Network
Diagrams
Devyn R. Lopez Aquino
Embry-Riddle Aeronautical University
LGMT 420 – Management of Production & Operations
Michael Davis
February 20, 2022
This study source was downloaded by 100000756164522 from CourseHero.com on 11-25-2022 00:31:44 GMT -06:00
Some ideas to shorten turn around could be to shorten servicing the gallery
to 15 minutes and refueling / water servicing to 20 minutes. This would
shorten the turn around time around 10 minutes
This study source was downloaded by 100000756164522 from CourseHero.com on 11-25-2022 00:31:44 GMT -06:00
G If activity E Refueling / Water
C servicing was reduced to15
B minutes, the critical path would
F change as would the total time of
A the process. The total time would
D reduce 5 minutes to 50 minutes.
E I See next slide for what would be
H the new critical path if only
refueling was reduced in time.
ES
AC
EF J 15 G 35
T
Red Arrows annotate
DU 0 B 5 5 C 15 20 20 40
LS LF critical path.
R
5 5 10 10 10 20 Time of completion: 55
Min
15 F 35
0 A 0 15 E 40 40 I 55
20 20 40
0 0 0 15 25 40 40 15 55
0 D 15
55 J 55
15 H 30
0 15 15
55 0 55
40 15 55
This study source was downloaded by 100000756164522 from CourseHero.com on 11-25-2022 00:31:45 GMT -06:00
Red Arrows annotate
15 G 35 critical path.
0 B 5 5 C 15 15 20 35 Time of completion: 50
Min
0 5 5 5 10 15
15 F 35
0 A 0 15 E 30 35 I 50
15 20 35
0 0 0 20 15 35 35 15 50
0 D 15
50 J 50
15 H 30
5 15 20
50 0 50
35 15 50