STUBB CREEK
GENERAL NOTES & HOLDS
Project Stubb Creek Marginal Field FEED Update Project Originated By SD
Client Universal / SIPEC JOT Checked By CA
Location STUBB CREEK Approved By KT
Job No. JU11867B Revision 0
Doc No. SCPF-PETW-LIS-P-01001 Date 19/01/2012
NOTES:
1. UTILITY WATER IS REQUIRED FOR VESSEL WASH OUT AND UTILITY STATIONS . NORMALLY NO FLOW
2. DELETED.
3. THE GIVEN VALUES FOR UTILITY CONSUMPTION ARE BASED ON NORMAL OPERATING DATA AND DOES NOT INCLUDE DESIGN MARGIN.
4. PEAK MAXIMUM CONSUMPTION
5. PROPANE BOTTLE (BACKUP FOR FUEL GAS) FOR FLARE PILOT
6. PRELIMINARY DATA. FUEL GAS DEMAND FOR FLARE PACKAGE AND PRODUCED WATER TREATMENT PACKAGE TO BE CONFIRMED BY PACKAGE VENDOR.
7. DELETED.
8. THE STATED VALUES ARE BASED ON MAXIMUM DOSAGE RATE.
HOLDS:
1. DELETED.
2. DELETED.
3. UTILISATION OF EPF CHEMICAL INJECTION PUMPS ( CORROSION INHIBITOR & DEMULSIFIER).