You are on page 1of 14

Axtivity

Consider the PERT/CPM network shown below.


D
A 2 3
E F
B
1 G J
4 6 7
H
C
I
5
a. Add the dummy activities that will eliminate the problem of
activities having the same starting and ending nodes.

1
2
Network exercise
b. Add dummy activities that will satisfy the following
immediate predecessor requirements:

Immediate
Activity Predecessor
H B, C
I B, C
G D, E

3
4
5
Network exercise with time
Construct a PERT/CPM network for a project with the
following activities and times:
Activity Immediate Time
Predecessor (months)
A - 4
B - 6
C A 2
D A 6
E C, B 3
F C, B 3
G D, E 5
a) Find the critical path for this project network.
6
PATH A,D AND G
b) This project must be complete in 1 1/2 years; do you
anticipate difficulty in meeting the deadline? Explain.
NO PROBLEM AT ALL SINCE THE DIAGRAM SHOWS THE PROJECT IS EXPECTED TO
FINISH EARLIEST THAN THE DEADLINE

7
8
Consider the following network
(times are in weeks)
2 C 5
7
A F
D H
5 3
6 8
1 G
4 6
B 10
E
3
3 7

a. Identify the critical path.PATH A,D,F AND H


b. How long will it take to complete this project?22 WEEKS
c. Can activity D be delayed without delaying the entire project?
How about activity C? If so, how many weeks?
9
NO IF “D’ IS DELAYED ENTIRE PROJECT WILL BE DELAYED BECAUSE THE DIAGRAM
SHOWS THAT THIS ENTER THE CRITICAL PATH.
“C” CAN BE DELAYED FOR 2 WEEKS ONLY
d. What is the schedule for activity E?
ACTIVITY TAKES 7 WEEKS TO COMPLETE

10
11
Network exercise with time
A project involving the installation of a computer system consists
of eight activities. The immediate predecessor and activity time
in weeks are shown below:
Activity Immediate Time
Predecessor (weeks)
A -3
B -6
C A 2
D B,C 5
E D 4

12
F E3
G B,C 9
H F,G 3
a. Draw the PERT/CPM network for this project.ATTACHED
BELOW
b. What are the critical path activities? PATH B,D,E,F AND H
c. What is the expected project completion time? 21 WEEKS

13
14

You might also like