Professional Documents
Culture Documents
(*E-SIGNED IS ACCEPTED)
DATE
Page 1 of 3
QUESTIONS - CONTINUATION]
1. [15points] Create a precedence diagram based on the given list of activities
Notes for Item no. 1
You could present your solution/answer thru either of the following: (1) Handwritten; (2) MS
office (word, excel, etc.); or (3) Any precedence diagram application, just make sure that it
follows our prescribe template for each node.
As discussed, for uniformity please do follow this template of the NODE for the precedence
diagram:
Activity ID
Ex.
0 3 3
A
0 0 0 3
2. [15points] Determine the critical path of the project path based on your answer on item no. 1 and
explain briefly why it is the critical path.
3. [20points] Scenario. Engr. Juana is working on numerous projects at the same time, and as a result,
he has neglected Project CE, creating delays in the procurement/mobilization of various resources.
Several activities were delayed as a result of this unexpected incident, including:
a. Excavation of electrical manholes; which was completed 14 days after it began; and
b. Installation of tank pipes and valves; which was finished on the 32nd day (or Day 32) of
construction.
3.1. How does the unforeseen events affect the critical path/s?
3.2. How does the unforeseen events affect the project duration?
Guide:
0 3 3 3 2 5
A B
**to be determined
0 0 0 3
[INTERPRETATION] Activity A will start at Day 1 and will end in Day 3; while, Activity B will start at Day 4 and
will end in Day 5
Page 2 of 3
[END]
Page 3 of 3