Activity ID Package Activity Name Original BL1 Start BL1 Finish 2018
Duration March April May June July August
26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20
INTEGRATED NETWORK PC&C 167 08-Mar-18 22-Aug-18
Utility 167 08-Mar-18 22-Aug-18
Steam IN-4000-0021/22/23 167 08-Mar-18 22-Aug-18
Milestone 137 06-Apr-18 21-Aug-18
A1000 P14-RF HP Steam Blowing 95 06-Apr-18 10-Jul-18
A1010 P14-RF MP Steam Blowing 54 04-May-18 27-Jun-18
A1020 P14-RF LP Steam Blowing 61 21-Jun-18 21-Aug-18
HP Steam : IN-4000-002
IN-4000-0023 125 08-Mar-18 10-Jul-18
P14 Interconnecting Hea
Header 84 08-Mar-18 30-May-18
Phase 1 59 08-Mar-18 05-May-18
IN-4000-23-10 P14 Install Sacrificial Valve at PCP (Hydrotest & Final Insulation) 29 08-Mar-18 05-Apr-18
IN-4000-23-11 P14 P14 HP Steam header blowing Phase-1 Part-1 SB-01 Main header 48". 5 06-Apr-18 10-Apr-18
IN-4000-23-12 P14 Shut down and Restoration Works (Remove Temp Piping, Install 48" 600# Temp. Blind Flange) 5 11-Apr-18 15-Apr-18
IN-4000-23-13 P14 P14 HP Steam Blowing (Phase-1 Part-1 rest of piping) 7 16-Apr-18 22-Apr-18
IN-4000-23-14 P14 Parellel act: Isolation system & Restoration works to start MP Ph1 (Reinstall Temp Piping, silencers) 12 20-Apr-18 01-May-18
IN-4000-23-15 P14 Shut down and Restoration Works at flange to SCC BL-03 3 29-Apr-18 01-May-18
IN-4000-23-16 P14 Warm Up Header 2 02-May-18 03-May-18
IN-4000-23-18 P14 Steam blow HP Phase-I part-2 SCC BL-03 & EOEG U-3220 2 04-May-18 05-May-18
Phase 2 10 21-May-18 30-May-18
IN-4000-23-32 P14 SB-01 Hp steam line towards ETP (U-6300) 1 21-May-18 21-May-18
IN-4000-23-34 P14 SB-02 HP steam line towards Polymer unit Until B/L of U-3200 7 U-3215. 1 22-May-18 22-May-18
IN-4000-23-35 P14 SB-03 Hp steam line towards (U-4200, U-4720, U-4820) 3 23-May-18 25-May-18
IN-4000-23-36 P3/P14 Isolation of system and restoration of normal MP steam header 5 26-May-18 30-May-18
P3 Interconnecting & RF EPCC Ma
Main Header 8 06-May-18 13-May-18
IN-4000-23-19 P14-P3 RF Interconnecting HP Steam Blowing 8 06-May-18 13-May-18
RC EPCC User (Branch Header) 68 04-May-18 10-Jul-18
IN-4000-23-17 P5 HP Steam Blowing P5 (BL04) 17 04-May-18 20-May-18
IN-4000-23-29 P5 HP Steam Blowing P5 (BL03) 17 06-May-18 22-May-18
IN-4000-23-30 P3-P1 HP Steam Blowing P1 15 14-May-18 28-May-18
IN-4000-23-33 P5 HHP Steam Blowing P5 35 21-May-18 24-Jun-18
IN-4000-23-31 P5 P5 HHP Steam header blowing 34 21-May-18 23-Jun-18
IN-4000-23-37 P3 HP Steam Blowing P3 15 29-May-18 12-Jun-18
IN-4000-23-38 P3-P4 HP Steam Blowing P4 8 13-Jun-18 20-Jun-18
IN-4000-23-39 P3-P2 HP Steam Blowing P2 20 21-Jun-18 10-Jul-18
MP Steam: IN-4000-0022 55 04-May-18 27-Jun-18
P14 Interconnecting Hea
Header 48 04-May-18 20-Jun-18
Phase 1 19 04-May-18 22-May-18
IN-4000-22-10 P14 P14 MP steam blowing via temporary HP to MP letdown station SB-1A, SB-1B, 19 04-May-18 22-May-18
Phase 2 21 31-May-18 20-Jun-18
IN-4000-22-14 P14 SB-01 MP steam line towards Ref. storage (U-59 00 ) 1 31-May-18 31-May-18
IN-4000-22-15 P14 SB-02MP steam line towards Polymer unit FDPE Until B/L of U-3215. 1 01-Jun-18 01-Jun-18
IN-4000-22-16 P14 SB-03 MP steam line towards C4/INA B/L of U-3600 1 02-Jun-18 02-Jun-18
IN-4000-22-17 P14 SB-01 MP steam line towards BFW U-4200 2 03-Jun-18 04-Jun-18
IN-4000-22-18 P14 SB-02 MP steam line towards ASU U-4400, AND EOEG U-3220 1 05-Jun-18 05-Jun-18
IN-4000-22-19 P14 Isolation of system and restoration of normal for LP steam header 15 06-Jun-18 20-Jun-18
P3 Interconnecting & RF EPCC Ma
Main Header 8 23-May-18 30-May-18
IN-4000-22-12 P3 RF Interconnecting MP Steam Blowing 8 23-May-18 30-May-18
Refinery EPCC User (Branch
(Bra Head
Header) 28 31-May-18 27-Jun-18
IN-4000-22-13 P3-P1 MP Steam Blowing P1 21 31-May-18 20-Jun-18
IN-4000-22-20 P3-P2 MP Steam Blowing P2 21 31-May-18 20-Jun-18
IN-4000-22-11 P5 MP Steam Blowing P5 20 31-May-18 19-Jun-18
IN-4000-22-21 P3 MP Steam Blowing P3 15 13-Jun-18 27-Jun-18