You are on page 1of 5

Practice problem

1. Cool homes Ltd specializes in constructing quality homes in the city of Bangalore. Cool
homes is known for timely completion of its projects. Consider one of the projects of cool
homes. Below Table lists the activities their precedence relationship with other activities,
their precedence relationship with other activities and their duration. Construct a network
for the project, clearly depicting the activities and their relationship.

Activity Description Duration Predecessors Successors


(weeks)
A Design/approval of plan 8 - B,C

B Foundation/superstructure 12 A D,E

C Select and order electrical 4 A H


and other accessories
D Wiring for the building 2 B F

E Carpentry works 8 B G,I

F Laying of roof 2 D G,I

G Wall plastering/laying 3 E,F H


floors
H Fixing fitting 2 C,G J

I Obtaining power and water 2 E,F J


connections for the site
J Final polishing, testing, 2 I,H -
handover

a. Draw the AOA diagram, estimate critical path.

Suppose Additional information is available to the project manager of cool homes


regarding crashing of some activities in the project. Analyze the time-cost trade-off
involved in crashing the project duration and identify the optimal crash length for the
project. The relevant information is available in below table. The indirect cost for the
project is estimated to be INR 5000 per week.

Activity Description Normal Crash Normal Crash cost


Time Time Cost
(Weeks) (Weeks)
A Design/approval of plan 8 6 12,000 20,000

B Foundation/superstructure 12 8 24,000 56,000

C Select and order electrical 4 4 8,000 NA


and other accessories
D Wiring for the building 2 2 9,000 NA
E Carpentry works 8 5 9,000 27,000

F Laying of roof 2 1 12,000 24,000

G Wall plastering/laying 3 2 12,000 22,000


floors
H Fixing fitting 2 1 8,000 22,000

I Obtaining power and water 2 2 6,000 NA


connections for the site
J Final polishing, testing, 2 1 8,000 10,000
handover

b. Compute the cost of crashing.

Let us assume that Cool homes have no prior experience in the kind of construction project
that they have currently undertaken. Consequently, there is considerable uncertainty in
estimating the activity duration. Assume that senior manager at cool homes has collectively
brainstormed and arrived at the following estimates for time duration.

Activity Description Optimistic Most likely Pessimistic

A Design/approval of plan 4 8 18

B Foundation/superstructure 11 12 25

C Select and order electrical 3 4 11


and other accessories
D Wiring for the building 1 2 3

E Carpentry works 6 8 22

F Laying of roof 2 2 8

G Wall plastering/laying 2 3 4
floors
H Fixing fitting 1 2 3

I Obtaining power and water 1 2 3


connections for the site
J Final polishing, testing, 1 2 3
handover

C. Use the PERT technique to compute and analyze the following.

i. What is the expected duration for each activity in the network?


ii. What is the variance of the duration for each activity in the network?
iii. Compute the expected duration for all the five paths in the network.
iv. What is the probability of completing the project by the end of week 45?
v. What are the key inference that one can draw from these results?
2. The Reliable Construction Company has just made the winning bid of $5.4 million to
construct a new plant for a major manufacturer. The manufacturer needs the plant to go into
operation within a year. Therefore, the contract includes the following provisions:

• A penalty of $300,000 if Reliable has not completed construction by the deadline 47


weeks from now.
• To provide additional incentive for speedy construction, a bonus of $150,000 to be paid
to Reliable if the plant is completed within 40 weeks.

Reliable is assigning its best construction manager, David Perty, to this project to help ensure
that it stays on schedule. Mr. Perty has earned the confidence of management through many
years of exemplary performance with the company. He began as a carpenter fresh out of
community college and soon became the youngest foreman in the company, so he knows the
construction business from the ground up. While a foreman, he went back to college part time
at night to earn his business degree. It was an arduous schedule that stretched out over five
years, but he found that he enjoyed his business major and was good at it. His favorite course
was a graduate-level elective in project management, and it was there that he thoroughly
learned the techniques of PERT/CPM. Immediately after earning his business degree with
honors, Mr. Perty was promoted to construction manager. He has been serving the company in
this capacity now for 14 years, and rumors have it that he may be next in line to move into top
management in a year when the retirement of the company president will cause some shuffling
of the top positions. Although Mr. Perty would welcome this opportunity, he does not feel any
hurry to move up. Despite its many stresses, he thoroughly enjoys the challenges of being a
construction manager, including the opportunities to apply the latest project management
techniques. Mr. Perty is very pleased to receive this latest assignment as the project manager
for such an important project. He looks forward to the challenge of bringing the project in on
schedule, and perhaps earning a promotion in the process. However, since he is doubtful that it
will be feasible to finish within 40 weeks without incurring excessive costs, he has decided to
focus his initial planning on meeting the deadline of 47 weeks.

He will need to arrange for a number of crews to perform the various construction activities at
different times. Table shows his list of the various activities. The third column provides
important additional information for coordinating the scheduling of the crews. For any given
activity, its immediate predecessors (as given in the third column of Table) are those activities
that must be completed by no later than the start time of the given activity. (Similarly, the given
activity is called an immediate successor of each of its immediate predecessors.)

Table: Activity List for the Reliable Construction Co. Project

Activity Activity Description Immediate Estimated


Predecessors Duration(weeks)
A Excavate --- 2
B Lay the foundation A 4
C Put up the rough wall B 10
D Put up the roof C 6
E Install the exterior plumbing C 4
F Install the interior plumbing E 5
G Put up the exterior siding D 7
H Do the exterior painting E,G 9
I Do the electrical work C 7
J Put up the wallboard F,I 8
K Install the flooring J 4
L Do the interior painting J 5
M Install the exterior fixtures H 2
N Install the interior fixtures K,L 6

For example, the top entries in this column indicate that


1. Excavation does not need to wait for any other activities.
2. Excavation must be completed before starting to lay the foundation.
3. The foundation must be completely laid before starting to put up the rough wall, and so on.

When a given activity has more than one immediate predecessor, all must be finished before
the activity can begin. In order to schedule the activities, Mr. Perty consults with each of the
crew foremen to develop an estimate of how long each activity should take when it is done in
the normal way. These estimates are given in the rightmost column of Table.
Adding up these times gives a grand total of 79 weeks, which is far beyond the deadline for the
project. Fortunately, some of the activities can be done in parallel, which substantially reduces
the project completion time. Given all the information in Table, Mr. Perty now wants to develop
answers to the following questions.

1. How can the project be displayed graphically to better visualize the flow of the activities?
2. What is the total time required to complete the project if no delays occur?
3. When do the individual activities need to start and finish (at the latest) to meet this project
completion time?
4. When can the individual activities start and finish (at the earliest) if no delays occur? 5.
Which are the critical bottleneck activities where any delays must be avoided to prevent
delaying project completion?
6. For the other activities, how much delay can be tolerated without delaying project
completion?
7. Given the uncertainties in accurately estimating activity durations, what is the probability of
completing the project by the deadline (47 weeks)?
8. If extra money is spent to expedite the project, what is the least expensive way of attempting
to meet the target completion time (40 weeks)?
9. How should ongoing costs be monitored to try to keep the project within budget?

You might also like