Concrete Field Summary

Project Number 201 – 11216 – 02 RFT Number 00190 – 0 – CON – 20231003 – 20231005 – 177.02 – BLD – USP – GLD - -
Project Name Union Station Area of Operation Area C Date October 6th, 2023
Sub-Contractor ONTrack Alliance Weather Conditions Clear Skies Ambient Temperature 17oC
Location Area C Pile Cap Foundations SPC42, , SPC39, SPC35, MPC3 Type of Element Casted Pile Cap
Concrete Supplier CRHCA Concrete Mix Design WC12U510 Specified Strength (MPa) 35 @ 56 day
Specified Slump 150 ± 30 mm Specified Air % 5–8% Admixtures Plastol 341
Operation Start 7:00 Operation End time 13:00 Total Volume Placed 81 m3

Concrete Test Results

Time
# Of
Load Plant Truck Ticket Qty Cum. Time Air Slump Temp Accept
Location Cast Time Cylinders Set I.D.
No. No. No. Number Batch Start End Qty Sampled % (mm) °C Y/N
I.D. taken
Time Time Time

7:24 8:00 9 USEP-


1 30 1861 24919411 6:18 SPC42 9 7:30 6 160 25 7:42 Y 2 CON-
231006-01

8:08 8:24 2 SPC42 USEP-


2 30 1248 24919415 6:40 18 8:11 8 150 26 8:20 Y 2 CON-
231006-02
8:24 8:40 7 SPC35

8:45 9:15 SP39 USEP-


9
3 30 1249 24919416 6:55 27 8:53 5.5 140 26.5 9:10 Y 2 CON-
231006-03

USEP-
4 30 1817 24919420 7:37 9:18 9:52 9 MPC3 36 9:30 5.5 155 25 9:42 Y 11 CON-
231006-04

Notes:

351 Steelcase Road West, Units 10-12, Markham, ON L3R 4H9 Canada T: +1 905 475 5591 F: +1 905 475 5257
On site as requested to carry out concrete testing for the pile cap foundations SPC35, MPC3, SPC39, and SPC42 in Area C at the above noted site. Two (2) cylinders were
casted for each of the first three loads (used in SPC42, SPC39, SPC35) and scheduled to be field cured and tested for compressive strength on day 5. For Load 4 (used in
MPC3), Eleven (11) cylinders were casted of which two (2) are scheduled to be field cured and tested for compressive strength on day 5, and nine (9) cylinders are stored in
a curing box with a max/min thermometer on site for the duration of the initial curing period and scheduled for testing at 1 – 7 days, 2 – 28 days, 2 – 56 days, 2 – AVS (1 for
testing, 1 for hold), and 2 -RCP (1 for testing, 1 for hold). It should also be noted that the volumes of concrete used per element are merely estimates that were made in the
field, and the exact split of concrete may differ in reality. All test results met project specifications which the client and contractor were informed of.

Technician Time on Site: 6:30 – 15:00 Technician Travel Time 2 hours


Technician Name: Zeel Thakkar
Field Summary Reviewed By: S. Reddy Yellu