P4
(P40,T0+45,2018/4/30) 0.00 07-Mar-18 17:00 A 07-Mar-18 17:00 A 0% 0%
ARDS - Atmospheric Residue Desulphurization 6936.00 13-Nov-15 08:00 A 22-Aug-18 17:00 99.94% 95.96%
1210 - Common ARDS
AR - Common Atmospheric Residue Desulphurization 5968.00 25-Apr-16 08:00 A 14-Aug-18 17:00 100% 98.84%
CVS-Civil Works 5752.00 25-Apr-16 08:00 A 10-Jul-18 17:00 100% 99.83%
C1210CVS0000 CVS-Civil Works(Manhours) 5712.00 25-Apr-16 08:00 A 08-Dec-17 00:00 A 100% 100%
Foundation 3048.00 25-Apr-16 08:00 A 23-Jun-17 17:00 A 100% 100%
Foundation for Piperacks
P 560.00 25-Apr-16 08:00 A 14-Apr-17 00:00 A 100% 100%
Foundation for Drum
D 320.00 13-May-17 08:00 A 23-Jun-17 17:00 A 100% 100%
Foundation for SS
S Structure 776.00 31-Dec-16 08:00 A 24-Feb-17 17:00 A 100% 100%
Foundation for Compressor/Shelter
C 688.00 17-Aug-16 08:00 A 30-Dec-16 17:00 A 100% 100%
Foundation for Exchange
E 368.00 13-May-17 08:00 A 23-Jun-17 17:00 A 100% 100%
Foundation for Pump
P 232.00 13-May-17 08:00 A 19-May-17 00:00 A 100% 100%
Foundation for Package
P 376.00 01-Apr-17 00:00 A 19-May-17 00:00 A 100% 100%
Foundation for AOC
A BASIN 6300-T-103 480.00 17-Aug-16 08:00 A 03-Feb-17 17:00 A 100% 100%
Road,Yards,Paving
Road,Yards,Pavin 2375.98 30-Sep-16 08:00 A 10-Jul-18 17:00 100% 99.15%
Road 1432.00 30-Sep-16 08:00 A 10-Jul-18 17:00 100% 97%
Heavy Duty Paving
Pav 872.00 17-Nov-17 08:00 A 22-Feb-18 00:00 A 100% 100%
Light Duty Paving 807.98 25-Mar-17 08:00 A 15-Feb-18 00:00 A 100% 100%
Pool,Drainage,Cable Trench/Slab, Fire Proofing
Pool,Drainage,Ca 3047.98 11-Dec-16 08:00 A 08-Dec-17 17:00 A 100% 100%
Drainage Pit£¨PCV+STW£©
Pit£¨PC 1791.98 11-Dec-16 08:00 A 30-Jun-17 17:00 A 100% 100%
Cable Trench/Sla
Trench/Slab (E&I) 336.00 10-Aug-17 08:00 A 07-Dec-17 17:00 A 100% 100%
Fire Proofing 432.00 04-Dec-17 08:00 A 08-Dec-17 17:00 A 100% 100%
CVS-Steel Structure
Structu 1200.00 17-Dec-16 08:00 A 08-Dec-17 17:00 A 100% 100%
C1210CVS9000 CVS-Steel Structure(Manhours) 1128.00 17-Dec-16 08:00 A 08-Dec-17 00:00 A 100% 100%
Erection of Main SSteel Structure 1160.00 17-Dec-16 08:00 A 05-Jul-17 17:00 A 100% 100%
Erection of STR Steel Structure 728.00 01-Apr-17 08:00 A 01-Jul-17 17:00 A 100% 100%
Erection of RCK Steel Work 480.00 17-Dec-16 08:00 A 14-Apr-17 00:00 A 100% 100%
Erection of Shelter
Shelt 696.00 28-Jan-17 08:00 A 05-Jul-17 17:00 A 100% 100%
Erection of Light Steel
S Structure(stair,ladder,platform,handrail) 900.00 04-Jan-17 08:00 A 08-Dec-17 17:00 A 100% 100%
Erection of Light Steel Structure 900.00 04-Jan-17 08:00 A 08-Dec-17 17:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 656.00 02-May-17 08:00 A 15-Dec-17 17:00 A 100% 100%
C1210MEC0000 Mechanical/Machinery/Heaters & Boilers(Manhours) 640.00 03-Jul-17 08:00 A 15-Dec-17 17:00 A 100% 100%
Equipment Installation
Installa 656.00 02-May-17 08:00 A 15-Dec-17 17:00 A 100% 100%
Drum 300.00 03-Jul-17 08:00 A 13-Oct-17 17:00 A 100% 100%
Heat Exchanger 60.00 08-Jul-17 08:00 A 14-Oct-17 17:00 A 100% 100%
Packages 200.00 09-Aug-17 08:00 A 15-Dec-17 17:00 A 100% 100%
Crane 248.00 02-May-17 08:00 A 16-Jun-17 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 78 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Rotating 896.00 20-Mar-17 08:00 A 24-Jan-18 17:00 A 100% 100%


C1210ROT0000 Rotating(Manhours) 600.00 09-Aug-17 00:00 A 15-Nov-17 17:00 A 100% 100%
Rotating 736.00 20-Mar-17 08:00 A 24-Jan-18 17:00 A 100% 100%
Compressor 540.00 20-Mar-17 08:00 A 15-Nov-17 17:00 A 100% 100%
Pump 440.00 09-Aug-17 00:00 A 24-Jan-18 17:00 A 100% 100%
Piping 3168.00 17-Aug-16 08:00 A 10-Jul-18 17:00 100% 99.78%
C1210PIP0000 Piping(Manhours) 1232.00 08-Jun-17 08:00 A 28-Apr-18 17:00 100% 0%
U/G Piping 1512.00 22-Oct-16 08:00 A 06-Dec-17 00:00 A 100% 100%
Accidently Oily Contaminated
C 1176.00 17-Dec-16 08:00 A 06-Dec-17 00:00 A 100% 100%
Continuous Oily Contaminated 720.00 22-Oct-16 08:00 A 09-Aug-17 00:00 A 100% 100%
Fire Fighting Water
Wa 424.00 17-Dec-16 08:00 A 14-Oct-17 00:00 A 100% 100%
A/G Piping 3168.00 17-Aug-16 08:00 A 01-Jun-18 17:00 100% 99.83%
Carbon Steel Piping
Pip 3168.00 17-Aug-16 08:00 A 01-Jun-18 17:00 100% 99.83%
Piping Support 2210.00 04-Jan-17 08:00 A 10-Jul-18 17:00 100% 98%
Piping Support 2210.00 04-Jan-17 08:00 A 10-Jul-18 17:00 100% 98%
Electrical 2560.00 12-Dec-16 08:00 A 29-Mar-18 17:00 A 100% 100%
C1210ELE0000 Electrical(Manhours) 1912.00 17-Dec-16 08:00 A 17-Aug-17 17:00 A 100% 100%
Electrical 2560.00 12-Dec-16 08:00 A 29-Mar-18 17:00 A 100% 100%
Earthing System 736.00 17-Dec-16 08:00 A 22-Dec-17 17:00 A 100% 100%
Cable Ladder 168.00 13-Apr-17 08:00 A 29-Nov-17 17:00 A 100% 100%
Wiring 40.00 08-Nov-17 08:00 A 29-Mar-18 17:00 A 100% 100%
Elec. Field Equipment
Equip 904.00 15-Mar-17 08:00 A 29-Mar-18 17:00 A 100% 100%
Lighting System 760.00 12-Dec-16 08:00 A 29-Mar-18 17:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 480.00 19-Apr-17 08:00 A 29-Mar-18 17:00 A 100% 100%
Cathodic Protection
Protect System 1016.00 21-Feb-17 08:00 A 17-Jun-17 17:00 A 100% 100%
Heat Tracing 440.00 03-Jul-17 08:00 A 17-Aug-17 17:00 A 100% 100%
Instrumentation an
and Control 1600.00 10-May-17 08:00 A 28-Apr-18 08:00 100% 100%
C1210INC0000 Instrumentation and Control(Manhours) 1600.00 10-May-17 08:00 A 28-Apr-18 08:00 100% 0%
Instrumentation a
and Control 1512.00 10-May-17 08:00 A 24-Apr-18 17:00 A 100% 100%
Cable Tray 584.00 10-May-17 08:00 A 10-Apr-18 00:00 A 100% 100%
Wiring 296.00 06-Nov-17 08:00 A 24-Apr-18 00:00 A 100% 100%
Cabling 472.00 11-Aug-17 08:00 A 16-Apr-18 00:00 A 100% 100%
Junction Boxes 512.00 10-May-17 08:00 A 15-Feb-18 00:00 A 100% 100%
Field Instrument 672.00 19-Jun-17 08:00 A 24-Apr-18 17:00 A 100% 100%
PIP/MEC Insulation 2040.00 21-Oct-17 08:00 A 14-Aug-18 17:00 100% 26.61%
C1210INS0000 PIP/MEC Insulation(Manhours) 744.00 28-Apr-18 08:00 14-Aug-18 17:00 100% 0%
Insulation of Equip
Equipment 476.00 21-Oct-17 08:00 A 06-Jul-18 17:00 100% 60.61%
Insulation of Equipment
Equ 476.00 21-Oct-17 08:00 A 06-Jul-18 17:00 100% 60.61%
Insulation of Pipes 528.00 27-Nov-17 08:00 A 14-Aug-18 17:00 100% 20.61%
Insulation of Pipes
Pipe 528.00 27-Nov-17 08:00 A 14-Aug-18 17:00 100% 20.61%
Navigation and Telecommunications
Te 856.00 18-Sep-17 08:00 A 25-Apr-18 17:00 A 100% 100%
Navigation and Telecommunications
Te 856.00 18-Sep-17 08:00 A 25-Apr-18 17:00 A 100% 100%
Navigation and Telecommunications
T 856.00 18-Sep-17 08:00 A 25-Apr-18 17:00 A 100% 100%
Precommissioning 2704.00 31-May-17 08:00 A 14-Aug-18 17:00 100% 84.3%
C1210GEN0000 Precommissioning(Manhours) 1944.00 31-May-17 08:00 A 14-Aug-18 17:00 100% 0%
Precommissioning 2704.00 31-May-17 08:00 A 14-Aug-18 17:00 100% 84.3%
Pre Commissioning
Commission for 1210 2568.00 31-May-17 08:00 A 14-Aug-18 17:00 100% 84.3%
MC for 1210 (P4
(P40,T0+45,2018/4/30) 0.00 16-Apr-18 17:00 A 16-Apr-18 17:00 A 0% 0%
1211 - ARDS - Atmospheric
Atmo Residue Desulphurization 6896.00 13-Nov-15 08:00 A 22-Aug-18 17:00 99.99% 95.61%
CVS-Civil Works 6040.00 13-Nov-15 08:00 A 12-Jun-18 17:00 100% 99.57%
C1211CVS0000 CVS-Civil Works(Manhours) 5696.00 02-Dec-15 08:00 A 28-Apr-18 08:00 100% 0%
Soil Improvement 1032.00 13-Nov-15 08:00 A 28-Apr-16 17:00 A 100% 100%
Piling 936.00 13-Nov-15 08:00 A 14-Apr-16 17:00 A 100% 100%
Test 648.00 18-Jan-16 08:00 A 28-Apr-16 17:00 A 100% 100%
Foundation 2416.00 08-Mar-16 08:00 A 19-May-17 00:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 79 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Foundation for Piperacks


P 2240.00 08-Mar-16 08:00 A 09-Dec-16 17:00 A 100% 100%
Foundation for Column
C 888.00 15-Jul-16 08:00 A 07-Oct-16 17:00 A 100% 100%
Foundation for Drum
D 1488.00 22-Jul-16 08:00 A 21-Apr-17 00:00 A 100% 100%
Foundation for Steel
S Structure 1688.00 25-Apr-16 08:00 A 23-Dec-16 17:00 A 100% 100%
Foundation for Pump
P 1008.00 24-Sep-16 00:00 A 23-Dec-16 17:00 A 100% 100%
Foundation for Heater
H 1584.00 01-Jul-16 08:00 A 14-Oct-16 17:00 A 100% 100%
Foundation for Exchange
E 856.00 01-Aug-16 08:00 A 19-May-17 00:00 A 100% 100%
Foundation for Filter
F 344.00 25-Sep-16 00:00 A 09-Dec-16 17:00 A 100% 100%
Foundation for Compressor
C 672.00 25-Sep-16 00:00 A 13-Jan-17 17:00 A 100% 100%
Road,Yards,Paving
Road,Yards,Pavin 2336.00 10-Nov-16 08:00 A 12-Jun-18 17:00 100% 98.43%
Road 1712.00 10-Nov-16 08:00 A 12-Jun-18 17:00 100% 91.87%
Light Duty Paving 1852.00 11-Feb-17 08:00 A 15-Dec-17 00:00 A 100% 100%
Heavy Duty Paving
Pav 1400.00 12-Dec-16 08:00 A 15-Dec-17 00:00 A 100% 100%
Pool,Drainage,Cable Trench/Slab, Fire Proofing
Pool,Drainage,Ca 3928.00 24-Sep-16 08:00 A 18-Dec-17 17:00 A 100% 100%
Drainage Pit 1816.00 24-Sep-16 08:00 A 10-Nov-17 00:00 A 100% 100%
Cable Trench/Sla
Trench/Slab (E&I) 260.00 29-Nov-16 08:00 A 08-Dec-17 00:00 A 100% 100%
Close Drain 640.00 25-Feb-17 08:00 A 13-Dec-17 00:00 A 100% 100%
Fire Proofing 1440.00 16-Jun-17 08:00 A 18-Dec-17 17:00 A 100% 100%
CVS-Steel Structure
Structu 1956.00 29-Jul-16 08:00 A 08-Dec-17 17:00 A 100% 100%
C1211CVS9000 CVS-Steel Structure(Manhours) 632.00 29-Jul-16 08:00 A 08-Dec-17 17:00 A 100% 100%
Erection of Main SSteel Structure 1648.00 29-Jul-16 08:00 A 02-Aug-17 17:00 A 100% 100%
Erection of RCK Steel Work 920.40 29-Jul-16 08:00 A 28-Jul-17 17:00 A 100% 100%
Erection of STR Steel Structure 824.00 01-Dec-16 08:00 A 02-Aug-17 17:00 A 100% 100%
Erection of Light Steel
S Structure(stair,ladder,platform,handrail) 1180.00 08-Oct-16 08:00 A 08-Dec-17 17:00 A 100% 100%
Erection of Light Steel Structure(stair,ladder,platform,handrail) 1180.00 08-Oct-16 08:00 A 08-Dec-17 17:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 2792.00 24-Oct-16 08:00 A 29-Mar-18 17:00 A 100% 100%
C1211MEC0000 Mechanical/Machinery/Heaters & Boilers(Manhours) 864.00 17-Mar-17 00:00 A 16-Mar-18 17:00 A 100% 100%
Equipment Installation
Installa 2496.00 24-Oct-16 08:00 A 16-Mar-18 17:00 A 100% 100%
Heater 930.00 11-Mar-17 08:00 A 16-Mar-18 17:00 A 100% 100%
Reactor 800.00 21-Feb-17 08:00 A 21-Jul-17 08:00 A 100% 100%
Air Cooler 1632.00 31-Dec-16 08:00 A 06-Oct-17 00:00 A 100% 100%
Column 1776.00 25-Oct-16 08:00 A 29-Sep-17 00:00 A 100% 100%
Drum 984.00 24-Oct-16 08:00 A 18-Oct-17 00:00 A 100% 100%
Heat Exchanger 1032.00 21-Feb-17 08:00 A 19-Oct-17 00:00 A 100% 100%
Filter 120.00 03-Jul-17 00:00 A 16-Aug-17 00:00 A 100% 100%
Crane /Hoist 360.00 01-Apr-17 00:00 A 16-Jun-17 00:00 A 100% 100%
Trays & Internals 664.00 28-Aug-17 00:00 A 29-Mar-18 17:00 A 100% 100%
Trays & Internals 664.00 28-Aug-17 00:00 A 29-Mar-18 17:00 A 100% 100%
Rotating 1232.00 11-Mar-17 08:00 A 19-Jan-18 17:00 A 100% 100%
C1211ROT0000 Rotating(Manhours) 848.00 23-May-17 00:00 A 13-Nov-17 17:00 A 100% 100%
Rotating 864.00 11-Mar-17 08:00 A 19-Jan-18 17:00 A 100% 100%
Compressor 696.00 11-Mar-17 08:00 A 13-Nov-17 17:00 A 100% 100%
Pump 864.00 18-Mar-17 00:00 A 19-Jan-18 17:00 A 100% 100%
Piping 3920.00 01-Aug-16 08:00 A 07-Jul-18 17:00 100% 99.76%
C1211PIP0000 Piping(Manhours) 3712.00 01-Aug-16 08:00 A 07-Jul-18 17:00 100% 0%
U/G Piping 2008.00 24-Sep-16 00:00 A 12-Aug-17 00:00 A 100% 100%
Accidently Oily Contaminated
C 1808.00 06-Nov-16 08:00 A 05-Aug-17 00:00 A 100% 100%
Continuous Oily Contaminated 640.00 08-Oct-16 08:00 A 05-Aug-17 00:00 A 100% 100%
Cooling Water Return
R / Cooling Water Supply 1744.00 15-Oct-16 08:00 A 10-May-17 00:00 A 100% 100%
Fire Fighting Water
Wa 1536.00 24-Sep-16 00:00 A 12-Aug-17 00:00 A 100% 100%
A/G Piping 3920.00 01-Aug-16 08:00 A 07-Jul-18 17:00 100% 99.82%
Carbon Steel Piping
Pip 3752.00 01-Aug-16 08:00 A 07-Jul-18 17:00 100% 99.82%
Stainless Steel Piping
P 3072.00 04-Dec-16 08:00 A 05-Jul-18 17:00 100% 99.82%
Alloy Steel Piping 3272.00 04-Oct-16 08:00 A 06-Jul-18 17:00 100% 99.82%
Duplex 22Cr Piping
Pip 1696.00 17-Apr-17 08:00 A 02-Jul-18 17:00 100% 99.82%

Remaining Level of Effort Actual Work Critical Remaining ... Page 80 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Piping Support 2840.00 04-Jan-17 08:00 A 06-Jul-18 17:00 100% 98%


Piping Support 2840.00 04-Jan-17 08:00 A 06-Jul-18 17:00 100% 98%
Electrical 3376.00 15-Nov-16 08:00 A 25-Apr-18 17:00 A 100% 100%
C1211ELE0000 Electrical(Manhours) 3176.00 15-Nov-16 08:00 A 25-Apr-18 17:00 A 100% 100%
Electrical 3376.00 15-Nov-16 08:00 A 25-Apr-18 17:00 A 100% 100%
Cable Ladder 490.00 19-Jan-17 08:00 A 29-Nov-17 00:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 1064.00 24-Apr-17 00:00 A 25-Apr-18 17:00 A 100% 100%
Elec. Field Equipment
Equip 1160.00 20-Mar-17 00:00 A 25-Apr-18 17:00 A 100% 100%
Wiring 1040.00 03-Oct-17 08:00 A 19-Apr-18 17:00 A 100% 100%
Lighting System 1464.00 27-Apr-17 08:00 A 25-Apr-18 17:00 A 100% 100%
Earthing System 1600.00 15-Nov-16 08:00 A 22-Dec-17 17:00 A 100% 100%
Cathodic Protection
Protect System 176.00 18-Feb-17 08:00 A 17-Jun-17 17:00 A 100% 100%
Heat Tracing 480.00 24-Jun-17 08:00 A 11-Aug-17 17:00 A 100% 100%
Instrumentation an
and Control 3000.00 18-Feb-17 08:00 A 10-Jul-18 17:00 100% 93.19%
C1211INC0000 Instrumentation and Control(Manhours) 2272.00 18-Feb-17 08:00 A 05-Jun-18 17:00 100% 0%
Instrumentation a
and Control 3000.00 18-Feb-17 08:00 A 10-Jul-18 17:00 100% 93.19%
Cable Tray 1824.00 18-Feb-17 08:00 A 06-Jul-18 17:00 100% 99.25%
Cabling 1256.00 09-Jul-17 00:00 A 23-Mar-18 00:00 A 100% 100%
Field Instrument 1424.00 01-Jun-17 00:00 A 09-Jun-18 17:00 100% 84.17%
Junction Boxes 1112.00 28-Apr-17 00:00 A 12-Jan-18 00:00 A 100% 100%
Wiring 1184.00 01-Sep-17 00:00 A 10-Jul-18 17:00 100% 94.04%
PIP/MEC Insulation 1872.00 05-Jun-17 08:00 A 08-Aug-18 15:00 100% 68.1%
C1211INS0000 PIP/MEC Insulation(Manhours) 1872.00 05-Jun-17 08:00 A 08-Aug-18 15:00 100% 0%
Insulation of Equip
Equipment 1104.00 05-Jun-17 08:00 A 19-Jan-18 17:00 A 100% 100%
Insulation of Equipment
Equ 1104.00 05-Jun-17 08:00 A 19-Jan-18 17:00 A 100% 100%
Insulation of Pipes 616.00 11-Sep-17 00:00 A 08-Aug-18 15:00 100% 58.38%
Insulation of Pipes
Pipe 616.00 11-Sep-17 00:00 A 08-Aug-18 15:00 100% 58.38%
Navigation and Telecommunications
Te 640.00 18-Sep-17 00:00 A 24-Jul-18 17:00 100% 69.48%
Navigation and Telecommunications
Te 640.00 18-Sep-17 00:00 A 24-Jul-18 17:00 100% 69.48%
Navigation and Telecommunications
T 640.00 18-Sep-17 00:00 A 24-Jul-18 17:00 100% 69.48%
Precommissioning 2448.00 19-May-17 08:00 A 22-Aug-18 17:00 99.78% 72.75%
C1211GEN0000 Precommissioning(Manhours) 1808.00 19-May-17 08:00 A 22-Aug-18 17:00 99.06% 0%
Precommissioning 2066.00 19-May-17 08:00 A 22-Aug-18 17:00 99.78% 72.75%
Pre Commissioning
Commission for 1211 2066.00 19-May-17 08:00 A 22-Aug-18 17:00 99.78% 72.75%
MC for 1211 0.00 22-Aug-18 17:00 22-Aug-18 17:00 0% 0%
1212 - ARDS - Atmospheric
Atm Residue Desulphurization 6648.00 16-Dec-15 08:00 A 14-Aug-18 17:00 99.87% 95.87%
CVS-Civil Works 5928.00 16-Dec-15 08:00 A 04-Jun-18 17:00 100% 99.58%
C1212CVS0000 CVS-Civil Works(Manhours) 5568.00 28-Dec-15 08:00 A 18-Dec-17 17:00 A 100% 100%
Soil Improvement 1112.00 16-Dec-15 08:00 A 28-Apr-16 17:00 A 100% 100%
Piling 944.00 16-Dec-15 08:00 A 07-Apr-16 17:00 A 100% 100%
Test 688.00 04-Mar-16 08:00 A 28-Apr-16 17:00 A 100% 100%
Foundation 2952.00 14-Mar-16 08:00 A 14-Apr-17 17:00 A 100% 100%
Foundation for Piperacks
P 808.00 14-Mar-16 08:00 A 03-Feb-17 17:00 A 100% 100%
Foundation for Column
C 856.00 06-Jul-16 08:00 A 19-Sep-16 17:00 A 100% 100%
Foundation for Drum
D 856.00 01-Aug-16 08:00 A 17-Feb-17 17:00 A 100% 100%
Foundation for Steel
S Structure 1728.00 25-Apr-16 08:00 A 30-Dec-16 17:00 A 100% 100%
Foundation for Pump
P 856.00 16-Oct-16 08:00 A 13-Jan-17 17:00 A 100% 100%
Foundation for Heater
H 608.00 01-Jul-16 08:00 A 23-Sep-16 17:00 A 100% 100%
Foundation for Exchange
E 544.00 15-Jul-16 08:00 A 14-Apr-17 17:00 A 100% 100%
Foundation for Filter
F 344.00 24-Sep-16 08:00 A 03-Feb-17 17:00 A 100% 100%
Foundation for Compressor
C 1352.00 01-Aug-16 08:00 A 30-Dec-16 17:00 A 100% 100%
Road,Yards,Paving
Road,Yards,Pavin 2104.00 05-Oct-16 08:00 A 04-Jun-18 17:00 100% 98.51%
Road 1600.00 05-Oct-16 08:00 A 04-Jun-18 17:00 100% 92.3%
Light Duty Paving 984.00 25-Mar-17 00:00 A 21-Dec-17 17:00 A 100% 100%
Heavy Duty Paving
Pav 1216.00 11-Feb-17 08:00 A 23-Jun-17 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 81 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Pool,Drainage,Ca
Pool,Drainage,Cable Trench/Slab, Fire Proofing 4056.00 24-Sep-16 08:00 A 19-Jan-18 00:00 A 100% 100%
Drainage Pit 968.00 24-Sep-16 08:00 A 30-Jun-17 17:00 A 100% 100%
Cable Trench/Sla
Trench/Slab (E&I) 480.00 28-Nov-16 08:00 A 19-Jan-18 00:00 A 100% 100%
Close Drain 560.00 11-Feb-17 08:00 A 20-Nov-17 17:00 A 100% 100%
Fire Proofing 1192.00 01-Jul-17 08:00 A 18-Dec-17 17:00 A 100% 100%
CVS-Steel Structure
Structu 1982.00 01-Aug-16 08:00 A 28-Apr-18 08:00 100% 100%
C1212CVS9000 CVS-Steel Structure(Manhours) 80.00 01-Aug-16 08:00 A 28-Apr-18 08:00 100% 0%
Erection of Main SSteel Structure 1920.00 01-Aug-16 08:00 A 17-Aug-17 17:00 A 100% 100%
Erection of STR Steel Structure 1048.00 01-Jan-17 08:00 A 17-Aug-17 17:00 A 100% 100%
Erection of RCK Steel Work 1248.00 01-Aug-16 08:00 A 17-Aug-17 17:00 A 100% 100%
Erection of Light Steel
S Structure(stair,ladder,platform,handrail) 1134.00 08-Oct-16 08:00 A 08-Dec-17 17:00 A 100% 100%
Erection of Light Steel Structure(stair,ladder,platform,handrail) 1134.00 08-Oct-16 08:00 A 08-Dec-17 17:00 A 100% 100%
Mechanical/Machinery/Heaters & Boilers
Mechanical/Machin 2816.00 24-Oct-16 08:00 A 11-Jun-18 17:00 100% 99.52%
C1212MEC0000 Mechanical/Machinery/Heaters & Boilers(Manhours) 1248.00 26-Feb-17 08:00 A 05-Nov-17 17:00 A 100% 100%
Equipment Installation
Installa 2656.00 24-Oct-16 08:00 A 11-Dec-17 17:00 A 100% 100%
Heater 1008.00 11-Mar-17 08:00 A 05-Nov-17 17:00 A 100% 100%
Reactor 920.00 26-Feb-17 08:00 A 31-Jul-17 17:00 A 100% 100%
Air Cooler 1264.00 18-Dec-16 08:00 A 16-Sep-17 17:00 A 100% 100%
Column 2088.00 24-Oct-16 08:00 A 16-Sep-17 17:00 A 100% 100%
Drum 768.00 24-Oct-16 08:00 A 11-Dec-17 17:00 A 100% 100%
Heat Exchanger 1088.00 11-Feb-17 08:00 A 20-Oct-17 17:00 A 100% 100%
Filter 168.00 21-Jun-17 00:00 A 10-Aug-17 17:00 A 100% 100%
Crane /Hoist 856.00 14-Apr-17 00:00 A 16-Jun-17 17:00 A 100% 100%
Trays & Internals 688.00 28-Aug-17 00:00 A 11-Jun-18 17:00 100% 96.03%
Trays & Internals 688.00 28-Aug-17 00:00 A 11-Jun-18 17:00 100% 96.03%
Rotating 1376.00 09-Mar-17 08:00 A 19-Jan-18 17:00 A 100% 100%
C1212ROT0000 Rotating(Manhours) 1080.00 12-May-17 00:00 A 08-Nov-17 17:00 A 100% 100%
Rotating 1256.00 09-Mar-17 08:00 A 19-Jan-18 17:00 A 100% 100%
Compressor 1136.00 09-Mar-17 08:00 A 16-Nov-17 17:00 A 100% 100%
Pump 960.00 24-Mar-17 00:00 A 19-Jan-18 17:00 A 100% 100%
Piping 3952.00 01-Sep-16 08:00 A 07-Jul-18 17:00 100% 99.77%
C1212PIP0000 Piping(Manhours) 3072.00 19-Sep-16 08:00 A 06-Jul-18 17:00 100% 0%
U/G Piping 2320.00 01-Sep-16 08:00 A 15-Nov-17 17:00 A 100% 100%
Accidently Oily Contaminated
C 2176.00 01-Sep-16 08:00 A 18-Sep-17 17:00 A 100% 100%
Continuous Oily Contaminated 640.00 22-Oct-16 08:00 A 13-Aug-17 17:00 A 100% 100%
Cooling Water Return
R / Cooling Water Supply 2096.00 15-Oct-16 08:00 A 07-Apr-17 17:00 A 100% 100%
Fire Fighting Water
Wa 664.00 08-Oct-16 08:00 A 15-Nov-17 17:00 A 100% 100%
A/G Piping 3864.00 19-Sep-16 08:00 A 07-Jul-18 17:00 100% 99.83%
Carbon Steel Piping
Pip 3328.00 19-Sep-16 08:00 A 07-Jul-18 17:00 100% 99.83%
Stainless Steel Piping
P 3192.00 07-Dec-16 08:00 A 07-Jul-18 17:00 100% 99.83%
Alloy Steel Piping 2888.00 04-Dec-16 08:00 A 07-Jul-18 17:00 100% 99.83%
Duplex 22Cr Piping
Pip 1744.00 20-Apr-17 08:00 A 06-Jul-18 17:00 100% 99.83%
Piping Support 3008.00 27-Oct-16 08:00 A 06-Jul-18 17:00 100% 98%
Piping Support 3008.00 27-Oct-16 08:00 A 06-Jul-18 17:00 100% 98%
Electrical 3672.00 28-Nov-16 08:00 A 27-Apr-18 17:00 A 100% 100%
C1212ELE0000 Electrical(Manhours) 3104.00 28-Nov-16 08:00 A 18-Aug-17 17:00 A 100% 100%
Electrical 3672.00 28-Nov-16 08:00 A 27-Apr-18 17:00 A 100% 100%
Cable Ladder 1088.00 11-Jan-17 00:00 A 29-Nov-17 00:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 1184.00 20-Mar-17 08:00 A 25-Apr-18 17:00 A 100% 100%
Elec. Field Equipment
Equip 1456.00 06-Mar-17 00:00 A 26-Apr-18 17:00 A 100% 100%
Wiring 1432.00 03-Oct-17 00:00 A 25-Apr-18 17:00 A 100% 100%
Lighting System 1080.00 03-Mar-17 00:00 A 27-Apr-18 17:00 A 100% 100%
Earthing System 1600.00 28-Nov-16 08:00 A 22-Dec-17 17:00 A 100% 100%
Cathodic Protection
Protect System 808.00 03-Dec-16 08:00 A 17-Jun-17 17:00 A 100% 100%
Heat Tracing 376.00 01-Jul-17 08:00 A 18-Aug-17 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 82 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Instrumentation an
and Control 2536.00 20-Apr-17 00:00 A 31-Jul-18 17:00 100% 93.51%
C1212INC0000 Instrumentation and Control(Manhours) 2240.00 25-Apr-17 00:00 A 31-Jul-18 17:00 100% 0%
Instrumentation a
and Control 2528.00 20-Apr-17 00:00 A 31-Jul-18 17:00 100% 93.51%
Cable Tray 1768.00 25-Apr-17 00:00 A 28-Apr-18 08:00 100% 98.8%
Cabling 1296.00 15-May-17 00:00 A 28-Apr-18 08:00 100% 100%
Field Instrument 1432.00 01-Jun-17 00:00 A 05-Jul-18 17:00 100% 83.47%
Junction Boxes 1368.00 20-Apr-17 00:00 A 09-Feb-18 00:00 A 100% 100%
Wiring 1112.00 06-Sep-17 00:00 A 31-Jul-18 17:00 100% 95.03%
PIP/MEC Insulation 2704.00 16-May-17 08:00 A 07-Jul-18 17:00 100% 71.75%
C1212INS0000 PIP/MEC Insulation(Manhours) 1616.00 26-May-17 08:00 A 07-Jul-18 17:00 100% 0%
Insulation of Equip
Equipment 2056.00 16-May-17 08:00 A 19-Jan-18 17:00 A 100% 100%
Insulation of Equipment
Equ 2056.00 16-May-17 08:00 A 19-Jan-18 17:00 A 100% 100%
Insulation of Pipes 880.00 11-Sep-17 00:00 A 07-Jul-18 17:00 100% 63.14%
Insulation of Pipes
Pipe 880.00 11-Sep-17 00:00 A 07-Jul-18 17:00 100% 63.14%
Navigation and Telecommunications
Te 640.00 18-Sep-17 00:00 A 04-Jun-18 17:00 100% 69.04%
Navigation and Telecommunications
Te 640.00 18-Sep-17 00:00 A 04-Jun-18 17:00 100% 69.04%
Navigation and Telecommunications
T 640.00 18-Sep-17 00:00 A 04-Jun-18 17:00 100% 69.04%
Precommissioning 2424.00 18-May-17 08:00 A 14-Aug-18 17:00 96.89% 72.75%
C1212GEN0000 Precommissioning(Manhours) 2224.00 18-May-17 08:00 A 14-Aug-18 17:00 89.11% 0%
Precommissioning 2136.00 18-May-17 08:00 A 14-Aug-18 17:00 96.89% 72.75%
Pre Commissioning
Commission for 1212 2136.00 18-May-17 08:00 A 14-Aug-18 17:00 96.89% 72.75%
MC for 1212 0.00 14-Aug-18 17:00 14-Aug-18 17:00 0% 0%
Electrical Substation 5096.00 28-Dec-15 08:00 A 05-May-18 17:00 100% 99.33%
6850-SUB-111 4688.00 06-Jan-16 08:00 A 03-May-18 17:00 100% 99.24%
CVS-Civil Works 3816.00 06-Jan-16 08:00 A 18-Oct-17 00:00 A 100% 100%
CS111CVS0000 CVS-Civil Works(Manhours) 3800.00 06-Jan-16 08:00 A 18-Oct-17 00:00 A 100% 100%
Soil Improvement 576.00 06-Jan-16 08:00 A 01-Apr-16 17:00 A 100% 100%
PILLING 384.00 06-Jan-16 08:00 A 25-Feb-16 00:00 A 100% 100%
TEST 176.00 10-Feb-16 08:00 A 01-Apr-16 17:00 A 100% 100%
Building 3016.00 03-May-16 08:00 A 18-Oct-17 00:00 A 100% 100%
Foundations & Structures
S 688.00 03-May-16 08:00 A 13-Jan-17 17:00 A 100% 100%
Building U/G Piping
Pip 392.00 25-Jan-17 08:00 A 03-Feb-17 17:00 A 100% 100%
Architecture 1280.00 03-Dec-16 08:00 A 16-Oct-17 00:00 A 100% 100%
Cable Trench/Slab
Trench/Sla 960.00 25-Jan-17 08:00 A 03-Feb-17 17:00 A 100% 100%
HVAC 640.00 02-Jan-17 08:00 A 18-Oct-17 00:00 A 100% 100%
Building Electrical 504.00 22-Jan-17 08:00 A 01-Jul-17 00:00 A 100% 100%
Electrical 664.00 01-Mar-17 00:00 A 16-Apr-18 17:00 A 100% 100%
CS111ELE0000 Electrical(Manhours) 536.00 10-Mar-17 00:00 A 16-Apr-18 08:00 A 100% 100%
Electrical 664.00 01-Mar-17 00:00 A 16-Apr-18 17:00 A 100% 100%
Installation of Ele
Electrical Equipment 560.00 10-Mar-17 00:00 A 16-Apr-18 17:00 A 100% 100%
Cable Ladder 456.00 01-Mar-17 00:00 A 18-Aug-17 00:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 384.00 02-May-17 08:00 A 11-Nov-17 00:00 A 100% 100%
Wring 168.00 13-Sep-17 00:00 A 03-Nov-17 00:00 A 100% 100%
Navigation and Telecommunications-6850
Te 592.00 31-May-17 00:00 A 24-Apr-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
Te 592.00 31-May-17 00:00 A 24-Apr-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
T 592.00 31-May-17 00:00 A 24-Apr-18 17:00 A 100% 100%
Precommissioning 680.00 21-Sep-17 08:00 A 03-May-18 17:00 100% 70.1%
CS111GEN0000 Precommissioning(Manhours) 0.00 21-Sep-17 08:00 A 03-May-18 17:00 100% 0%
Navigation and Telecommunications
Te 120.00 15-Mar-18 00:00 A 03-May-18 17:00 100% 4%
Navigation and Telecommunications
T TEST 120.00 15-Mar-18 00:00 A 03-May-18 17:00 100% 4%
BUILDING 488.00 21-Sep-17 08:00 A 03-May-18 17:00 100% 95%
HVAC & Building Electrical TEST 488.00 21-Sep-17 08:00 A 03-May-18 17:00 100% 95%
Equipment Funda
Fundation test & Withstand voltage test 336.00 16-Jan-18 00:00 A 03-May-18 17:00 100% 50%
Equipment Fund
Fundation test & Withstand voltage test 336.00 16-Jan-18 00:00 A 03-May-18 17:00 100% 50%
MC for S111 (P40
(P40,T0+45,2018/4/30) 0.00 03-May-18 17:00 03-May-18 17:00 0% 0%

Remaining Level of Effort Actual Work Critical Remaining ... Page 83 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

MC for S111 (P4


(P40,T0+45,2018/4/30) 0.00 03-May-18 17:00 03-May-18 17:00 0% 0%
6850-SUB-121 6272.00 28-Dec-15 08:00 A 05-May-18 17:00 100% 99.36%
CVS-Civil Works 4528.00 28-Dec-15 08:00 A 17-Oct-17 00:00 A 100% 100%
CS121CVS0000 CVS-Civil Works(Manhours) 3704.00 28-Dec-15 08:00 A 12-Oct-17 00:00 A 100% 100%
Soil Improvement 544.00 28-Dec-15 08:00 A 22-Apr-16 17:00 A 100% 100%
PILLING 384.00 28-Dec-15 08:00 A 17-Feb-16 00:00 A 100% 100%
TEST 176.00 25-Feb-16 00:00 A 22-Apr-16 17:00 A 100% 100%
Building 3536.00 19-May-16 08:00 A 17-Oct-17 00:00 A 100% 100%
Foundations & Structures
S 688.00 19-May-16 08:00 A 02-Apr-17 00:00 A 100% 100%
Building U/G Piping
Pip 480.00 21-Jan-17 08:00 A 24-Feb-17 17:00 A 100% 100%
Architecture 1264.00 07-Jan-17 08:00 A 17-Oct-17 00:00 A 100% 100%
Cable Trench/Slab
Trench/Sla 992.00 04-Feb-17 08:00 A 10-Feb-17 17:00 A 100% 100%
HVAC 640.00 15-Mar-17 08:00 A 12-Oct-17 00:00 A 100% 100%
Building Electrical 1368.00 13-Jan-17 08:00 A 10-Sep-17 00:00 A 100% 100%
Electrical 1808.00 15-Mar-17 00:00 A 26-Apr-18 17:00 A 100% 100%
CS121ELE0000 Electrical(Manhours) 1560.00 15-Apr-17 00:00 A 16-Apr-18 08:00 A 100% 100%
Electrical 1424.00 15-Mar-17 00:00 A 26-Apr-18 17:00 A 100% 100%
Installation of Ele
Electrical Equipment 1176.00 15-Apr-17 00:00 A 26-Apr-18 17:00 A 100% 100%
Cable Ladder 528.00 15-Mar-17 00:00 A 28-Dec-17 17:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 704.00 01-Sep-17 00:00 A 01-Dec-17 00:00 A 100% 100%
Wring 360.00 28-Sep-17 00:00 A 10-Jan-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
Te 592.00 31-May-17 00:00 A 25-Apr-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
Te 592.00 31-May-17 00:00 A 25-Apr-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
T 592.00 31-May-17 00:00 A 25-Apr-18 17:00 A 100% 100%
Precommissioning 1224.00 21-Sep-17 08:00 A 05-May-18 17:00 100% 75.1%
CS121GEN0000 Precommissioning(Manhours) 368.00 21-Sep-17 08:00 A 05-May-18 17:00 100% 0%
Navigation and Telecommunications
Te 120.00 15-Mar-18 00:00 A 04-May-18 17:00 100% 4%
Navigation and Telecommunications
T TEST 120.00 15-Mar-18 00:00 A 04-May-18 17:00 100% 4%
BUILDING 488.00 21-Sep-17 08:00 A 05-May-18 17:00 100% 95%
HVAC & Building Electrical TEST 488.00 21-Sep-17 08:00 A 05-May-18 17:00 100% 95%
Equipment Funda
Fundation test & Withstand voltage test 336.00 01-Jan-18 00:00 A 05-May-18 17:00 100% 70%
Equipment Fund
Fundation test & Withstand voltage test 336.00 01-Jan-18 00:00 A 05-May-18 17:00 100% 70%
MC for S121 (P40
(P40,T0+45,2018/4/30) 0.00 05-May-18 17:00 05-May-18 17:00 0% 0%
MC for S121 (P4
(P40,T0+45,2018/4/30) 0.00 05-May-18 17:00 05-May-18 17:00 0% 0%
6850-SUB-122 6128.00 05-Jan-16 08:00 A 04-May-18 17:00 100% 99.36%
CVS-Civil Works 4352.00 05-Jan-16 08:00 A 18-Sep-17 00:00 A 100% 100%
CS122CVS0000 CVS-Civil Works(Manhours) 3720.00 05-Jan-16 08:00 A 18-Sep-17 00:00 A 100% 100%
Soil Improvement 512.00 05-Jan-16 08:00 A 15-Apr-16 17:00 A 100% 100%
PILLING 384.00 05-Jan-16 08:00 A 10-Feb-16 17:00 A 100% 100%
TEST 176.00 25-Feb-16 00:00 A 15-Apr-16 17:00 A 100% 100%
Building 3584.00 18-Apr-16 08:00 A 18-Sep-17 00:00 A 100% 100%
Foundations & Structures
S 768.00 18-Apr-16 08:00 A 13-Jan-17 17:00 A 100% 100%
Building U/G Piping
Pip 392.00 18-Jan-17 08:00 A 03-Feb-17 17:00 A 100% 100%
Architecture 1280.00 13-Dec-16 08:00 A 15-Sep-17 00:00 A 100% 100%
Cable Trench/Slab
Trench/Sla 960.00 27-Jan-17 08:00 A 03-Feb-17 17:00 A 100% 100%
HVAC 640.00 27-Feb-17 08:00 A 18-Sep-17 00:00 A 100% 100%
Building Electrical 496.00 30-Jan-17 08:00 A 16-Sep-17 00:00 A 100% 100%
Electrical 2768.00 15-Mar-17 00:00 A 26-Apr-18 17:00 A 100% 100%
CS122ELE0000 Electrical(Manhours) 1464.00 10-Apr-17 08:00 A 16-Apr-18 08:00 A 100% 100%
Electrical 2120.00 15-Mar-17 00:00 A 26-Apr-18 17:00 A 100% 100%
Installation of Ele
Electrical Equipment 1080.00 10-Apr-17 08:00 A 26-Apr-18 17:00 A 100% 100%
Cable Ladder 528.00 15-Mar-17 00:00 A 13-Sep-17 00:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 104.00 18-Aug-17 00:00 A 11-Nov-17 00:00 A 100% 100%
Wring 96.00 28-Sep-17 00:00 A 10-Jan-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
Te 592.00 31-May-17 00:00 A 24-Apr-18 17:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 84 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Navigation and Telecommunications-6850


Te 592.00 31-May-17 00:00 A 24-Apr-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
T 592.00 31-May-17 00:00 A 24-Apr-18 17:00 A 100% 100%
Precommissioning 1856.00 21-Sep-17 08:00 A 04-May-18 17:00 100% 75.1%
CS122GEN0000 Precommissioning(Manhours) 1184.00 21-Sep-17 08:00 A 04-May-18 17:00 100% 0%
Navigation and Telecommunications
Te 120.00 14-Mar-18 00:00 A 30-Apr-18 17:00 100% 4%
Navigation and Telecommunications
T TEST 120.00 14-Mar-18 00:00 A 30-Apr-18 17:00 100% 4%
BUILDING 488.00 21-Sep-17 08:00 A 04-May-18 17:00 100% 95%
HVAC & Building Electrical TEST 488.00 21-Sep-17 08:00 A 04-May-18 17:00 100% 95%
Equipment Funda
Fundation test & Withstand voltage test 336.00 03-Jan-18 00:00 A 04-May-18 17:00 100% 70%
Equipment Fund
Fundation test & Withstand voltage test 336.00 03-Jan-18 00:00 A 04-May-18 17:00 100% 70%
MC for S122 (P40
(P40,T0+45,2018/4/30) 0.00 04-May-18 17:00 04-May-18 17:00 0% 0%
MC for S122 (P4
(P40,T0+45,2018/4/30) 0.00 04-May-18 17:00 04-May-18 17:00 0% 0%
6850-SUB-152 5840.00 06-Jan-16 08:00 A 03-May-18 17:00 100% 99.36%
CVS-Civil Works 4256.00 06-Jan-16 08:00 A 16-Sep-17 00:00 A 100% 100%
CS152CVS0000 CVS-Civil Works(Manhours) 3720.00 06-Jan-16 08:00 A 16-Sep-17 00:00 A 100% 100%
Soil Improvement 512.00 06-Jan-16 08:00 A 22-Apr-16 17:00 A 100% 100%
PILLING 320.00 06-Jan-16 08:00 A 20-Jan-16 17:00 A 100% 100%
TEST 176.00 25-Feb-16 00:00 A 22-Apr-16 17:00 A 100% 100%
Building 3488.00 25-Apr-16 08:00 A 16-Sep-17 00:00 A 100% 100%
Foundations & Structures
S 704.00 25-Apr-16 08:00 A 06-Jan-17 17:00 A 100% 100%
Building U/G Piping
Pip 1280.00 04-Feb-17 08:00 A 10-Feb-17 17:00 A 100% 100%
Architecture 1280.00 12-Dec-16 08:00 A 11-Sep-17 00:00 A 100% 100%
Cable Trench/Slab
Trench/Sla 960.00 04-Feb-17 08:00 A 10-Feb-17 17:00 A 100% 100%
HVAC 640.00 11-Feb-17 08:00 A 16-Sep-17 00:00 A 100% 100%
Building Electrical 536.00 04-Feb-17 08:00 A 01-Jul-17 17:00 A 100% 100%
Electrical 1288.00 13-Mar-17 00:00 A 25-Apr-18 17:00 A 100% 100%
CS152ELE0000 Electrical(Manhours) 664.00 17-Apr-17 00:00 A 16-Apr-18 08:00 A 100% 100%
Electrical 1288.00 13-Mar-17 00:00 A 25-Apr-18 17:00 A 100% 100%
Installation of Ele
Electrical Equipment 816.00 17-Apr-17 00:00 A 25-Apr-18 17:00 A 100% 100%
Cable Ladder 432.00 13-Mar-17 00:00 A 12-Sep-17 17:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 568.00 14-Aug-17 00:00 A 09-Nov-17 00:00 A 100% 100%
Wring 50.00 03-Oct-17 00:00 A 10-Jan-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
Te 432.00 31-May-17 00:00 A 27-Apr-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
Te 432.00 31-May-17 00:00 A 27-Apr-18 17:00 A 100% 100%
Navigation and Telecommunications-6850
T 432.00 31-May-17 00:00 A 27-Apr-18 17:00 A 100% 100%
Precommissioning 1568.00 21-Sep-17 08:00 A 03-May-18 17:00 100% 75.1%
CS152GEN0000 Precommissioning(Manhours) 1028.00 21-Sep-17 08:00 A 03-May-18 17:00 100% 0%
Navigation and Telecommunications
Te 120.00 27-Mar-18 00:00 A 03-May-18 17:00 100% 4%
Navigation and Telecommunications
T TEST 120.00 27-Mar-18 00:00 A 03-May-18 17:00 100% 4%
BUILDING 488.00 21-Sep-17 08:00 A 03-May-18 17:00 100% 95%
HVAC & Building Electrical TEST 488.00 21-Sep-17 08:00 A 03-May-18 17:00 100% 95%
Equipment Funda
Fundation test & Withstand voltage test 64.00 01-Jan-18 00:00 A 03-May-18 17:00 100% 70%
Equipment Fund
Fundation test & Withstand voltage test 64.00 01-Jan-18 00:00 A 03-May-18 17:00 100% 70%
MC for S152 (P40
(P40,T0+45,2018/4/30) 0.00 03-May-18 17:00 03-May-18 17:00 0% 0%
MC for S152 (P4(P40,T0+45,2018/4/30) 0.00 03-May-18 17:00 03-May-18 17:00 0% 0%
Field Auxiliary Rooms 6160.00 16-Dec-15 08:00 A 04-Jun-18 17:00 100% 98.01%
6750-FAR-111 6152.00 16-Dec-15 08:00 A 02-Jun-18 17:00 100% 98.02%
CVS-Civil Works 4496.00 16-Dec-15 08:00 A 17-Sep-17 00:00 A 100% 100%
CF111CVS0000 CVS-Civil Works(Manhours) 3776.00 16-Dec-15 08:00 A 17-Sep-17 00:00 A 100% 100%
Soil Improvement 440.00 16-Dec-15 08:00 A 08-Mar-16 17:00 A 100% 100%
Piling 280.00 16-Dec-15 08:00 A 04-Mar-16 17:00 A 100% 100%
test 176.00 13-Jan-16 08:00 A 08-Mar-16 17:00 A 100% 100%
Building 3672.00 18-Apr-16 08:00 A 17-Sep-17 00:00 A 100% 100%
Foundations & Structures
S 672.00 18-Apr-16 08:00 A 13-Jan-17 17:00 A 100% 100%
Architecture 1280.00 15-Dec-16 08:00 A 03-Jul-17 00:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 85 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

HVAC 480.00 11-Mar-17 08:00 A 17-Sep-17 00:00 A 100% 100%


Cable Trench/Slab
Trench/Sla 504.00 04-Feb-17 08:00 A 09-Feb-17 17:00 A 100% 100%
Building Electrical 560.00 04-Feb-17 08:00 A 04-Jul-17 00:00 A 100% 100%
Electrical 944.00 01-Jun-17 00:00 A 28-Oct-17 00:00 A 100% 100%
CF111ELE0000 Electrical(Manhours) 456.00 01-Jun-17 00:00 A 27-Oct-17 00:00 A 100% 100%
Electrical 944.00 01-Jun-17 00:00 A 28-Oct-17 00:00 A 100% 100%
Cable Ladder 208.00 01-Jun-17 00:00 A 31-Jul-17 00:00 A 100% 100%
Installation of Ele
Electrical Equipment 144.00 15-Jun-17 00:00 A 28-Oct-17 00:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 320.00 18-Sep-17 00:00 A 27-Oct-17 00:00 A 100% 100%
Instrumentation 968.00 10-Apr-17 00:00 A 08-Dec-17 17:00 A 100% 100%
CF111INC0000 Instrumentation(Manhours) 800.00 10-Apr-17 08:00 A 08-Dec-17 17:00 A 100% 100%
Instrumentation 928.00 10-Apr-17 00:00 A 08-Dec-17 17:00 A 100% 100%
Cable Tray 280.00 10-Apr-17 00:00 A 10-Aug-17 00:00 A 100% 100%
Cabling 640.00 28-Jul-17 00:00 A 04-Nov-17 00:00 A 100% 100%
Instrumentation Equipment(Control Panel) 480.00 10-Apr-17 00:00 A 08-Dec-17 17:00 A 100% 100%
Navigation and Telecommunications-6750
Te 320.00 03-Jul-17 00:00 A 23-May-18 17:00 100% 97%
Navigation and Telecommunications-6750
Te 320.00 03-Jul-17 00:00 A 23-May-18 17:00 100% 97%
Telecommunications system
Telecommunicat 320.00 03-Jul-17 00:00 A 23-May-18 17:00 100% 97%
Precommissioning 1400.00 21-Sep-17 08:00 A 02-Jun-18 17:00 100% 73.85%
CF111GEN0000 Precommissioning(Manhours) 272.00 24-Jan-18 08:00 A 02-Jun-18 17:00 100% 0%
Navigation and Telecommunications
Te 160.00 24-Jan-18 08:00 A 22-May-18 17:00 100% 4%
Navigation and Telecommunications
T TEST 160.00 24-Jan-18 08:00 A 22-May-18 17:00 100% 4%
BUILDING 200.00 21-Sep-17 08:00 A 01-Jun-18 17:00 100% 95%
HVAC & Building Electrical TEST 200.00 21-Sep-17 08:00 A 01-Jun-18 17:00 100% 95%
Instrument 512.00 11-Nov-17 08:00 A 02-Jun-18 17:00 100% 85%
Instrument 512.00 11-Nov-17 08:00 A 02-Jun-18 17:00 100% 85%
MC for F111 (P40
(P40,T0+45,2018/4/30) 0.00 02-Jun-18 17:00 02-Jun-18 17:00 0% 0%
MC for F111 (P4
(P40,T0+45,2018/4/30) 0.00 02-Jun-18 17:00 02-Jun-18 17:00 0% 0%
6750-FAR-121 6112.00 23-Dec-15 08:00 A 04-Jun-18 17:00 100% 98%
CVS-Civil Works 4592.00 23-Dec-15 08:00 A 14-Sep-17 00:00 A 100% 100%
CF121CVS0000 CVS-Civil Works(Manhours) 3680.00 23-Dec-15 08:00 A 14-Sep-17 00:00 A 100% 100%
Soil Improvement 360.00 23-Dec-15 08:00 A 08-Mar-16 17:00 A 100% 100%
test 176.00 13-Jan-16 08:00 A 08-Mar-16 17:00 A 100% 100%
Piling 280.00 23-Dec-15 08:00 A 14-Jan-16 17:00 A 100% 100%
Building 3504.00 18-May-16 08:00 A 14-Sep-17 00:00 A 100% 100%
Foundations & Structures
S 672.00 18-May-16 08:00 A 13-May-17 08:00 A 100% 100%
Architecture 1280.00 31-Dec-16 08:00 A 12-Aug-17 00:00 A 100% 100%
HVAC 440.00 11-Mar-17 08:00 A 14-Sep-17 00:00 A 100% 100%
Cable Trench/Slab
Trench/Sla 472.00 04-Feb-17 08:00 A 09-Feb-17 17:00 A 100% 100%
Building Electrical 104.00 04-Feb-17 08:00 A 06-Jul-17 00:00 A 100% 100%
Electrical 1144.00 01-Jun-17 00:00 A 16-Apr-18 08:00 A 100% 100%
CF121ELE0000 Electrical(Manhours) 472.00 01-Jun-17 00:00 A 16-Apr-18 08:00 A 100% 100%
Electrical 1144.00 01-Jun-17 00:00 A 10-Nov-17 00:00 A 100% 100%
Cable Ladder 432.00 01-Jun-17 08:00 A 28-Jul-17 00:00 A 100% 100%
Installation of Ele
Electrical Equipment 224.00 01-Jun-17 00:00 A 28-Oct-17 00:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 448.00 18-Sep-17 00:00 A 10-Nov-17 00:00 A 100% 100%
Instrumentation 1880.00 01-May-17 00:00 A 28-Apr-18 08:00 100% 100%
CF121INC0000 Instrumentation(Manhours) 1160.00 01-May-17 00:00 A 28-Apr-18 08:00 100% 0%
Instrumentation 1680.00 01-May-17 00:00 A 15-Dec-17 00:00 A 100% 100%
Cable Tray 280.00 01-May-17 00:00 A 10-Aug-17 00:00 A 100% 100%
Cabling 840.00 12-Aug-17 00:00 A 15-Dec-17 00:00 A 100% 100%
Instrumentation Equipment(Control Panel) 480.00 01-May-17 00:00 A 06-Dec-17 00:00 A 100% 100%
Navigation and Telecommunications-6750
Te 320.00 03-Jul-17 00:00 A 02-Jun-18 17:00 100% 96.4%
Navigation and Telecommunications-6750
Te 320.00 03-Jul-17 00:00 A 02-Jun-18 17:00 100% 96.4%
Telecommunications system
Telecommunicat 320.00 03-Jul-17 00:00 A 02-Jun-18 17:00 100% 96.4%

Remaining Level of Effort Actual Work Critical Remaining ... Page 86 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Precommissioning 1432.00 21-Sep-17 08:00 A 04-Jun-18 17:00 100% 73.85%


CF121GEN0000 Precommissioning(Manhours) 520.00 21-Sep-17 08:00 A 04-Jun-18 17:00 100% 0%
Navigation and Telecommunications
Te 160.00 15-Mar-18 00:00 A 02-Jun-18 17:00 100% 4%
Navigation and Telecommunications
T TEST 160.00 15-Mar-18 00:00 A 02-Jun-18 17:00 100% 4%
BUILDING 320.00 21-Sep-17 08:00 A 02-Jun-18 17:00 100% 95%
HVAC & Building Electrical TEST 320.00 21-Sep-17 08:00 A 02-Jun-18 17:00 100% 95%
Instrument 360.00 08-Nov-17 08:00 A 04-Jun-18 17:00 100% 85%
Instrument 360.00 08-Nov-17 08:00 A 04-Jun-18 17:00 100% 85%
MC for F121 (P40
(P40,T0+45,2018/4/30) 0.00 04-Jun-18 17:00 04-Jun-18 17:00 0% 0%
MC for F121 (P4
(P40,T0+45,2018/4/30) 0.00 04-Jun-18 17:00 04-Jun-18 17:00 0% 0%
6750-FAR-122 6160.00 17-Dec-15 08:00 A 04-Jun-18 17:00 100% 98.02%
CVS-Civil Works 4552.00 17-Dec-15 08:00 A 14-Sep-17 17:00 A 100% 100%
CF122CVS0000 CVS-Civil Works(Manhours) 3720.00 17-Dec-15 08:00 A 14-Sep-17 00:00 A 100% 100%
Soil Improvement 696.00 17-Dec-15 08:00 A 22-Apr-16 17:00 A 100% 100%
Test 176.00 04-Mar-16 08:00 A 22-Apr-16 17:00 A 100% 100%
Piling 280.00 17-Dec-15 08:00 A 06-Jan-16 17:00 A 100% 100%
Building 3744.00 15-Apr-16 08:00 A 14-Sep-17 17:00 A 100% 100%
Foundations & Structures
S 672.00 15-Apr-16 08:00 A 23-Dec-16 17:00 A 100% 100%
Architecture 1280.00 03-Dec-16 08:00 A 04-Jul-17 17:00 A 100% 100%
HVAC 392.00 04-Feb-17 08:00 A 14-Sep-17 17:00 A 100% 100%
Cable Trench/Slab
Trench/Sla 280.00 04-Feb-17 08:00 A 09-Feb-17 17:00 A 100% 100%
Building Electrical 456.00 11-Feb-17 08:00 A 03-Jul-17 17:00 A 100% 100%
Electrical 1016.00 01-Jun-17 08:00 A 24-Apr-18 17:00 A 100% 100%
CF122ELE0000 Electrical(Manhours) 448.00 01-Jun-17 08:00 A 16-Apr-18 17:00 A 100% 100%
Electrical 1016.00 01-Jun-17 08:00 A 24-Apr-18 17:00 A 100% 100%
Cable Ladder 432.00 01-Jun-17 08:00 A 01-Aug-17 17:00 A 100% 100%
Installation of Ele
Electrical Equipment 208.00 01-Aug-17 08:00 A 24-Apr-18 17:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 448.00 18-Sep-17 08:00 A 11-Oct-17 17:00 A 100% 100%
Instrumentation 1576.00 05-May-17 08:00 A 20-Dec-17 17:00 A 100% 100%
CF122INC0000 Instrumentation(Manhours) 896.00 05-May-17 08:00 A 20-Dec-17 17:00 A 100% 100%
Instrumentation 1376.00 05-May-17 08:00 A 20-Dec-17 17:00 A 100% 100%
Cable Tray 280.00 05-May-17 08:00 A 01-Aug-17 17:00 A 100% 100%
Cabling 840.00 10-Aug-17 08:00 A 20-Dec-17 17:00 A 100% 100%
Instrumentation Equipment(Control Panel) 480.00 05-May-17 08:00 A 13-Dec-17 17:00 A 100% 100%
Navigation and Telecommunications-6750
Te 320.00 03-Jul-17 08:00 A 23-May-18 17:00 100% 97%
Navigation and Telecommunications-6750
Te 320.00 03-Jul-17 08:00 A 23-May-18 17:00 100% 97%
Telecommunications system
Telecommunicat 320.00 03-Jul-17 08:00 A 23-May-18 17:00 100% 97%
Precommissioning 1288.00 21-Sep-17 08:00 A 04-Jun-18 17:00 100% 73.85%
CF122GEN0000 Precommissioning(Manhours) 160.00 15-Mar-18 08:00 A 04-Jun-18 17:00 100% 0%
Navigation and Telecommunications
Te 160.00 15-Mar-18 08:00 A 04-Jun-18 17:00 100% 4%
Navigation and Telecommunications
T TEST 160.00 15-Mar-18 08:00 A 04-Jun-18 17:00 100% 4%
BUILDING 320.00 21-Sep-17 08:00 A 04-Jun-18 17:00 100% 95%
HVAC & Building Electrical TEST 320.00 21-Sep-17 08:00 A 04-Jun-18 17:00 100% 95%
Instrument 312.00 08-Nov-17 08:00 A 04-Jun-18 17:00 100% 85%
Instrument 312.00 08-Nov-17 08:00 A 04-Jun-18 17:00 100% 85%
MC for F122 (P40
(P40,T0+45,2018/4/30) 0.00 04-Jun-18 17:00 04-Jun-18 17:00 0% 0%
MC for F122 (P4
(P40,T0+45,2018/4/30) 0.00 04-Jun-18 17:00 04-Jun-18 17:00 0% 0%
Operating Shelter Building
Bu 6064.00 28-Dec-15 08:00 A 16-May-18 17:00 100% 94.15%
6760-OSB-101 6064.00 28-Dec-15 08:00 A 16-May-18 17:00 100% 94.15%
CVS-Civil Works 4464.00 28-Dec-15 08:00 A 10-Oct-17 00:00 A 100% 100%
CO101CVS0000 CVS-Civil Works(Manhours) 3760.00 28-Dec-15 08:00 A 14-Sep-17 00:00 A 100% 100%
Soil Improvement 464.00 28-Dec-15 08:00 A 04-Feb-16 17:00 A 100% 100%
test 176.00 13-Jan-16 08:00 A 04-Feb-16 17:00 A 100% 100%
Pilling 280.00 28-Dec-15 08:00 A 20-Jan-16 17:00 A 100% 100%
Building 3736.00 18-Apr-16 08:00 A 10-Oct-17 00:00 A 100% 100%

Remaining Level of Effort Actual Work Critical Remaining ... Page 87 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

Foundations & Structures


S 672.00 18-Apr-16 08:00 A 10-Feb-17 17:00 A 100% 100%
Architecture 1280.00 15-Dec-16 08:00 A 10-Oct-17 00:00 A 100% 100%
HVAC 1088.00 11-Mar-17 08:00 A 14-Sep-17 00:00 A 100% 100%
Cable Trench/Slab
Trench/Sla 712.00 04-Feb-17 08:00 A 10-Feb-17 17:00 A 100% 100%
Building Electrical 712.00 04-Feb-17 08:00 A 13-Sep-17 00:00 A 100% 100%
Electrical 1464.00 01-Jul-17 00:00 A 27-Apr-18 08:00 A 100% 100%
CF122ELE4024 Electrical(Manhours) 304.00 01-Jul-17 00:00 A 26-Apr-18 17:00 A 100% 100%
Electrical 1464.00 01-Jul-17 00:00 A 27-Apr-18 08:00 A 100% 100%
Installation of Ele
Electrical Equipment 88.00 20-Dec-17 08:00 A 27-Apr-18 08:00 A 100% 100%
Cable Ladder 432.00 01-Jul-17 00:00 A 18-Sep-17 00:00 A 100% 100%
Cabling(LV,MV,Control,Lighting)
Cabling(LV,MV,C 496.00 23-Oct-17 08:00 A 01-Nov-17 00:00 A 100% 100%
Instrumentation & Lab 832.00 30-Jun-17 00:00 A 16-May-18 17:00 100% 70%
CO101INC0000 Instrumentation & Lab(Manhours) 0.00 30-Jun-17 00:00 A 16-May-18 17:00 100% 0%
Instrumentation & Lab 832.00 30-Jun-17 00:00 A 16-May-18 17:00 100% 70%
Instrumentation 480.00 30-Jun-17 00:00 A 16-Feb-18 00:00 A 100% 100%
Laboratory Facilities
Facil 256.00 20-Apr-18 08:00 A 16-May-18 17:00 100% 0%
Navigation and Telecommunications-6760
Te 320.00 08-Aug-17 00:00 A 16-May-18 17:00 100% 96.4%
Navigation and Telecommunications-6750
Te 320.00 08-Aug-17 00:00 A 16-May-18 17:00 100% 96.4%
Telecommunications system
Telecommunicat 320.00 08-Aug-17 00:00 A 16-May-18 17:00 100% 96.4%
Precommissioning 1600.00 21-Sep-17 08:00 A 16-May-18 17:00 100% 67.81%
CO101GEN0000 Precommissioning(Manhours) 200.00 22-Mar-18 00:00 A 16-May-18 17:00 100% 0%
Navigation and Telecommunications
Te 200.00 22-Mar-18 00:00 A 16-May-18 17:00 100% 4%
Navigation and Telecommunications
T TEST 200.00 22-Mar-18 00:00 A 16-May-18 17:00 100% 4%
BUILDING 320.00 21-Sep-17 08:00 A 23-Feb-18 17:00 A 100% 100%
HVAC & Building Electrical TEST 320.00 21-Sep-17 08:00 A 23-Feb-18 17:00 A 100% 100%
Electrical 400.00 08-Nov-17 08:00 A 23-Feb-18 17:00 A 100% 100%
Electrical Test 400.00 08-Nov-17 08:00 A 23-Feb-18 17:00 A 100% 100%
Instrument 192.00 27-Oct-17 08:00 A 16-May-18 17:00 100% 85%
Instrument 192.00 27-Oct-17 08:00 A 16-May-18 17:00 100% 85%
MC for O101 (P4(P40,T0+45,2018/4/30) 0.00 16-May-18 17:00 16-May-18 17:00 0% 0%
MC for O101 (P (P40,T0+45,2018/4/30) 0.00 16-May-18 17:00 16-May-18 17:00 0% 0%
Commisioning 3152.00 24-Apr-18 08:00 A 31-May-19 17:00 1.72% 1.45%
CDU - Crude Distillation
Distilla Unit 2392.00 24-Apr-18 08:00 A 02-Apr-19 17:00 4.3% 5.04%
1110 - CDU - Crude Distillation Unit 2392.00 24-Apr-18 08:00 A 02-Apr-19 17:00 4.3% 5.04%
System 2392.00 24-Apr-18 08:00 A 02-Apr-19 17:00 4.3% 5.04%
Subsystem 2392.00 24-Apr-18 08:00 A 02-Apr-19 17:00 4.3% 5.04%
Commissioning for f 1110 384.00 24-Apr-18 08:00 A 03-Sep-18 17:00 4.32% 5.22%
RFSU & Provisional
Provisio Acceptance for 1110 (C26,T0+51,2018/10/30) 2392.00 08-Jun-18 08:00 02-Apr-19 17:00 3.67% 0%
HCDU - Hydrogen Collection
C & Distribution 2496.00 11-Jul-18 08:00 18-May-19 17:00 4.21% 0%
1520 - HCDU - HydHydrogen Collection & Distribution 2496.00 11-Jul-18 08:00 18-May-19 17:00 4.21% 0%
System 2496.00 11-Jul-18 08:00 18-May-19 17:00 4.21% 0%
Subsystem 2496.00 11-Jul-18 08:00 18-May-19 17:00 4.21% 0%
Commissioning ffor 1520 256.00 14-Aug-18 08:00 14-Sep-18 17:00 4.23% 0%
RFSU for 1520 ((C26,T0+51,2018/10/30) 2496.00 11-Jul-18 08:00 18-May-19 17:00 3.56% 0%
FOS - Fuel Oil Syste
System 2728.00 03-May-18 08:00 08-Apr-19 17:00 4.86% 0%
4550 - FOS - Fuel O Oil System 2728.00 03-May-18 08:00 08-Apr-19 17:00 4.86% 0%
System 2728.00 03-May-18 08:00 08-Apr-19 17:00 4.86% 0%
Subsystem 2728.00 03-May-18 08:00 08-Apr-19 17:00 4.86% 0%
Commissioning ffor 4550 408.00 20-Jul-18 08:00 08-Sep-18 17:00 4.92% 0%
RFSU & Provisional
Provisio Acceptance for 4550 (C26,T0+51,2018/10/30) 2728.00 03-May-18 08:00 08-Apr-19 17:00 4.17% 0%
ARDS - Atmospheric Residue Desulphurization 2856.00 09-Jun-18 08:00 31-May-19 17:00 0.27% 0%
1210 - Common ARDSAR - Common Atmospheric Residue Desulphurization 2448.00 11-Jul-18 08:00 12-May-19 17:00 4.84% 0%
System 2448.00 11-Jul-18 08:00 12-May-19 17:00 4.84% 0%
Subsystem 2448.00 11-Jul-18 08:00 12-May-19 17:00 4.84% 0%
Commissioning ffor 1210 344.00 15-Aug-18 08:00 26-Sep-18 17:00 4.92% 0%

Remaining Level of Effort Actual Work Critical Remaining ... Page 88 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
EPCC OF SD1 UPT2 PACKAGE(IFE_0)(Updated) Classic WBS Layout - CKS (MON REP) 05-May-18 11:25

Activity ID Activity Name Original Start Finish Schedule % Performance J A J A JJA J A JJA J A JA J A JJA J A
Duration Complete % Complete

RFSU & Provisional


Provisio Acceptance for 1210 (C26,T0+51,2018/10/30) 2448.00 11-Jul-18 08:00 12-May-19 17:00 4.15% 0%
1211 - ARDS - Atmospheric
Atmo Residue Desulphurization 2824.00 13-Jun-18 08:00 31-May-19 17:00 0% 0%
System 2824.00 13-Jun-18 08:00 31-May-19 17:00 0% 0%
Subsystem 2824.00 13-Jun-18 08:00 31-May-19 17:00 0% 0%
Commissioning ffor 1211 792.00 23-Aug-18 08:00 29-Nov-18 17:00 0% 0%
RFSU & Provisional
Provisio Acceptance for 1211 (C26,T0+51,2018/10/30) 2824.00 13-Jun-18 08:00 31-May-19 17:00 0% 0%
1212 - ARDS - Atmospheric
Atm Residue Desulphurization 2776.00 09-Jun-18 08:00 21-May-19 17:00 0% 0%
System 2776.00 09-Jun-18 08:00 21-May-19 17:00 0% 0%
Subsystem 2776.00 09-Jun-18 08:00 21-May-19 17:00 0% 0%
Commissioning ffor 1212 776.00 15-Aug-18 08:00 19-Nov-18 17:00 0% 0%
RFSU & Provisional
Provisio Acceptance for 1212 (C26,T0+51,2018/10/30) 2776.00 09-Jun-18 08:00 21-May-19 17:00 0% 0%

Remaining Level of Effort Actual Work Critical Remaining ... Page 89 of 89 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation