CLASSWORK NO.

NAME (SURNAME, GIVEN NAME, MI)

STUDENT NO. SECTION SIGNATURE


20191358917
(*E-SIGNED IS ACCEPTED)
DATE

PART 1.
Instruction. Using the activities listed below of Project CE, determine the following:
Activity Predecessor
Duration
ID Description Description ID
(Days)
A Site Clearing 3 - -
Cannot start before the site is cleared; otherwise, many of the survey
B Surveying and layout. 2 A
stakes would be lost in the clearing operation
C Rough Grading 2 Cannot start until the area has been survey and laid out. B
D Drilling of well 15 Cannot start until the rough grading operation is completed. _C_
E Installation of well pump 2 Cannot be done until well is completed drilled. _D_
Underground water Although this might be started earlier, the site contractor prefers to
F 8 _E_
piping work starting from the pump toward the building site.
Installation of Water
G 4 After the rough grading, these simple foundations can be installed. _C_
tank foundation
H Erection of water tank 10 The water tank cannot be erected until the foundations are poured. _H_

I Tank piping and valves 10 Cannot be fabricated and installed until the water tank is completed. _I_
Connecting all the water The water piping cannot be linked up until both sections (tank piping
J 2 F, _I_
pipes & valves & valves) are completed.
K Excavation for sewer 10 Can be started after rough grading. _C_
Installation of the sewer
L 5 Immediately follows after sewer excavation. _K_
and backfill
Excavation for electrical
M 1 Can start after rough grading. _C_
manholes
Installation of electrical
N 5 Cannot start until the excavation for manholes is completed. _M_
manholes
Installation of electrical Start after the electrical manholes are complete and the completion of _N_,
O 3
duct bank the sewer line, because that line is deeper than the duct bank. _L_
Installation of overhead
P 6 Can be started after the site is rough graded. _C_
pole line
Pulling of the power Can start after both the duct bank and the overhead pole line are _O_,
Q 5
feeder (electric) installed and ready to receive the cable _P_
Drafting of Building It is dependent on the completion of the installation of all electric and _J_,
R 1
Layout water lines (pipes & valves). _Q_
End

Page 1 of 2
[QUESTIONS - CONTINUATION]
1. [10points] Fill in the Blanks (__). Complete the Predecessor – ID column on the given table.

2. [20points] Create a table for the Gantt chart following the template as shown below:

Activity
Duration Start Date End Date
ID Description
(Days)
A Site Clearing 3 [CHECK NOTE BELOW]

NOTE:
 The START DATE will be 07 June 2023
 All successor activity will start the day after all its predecessor is finished.

3. [20 points] Create a Gantt chart using your answers in Item no. 2. You may use any application (such
as excel, MS project, etc.) or in handwritten. (Note: Link displaying dependencies is not required for
now, but you may include it if you can.)

4. [10 points] Determine total duration (in days) of the project and at what date (DD-MM-YYYY) it will be
completed.

[END]

Page 2 of 2