A - 12
B - 13
C A 12
D B 14
E C 14
F C 13
G D,E 15
H F,G 12
ii. Determine the slack for each task and clearly deduce the critical path for the
project.[5]
3. You have to manage a project with activities and their respective durations as listed in
Table 1 below:
i. Construct a precedence diagram to analyze your project. [5]
ii. What is the project duration? [2]
iii. What are the critical activities? [2]
iv. Show the critical path on your precedence diagram. [2]
v. When is the latest time that activity G must be completed in order that the project is
not delayed? [2]
vi. When is the earliest time that activity D can possibly be completed? [2]
vii. What is the free float for activity E with respect to activity H? [2]
TOTAL 40